OAH Docket No.
10-2901-12620-2
MEQB Docket No.
MP-HVTL-EA-1-99
STATE OF MINNESOTA
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE MINNESOTA ENVIRONMENTAL QUALITY BOARD
|
In the Matter of
the Exemption Application by Minnesota Power for a 345/230 kV High Voltage
Transmission Line Known as the Arrowhead Project |
FINDINGS OF FACT,
CONCLUSIONS AND RECOMMENDATION |
This matter was heard by
Administrative Law Judge Kenneth A. Nickolai beginning at 9:00 a.m. on August
28, 2000, continuing for technical hearings on August 29 through September 1,
and September 5-9, 2000. Public
hearings were held on August 28 and August 29, 2000, from 7:00 p.m. to
approximately 10:30 p.m. Hearings were
held at the Black Woods Conference Center 195 Highway 2, Proctor, Minnesota. [1] Following the close of the hearing, with
agreement of all parties, the Administrative Law Judge toured the proposed
route with guidance of EQB staff member, Bob Cupit. The record remained open for the submission of public comments
until September 13, 2000. Initial
briefs were filed on November 15, 2000 and reply briefs on December 5,
2000. The record in this matter closed
for all purposes on December 5, 2000.
Appearances: Michael C. Krikava, Briggs & Morgan,
2400 IDS Center, 80 South 8th Street,
Minneapolis, MN 55402, and Deborah Amberg, Senior Attorney for Minnesota Power,
30 West Superior Street, Duluth, MN
55802-2093 appeared on behalf of Minnesota Power (“Applicant”, “Company”
or “MP”). Dwight Wagenius, Assistant
Attorney General, 900 NCL Tower, 445 Minnesota Street, St. Paul, MN 55101-2127, appeared on behalf of the
Minnesota Environmental Quality Board (“MEQB”). Bob Cupit, MEQB Staff Project Manager, 300 Centennial
Building, 658 Cedar Street, St. Paul, Minnesota 55155, represented the MEQB
staff. Suzanne Steinhauer, Public
Advisor, 300 Centennial Building, 658 Cedar Street, St. Paul, Minnesota
55155, appeared to assist members of the public participating in this
proceeding. Ginny Zeller, Assistant
Attorney General, 525 Park Street, Suite 200, St. Paul, MN 55103-2106, appeared on behalf of the
Minnesota Department of Commerce ("Commerce"). George Crocker, PO Box 174, Lake Elmo, MN
55042, appeared on behalf of the North American Water Office
("NAWO"). Pam McGillivray,
Garvey & Stoddard, 634 West Main Street, Suite 201, Madison, WI 53703, appeared on behalf of Save Our Unique
Lands ("SOUL"). Carol A.
Overland, Attorney at Law, 402 Washington Street So., Northfield, MN 55057,
appeared on behalf of World Organization for Landowner Freedom
("WOLF").
Notice
is hereby given that pursuant to Minnesota Statutes § 14.61 and Minn. Rule
4405.0900, exceptions to this report, if any, by any party adversely affected
must be filed within fourteen (14) days of the mailing date of this document. Exceptions must be filed with the Director
of the Minnesota Environmental Quality Board, 658 Cedar Street, St. Paul,
Minnesota 55155. Exceptions must be
specific and stated and numbered separately.
Proposed Findings of Fact, Conclusions and Order should be included, and
copies thereof shall be served upon all parties.
The
MEQB will make the final determination of the matter after the expiration of
the period for filing exceptions as set forth above or after oral argument if
such is requested and granted in this matter.
Further
notice is hereby given that the MEQB may accept or reject the Administrative
Law Judge’s Recommendation.
STATEMENT OF ISSUE
May the
Minnesota Environmental Quality Board exempt the proposed Arrowhead Project
from the requirements of the Minnesota Power Plant Siting Act (Minn. Stat. §§
116C.51-.69) and, if so, should the requested exemption be granted?
Based
upon all the proceedings herein, the Administrative Law Judge makes the
following:
FINDINGS OF FACT
A. Procedural
History
1.
The Applicant, MP, is an investor-owned corporation engaged
in the production, distribution, and sale of electricity. MP seeks an exemption from the requirements
of the Power Plant Siting Act (Minn. Stat. Chap. 116C or PPSA) allowing it to
upgrade an existing power line from the Arrowhead substation connecting to a
facility at Oliver, Wisconsin. The line upgrade will only be completed if the
State of Wisconsin approves construction of a 345 kV HVTL from Oliver,
Wisconsin to the Weston substation.[2] Before filing this request for exemption, MP
held public information meetings in Midway Township, Minnesota on May 26 and
27, 1999 on their proposal to upgrade the power line. These meetings were held at 2:00 p.m. and 7:00 p.m. in the Midway
Town Hall. Notices of the meetings were
published in local newspapers and mailed to landowners within 1,000 feet of the
proposed right-of-way; local, state, and federal agencies; and elected
governmental representatives.[3]
2.
On September 16, 1999, MP submitted an application for
exemption from the PPSA to the MEQB for the proposed 345/115-kV Transmission
Line addition and rebuild.[4]
3.
Notice of the exemption application was published in the
Duluth News-Tribune newspaper on
September 19, 1999, the Duluth Budgeteer
on September 26, 1999, and the Proctor Journal
on September 23, 1999. (MEQB Exhibit
2.) The notice described the proposed
project and provided that interested persons had the opportunity to comment and
to request a public hearing. Similar
information was included in the letters mailed to affected landowners and
government officials. (MEQB Exhibit
2.) Those letters were mailed on
September 21, 1999. Id.
4.
The MEQB received nine objections to the application for
exemption. On November 18, 1999, the
MEQB met and ordered that a public hearing be held on the application. (MEQB Exhibit 4.) The MEQB also received over one thousand public comments
responding to the public notice of MP's application.[5]
5.
Notice of the public hearing in this matter scheduled for
January 31, 2000 was given by publication in the Duluth News-Tribune on December 17, 1999 and January 23, 2000. (MEQB Exhibits 5a and 5b.) Because a motion to clarify the scope of
this proceeding was certified by the Administrative Law Judge to the MEQB, that
scheduled public hearing was postponed.
(MEQB Exhibit 5c.)
6.
The MEQB issued an Order Clarifying Scope of Hearing Record
on May 3, 2000 "that the hearing be limited to impacts from the
construction or operation of the project facility on human health and the
environment experienced in Minnesota."
(MEQB Exhibit 7, at 8.) The
matter was then remanded to the Administrative Law Judge for hearing.
7.
The Notice of Public Hearing was published in the Duluth News-Tribune on August 11, 2000. (MEQB Exhibit 5e.) The hearing schedule was also published in the EQB Monitor on August 21, 2000. (MEQB Exhibit 5g.) Both of these notices indicated that updated information about
the hearing process would be posted on the Internet at the site maintained for
this proceeding, located on the OAH website at http://www.oah.state.mn.us/cases/arrowhead/arrowhead.html. The Notice of Public Hearing was mailed to
each of the persons on the MEQB's list of persons who had requested notice and
to three officials of affected units of local government. (MEQB Exhibit 6b.)
B.
Existing
Facilities and Route
8.
MP owns and operates an electric power substation, known as
the Arrowhead substation, covering 22 acres[6]
in Hermantown, MN.[7] The substation was first developed in 1962, was expanded in 1971
and 1977, and is now MP's second largest substation.[8] The substation has twelve power lines
running from it connecting to other facilities.[9]
One of those power lines is a 115 kV line, which leaves the substation in a
southerly direction crossing the St. Louis River at Gary-New Duluth, Minnesota
and Oliver, Wisconsin and connecting to another utility's facility in Oliver,
Wisconsin.[10]
9.
Three of the five 115 kV power lines exiting the substation
to the south run in a common right of way corridor for 3.2 miles. These three
lines are known as Lines 22, 70 and 131.
Line 22 is the line located farthest west of the three lines in the 3.2
mile corridor.[11] Only Line 131 continues south and east for six miles to the substation at Gary,
Minnesota. Line 131 currently travels
along the western edge of the DM&IR railroad tracks, adjacent to homes in
Gary[12]. From the Gary substation, a line designated
as Line 132 provides the existing 115 kV connection to facilities at Oliver,
Wisconsin. The route now occupied by
Lines 22, 131 and 132 (except for 0.8 miles along the DM&IR rail yard) is
the route proposed for the line rebuild and addition.
C.
The Proposed
Power Line and Route
10.
MP proposes a 345/115 kV double
circuit HVTL running from the Arrowhead substation for a distance of
approximately 12.5 miles to the Wisconsin border at Oliver, Wisconsin.[13]
The proposed transmission line (hereinafter "the Arrowhead Project")
will follow existing power line right-of-way, except for eight-tenths of a
mile. The width of the right-of-way will be increased by twenty feet along
approximately 3.2 miles of the route.
MP proposes to use double circuit, single pole structures set upon
concrete foundations to support the lines.
A 48-strand fiber-optic cable is proposed along the top of the new
structure. The fiber-optic cable would
be used for communications, including information transfer needed in
transmitting electricity.[14] The initial 3.2
miles of 115 kV power line will be constructed for operation as a 230 kV HVTL
(but only operated at 115 kV).[15] Six additional facility changes would need
to be undertaken prior to operating that line at 230 kV.[16]
11.
The Arrowhead Project, including the 345 kV HVTL connection
from the Arrowhead substation to a line at Oliver, Wisconsin, includes the
major following facility changes to the Arrowhead substation:
·
Increase the area covered by substation equipment by 10
acres, increasing it from 22 to 32 acres. [17]
·
Adding four single-phase 345/230 kilovolt transformers to interface
with the 345 kV line. These transformers step up the voltage from 230 kV to
345kV. [18]
·
Adding one 230 kV to 230 kV phase-shifting transformer to
adjust the phase angle of electricity being transmitted on the 345 kV HVTL.[19]
·
Adding control equipment, switched capacitors, 230 kV
circuit breakers, and 345 kV circuit breakers.[20]
Major
changes to the transmission line facilities and route from the proposed project
will be described by line segment:
12.
