6-3300-7122-1

 

                                 STATE OF MINNESOTA

                        OFFICE OF ADMINISTRATIVE HEARINGS

 

                FOR THE MINNESOTA BOARD OF WATER & SOIL RESOURCES

 

 

In the Matter of the Proposed                                   REPORT OF THE

Rules to Implement the Wetland                            ADMINISTRATIVE LAW JUDGE

Conservation Act of 1991

 

 

     Public hearings on these proposed rules were held     at 1:00 p.m. and

7:00 p.m.  in the following locations:

 

           December  7, 1992                      Alexandria

           December  9, 1992                      Thief River Falls

           December  10,  1992                    Grand Rapids

           December  14,  1992                    Marshall

           December  15,  1992                    Mankato

           December  17,  1992                    St. Paul

 

     Attendance   at  each of the hearing sessions was substantial, with more

than 200 persons at each location.  The written transcript of the hearings

occupies more than  a  thousand  pages.  More  than  200 written comments were

submitted during the post-hearing comment period.

 

     The Board of Water & Soil Resources had one or more of its members in

attendance at each of the hearings.  The Board was represented by Special

Assistant Attorney General A. W. Clapp III.  The Board panel included Greg

Larson and John Jaschke, as well as personnel from the Board's regional

offices.

 

     The Board of Water & Soil Resources must wait at least five working days

before taking any final action on the rules; during that period, this Report

must be made available to all interested persons upon request.

 

     Pursuant to the provisions of Minn.  Stat.  14.15, subd. 3 and 4, this

Report has been submitted to the Chief Administrative Law Judge for his

approval,  If the Chief Administrative Law Judge approves the adverse findings

of this Report, he will advise the Board of actions which will correct the

defects and the Board may not adopt the rule until the Chief Administrative

Law Judge determines that the defects have been corrected.  However, in those

instances where the Chief Administrative Law Judge identifies defects which

relate to the issues of need or reasonableness, the Board may either adopt the

Chief Administrative Law Judge's suggested actions to cure the defects or, in

the alternative, if the Board does not elect to adopt the suggested actions,

it must submit the proposed rule to the Legislative Commission to Review

Administrative Rules for the Commission's advice and comment.

 

     If the Board elects to adopt the suggested actions of the Chief

Administrative Law Judge and makes no other changes and the Chief

Administrative Law Judge determines that the defects have been corrected, then

 


the Board may proceed to adopt the rule and submit it to the Revisor  of

Statutes for a review of the form.  If the Board makes changes in  the  rule

other than those suggested by the Administrative Law Judge and the Chief

Administrative Law Judge, then it shall submit the rule, with the  complete

record, to the Chief Administrative Law Judge for a review of the changes

before adopting it and submitting it to the Revisor of Statutes.

 

     When the Board files the rule with the Secretary of State, it shall give

notice on the day of filing to all persons who requested that they be informed

of the filing.

 

     Based upon all the testimony, exhibits and written comments, the

Administrative Law Judge makes the following:

 

 

                               FINDINGS OF FACT

 

Procedural Requirements

 

     1.  On October 27, 1992, the Board filed the following documents with the

Chief Administrative Law Judge:

 

     (a)  A copy of the proposed rules certified by the Revisor of Statutes.

     (b)  The Order for Hearing.

     (c)  The Notice of Hearing proposed to be issued.

     (d)  A Statement of the number of persons expected to attend the hearing

         and estimated length of the Agency's presentation.

     (e)  A Statement of Additional Notice.

     (f)  The Certificate of the Board's authorizing resolution.

     (g)  A schedule of ten information meetings to be held around the State

         immediately prior to the hearings.

     (h)  Minutes of the Board's September 30 - October 1 meeting ordering the

         rules for publication.

 

     2.  On October 29, 1992, the Board filed its Statement of Need  and

Reasonableness, along with a group of exhibits to support it, and a list of

the names of Board personnel who would represent the Agency at the hearing.

 

     3.  On November 2, 1992, a Notice of Hearing and a copy of the proposed

rules were published at 17 State Register 976.

