EQB Exemption Application Arrowhead Transmission Line
Information
ALJ Recommendation Issued
Judge Nickolai has issued his Recommendation in this matter. Please note that the document is large and your download time may vary. A copy of the Recommendation has been faxed to the parties and the Recommendation will be mailed on January 30.
One copy of the transcript is available for review at the EQB offices. Arrange to use the transcript by contacting:
Suzanne Steinhauer
Public Advisor
Room 300
Centennial Building
658 Cedar Street
St. Paul, MN 55155
651/296-2878 (phone)
651/296-3698 (fax)
Suzanne.Steinhauer@mnplan.state.mn.us
General Information
Minnesota Power has applied for an exemption under Minn. Rule 4400.3900 from the Power Plant Siting Act as relating to the planned rebuilding of its electrical transmission line from the Arrowhead Substation to the St. Louis River, near Gary, Minnesota.
The current transmission line is 115 kV. The proposed construction would convert the 12-mile section of line in Minnesota to a double circuit 115-345 kV line. The purpose of this proceeding is to determine whether the project will create significant human and environmental effects and whether the project is eligible for exemption from the Plant Siting Act.
Notice
Due to the prohibition against ex parte contacts in utility matters, Judge Nickolai cannot accept e-mails from members of the public regarding this matter. A public comment period will be scheduled as part of this proceeding. The dates of that comment period and methods for participation will be posted on this site.
Check back here periodically for details.
Addresses and Fax Numbers of Parties and Intervenors
Documents
August 11, 2000 Notice
Posthearing Briefs
Those parties who have submitted their briefs in electronic format have those briefs posted
here. The remaining documents have been scanned and are posted here in PDF format. Please note
that the document size limit was fifty pages and several of these documents are large and will require some time to download.
Department of Commerce Brief Minnesota Power Brief
North American Water Office Brief WOLF Brief
SOUL Brief
Minnesota Power Reply Brief WOLF Reply Brief
SOUL Reply Brief
MN Power Proposed Findings WOLF Proposed Findings
Motions and Replies
January 26, 2000 North American Water Office Motion
Administrative Law Judge Orders
January 4, 2000 Prehearing Order
January 20, 2000 Intervention Order
January 31, 2000 Order
February 7, 2000 Certification Order
May 26, 2000 Order
July 28, 2000 Discovery Order
August 24, 2000 Prehearing Order
News
The following documents and links are information appearing in the press concerning this matter. The presence of these articles does not constitute endorsement of the information or opinions contained therein.
Press outlets seeking to have their information posted here should contact the OAH Webmaster.
Duluth-Wausau power line project divides Wisconsin, Duluth News-Tribune, Jan. 23, 2000
Hearings on power line delayed, Duluth News-Tribune, Jan. 25, 2000
Public hearings crucial to future of power line, Duluth News-Tribune, Jan. 30, 2000
Minnesota, Wisconsin approval processes differ, Duluth News-Tribune, Jan. 30, 2000
Opponents electrify meeting called by lawmaker, Duluth News-Tribune, Jan. 31, 2000
Power line's impacts could be debated, Duluth News-Tribune, Feb. 8, 2000
To ensure that those interested will be able to access documents on the website, OAH posts documents, whenever feasible, as webpages. Otherwise,
the document will be posted in its native wordprocessing format or in PDF format. Documents in PDF format can be read using the Adobe Acrobat Reader, which is freely available.
To download the Reader, click on the button.

Last updated - January 29, 2001
|