The first segment ("Midway segment") is the 3.2
mile corridor from the Arrowhead substation to Midway Township.[21] The geography of segment 1 is flat, with
areas of wetlands and woods. The
existing right of way currently holds three 115 kV lines. The changes proposed for this segment
include:
·
Dismantling the existing 115 kV line[22]
on the western side of the corridor, and the H frame structures supporting
it.
·
Replacing that line with a double circuit, single pole,
steel structure designed for 345/230 kV operation for the first 3.2 miles. The single pole, steel structures would be
placed in a concrete foundation.
·
Placing a 345 kV high voltage transmission line on those
structures, extending from the Arrowhead substation to Oliver, Wisconsin, as
part of a circuit intended to terminate at the Weston substation near Wausau,
Wisconsin.
·
Also placing on those structures, for 3.2 miles, a 230 kV
circuit. This 230 circuit would
initially be operated at 115 kV replacing the 115 kV line currently connecting
to Hibbard in this segment of the corridor.
·
Reconfigure the power line arrangement in the initial 3.2
mile corridor to substitute the new 230 kV circuit for the existing 115 kV line
now running to Hibbard. The existing
115kV line now serving Hibbard would be used to provide service from the
Arrowhead substation to the Cloquet substation.
·
Widening the initial 3.2 miles of right of way by 20 feet on
the westerly side of the corridor.[23]
13.
Segment 2 ("Beck's Road segment") runs six miles
through Midway Township, along the west end of the City of Duluth, and
terminating at the City of Gary.[24] This segment begins with geography similar
to the Midway segment until the right of way crosses Interstate Highway
35. At that point, the Beck's Road
segment crosses a ridge and follows the base of that elevation, closely
paralleling railroad tracks traveling to the southeast. The area around the right of way is
wooded. Several gravel pits and a
bituminous asphalt plant are located near the right of way. Major facility changes in this segment
include:
·
Dismantling the present Arrowhead-Gary 115 kV line
identified as Line 131 and the H frame structures supporting the line.
·
Replacing the structures with single pole structures with
two circuits: a 345 kV line as described in segment one and a 115kV line.
·
No changes are anticipated to the right of way in this
six-mile segment.
14.
Segment 3 ("Gary segment") travels east, beginning
near Commonwealth Avenue in Gary, Minnesota, then turns south at the DM&IR
Railroad tracks and follows those tracks south to the Wisconsin border. This existing line is identified as Line
132. The transmission line parallels the existing crossing of the St. Louis
River into Wisconsin (the Highway 39 railroad/vehicle bridge).[25] The area along the right of way has some
residences, but is predominantly occupied by industrial uses. The Gary segment
is 2.8 miles long. Major changes in
this portion of the corridor include:
·
Dismantling the existing 115kV identified as Line 132.
·
Abandoning 0.8 mile of existing right of way.
·
Establishing a new right of way for that piece of the route
approximately 900 feet east of 96th Avenue West in Gary. This new portion of the right of way will be
a 100-foot-wide right of way east of the DM&IR railroad tracks.
·
Replacing the dismantled structures and establishing two
circuits, a 345 kV circuit as described above and a 115kV circuit replacing the
existing Line 132.
15.
In all the segments, the 345 kV circuit will consist of
two-wire bundled 1272 kcmil ACSR conductor for each of the three segments for a
total of twelve. The 115 kV circuit
will consist of a single 954 kcmil ACSR conductor.[26] The 230 kV segment will use a single 954
kcmil ACSR conductor, the same as that used on the 115 kV portion of the line.[27] Shield wire and optical ground wire will be
utilized for lighting protection and communication.[28]
The 345 kV HVTL will include new steel structures, hardware, insulators and
wire. The proposed 345 kV HVTL will
have a minimum clearance of 30 feet from the conductor to ground.[29]
The line has a maximum achievable operating temperature of 100 degrees
Centigrade (212 degrees Fahrenheit). [30].
16.
The transmission lines will be supported by double-circuit
single pole structures for straight, inline, and slightly-angled
locations. Single poles will be
composed of self-weathering steel. MP
originally proposed that lines could be supported by steel lattice structures
at medium-angled, heavy-angled, and dead-end locations. Lattice structures will be composed of
hot-dipped galvanized steel. Both
lattice and pole structures will be supported by concrete structures extending
approximately twenty feet below grade.
The maximum below grade depth of the footing will be forty feet, in
situations where the ground provides little shear strength and fifty feet for
heavily-angled structures.[31] The average height of the structure is 135
feet.[32]
The tallest structure could extend to approximately 185 feet above grade.[33] Connection of the conductors to the
supporting structures will be accomplished using dampers to control vibration.[34]
17.
Power for the lines will be drawn from existing power
flowing into the Arrowhead substation from generating facilities in North
Dakota and Manitoba, Canada.[35] The existing flows enter at 230 kV, 115 kV,
and 250 kV (from a DC line originating at the Square Butte substation in North
Dakota).[36] These flows will be stepped up to 345 kV for
transmission on the 345 kV line.
D. Exemption
Standards
18.
MP has applied for an exemption from the siting process
under Minn. Stat. § 116C.57, subd. 5.
In determining whether to grant the exemption, the MEQB must apply the
following standard:
If
the board determines that the proposed high voltage transmission line will not
create significant human or environmental impact, it may exempt the proposed
transmission line with any appropriate conditions, but the utility shall comply
with any applicable state rule and any applicable zoning, building and land use
rules, regulations and ordinances of any regional, county, local and special
purpose government in which the route is proposed.[37]
19.
The MEQB Rule 4400.3900 governs the exemption application
process. Minn. Rule 4400.3900, subp.1a
requires the applicant to provide a "description of the potential human
and natural environmental effects…" as identified in Minn. Rule 4400.1310.[38] The following findings address the
categories of impacts listed in Minn. Rule 4400.1310, subp. 1.
E. Assessment of Impacts
Effects on Human Settlement
Displacement
20.
No residential dwellings would be displaced by the proposal
and there are no homes or garages located within the proposed right-of-way. The existing transmission line route has
been used for approximately 20 years. In the Midway and Beck's Road segments,
the route passes through sparsely populated areas. A railroad yard separates the proposed route from the residential
development in Gary-New Duluth.[39] MP identified nine homes located within
three hundred feet of the centerline of the right-of-way.[40] The nearest distance between a home and the
centerline of the HVTL is between 160 to 180 feet.[41]
The distance between several homes and the western edge of the right of way
will be reduced by twenty feet in the segment running south from the Arrowhead
substation for 3.2 miles (Midway segment).[42] The distance between the edge of the right
of way and homes on the east side will not change. No specific distance is recommended as needed between HVTL and
homes.[43] The relocation of the right of way in
segment 3 will result in the power line being removed from a residential area.[44]
This will result in a number of homes being farther from the line than
previously.
Noise
21.
Two sources of additional noise from the proposed project
were identified. These sources are
noise from changes to the Arrowhead substation and noise from the additional
345 kV line. MP measured existing noise
levels from operation of the Arrowhead substation at several locations. Those measurements show that noise levels at
the substation property lines are currently within the MPCA noise standards.[45] Short term measurements taken show constant
sound levels (L90) ranging from 35 dba to 43 dba[46] The middle level of sounds (L50) experienced
at those locations ranged from 37 dba to 45 dba.[47] The high-end sounds (L10) experienced at
those locations ranged from 40 dba to 48 dba.[48] The MPCA noise standards for residences are
60 dba (L50) and 65 dba (L10) in the daytime, and 50 dba (L50) and 55 dba (L10)
at night.[49]
22.
The phase shifting transformer to be added at the substation
will emit 89 dba[50] measured at
a distance of one meter. Each of the
other three transformers will emit 84 dba at that distance.[51] After these additions, the calculated noise
levels are 47 dba at 2000 feet from the substation and 50 dba at 1,400 feet.[52] Due to the nature of the noise generated,
these noise levels are expected to be constant, that is, the noise levels will
be the same at all hours of the day and night.[53] There are at least two residences within
1,200 feet of the substation.[54] The increase in noise levels is likely to
exceed 10 dba at the location of the residences.[55] Unless noise is reduced by some other
mechanism, the noise levels at the nearest residences are likely to exceed 50
dba at night.[56]
23.
An increase of 10 db in a sound level is perceived by the
human ear as being twice as loud.[57]
24.
The increased levels of sound produced by the addition of
the transformers for the Arrowhead project can be reduced to below 50 dba at
the nearest residences through noise mitigation. Effective noise mitigation can be achieved through the use of
lower noise level transformers, the installation of sound barriers, or the use
of a combination of both methods.[58] Using noise mitigation technology will
prevent nearby residents from perceiving a significant increase in the noise
emitted from the Arrowhead substation.
25.
The second source of noise is from operation of the
lines. Directly under the line in
periods of high humidity when the 345 kV HVTL is operated in corona, the noise
level will be approximately 50-55 dba.[59]
That sound becomes attenuated within approximately 100 feet and is no longer
audible at that distance.[60]
Cultural
Values
26.
The Minnesota Historical Society State Historic Preservation
Office identified no properties listed on the National or State Registers of
Historical Places, nor any known or suspected archaeological properties.[61]
No properties were identified as eligible for inclusion on those Registers.
There are no significant cultural resources associated with the proposed route.
Aesthetics
27.
The existing transmission line is supported by H frame poles[62]
of approximately 65 to 75 feet in height, with an above ground height of 56.5
to 66.5 feet.[63]. For this project, MP intends to replace
those poles with approximately 104 self-weathering steel structures.[64] The tallest structure would be not higher
than 185 feet with a predominate structure height approximately 130 feet above
ground.[65] Taller structures are required because of
the proposed design of three conductors for each circuit stacked vertically.[66]
The total number of poles will be reduced by replacing an H frame structure
with a single pole structure.[67]
At some angle locations, up to three poles may be replaced with a single,
taller pole. The footprint of the single-pole structure is smaller than the
footprint of the combined perimeter of the two or three-pole structures.[68]
Recreation
28.