 

     4.  On November 7, 1992, the Board mailed the Notice of Hearing to  all

persons and associations who had registered their names with the Board for the

purpose of receiving such notice.  In addition, a copy of the notice  and

proposed rule was mailed to all 91 soil and water conservation districts, 41

watershed districts, 42 watershed management organizations, 141 other local

government units, approximately 300 interested citizens who had requested a

copy of the proposed rules, and a variety of other government and quasi-

government entities.

 

     5.  Appendix A to the SONAR is a six-page set of examples using  the

wetland type index system proposed in the rules.  Two of the six examples

contained an error as originally filed.   On November 20, 1992, the Board filed

a corrected version of Appendix A to the SONAR.  The November 20 filing

corrected the error in those two examples.  (Ex. 3 and Ex. 4.)  No person

 

 

 

                                     -2-

 


complained about this during the hearing process, and it is found that the

erroneous filing did not deprive any person or entity of an opportunity to

participate meaningfully in the rulemaking process.  The  error  is,  therefore,

a harmless error.

 

     6. On December 7, 1992, at the start of the  first  public  hearing,  the

Board formally entered the procedural documents into  the  record.  In  addition

to those already noted above as having been previously filed with the

Administrative Law Judge, the Board entered the following documents:

 

     (a)  A copy of the State Register containing the Notice  of  Hearing  and

          proposed rules.

     (b)  The Board's certification that its mailing list was accurate and

          complete.

     (c)  The Affidavit of Mailing the Notice to all persons  on  the  Board's

          list (and others, as noted above).

     (d)  A copy of the Notice of Intent to Solicit Outside  Opinion  which  was

          published at 16 State Register 2038 on March 9,  1992.  Later  in  the

          hearing process, on December 17, 1992, the Board introduced the

          three letters which had been received in response to its

          solicitation (Exhibit 15a), as well as a variety of  news  releases,

          advertising material, newsletters, and newspaper  articles  about  the

          rules and the hearings.  Ex. 33.

 

     7. Minn.  Rule pt. 1400.0600 requires that  certain  of  the  jurisdictional

documents noted in the immediately preceding Finding be filed with the

Administrative Law Judge at least 25 days prior to the  hearing.  This  was  not

done.  However, only one person asked the Administrative Law Judge for an

opportunity to view any of the documents within the 25 days prior to the

hearing, and that person did not raise the issue of the Board's failure to

timely file them during the public hearing process.    No person raised the

issue in any manner.   It is found that all of the necessary documents  are  in

the record, and that no person was prejudiced by the Board's failure  to  file

some of them prior to the start of the hearing.  No person  was  deprived  of  an

opportunity to participate meaningfully in the rulemaking process.  The

Board's failure was, therefore, a harmless error within the meaning  of  Minn.

Stat.  14.15, subd. 5 (1992).

 

     8.   The period for submission of written comments and statements

remained open through December 31, 1992, the period having been extended by

Order of the Administrative Law Judge to 14 calendar days following  the  last

hearing session.   The record closed for all purposes on January  8,  1993,  the

fifth working day following the close of the comment period.

 

 

Statutory Authority

 

     9.   Minn.  Stat.  103B.101, subd. 7 (1992) authorizes the Board to

"adopt rules necessary to execute its duties".

 

     10.  Minn.  Stat.  103B.3355 (1992) directs the Board, in consultation

with the Commissioner of Natural Resources, to "adopt rules establishing

criteria to determine the public value of wetlands".

 

                                      -3-

 


      11.  Minn.  Stat.    103G.2242,  subd.  1  (1992)  directs  the  Board,  in

consultation  with  the  Commissioner,  to  "adopt  rules  governing  the   approval   of

wetland value replacement plans".        The  subdivision  goes  on  to  identify  a

number of issues and procedures which the rules may address,

 

      12.  No one seriously questioned the Board's overall authority to adopt

these  rules.  There  were  specific  questions  raised  about  whether   or   not

particular rules were authorized or conflicted with various statutory

provisions.  Those questions will be dealt with in the context of the

particular rule at issue.       The  Administrative  Law  Judge  concludes,  as   a

general matter, that the Board does have statutory authority to adopt the

proposed    rules.