Two of the three segments of the route, the Beck's Road
segment and the Gary segment, contain recreational areas near the right of
way. Magney Park, Short Line Park,
Merritt Park, and portions of the Willard Munger Trail are within relatively
short distances of the Beck's Road segment and portions of the Gary
segment. The Buffalo House Campground
is within a half-mile south of the Beck's Road segment. Fond du Lac State Park is located within one
mile of the Beck's Road segment at the nearest point to the park boundary.[69]
Both the Willard Munger Trail and the Western Waterfront Trail intersect the
existing power line right of way.[70] The proposed HVTL runs along the existing
power line right of way.
29.
Short Line Park lies between two sets of railroad tracks
along a sloping elevation below Elys Peak.[71] There is no direct road access, provision
for automobile parking, or facilities in Short Line Park for recreation.[72] Short Line Park is occasionally used by rock
climbers.[73] The existing 115 kV power line abuts the
western end of Short Line Park.
30.
Merritt Park lies directly south of Short Line Park, south
of Beck's Road and the existing 115 kV power line right of way.[74] At its nearest point, the power line right
of way is within 1,000 feet of Merritt Park.[75] There is road access to Merritt Park, from
Beck's Road, but no facilities are located there for recreation
activities. A demolition landfill is
located adjacent to Merritt Park.[76]
31.
Magney Park is located atop the ridge overlooking the Gary
segment and much of the Beck's Road segment.[77] A portion of the Willard Munger Trail runs
through Magney Park. Direct road access
is provided to Magney Park by Skyline Parkway.
There are no facilities in Magney Park for recreation.[78]
32.
The Willard Munger Trail and Western Waterfront Trail are
recreational trails. The Willard Munger
Trail is constructed along an abandoned railroad right of way.[79] It runs parallel to the power line right of
way for approximately 1,000 feet with a distance of 300 to 400 feet separating
the two.[80] The two intersect at one point. The Willard Munger Trail is a popular
recreational resource. The 345 kV HVTL
will not be significantly more visible to users of the Willard Munger Trail
than the existing 115 kV power line that currently occupies the right of way.
33.
The Western Waterfront Trail runs along a railroad right of
way located along the St. Louis River.[81] The City of Gary, radio towers, extensive
railroad facilities, and a steel casting plant are all visible to the landward
side of the Western Waterfront Trail.[82] The existing 115 kV power line is visible
from all points of the Western Waterfront Trail.[83]
34.
The Buffalo House Campground is south of the Beck's Road
segment of the proposed right of way.
The Campground is located within a half-mile of the right of way, where
the right of way crosses Interstate 35.[84] A restaurant is located at the entrance to
the Campground.
35.
The Fond du Lac State Park is located approximately one mile
south of the 115 kV power line right of way at its nearest point.[85] The topography between the right of way and
the State Park precludes park visitors from seeing the Arrowhead HVTL.[86]
36.
There are no long-term impacts on public recreation arising
out of the Arrowhead Project. There may
be temporary interruptions to some recreational uses during the construction
period.[87]
Public
Services
37.
MP will notify the DM&IR railroad when installation of
the 345 kV HVTL and 115 kV power line will be affecting the railroad's
trackage. Similar notification to the
Minnesota Department of Transportation will occur when the construction crosses
Interstate 35. MP will schedule its
construction activities to minimize the affect on vehicular traffic.[88] There are no impacts on public services
arising out of the Arrowhead Project.
Public Health and Safety
38.
Electric and magnetic fields (EMF) arise from the flow of
electricity and the voltage of a line.
The intensity of the electric field is related to the voltage of the
line and the intensity of the magnetic field is related to the current flow
through the conductors.[89]
There are no state or federal standards for transmission line electric
fields. The MEQB has included permit
conditions for other transmission lines specifying that maximum electric fields
must not exceed 8 kV/meter.[90] The maximum anticipated electric field
exposure, measured directly under the HVTL is approximately 6.5 kV/meter.[91] Within 100 feet of the centerline of the
HVTL, the electric field strength nears zero.
[92]
39.
EMF is also measured in milligauss (mG). Common electrical appliances produce EMF
fields while in operation, as do HVTLs.
The Arrowhead Project will increase EMF exposures for persons living
along the right of way above current EMF levels.[93] The amount of the increase is small, ranging
from approximately 50 mG at the edge of the right of way to approximately 10 mG
at the distance of the nearest home to the Arrowhead HVTL.[94] These increased levels occur at the periods
of peak flow and are present approximately 5% of the time.[95]
40.
The record of this matter contains an evaluation of research
and investigations conducted into the effects of HVTL, including "electric
fields resulting from such facilities on public health and welfare, vegetation,
animals, materials and aesthetic values."[96] Research into human health impacts from
electric fields, issued by the National Institute of Environmental Health
Sciences shows "weak scientific evidence that exposure may cause a
leukemia hazard. In our opinion, this finding is insufficient to warrant
aggressive regulatory concern."[97]
41.
The "Henshaw Hypothesis" asserts that aerosols are
affected by the electromagnetic fields surrounding HVTL, resulting in the
deposition of particulate matter under and around power lines, resulting in
adverse health effects.[98] The research conducted into the Henshaw
Hypothesis does not support a conclusion that adverse environmental effects or
health effects arise from the presence of aerosols or deposition of particulate
matter in the area of HVTLs.[99]
42.
Electric currents in the earth can be caused by transmission
of electricity where grounding is used to complete the electric circuit.[100] In one of the two design options under
consideration, the Arrowhead HVTL will use grounding only in one location for
every distinct segment of HVTL (approximately one to two miles apart).[101] The other design option uses grounding at
only one end of the line. Both
arrangements prevent completion of an electric circuit in the earth between the
segments.[102] There is no evidence of adverse health
effects arising from such currents.[103]
Land-Based Economies
43.
An aggregate quarry (gravel pit) operates adjacent to the
Beck's Road segment. There is no
indication that current or future operations of the quarry will be affected by
the Arrowhead HVTL. Since the Arrowhead
HVTL will be using existing right of way currently occupied by a 115 kV power
line, the impact on land values from the proposed 345 kV HVTL will not be
significant. With the increase of the
width of the Midway segment of the right of way some additional agricultural
land will be affected, but the effect is not significant. No significant effects on land-based
economies have been identified arising out of the Arrowhead Project.
Archaeological and Historic Resources
44.
No archaeological or historic resources have been identified
along the route of the Arrowhead Project HVTL.
No significant effects on archaeological or historic resources have been
identified arising out of the Arrowhead Project.
Natural Environment
45.
Ten acres of cleared, undeveloped ground will be occupied by
equipment when the Arrowhead project is constructed. A twenty-foot-wide area. 3.2 miles in length will be cleared in
order to widen the existing right of way.
No environmental resources have been identified that would be affected
by this clearing. Use of the existing
right of way reduces the potential long-term impact to a minimum. MP has indicated that, where the line
crosses wetlands, construction will occur in winter, when the ground is
frozen. Where wetlands are not
sufficiently frozen, mats will be used to minimize damage to plant life present.[104] No significant adverse effects on the
natural environment have been identified from the operation of the Arrowhead
HVTL.
Rare and Unique Natural Resources
46.
The Natural Heritage and Non-game Research Program of the
Minnesota Department of Natural Resources (DNR-NHNRP) conducted a review of its
records to assess the potential impact of the Arrowhead Project on rare or
unique plant or animal species.
DNR-NHNRP indicated that seven known instances of such plants and
animals exist in the area, but not within 1,000 feet of the HVTL right of way.[105] These instances are four observations of
lake sturgeon, two observations of moschatel (a flowering plant) and one
observation of Carolina spring-beauty (a flowering plant).[106] The distance between the instances of these
species and the HVTL right of way is sufficient to prevent adverse impact on
those species. The Arrowhead Project is
not expected to adversely impact any rare or unique plant or animal species.
Application of Design Options
47.
MP has opted for single-pole construction for the Arrowhead
HVTL to minimize the right of way required.
A portion of the existing Arrowhead-Cloquet 115 kV power line (Line 22)
will be reconstructed to enable it to carry a 230 kV load. This reconstruction precludes the need to
undertake an additional approval proceeding in the event that this load is
needed to meet anticipated future demand for electricity. MP has examined design options to optimize
the efficiency and minimize the impact of the Arrowhead HVTL.
Existing Rights-of-way
48.
The siting considerations for transmission lines favor the
use of existing rights-of-way to minimize the impact of those lines on the
areas they traverse. The Arrowhead
Project uses the existing corridor for right of way. In the Midway segment, that right of way must be widened by
twenty feet over a 3.2 mile distance.
The land affected is primarily agricultural. The expansion of the existing right of way for that segment has
no significant impact.
49.
The other alteration to the right of way for the Arrowhead
Project moves the 0.8 miles of the existing route to the eastern side of the
DM&IR rail yard. The change is
proposed at the request of the landowner, the DM&IR railroad. The movement of the 0.8 mile length of right
of way does not result in significant human or environmental impact. Removing the existing 0.8 mile segment of
115 kV power line from its existing location is a benefit to persons living in
the eastern portion of Gary. The
Arrowhead Project uses existing rights-of-way to minimize the impact of
upgrading the existing 115 kV power line to a 345 kV HVTL.
Electrical System Reliability
50.
The Arrowhead Project will improve the electrical system
reliability for consumers in both Minnesota and Wisconsin. The existing system of distribution has only
one major source of electricity for western Wisconsin from Minnesota, the 345
kV King-Eau Claire-Arpin HVTL (K-EC-A HVTL).
The K-EC-A HVTL experienced a significant failure on June 25, 1998 that
adversely affected electricity consumers in both Wisconsin and Minnesota. Other situations have arisen over past few
years that could have resulted in failures similar to that on June 25,
1998. Adding a second 345 kV connection
to the Wisconsin transmission and distribution systems will reduce the likelihood
of such failures and improve the reliability of the electrical system for both
Minnesota and Wisconsin consumers.
Design and Route Dependent HTVL Costs
51.
There have been no costs identified for constructing,
operating, and maintaining the Arrowhead Project HVTL which are dependent on
design and route.
Unavoidable Adverse Human and Natural
Environmental Effects
52.
There have been no significant adverse human, natural and
environmental effects from the Arrowhead Project identified either at the
Arrowhead substation or along the HVTL route that are unavoidable consequences
of the construction of the Arrowhead project or operation of the 345 kV HVTL
that will be installed.
Mitigation of
Adverse Environmental Effects
53.
The proposed construction of the Arrowhead HVTL incorporates
several features to minimize potential adverse environmental effects[107]
associated with the construction and operation of the Project.
·
Right of way clearing will be limited to vegetation actually
affecting the safe operation of the HVTL.
MEQB Ex. 1, at 11. The only new
right of way clearing would occur along the 3.2 mile length of the Midway
segment and the 0.8 mile length of the Gary segment with relocated right of
way.
·
All construction debris will be removed from the right of
way. Grass and low-growing vegetation
will be "encouraged" to provide revegetation of construction
areas. MEQB Ex. 1, at 11. Silt will be prevented from entering surface
waters by installation of barriers and use of set back zones, where
appropriate.
·
Special consideration will be given where the right of way
crosses stream banks to ensure that erosion will be minimized and existing
shade retained to prevent changes in water temperature. MEQB Ex. 1, at 17. No in-stream work will be performed between September 15 and
April 30 to protect the four designated trout streams being crossed by the
right of way. Id.
·
The potential for damaging vegetation during installation
will be minimized by constructing the structures for carrying the HVTL during
the winter months, when the wetlands areas are frozen. When weather conditions have resulted in
insufficiently frozen ground, mats will be used to prevent damage.
·
Structures crossing open fields will be placed so as to
minimize maneuvering for farmers during haying.[108]
Cumulative
Present and Future Demands of the Project on Air and Water Resources
54.
The Arrowhead Project will not impose demands on air or
water resources.
Based on the
foregoing Findings of Fact, the Administrative Law Judge makes the
following:
CONCLUSIONS
1.
Any of the foregoing Findings more properly designated as
Conclusions are hereby adopted as such.
2.
The Administrative Law Judge and the Minnesota Environmental
Quality Board have jurisdiction over the subject matter of the hearing pursuant
to Minn. Stat. §§ 14.50 and 116C.06.
3.
All relevant substantive and procedural requirements of law
and rule have been fulfilled prerequisite to an application for exemption from
the Power Plant Siting Act.
4.
The proposed project
"will not create significant human or environmental impact" in
any of the categories of impact examined under the terms of Minn. Rule
4400.3310, except the noise impact noted at Finding 22. This impact can be eliminated by utilizing
the mitigation methods noted at Finding 24.
5.
The Applicant has demonstrated that the Arrowhead Project
meets the standards for exemption from the Minnesota Power Plant Siting Act
process in Minn. Stat. § 116.57, subd. 5.
Based upon the
foregoing Conclusions, of Law, the Administrative Law Judge makes the
following:
RECOMMENDATION
That
the MEQB grant the Applicant’s Application for exemption from the requirements
of the Minnesota Power Plant Siting Act (Minn. Stat. §§ 116C.51-.69) for the
construction of the 345 kV/115 kV and 345/230 kV High Voltage Transmission Line
(for one segment operated at 115 kV), and modifications to the Arrowhead
substation, known as the Arrowhead Project, subject to the condition that noise
impacts be reduced at the Arrowhead substation, and necessary permits be
obtained from the federal and state agencies and local units of government with
appropriate jurisdiction.
Dated this _29th_
day of January, 2001
/s/ Kenneth A.
Nickolai_ _____
KENNETH A.
NICKOLAI
Administrative Law Judge
Reported: Karen J. Macaulay, Citran, Duluth,
Minnesota
Transcript
prepared, Twelve Volumes.
NOTICE
Under Minn. Stat. § 14.62, subd.
1, the agency is required to serve its final decision upon each party and the
Administrative Law Judge by first class mail or as otherwise provided by law.
MEMORANDUM
Burden
of Proof
The parties dispute
the burden of proof. By applying for an
application for exemption from the PPSA, MP has the burden to demonstrate that
the exemption should be granted. MP's
burden is to present credible evidence that the proposal will not “have a
significant impact……” MP argues that
the burden is on the opponents to the application to demonstrate that a
significant impact exists. In advancing
this argument, MP relies on decisions made in cases arising under the Minnesota
Environmental Rights Act[109]. In PEER the Supreme Court explained
that under that act, "in order to make "a prima facie
showing" the plaintiff must prove the existence of a "(1) protectible
natural resource, and (2) pollution, impairment or destruction of that
resource."[110] However, this case is not a
citizen-initiated action under MERA, but a utility initiated request that a
project be exempted from the Power Plant Siting Act.
The
Administrative Law Judge concludes that MP met its burden of presenting
credible evidence that the proposal would not have a “significant human or
environmental impact….” The ALJ also
concludes that the opponents did not counter MP’s evidence and establish the
likelihood of significant human or environmental impact. As will be discussed later in this memo,
there is evidence that this project will or may have an impact on humans or the
environment. However, the ALJ was not
convinced that the potential impacts met the legal test for significance.
NAWO maintains
that the applicant for an exemption must prove there are no significant impacts
"beyond a reasonable doubt."
NAWO Brief, at 2. The law does
not impose that high an evidentiary standard to this administrative proceeding.[111] Minn. Rules 1405.1700, Subp. 7 provides,
"Any route or site proposer must prove the facts at issue by a
preponderance of the evidence…".
Regardless of
the burden of proof, NAWO correctly points out that Minn. Stat. § 116C.57,
subd. 5, states that the MEQB "may" exempt a proposed transmission
line from the certificate of need process.
The statute then gives the MEQB discretion to grant or deny an
exemption. The final agency decision will be made by the MEQB using the
following standard:
If
the board determines that the proposed HVTL will not have a significant human
or environmental impact, the board may exempt from the act with any appropriate
conditions the construction of the proposed facility within the proposed route.[112]
Significant
Human or Environmental Impact
Almost every action has some impact on
humans or on the environment. The issue
in this case is whether the identified impacts rise to the level of being
"significant" under the law.
NAWO, WOLF, and SOUL assert that MP failed to demonstrate that no
significant human or environmental impact will occur based on the application
of the "precautionary principle."
SOUL described the precautionary principle as follows:
When
an activity raises threats of harm to human health or the environment,
precautionary measures should be taken even if some cause and effect
relationships are not fully established scientifically.[113]
MP objected to
using the precautionary principle as requiring proof of "negative
facts."[114] To use the precautionary principle would, in
MP's opinion, replace the existing standard with "unsubstantiated or
speculative impacts."[115]
Minnesota law
does not recognize the precautionary principle as the standard for determining
a “significant impact.”[116] The term "significant" is an
important limitation in law. The ALJ
concludes that it requires a showing that a potential impact is serious and
material. It further is not merely
incidental and cannot be readily mitigated.[117] In this case, which is to determine whether
or not the MEQB should allow the exemption sought by MP, the determination of
significance must be made by looking to the difference between the
operation of the existing power line and the upgraded line proposed.[118]
Health
Effects
WOLF, SOUL,
and NAWO assert that MP failed to demonstrate that the Arrowhead Project will
not create significant human or environmental impact because MP has not proven
that 345 kV HVTL has no effect on human health. WOLF noted the conclusion of NIEHS that:
The
NIEHS concludes that ELF-EMF exposure cannot be recognized as entirely safe
because of weak scientific evidence that exposure may cause a leukemia hazard. [119]
WOLF also
relied upon the NIEHS conclusion that "[ELF-EMF is a] possible human
carcinogen."[120]
WOLF asserts
that MP has failed to account for the higher exposure to magnetic fields that
persons living along the Arrowhead Project route will experience due to the
increase in voltage from the existing 115 kV power line to the 345 kV
HVTL. Based on measurements made at a
345 kV HVTL between northern Wisconsin and Michigan's Upper Peninsula,[121]
the ambient EMF levels are 30 mG within one hundred feet of the right of way
centerline to one side and 80 mG within one hundred feet of the centerline on
the other side.[122] The difference is due to the 345 kV HVTL
being located off-center in the right of way.
There are higher estimates of increased EMF levels of 60 mG and 100 mG
at 100 feet from each side of the right of way centerline when the 345 kV HVTL
is operated at peak capacity.
In the case of
the Arrowhead HVTL, the nearest homes are within 300 feet of the route.[123] But the intensity of a magnetic field drops
exponentially with distance.[124] MP calculates that, during peak periods, the maximum exposure of persons in the
closest residence is 10 mG.[125] WOLF, SOUL, and NAWO have not shown that
persons in the homes nearest to the Arrowhead HVTL will be experiencing EMF
levels in excess the average exposure that is normally experienced by any user
of electricity and common household appliances. From the distances between the nearest homes and the Arrowhead
HVTL, those residents will not experience significantly higher (and perhaps not
even measurably higher) EMF levels. The average daily exposures of persons
studied in EMF-RAPID ranged from 28% of persons exceeding 10 mG (milligauss),
11% exceeding 20 mG, and 2% exceeding 50 mG.[126] The in-home averages were 8 mG while awake
and 5 mG while sleeping.[127]
The EMF-RAPID
study arrived at a conclusion regarding the risks posed by EMF and what
precautionary action should be taken.