 

                           Introduction and scope of this report

 

      13.  The  Legislature  has  authorized  and  directed  the  Board  to   adopt

rules .  Before  those  rules  can  take  effect,  however,  the   Legislature   has

required that they be subjected to a public hearing process and review by an

independent  third  party,   the   Administrative  Law  Judge.  The  scope  of   the

Administrative  Law  Judge's   review,   however,  is not unlimited.      The

Administrative  Law  Judge's  duties  have   also  been specified by the

Legislature.  They include the preparation of a Report which is to include a

review of the degree to which the Board has:

 

           (i)   documented its statutory authority to take the

                 proposed action,

 

          (ii)   fulfilled all relevant, substantive and procedural

                 requirements of law or rule, and

 

         (iii)   demonstrated  the  need  for  and  reasonableness  of   its

                 proposed  action  with  an  affirmative   presentation   of

                 facts.

 

     14.    Many  of the rules  proposed  by  the  Board  are  controlled  by  the  detail

of the statute.  Most  of  the  persons  who  spoke  at  the  hearings  and  most  of  the

persons who submitted written comments made suggestions that require changes

in the statute, as well as the rule.       Many of the rules are based on specific

language or specific procedures required by the statute.          It  is  impossible   for

the Board to adopt those suggestions until the statute has been amended.  The

Board  can  only  adopt  rules  which  are  consistent  with  the  current  statute.  The

numerous criticisms of the Board's proposed rules that are really criticisms

of the  statute  cannot  be  recommended  by  the  Administrative  Caw  Judge  nor

adopted by the Board, until the statute is changed.         The   Legislature   has

required that  the  proposed  rules,  and  the  public  comments  on  the  proposed

rules, be submitted to the Agriculture and Environment Committees by March 1,

1993.  The  Legislature  has  prohibited  the  Board  from  finally  adopting   the

rules until at least sixty (60) days after these materials have been

submitted.  Therefore, the Legislature will have an opportunity to review the

public comments and determine whether it is appropriate to change the

statute.   This  Report  will  not  deal  with  those  suggestions  which   require

statutory  changes.  The  majority  of  them  are  based  upon   substantial

philosophical differences with the current statute, and only the Legislature

 

 

 

                                          -4-

 


can resolve those.  Instead, this Report  will  focus  upon  those  areas  where

public comment suggested that the rule was:

 

            (1)  beyond the Board's statutory authority, or in

                conflict with the current statute;

 

          (2)   not supported by the Statement of Need and

                Reasonableness; or

 

          (3)   was unnecessary or unreasonable.

 

     15.   Some  of the proposed rule provisions  received  no  negative  public

comment and were adequately supported by the Statement of Need and

Reasonableness.  This Report will not  specifically  address  those  provisions  in

the discussion below.  It is found that  the  need  for  and  reasonableness  of

those  proposed  rules which are not discussed below  has  been  demonstrated,  and

that the  Board  does have statutory authority to  adopt  them.  The  discussion

which follows will only address remaining substantive issues of need,

reasonableness or statutory authority.

 

     16.  In order for the Board to meet its burden of demonstrating

reasonableness, the Board must demonstrate that the  rule  is  rationally  related

to the end sought to be achieved.  Blocher Outdoor Advertising Co. v.

Minnesota Deptment of Transportation, 347 N.W.2d 88, 91  (Minn.  App.  1984).

This demonstration may be either by adjudicative facts  or  legislative  facts.

Manufactured Housing institute v. Pettersen, 237 N.W.2d 238, 244 (Minn.

1984).  The Board must show that a reasoned  determination  has  been  made,  as

opposed to an arbitrary one.  Id. at 246.  It is not the job of the

Administrative Law Judge to declare a rule to be  unreasonable  simply  because  a

more reasonable alternative was proposed, or a better  job  of  drafting  might

have been done.  An agency is entitled  to  choose  among  possible  alternative

standards so long as its choice is one that a rational  person  could  have  made,

and the choice does not conflict with the statute.  federal Sec. Adm'r v,

QuaKer Oats Co,, 318 U.S. 218, 233 (1943).    This Report will  not  attempt  to

select the "best rule" from among the various options  proposed  by  the  Board

and the commentators.  Instead, it will only determine whether the Board's

rule is a reasonable one.  See, Memorandum at the end of this Report.