That conclusion states:
The
NIEHS concludes that ELF-EMF exposure cannot be recognized as entirely safe
because of weak scientific evidence that exposure may pose a leukemia hazard.
In our opinion, this finding is insufficient to warrant aggressive regulatory
concern. However, because virtually
everyone in the United States uses electricity and therefore is routinely
exposed to ELF-EMF, passive regulatory action is warranted such as a continued
emphasis on educating both the public and the regulated community on means
aimed at reducing exposures. The NIEHS
does not believe that other cancers or non-cancer health outcomes provide
sufficient evidence of a risk to currently warrant concern.[128]
The
EMF-RAPID description of ELF-EMF as a "possible human carcinogen"
does not demonstrate that HVTL constitutes a substantial human impact.[129]
NAWO, SOUL, and
WOLF also asserted that MP failed to account for the impact of ground current
on human health. The transmission of electricity along HVTLs can create a
return current through the ground. This
phenomenon, known as ground current, passes electricity back along the ground
under the line to complete the electric circuit.[130] MP responded that there has never been any
showing of adverse health impacts from ground currents arising from HVTLs and
that no studies have been performed to show any such impact.[131]
Evidence of
the impact caused by "stray voltage" on humans and livestock was
introduced to support a claim of substantial impact caused by the Arrowhead
Project.[132] Stray voltage is caused by the grounding of
the distribution system to individual consumers. The Arrowhead substation and Arrowhead HVTL are designed without
the sort of grounding that can result in stray voltage.
There is no
evidence in the record from which to draw a conclusion that ground currents
have general impacts on human health or the environment. Stray voltage will not be caused by the
Arrowhead Project. There has been no
showing in this matter of an adverse human health impact that would trigger a
full-scale routing review under the PPSA.
Noise
MP asserted
that no significant increase in noise will arise from the proposed line or
modifications to the Arrowhead substation.
The mitigation originally proposed in MP's application for exemption was
withdrawn, due to the asserted lack of additional noise. MP cites the measurements conducted of the
noise levels around the Arrowhead Substation and conclusions drawn from a study
conducted to support this assertion and modification of the application.[133]
The study
relied upon by MP was designed and assessed by Dr. Hooshang Khosrovani of
Veneklasen Associates. An employee of
MP performed the measurements using equipment calibrated and provided by
Veneklasen Associates. Dr. Khosrovani
“performed noise calculations and analysis for estimating the expected noise
levels around the Arrowhead substation due to the operation of transformers and
impact of proposed additions.”[134] MP asserts that "the results of the
noise tests showed that in all instances, applicable Minnesota noise standards
will not be exceeded."[135] MP maintains that any increase in noise caused
by the upgrade will be "below the human ear’s ability to perceive any
meaningful difference."[136] MP also relies upon the presence of roadways
and truck traffic near the substation in concluding there will be no
substantial impact on nearby residents due to noise.[137] MP also cites the MPCA noise standards as
support for its proposal to modify the Arrowhead substation without conducting
any mitigation.
The MPCA has
set out "rules of thumb" to assess the impact of sound.[138] An increase of 3 dB reaches the level of
human perception.[139] An increase of 5 dB is described as
"quite noticeable."[140] When sound increases by 10 dB, the sound is
perceived as "twice as loud."[141] The Veneklasen study assessed sound levels
as perceived by persons at existing homes near the Arrowhead substation
operating with existing equipment. The
study used instruments to quantitatively measure the sounds near the Arrowhead
substation. In addition to the quantitative
measurements, subjective assessment of impact by ear of existing facilities was
noted by the person conducting the testing and shows audible noise as
"slightly, "noticeable," "somewhat loud," "very
noticeable," and "loud, but not obvious."[142] The measurements for some of the noise
impacts at adjacent homes were conducted when the DC converter station was out
of service.[143]
MP is adding
four transformers, using one as a back-up to the three that will be in
operation. The calculated noise level
that would occur with the addition of the transformers was based upon the
measurement of existing equipment. The
single transformers would emit 84 dBA at a distance of one meter. The phase shifting transformer emits 89 dBA
at that distance.[144] The EEI Electric Power Plant Environmental
Noise Guide methodology was used to determine the potential impact of the new
equipment on adjacent residents. Using
the EEI methodology, the conclusion derived in MP's study stated:
The
results of these calculations indicate a noise level of approximately 47 dBA,
due only to transformer contributions, may be expected at a distance of 2000
feet away. Any location at a distance
of less than 2000 feet will have a higher level of transformer noise impact.[145]
Due to the anticipated contribution to
the noise impact by the new equipment, the report commissioned by MP
recommended that noise reduction be accomplished by requiring that the three
300 MVA transformers being added as a result of the Arrowhead Project be
specified at "noise levels of 12 dBA below NEMA ratings for these
transformers (NEMA-12) in the procurement specifications."[146]
The evidence
is that noise from this equipment will be both perceptible and annoying.[147] MP pointed out that the existing noise was
within the MPCA standards for residential areas. MP asserted that the resulting noise from the Arrowhead Project
upgrade would fall within that limit and therefore no mitigation of noise
impacts is required. MP claimed that
there would be no perceptible increase in sound at the property line of the
Arrowhead substation caused by the new equipment.[148]
That assertion is contradicted by the
report and is not supported by facts in the record. The author of the study was
unaware of the distance between the Arrowhead substation and the location of
either the monitoring equipment or the adjacent homes.[149] The nearest houses to the Arrowhead
substation are well within 2000 feet.[150] MP cannot rely upon a calculation of a noise
impact on a location beyond the actual person hearing the sound to establish
that there will be no substantial impact on that person.
MP also relies
upon the MPCA standards as establishing the standard to be met in obtaining the
exemption in this proceeding without conducting mitigation. The appropriate test for obtaining an
exemption is not whether the MPCA noise limit is met. Rather, the test is whether a substantial impact will be caused
by the new equipment. MP has failed to
meet its burden to demonstrate that there will be no substantial impact on
nearby residents without the inclusion of some noise mitigation at the
Arrowhead substation. This noise
mitigation can be accomplished by purchasing transformers that emit less
noise. Noise mitigation may be
accomplished by installing sound barriers that will reduce the overall noise
impact of the Arrowhead substation. The
reduction methods will reduce the noise created by the project to eliminate any
substantial impact.
Land
Valuation
WOLF asserts
that MP's failure to prepare appraisals results in a failure of proof that the
Arrowhead Project will not have significant impact on land values. WOLF, however, relies on the eminent domain
provision of the PPSA as the basis for this claim. This proceeding is to determine if the Arrowhead Project is to be
exempted from the requirements of the PPSA.
The standards to be met in applying for an exemption are clearly set
out. Impact on land valuation is not,
by itself, a consideration in determining whether an exemption is
appropriate. Land valuation can be
included to the extent that it affects other listed considerations. In this matter, there is no evidence that
market values will be measurably affected by replacing a 115 kV power line with
a 345 kV HVTL. The homes that were part
of the market survey conducted by MP were on the market for an average of 110
days, which is above the market average.
There is no evidence that size of the power line will further increase
that average. There is no evidence that
market values for land, even if altered, will affect human settlement or land
economies.
Mining
Operations
An aggregate
quarry and an asphalt facility are located on the Beck's Road segment.[151] MP maintains that the Arrowhead HVTL will
not impair the functioning of either operation.[152] WOLF maintains that MP used the wrong
standard in assessing the impact on mining operations. According to WOLF, the potential impact of
particulate matter interacting with the corona of the HVTL is key. That
potential impact was addressed as a consideration regarding health affects and
it was determined to not have the potential for significant impact.[153] There is no evidence of substantial impact
on land-based economies arising from the location of the Arrowhead HVTL.
Eminent
Domain
MP intends to
seek additional easements to widen the right of way in the initial 3.2 miles of
the corridor. MP has indicated that it will
seek to negotiate with landowners for easements. But MP will use eminent domain to obtain those easements if
mutually agreeable terms cannot be reached.
WOLF asserts that only if the full routing provisions of the PPSA are
applied will landowners have their property interests protected. Further, WOLF asserts that eminent domain is
only available to MP if the Arrowhead Project has been subjected to the
Certificate of Need process and the demonstration of need made. In this matter, only the impacts on human
settlement that result in significant human impact are to be considered. There has been no showing that the potential
application of eminent domain will result in such impact. WOLF's assertion that eminent domain is not
available without a finding of need cannot be addressed in this
proceeding. That dispute is properly
brought before the District Court in the event that such a proceeding arises.
Historic
Resources
A bridge
(Historic Bridge No. L-6007, hereinafter "Stewart Creek Bridge") on
Skyline Parkway is identified by WOLF as a historic resource affected by the
Arrowhead HVTL.[154] The Oliver Bridge over the St. Louis River
is also identified as a "unique bridge." These resources are cited as being substantially affected by the
Arrowhead HVTL. The automobile traffic
over the Oliver Bridge passes on the deck beneath railroad tracks. Visibility is significantly impaired from
the automobile level of the Oliver Bridge.[155] The current power line at the Oliver Bridge
crossing is visible from the approaches.
REL-8. No one has described any
meaningful aesthetic difference affecting these resources between seeing the
proposed single pole structures and seeing the existing H-pole structures.
WOLF maintains
that the Arrowhead HVTL affects the Stewart Creek Bridge on Skyline
Parkway. There is no testimony in the
record of where that bridge is in relation to the proposed Arrowhead HVTL. There is no testimony to support a finding
that the proposed HVTL will be visible from that bridge. Based on a topological map of the area, the
Stewart Creek Bridge is located approximately 1.5 miles from the nearest point
along the Arrowhead HVTL route.[156] The topography surrounding that location
strongly suggests that the Arrowhead HVTL will not be visible from the Stewart
Creek Bridge.[157] The record is insufficient to demonstrate
that the Arrowhead Project will have a significant impact on historic
resources.
Recreational
Resources
The impact on
recreational resources caused by the Arrowhead HVTL is limited to the change in
visibility of the power line. In some
areas, the switch to a single pole design will reduce the intrusiveness of the
power line because of its smaller footprint.
The much taller poles will, however, be more visible from viewpoints at
several recreational areas. The parties
differed on how much impact this additional visibility would have on people
using the recreational resources in the vicinity of the Arrowhead HVTL.
One example of
an affected viewshed is the overlook portion of Skyline Drive. From this vantage point, one can observe
much of the Beck's Road segment and the entirety of the Gary segment.[158] The Skyline Drive area overlooking the
Arrowhead route is both passable by automobile and frequently used.[159] The views from Short Line Park and the western
end of Magney Park are substantially similar to that of the Skyline Drive
overlook. The viewshed of the
easternmost end of Magney Park contains all of the Gary segment and St. Louis
River running north to the waterfront area of the City of Duluth.
WOLF
demonstrated that the Arrowhead HVTL will be visible from the road access point
to the Willard Munger Trail.[160] No evidence was introduced to support a
finding of substantial impact from the Willard Munger Trail itself since the
difference is the height and footprint of the pole, not its existence. Similar problems exist with the claims of
substantial impact from the scenic views overlooking the Beck's Road and Gary
segments. The views afforded to
individuals from these points are not just of a power line, but also of an area
dedicated to industrial uses. Railway
lines, rail yards, a 115 kV power line, an electrical substation, quarries,
factories, and docks are all visible from the vantage points above the proposed
Arrowhead HVTL. The ALJ concludes that
the overall visual impact of the proposed Arrowhead HVTL will be
indistinguishable from the existing uses along the route.
Electrical
System Reliability
Reliability is
defined by NERC as adequacy and security.[161] Adequacy is the ability of the electrical
system to supply the demands of customers, including during periods of
outages. Security refers to the ability
of the system to withstand disturbances through short circuits (tripping) or
unanticipated loss of generation or transmission capacity. There is no meaningful difference between
system loading that occurs due to consumer demand and system loading occurring
due to environmental disruption. A
failure on one portion of the electrical transmission grid can cause power
disruptions in other areas. A primary
reason cited by MP for upgrading the existing 115 kV power line to a 345 kV
HVTL is to improve the reliability of the existing electrical transmission
system. The Department of Commerce
indicated that the existing connection between the Mid-Continent Area Power
Pool (MAPP) and the Mid-American Interconnected Network (MAIN) is supported
only by the K-EC-A 345 kV HVTL and this sole connection has resulted in
reliability problems.
A disturbance
in the regular transmission of electricity between MAPP and MAIN occurred on
June 10-11, 1997 (hereinafter "the 1997 disturbance").[162] On June 10, 1997 the K-EC-A line was
operating at 945 MW (which would ordinarily result in action being taken), but
the load dropped to 850 MW, so no relief was requested. Shortly thereafter, the southern
interconnection (known as "SPP") with MAIN showed signs of
overloading. Shortly after midnight,
the K-EC-A line tripped and the resulting power flows were far over the SPP's operating
limits for its lines. The overload
condition existed until approximately 1:30 a.m. on June 11, 1997.[163] The conclusion reached after the 1997
disturbance was that a significant risk of a regional blackout existed and such
a blackout had been narrowly averted.[164]
The K-EC-A
HVTL failed on June 25, 1998 (”1998 service interruption"). The 1998 service interruption occurred
during a thunderstorm that tripped both the Prairie Island-Byron 345 kV HVTL
and the K-EC-A HVTL. "Cascade
tripping" then ensued, causing more than 60 transmission lines (ranging
from 345 kV to 69 kV) to fail. The
resulting disruption of power delivery adversely affected electricity consumers
in both Wisconsin and Minnesota. A
significant risk of electrical blackout throughout Minnesota was avoided only
when some of the lower voltage lines automatically reclosed and held.
Another
disturbance in the regular transmission of electricity between MAPP and MAIN
occurred on June 10, 1999 (hereinafter "the 1999 disturbance").[165] The 1999 disturbance was the result of
system loading on the K-EC-A line. The
system was considered to be "insecure" for several hours. An additional element of risk to the
delivery of electricity was posed at that time due to the presence of
thunderstorms in the area.
The 1998
service interruption and the system disturbances in 1997 and 1999 were cited by
both MP and Commerce as demonstrating the need for an additional 345 kV
connection between MAPP and MAIN. MP
maintains that the proposed Arrowhead project will improve the performance of
the electrical grid between Minnesota and Wisconsin. On the other hand, WOLF asserted that:
The
transmission crisis is a crisis of the utilities' making through their
"increased market transactions" in their desire to move all the power
they can sell, overloading lines for bulk transfer and putting local loads and
the grid in jeopardy.[166]
With these arguments, NAWO, SOUL, and
WOLF argue that the purchase and sale of bulk power should be examined
separately from the existing transmission system. Under this approach, increases in market demand would not be
included in the assessment of system security.
Thus, a project proposed to meet market demands on a system would not
qualify as being needed to improve system security. The ALJ concludes this is not the correct standard since either
demand or an incident can affect system reliability and security.
NAWO also
asserts that the Arrowhead project is dependent upon all of the associated
projects being completed [167]
and it is no longer necessary. NAWO
quotes the WRAO[168]
Executive Summary:
In
order to achieve the benefits which construction of plan 3j would provide, it
must be constructed in its entirety.
For all the plans presented, several significant additions of upgrades
to the underlying transmission system are required. Notably, the Chisago-Apple River 230 kV project presently under
regulatory review in Wisconsin and Minnesota is considered a critical
requirement for all of the plans (except plan 5a, Chisago-Weston 345 kV). The Chisago-Apple River project is an
integral system reinforcement and is also critical for local load serving. If transmission plan 3j ultimately is not
constructed in its entirety, the WRAO has identified transmission plan 5b
(Apple River-Weston 230 kV) as an alternative.[169]
NAWO urges
that "administrative notice" be taken that Brief the Chisago-Apple
River 230 kV project has been withdrawn.[170] The activity listed as "associated
projects and upgrades" in the WIRES[171]
Phase II Report for Plan 3j does not include the Chisago-Apple River 230 kV
project.[172] The language cited by NAWO from the
Executive Summary describes the withdrawn Chisago-Apple River project as
"an integral system reinforcement and is also critical for local load
serving." This language, without
more, does not support a conclusion that the absence of the Chisago-Apple River
230 kV project will eliminate the benefits of the Arrowhead project.
MP has
demonstrated that the Arrowhead project will result in improvements in adequacy
and security and benefit electric consumers in both MAPP (including Minnesota)
and MAIN.
Relationship
to Other Projects
NAWO, SOUL,
and WOLF maintain that MP cannot obtain an exemption in this matter because the
Arrowhead Project is part of a connected action or phased upgrade of other
facilities to provide the electricity that will be transmitted to Wisconsin,
and that, when taken together, these actions will require a Certificate of Need
from the Minnesota Public Utilities Commission.
Minn. Rule
4410.0200, subd. 9b defines "connected actions" and subd. 60 defines
"phased action." Both of
these rules set out the standards for determining if different projects must be
combined to determine the appropriate scope of review. NAWO, SOUL, and WOLF
asserted that an exemption to the PPSA process cannot be granted since the
Arrowhead Project cannot be completed without also completing associated
projects that would trigger the Certificate of Need review process.[173] These associated projects are asserted to be
the Hilltop upgrade, modifications to the Forbes HVTL, and the Blackberry HVTL.
There is no evidence indicating that
any upgrades to the Forbes HVTL or the Blackberry HVTL are being undertaken by
MP.
A portion of
the Arrowhead Project upgrades a 3.2 mile portion of the existing 115 kV power
line (Line 22) to the capacity for operation at 230 kV. MP intends to continue operating Line 22,
now running from the Arrowhead substation to the Cloquet substation, at 115
kV. Additional upgrades are required
before MP will be able to operate Line 22 at 230 kV and reconfigure the
connection to transmit electricity to the Hilltop substation.[174].
No time frame
has been established for performing the additional upgrades to Line 22 and the
eastern portion of Line 70 to operate that line at 230 kV.
NAWO, SOUL,
and WOLF maintain that the upgrade of Line 22 demonstrates that the Arrowhead
Project is a phased upgrade, and thus the distance between the Arrowhead and
Hilltop substations must be added to the length of the HVTL. Minn. Rule 4400.1310, subp. 1.G., requires
that utilities include planning for additional upgrades along existing rights
of way whenever a project is planned.
Excluding projects for complying with the rule for prior planning is not
consistent with the statutorily-authorized exemption process. There is no evidence to establish that a timetable
exists to complete a 230 kV HVTL between the Arrowhead and Hilltop substations.
In the course
of planning the Arrowhead Project, the potential for finishing a 230 kV HVTL
between the Arrowhead and Hilltop substations became apparent.[175] The need for a 230 kV HVTL is not
anticipated in the Hilltop substation service area before 2005 to 2010.[176] This does not constitute either a phased
action or connected action.
The Arrowhead
Project is essentially identified in the WIRES Study as the Minnesota portion
of Plan 3j. Plan 3j has a number of
"associated projects and upgrades" identified as needed to complete
Plan 3j. The activity listed as
"associated projects and upgrades" in the WIRES Phase II Report all
occurs in Wisconsin.[177] These "associated projects and
upgrades" are not part of the Arrowhead Project and do not constitute
phased or connected actions.
The only
changes required to substations other than Arrowhead and Gary are upgrading
software to accommodate the relaying needs of the altered system.[178] These changes do not preclude MP from
obtaining an exemption from the PPSA on that basis.