 

    17. After the hearings had concluded,  and  the  initial  comment  period  had

ended, the Board's staff reviewed the record and proposed numerous changes

(modifications) to the rules in response to the public comments.  This Report

will focus on the "modified version" of the rule, and will  not  dwell  on  the

rule as initially proposed.  In each case where the Board has proposed a

change from the rule as originally proposed, the  Administrative  Law  Judge  must

determine whether or not the new rule constitutes a "substantial change" such

that interested persons were denied an opportunity to comment.  The

Administrative Law Judge finds that the changes proposed by the  Board  do  not

constitute "substantial changes".

 

    18. Substantial change problems were lessened  by  the  form  of  the  Hearing

Notice which was issued by the Board.  In addition  to  the  normal  description

of the rules, the Board laid out five specific issues  where  public  comment  was

particularly invited.   In four of the five cases, the descriptions of the

issues offered alternatives for public comment.  An example of this technique

is the following:

 

 

 

                                      -5-

 


          Whether, when a wetland is drained or filled without

          replacement under an agricultural exemption, the notice

          of agricultural use should be required to be recorded

          with the deed only when the land is in a city, or in all

          cases .

 

     After listing the five issues, the Board inserted the following statement

in the Notice:

 

          Since the purpose of the hearing is to improve the rule

          as proposed, interested persons must understand that the

          final rule may differ from the rule as it is now proposed.

 

In addition to highlighting those five issues in the Notice, the Board staff

also highlighted them in their introductory remarks at the start of each

hearing session.  The Board also laid out the five issues in press releases

which it issued prior to the start of the hearings.

 

 

Definition of Agricultural Land

 

     19.  Agricultural land is given favored treatment in the statute and the

rules.  There are two principal places where this occurs.  First of all, there

are exemptions which apply only to wetlands on agricultural land.  Secondly,

the replacement ratio for wetlands on agricultural land is only half as large

as the replacement ratio that applies to non-agricultural lands.  Because of

the favored treatment given to agricultural land, the question of how that

term is defined became a hotly contested one.

 

     20.  The statute itself gives no definition of the term.

 

     21.  The definition proposed by the Board is a split definition.  For

purposes of determining whether or not the exemptions are available, the Board

has proposed a relatively narrow definition.  However, for purposes of

determining the applicable replacement ratio, the Board has proposed a broader

definition.  The Board supported this use of two definitions by pointing to

the overall goal of the law, which is to achieve "no net loss" in the

quantity, quality, and biological diversity of existing wetlands.  By

providing only narrow exemptions from the replacement requirements, the

quantity of wetlands lost will be minimized.  Nonetheless, the adverse impact

on farmers who must replace drained wetlands (because they do not fit into one

of the exemptions) will be minimized if they must only replace at a 1:1 ratio,

rather than a 2:1 ratio.  Therefore, the Board reasoned, applying a broad

definition, and maximizing the opportunity for 1:1 replacement, will still

result in "no net loss".

 

    22.  Public comments on the Board's proposed rule were numerous and

diverse.  There were those who thought the Board's proposed split definition

allowed too many wetlands to be drained without replacement, and should be

tightened up as much as possible.  On the other hand, some commentators

believed the Board's proposed definitions were far too restrictive, and did

not allow farmers enough latitude to earn a living.  Some even urged that the

term "agricultural land" be defined to include not only crop land, pasture and

 

 

 

                                     -6-

 


gravel pits, but also hunting, trapping, and recreational land.      Tr . 26.

There were a number of allegations about what the Legislature intended.

 

     2 3.  Minn.  Stat.  645.16 provides that when the words of a law are not

explicit, the intention of the Legislature may be ascertained by considering,

among other matters:

 

          (1)  the occasion and necessity for the loss;

 

          (2)  the  circumstances under which it was enacted;

 

          (3)  the  mischief to be remedied;

 

          (4)  the  object to be attained;

 

          (5)  the  former law, if any, including other laws upon

               the  same or similar subjects;

 

          (6)  the  consequences of a particular interpretation;

 

          (7)  the  contemporaneous legislative history; and

 

          (8)  legislative and administrative interpretation of the

               statute.

 

The rulemaking  record does not contain the kind of  legislative  history  that

would enable a  finding of legislative intent to be made  with  any  certainty.

Two of the authors of the House bill, Representatives Willard Munger and

Marcus Marsh, both testified to a narrow definition  of  "agricultural  land".