Environmental
Effects from Coal-fired Generation
NAWO and the
National Wildlife Federation (NWF) introduced substantial evidence that
coal-fired electricity generation (such as that conducted in North Dakota)
causes pollutants, including mercury, to be emitted into the atmosphere.[179] Once in the atmosphere, mercury is deposited
into bodies of water, where it collects.[180] Once in these bodies of water, mercury is
absorbed by fish and from there to aquatic animals and humans.[181] Mercury contamination poses both an adverse
environmental effect and an adverse public health impact.[182]
MP maintained
that the Arrowhead Project would result in the reduction of mercury emissions
from existing coal-fired generating plants.[183] This estimate was based on computer-modeling
performed by a consultant indicating that completion of the Arrowhead project
would reduce line losses.[184] SOUL introduced an assessment of the
computer-modeling performed that identified limitations of with this analysis.[185] A number of the concerns were conceptual in
nature, addressing the potential for long-term changes in the electricity
generation mix that might result from the Arrowhead Project.[186]
One specific concern
raised by SOUL was the critical dependence on the data used to generate its
model.[187] Under cross-examination, MP's witness on the
computer model was unable to respond to questions regarding the specific data
relied upon for the computer model.[188] Some of the data initially provided by MP
had been incorrectly used.[189] Some of the data used in the modeling
appears to have been of the "best guess" variety.[190] The data run of the information was not
retained or produced to support the conclusions reached.[191]
If the data input into the model cannot
be verified, the model's conclusions cannot be relied upon.[192]
The reduction
in mercury asserted by MP is predicated on the need to burn less coal since
less electricity is lost in transmission.
MP does not appear to have considered the possibility that reducing line
losses will result in the current production of electricity being maintained
and more of the electricity produced reaching consumers.[193] The record in this proceeding indicates that
demand for electricity is increasing.[194] MP relies upon an assertion, unsupported by
the record, that the increased generating needs will be met with natural
gas-fired generation.[195] The evidence indicates that a reduction of
line losses accomplished by the Arrowhead Project will most likely result in
more electricity being purchased, not less coal burned to produce
electricity. Such an outcome would not
reduce mercury emissions. MP's evidence
does not support a finding that mercury emissions will be reduced as a result
of the Arrowhead Project.
While the
evidence is insufficient to show mercury reduction, MP is not required to
demonstrate that mercury emissions will be reduced. There is no evidence in this record that mercury deposition will
increase in Minnesota from construction of the proposed project. Absent an increase in mercury deposition,
the Arrowhead Project does not result in significant impact on the environment
through deposition of that pollutant.
Potential
for Inducing New Generation Sources
MP asserted
that no additional lignite coal-fired electricity generation from North Dakota
is likely to be caused by the Arrowhead Project.[196] This assertion is based upon the fact that
current coal-fired generators are operating at near full capacity.[197] NAWO, SOUL, and WOLF dispute claims
regarding that capacity.
The existing
coal-fired generators are operating at between 76% and 82% of their rated
capacities.[198] The trend over the last ten years is for
those generators to operate at slightly higher percentages of their rated capacity.[199] The increase is attributable to efficiencies
developed over time to enable these generators to operate with less
"down-time" for maintenance and repairs.[200] These plants are among the lowest cost
producers of electricity available to utilities such as MP.[201] For this reason, there has always been an
incentive for these producers to operate at the maximum possible capacity. This incentive exists whether or not the
Arrowhead Project is built. The current
operating percentages are unlikely to be changed due to the Arrowhead Project.
While marginal
efficiencies in electric transmission are likely to result from the additional
transmission capacity afforded by the Arrowhead Project, the potential for the
construction of new baseline generation always exists.[202]
There is no evidence in the record to indicate that new coal-fired generation
has been proposed or is sufficiently far into the approval process to conclude
that the Arrowhead Project is connected to, or a phase of, some additional
project that would include new electricity generation.
Conclusion
MP has
demonstrated by a preponderance of the evidence that, with one exception, the
Arrowhead Project will not create significant human or environmental impact, as
set out in Minn. Stat. § 116C.57, subd. 5.
The sole exception is the impact caused by noise generated at the
Arrowhead substation by the new transformers to be installed. The impact of that noise can be mitigated by
the use of sound barriers, the installation of quieter transformers, or the use
of both. With noise mitigation, the
Arrowhead Project will have no significant impact and the MEQB may grant the
requested exemption from the Minnesota Power Plant Siting Act.
K.A.N.
[1] Because of a
scheduling conflict, the final day of hearing was held in the basement of the
Forbes First Methodist Church,
Proctor, Minnesota
[2] Tr. at 1688.
[3] MEQB Exhibit
1, at 19
[4] MEQB Exhibit 1.
[5] MEQB Exhibit 8.
[6] Tr. at 1619.
[7] The
substation location is further identified as T50N, R15N, Section 31. MEQB Exhibit 1 at 1.
[8] Tr. at 1615.
[9] Tr. at
1616. The twelve lines are as follows:
to the south, one 230kV and five 115 kV circuits; to the north, three 115kV
circuits and two 230 kV circuits; and to the west, one 250 kV DC line.
[10] MEQB Exhibit
1.
[11] Line 22 turns and heads west to connect with
MP's Cloquet substation. Line 70 turns
east and connects to MP's Hibbard substation.
A portion of Line 70 was rebuilt to 230 kV standards in 1992. MEQB Exhibit 11.
[12] The proposed right of way travels south on
the eastern side of the DM&IR railroad tracks and connects to MP's Gary
substation.
[13] The proposed
line would be 345/230kV for the initial 3.2 miles. The remainder would be 345/115kV.
[14] MEQB Exhibit
1; at 1 and 10; Tr. at 1527-9.
[15] MEQB Exhibit
11, Attachment 28.
[16] Id.
[17] Tr. at 1619.
[18] Tr. at 1623.
[19] MEQB Exhibit
1, at 1.
[20] MEQB Exhibit
1, at 1.
[21] See
REL-17 and REL-18
[22] That power
line is designated as Line 22, which is the line currently running from the
Arrowhead substation to the Cloquet substation.
[23] MEQB Exhibit 1, at 1.
[24] See
REL-18 and REL-19; MEQB Exhibit 1, at 2.
[25] REL-19
[26] MEQB Ex. 1,
at 2.
[27] Tr. at 1450.
[28] MEQB Exhibit
1, at 10, Public Hearing Transcript, at 165.
[29] Tr. at
1452-3.
[30] MEQB Ex. 14
[31] Tr. at 1542
and 1553
[32] MEQB Exhibit
1, Appendix E.
[33] Tr. at 1567.
[34] Tr. at 1556
[35] MEQB Exhibit 1, at 18.
[36] Id.
[37] Minn. Stat. §
116C.57, subd. 5. Should the MEQB
exercise its discretion and deny the exemption, Minn. Rules 4400.3900, provide:
"If the board denies an HVTL exemption, it shall indicate the reason and
indicate the project changes necessary for approval."
[38]
Those impacts are:
A.
effects on human settlement, including but not limited to, displacement, noise,
aesthetics, cultural values, recreation, and public services;
B.
effects on public health and safety;
C.
effects on land-based economies, including but not limited to, agriculture,
forestry, tourism, and mining;
D.
archaeological and historic resources;
E.
effects on the natural environment;
F.
rare and unique natural resources;
G.
application of design options which maximize energy efficiencies, mitigate
adverse environmental effects, and could accommodate expansion of transmission
capacity;
H.
use or paralleling of existing rights-of-way, survey lines, natural division
lines, and agricultural field boundaries;
I.
electrical system reliability;
J.
costs of constructing, operating, and maintaining the HVTL which are dependent
on design and route; and
K.
adverse human and natural environmental effects which cannot be avoided.
[39] MEQB Exhibit
1 at 12.
[40] Tr. at
312. In its application, MP identified
11 residences as being within 300 feet of the centerline of the route. MEQB Exhibit 1, at 12. MP reduced that number at the time of
hearing.
[41] Tr. at
313-4. A homeowner indicated that
"From the edge of the existing power line to the middle of our home is 117
feet. Our garage/workshop is 50 feet
from the line." Peters Comment, at
2. These distances appear to be from
the edge of the existing right of way.
This residence appears to be located south of the Midway segment and the
right of way is not proposed for widening at the homeowner's location. REL-2.
[42] REL-2.
[43] WOLF Exhibit
1, at 37-8. However, NIEHS has
suggested "that the power industry continue its current practice of siting
power lines to reduce exposures and continue to explore ways to reduce the
creation of magnetic fields around transmission and distribution lines without
creating new hazards." Id.
at 38.
[44] MEQB Exhibit
11, Attachment 16.
[45] In its
application, MP concluded that that noise impact would not be increased
provided low noise transformers or other sound reduction methods were
used. During the hearing, MP indicated
it had concluded that noise reduction was not necessary. Tr. at 1234.
[46] MP Exhibit
17, DLV-13. The number indicates the
percentage of time the measured noise exceeds the indicated level. Thus, L(90) means the indicated noise level
is exceeded ninety percent of the time.
[47] Id.
[48] Id.
[49] MP Exhibit
18, at 20; Minn. Rule 7030.0040, subp. 2.
[50] MP Exhibit 2,
at 8.
[51] MP Exhibit 2,
at 8.
[52] MP Exhibit 2,
at 7.
[53] MP Exhibit 2,
at 7.
[54] MP Exhibit
17, DLV-11.
[55] WOLF Exhibit 3, Appendix, Results of Long Term
Measurements.
[56] WOLF Exhibit 3, at 4.2 ("Any location at a distance of less than 2000 feet will have a higher level of transformer noise impact."); MP Exhibit 18, at 6.
[57] MP Exhibit
18, at 9.
[58] WOLF Exhibit
3, at 6.0-7.0.
[59] Tr. at 138.
[60] Tr. at
137.
[61] MEQB Exhibit
1; Appendix F, Bloomberg Letter dated June 10, 1999.
[62] [62]
There are also single pole wood supports on the existing line. MEQB Exhibit 1
at 12.