Munger at Tr. 809, and Marsh in a letter dated December 28.  However,

Representative Bertram, who was also heavily involved in the bill, testified

to the variety of farming practices that exist in different parts of the state

and the difficulty in trying to come up with a definition  that  treated  them

all fairly.  He pointed out that he did not know what the intent of the entire

Legislature was, and thought it "humorous" to hear firm and unequivocal

statements of legislative intent from persons with opposite ideas of what the

intent was.  Representative Bertram stated that he could tell what his intent

was, but that other legislators might well have had different intents of what

the language in the bill meant.  Tr. 70-75.  Indeed, the Board, in its

post-hearing submission on the issue, pointed out that they had received

exactly opposite opinions from legislators.

 

    24.  The record demonstrates that the Board (and its two drafting

committees, the Wetland Heritage Advisory Committee and the Rule Working

Group) deliberated long and hard over this issue.  They were presented with a

number of options to choose from, and the ultimate decision in favor of a

"compromise" split definition was a reasoned one.  For example, the record

contains a memo dated May 11, 1992 from Special Assistant Attorney General

Clapp setting forth a variety of options from other statutes, and a June 3

memo from Greg Larson showing how the various options would work.  The Board

chose to use a split definition with these materials available.  The

Administrative Law Judge concludes that the Board's split definition has been

justified as a reasonable response to the problem.

 

                                      -7-

 


     25.  During the hearings, one person noted that the Board's definition of

agricultural land did not include  farm  yards  or  lands  which  would  be  used  for

building farm barns or sheds.       Paul Brutlag, at Tr. 312-13.     He said that land

used for farm buildings ought to  be  treated  the  same  as  land  used  for  crop

production.    The Board agreed  with  this  comment  to  the  extent  that  it  was

willing to add the  language  "and  associated  buildings"  to  that  part  of  the

definition  of  "agricultural  land"  which  applied  to  the  reduced  replacement

ratios, so that a wetland drained or  filled  for  a  silo  would  still  have  to  be

replaced, but only at a 1:1 ratio, rather than a 2:1 ratio.         The  change   is

reasonable, and is not a substantial one.

 

 

Related Defiitions

 

     26.   Both parts of  the  split  definition  of  "agricultural  land"  include

two terms that drew criticism and comment.       Those terms are "introduced

pasture" and  "introduced  hayland".  Both  are  defined  in  the  proposed  rules  as

being in "agricultural crop production" if  they  meet  any  one  of  a  number  of

tests.  One of the  tests  is  that  they  have  been  interseeded  with  introduced

species at  least  once  during  the  20-year period before January 1, 1991.       The

definition  of  introduced   hayland  goes even further  --  it  will  be  considered

agricultural land  if  it  has  been  interseeded  with  introduced  or native   species

at least  once  during  the  20-year  period before January 1, 1991.

 

     27.   A concern about the definitions of "introduced pasture" and

"introduced hayland" is  that  they  are  impossible  to  enforce,  because  it  is

impossible to determine whether or  not  a  piece  of  ground  was  interseeded

within the last 20 years.     One commentator asserted that USDA offices do not

keep records of interseeding, and interseeding  may  or  may  not  show  up  on

aerial photographs.    Tr. 698.    Another stated  that  the  ASCS  only  keeps  records

for ten years.    Clearwater SWCD,  letter  of  December  18.   The   Department   of

Natural  Resources,  whose  conservation  officers  are  the  primary  persons  who

will be enforcing the Act,  stated  that  the  proposed  definitions  would  be  "very

difficult to verify, creating significant enforcement problems."        Letter  of  17

December, 1992; Tr. 839.     Clearwater SWCD stated  that  it  would  be  almost

impossible for people to prove that they had interseeded (Id.)       A similar

concern over  enforceability  came  from  the  Isaac  Walton  League,  which  asserted

that enforcement would be extremely difficult.       Letter of December 17.     The

Department recommended  that  the  once  in  20-year  limitation  in  planting  and

twice in 10-year limitation on harvesting  be  changed  to  twice  in  ten  years  for

planting and twice in five years for harvesting.        These  are the time periods

used in the RIM  definitions  (Minn.  Rule  pt.  8400.3030).  The   Department   urged

that in the interests  of  consistency  and  simplicity,  as  well as

enforceability, that  the  RIM  definitions  be  substituted  for the Board's

proposed definitions.