[63] Tr. at 1569.
[64] Tr. at
1565-66. The record is not clear,
however, on what approach will be taken at angled locations. Testimony at the hearing indicted that
single-pole structures would be used.
Tr. at 1552 and 1572. MP has
earlier indicated that alternatives such as lattice structures, self-supporting
monopoles, and self-supporting twin monopoles (each supporting a separate
circuit) could be used at such locations.
MEQB Exhibit 11, at 4.
[65] Tr. at 1569.
[66] MEQB Exhibit
1 at 12.
[67] Tr. at 1571.
[68] Tr. at 1572.
[69] REL-18.
[70] REL-2; REL-3.
[71] MEQB Exhibit 1, Figure 5.
[72] Tr. at 882.
[73] Tr. at 323.
[74] MEQB Exhibit 1, Figure 5.
[75] Id.
[76] Tr. at 882.
[77] MEQB Exhibit 1, Figures 5 and 6.
[78] Tr. at 896-97.
[79] Tr. at 259.
[80] Tr. at 257 and 291.
[81] REL-3.
[82] REL-3.
[83] REL-3.
[84] REL-2.
[85] REL-2.
[86] REL-2.
[87] MEQB Exhibit
1, at 14.
[88] MEQB Exhibit 1, at 14.
[89] MEQB Exhibit
1 at 14.
[90] MEQB Exhibit
1 at 15.
[91] MP Exhibit
17; DLV-1, Sheets 1-6.
[92] Id.
[93] MP Exhibit
-17; DLV-4, Sheets 1-6.
[94] By way of
comparison, an electric stove emits an EMF field of 21.6 mG at distance of one
foot. A person making a photocopy is
exposed to an EMF field of 31 mG.
MP-17; DLV-6.
[95] MP Exhibit
17, at 6.
[96] Minn. Stat. §
116C.57, subd. 4(1).
[97] WOLF Exhibit
1, EMF-RAPID, at 10. MP Ex. 1 at 8.
[98] NAWO Exhibit 1.
[99] Tr. at 77-78.
[100] Ringstad
Comment, Electrical and Biological
Effects of Transmission Lines: A Review , at 1-19 (Public Comments).
[101] Tr. at 2291.
[102] Tr. at 2292.
[103] MP Exhibit 6,
at 38; Tr. at 491.
[104] Tr. 283-84,
and 1631.
[105] MEQB Exhibit 1; Appendix D, DNR-NHNRP Letter dated June 21, 1999.
[106] Id.
[107] MP withdrew its original proposal to lower noise levels by specifying quieter transformers. Tr. at 1417.
[108] Tr., at 889.
[109] Minn. Stat. §
116B.03
[110] People
for Environmental Enlightenment & Responsibility (PEER), Inc. v. Minnesota
Environmental Quality Council, 266 N.W.2d 858, at 867 (Minn. 1978).
[111] In the
Matter of the Quantification of Environmental Costs, 578 N.W.2d 794,
801 (Minn. App. 1998), rev. denied (Minn. Aug. 18, 1998)("…the
commission's determination that parties must present a preponderance on the
evidence is consistent with established contested case procedure.").
[112] Minn. Rule 4400.3900, subp. 7.
[113] SOUL Ex. 2, at 25.
[114] MP Brief, at 17.
[115] MP Brief, at 17.
[116] State
by Schaller v. County of Blue Earth, 563 N.W. 2d 260, 265 (1997)
[117] Iron Rangers for Responsible Ridge Action v. Iron
Range Resources, 531 N.W.2d 874,
881 (Minn.App. 1995)(citing Audubon Soc'y v. Dailey, 977 F.2d
428, 435-36 (8th Cir.1992) for the proposition that "agency may base
determination of no significant impact on fact that mitigation measures keep
the impacts below significant level.").
[118] The issue of
whether power lines themselves create a significant human or environmental
impact is not properly before the ALJ.
There is a power line currently operating in the corridor. The only question is whether the proposal so
changes conditions as to create a significant human or environmental impact
that does not now exist.
[119] WOLF Exhibit 1, EMF-RAPID, at iii.
[120] WOLF Exhibit 1, EMF-RAPID, at 35. NIEHS suggests that the electric industry maintain its current practice of siting power lines to reduce exposures. At 38.
[121] Tr. at 1455.
[122] MP Exhibit 17, DLV-4.
[123] SOUL Brief, at 3; Tr. at 255.
[124] MP-17, at 5.
[125] MP Brief, at 20.
[126] WOLF Brief, at 24.
[127] WOLF Brief, at 24.
[128] WOLF Exhibit 1, at iii.
[129] Under the classification scheme used by the NIEHS group in the EMF-RAPID study, there are only two categories for substances studied for carcinogenic effects. A substance is a known carcinogen when the causal link between the substance and a health effect is demonstrated. All other substances are "possible carcinogens."
[130] Tr. at 456-57.
[131] MP Brief, at 22.
[132] SOUL Exhibits 1 and 2.
[133] MP Brief, at 35.
[134] MP Exhibit 2, at 3.
[135] MP Brief at 35.
[136] MP Reply Brief at 19.
[137] Tr. at 132.
[138] MP-18, at 17.
[139] Id.
[140] Id.
[141] Id.
[142] WOLF-3, Attachment on Meter Locations.
[143] Id.
[144] Khosrovani Direct, at 3.
[145] WOLF-3, at 4.2.
[146] WOLF-3, at 7.0.
[147] Tr. at 131.
[148] Tr. at 144.
[149] Tr. 1, at 128.
[150] DLV-11; Tr. at 1404-5.
[151] REL-13, REL-18.
[152] MP Reply Brief, at 22.
[153] See Finding 41.
[154] WOLF Exhibit 8.
[155] WOLF Exhibits 5 and 6.
[156] REL-19.
[157] REL-19.
[158] NAWO Exhibit 4.
[159] NAWO Exhibit 4; MP-14.
[160] WOLF Exhibit 4.
[161] DOC Exhibit 4, at 9.
[162] MP Exhibit 27.
[163] Id.
[164] MP Exhibit 27, at 2.
[165] MP Exhibit 1, at 6.
[166] WOLF Brief, at 46.
[167] The Arrowhead
Project is essentially identified in the WIRES Study as Plan 3j. Plan 3j has a number of "associated
projects and upgrades" identified as needed to complete Plan 3j.
[168]
WRAO is
the Wisconsin Reliability Assessment Organization, a group formed of the MAPP
and MAIN reliability councils, utilities in those regions, and interested
regulatory agencies acting as ex officio
members. DOC Exhibit 3, at 1.
[169] MEQB Exhibit 1, Appendix F, Executive Summary of the WRAO Report.
[170] NAWO Brief, at 25.
[171]
WIRES is
the Wisconsin Interface Reliability Enhancement Study, a report to the WRAO.
[172] DOC-3, WIRES Phase II Report, Appendix C1-3.
[173]
A
certificate of need is required if the project is a "large energy
facility." Minn. Stat. § 216B.243,
subd. 2. "Large energy facility" for power lines is defined as:
(2) any high voltage transmission line with a capacity of
200 kilovolts or more and with more than 50 miles of its length in Minnesota;
or, any high voltage transmission line with a capacity of 300 kilovolts or more
with more than 25 miles of its length in Minnesota . . . Minn. Stat. § 216B.2421, subd. 2(2).
[174] MEQB Ex. 11, Attachment 28.
[175] MEQB Exhibit 11, Attachment 28.
[176] Id.
[177] DOC Exhibit 3, WIRES Phase II Report, Appendix C1-3.
[178] Tr. at 1622.
[179] NAWO Exhibit 26; NWF Public Exhibit, Attachment 10.
[180] NAWO Exhibits 13-16, 18 and 19; NWF Public Exhibit, Attachment 3.
[181] NWF Public Exhibit, Attachments 1 and 2.
[182] NAWO Exhibits 13-16, 18 and 19; NWF Public Exhibit, Attachments 1, 4 and 12.
[183] MP Brief, at 29.
[184] MP Exhibit 3.
[185] SOUL Exhibit 3.
[186] SOUL Exhibit 3, at 7.
[187] SOUL Exhibit 3, at 8.
[188] Tr. at 164.
[189] Tr. at 1837.
[190] Tr. at 1988-89, 1992-93.
[191] Tr. at 192.
[192] Tr. at 1943-45.
[193] Tr. at 2085.
[194] MP Exhibit 3,
at 6 (estimating the increase in demand in MAPP over the next 10 years at 8,000
megawatts).
[195] MP Exhibit 3,
at 7.
[196] MP Exhibit 30; MP Brief, at 27.
[197] MP Brief, at 27.
[198] Tr. at 161.
[199] MP Exhibit 30.
[200] Tr. at 210-12.
[201] Tr. at 189-90.
[202] The Pimickikamak Cree Nation raised
objections to the Arrowhead project, asserting that improving the capacity of
electricity transmission into northern Wisconsin would cause Manitoba Hydro to
increase its hydroelectric generation capacity. To do so, Manitoba Hydro would need to inundate more of the
Nelson River Watershed. Public Hearing
Tr., at 17. The Tataskweyak Cree
Nation indicated that any increase in the generating capacity from the Nelson
River Watershed would be controlled by the Northern Flood Agreement. Public Hearing Tr., at 20. Environmental review would be conducted as
part of that process. Id. at 21. The MEQB has expressly
addressed the limits to the issues that are to be considered in this
proceeding. In its Scope Order, the
MEQB stated:
IT IS HEREBY
ORDERED, ... that the hearing be limited to impacts from construction or
operation of the project facility on human health and the environment
experienced in Minnesota. MEQB Ex. 7,
at 8.
The
environmental and human impacts of expanded hydroelectric generation would not
be experienced in Minnesota. Under the
Scope Order, evidence of those impacts must not be considered in determining
whether the Arrowhead project qualifies for an exemption from the routing
process in the PPSA.