 

    28.   The Board  justified  its  proposals  by  pointing  out that the rule

drafters began with the RIM definitions, but then the Heritage Advisory

Committee modified them  to  make  them  less  restrictive  as  a  compromise  between

those trying to  minimize  loss  of  wetlands  and  those  seeking  broad  application

of the exemptions  to  all  farmers.   SONAR, p. 4-5.    While   the   Administrative

Law Judge is hesitant to upset policy compromises that took many hours to

achieve, it is a matter of great  concern  when  those  who  will  be  doing  most  of

the  enforcement  state  that  the  proposed  definition  will  create  significant

enforcement problems because it would be very difficult to verify.  The

 

 

 

                                         -8-

 


Department, presumably, has had experience in enforcing the RIM program and

working with its definitions.  It is, therefore, in a good position to

evaluate the practicality of verification.

 

     29. Difficulties in verification are a two-edged sword:  not  only  is  an

enforcement officer unable to determine if a violation has occurred,  but  also

a landowner may be unable to prove entitlement to an exemption.  Absent some

scheme of filing with the ASCS, SWCD or other type of body, it will be very

difficult for a landowner to convince a skeptical LGU or enforcement officer

that land was, in fact, cropped or interseeded 18 or 19 years ago.

 

     30.  The Board has failed to demonstrate the reasonableness of its

proposed definitions of introduced hayland and introduced pasture insofar as

they are based on unenforceable measures.  In order to cure this defect, the

Board must adopt definitions that have some reasonable likelihood of  objective

verification and consistent enforcement.  The Department's experience  with  the

RIM program would support the timelines in the RIM definitions as being

verifiable and enforceable.  There may be other timelines which have  also  been

demonstrated in the record to be verifiable and enforceable, but the

Administrative Law Judge is not aware of any.  Therefore, he recommends that

the Board adopt the timelines in the RIM definitions.  Another  alternative

would be for the Board to fashion some sort of verification  provision  whereby

longer timelines, such as 20 years, could be used if the landowner  could

prove, by aerial photographs, ASCS records, or some other reliable means,  that

the activities had, in fact, occurred.

 

 

Other Definitions

 

    31.  The statute and these rules both provide that an impacted wetland

must be replaced by a wetland within the same watershed or county, with  a  few

major exceptions.  One of the exceptions is described in the  statutes  as

follows:

 

         Wetlands impacted by public transportation projects may

         be replaced statewide, provided they are approved by the

         commissioner under an established wetland banking system,

         or under the rules for wetland banking as provided for

         under section 103G.2242.

 

One of the issues that arose during the public hearing process was the

proposed definition of "public transportation projects".  The rules define a

"public transportation project" as a project "conducted by a public  agency

involving transportation facilities open to the  public".  Representative

Munger testified that it was the intent of the Legislature to limit  this

benefit to projects administered by the Minnesota Department of

Transportation.  He explained that MNDOT had created a wetland  mitigation  bank

at the time of the 1991 enactment with the anticipation of being able to use

it for statewide projects.  Representative Munger pointed out that  the  Board's

proposed rule covers any kind of public transportation, including airports,

trains, public transit and similar projects, and is not limited to the state

Department of Transportation.  Tr. 809.  A similar comment was  made  by  the

Wetlands Conservation Coalition (Letter of December 31), which urged that the

definition be rewritten to apply solely to projects conducted by the  state

Department of Transportation.

 

 

 

                                     -9-

 


     32. In response, MNDOT (Letter of December 24) and the  Association  of

Minnesota Counties (Letter of January 8) both point out that had the

Legislature intended to limit transportation projects to MnDOT projects, they

clearly could have.  The AMC comment notes that a number of counties were in

the process of implementing a banking program similar to that of MNDOT,  and

there is no reason why their transportation projects should not  be  treated

similarly to MnDOT's.

 

     33. The Board, in its Statement of Need and Reasonableness and  in  its

post-hearing submission, justified its definition as consistent with the

statute.  They point out that the statute contains no special preference for

MNDOT, and that it would be improper for the Board to impose one.  The

Administrative Law Judge accepts the Board's position.  If  the  Legislature

intended a narrower interpretation, it will have an opportunity to insert it

following the March submission.

 

 

 

 

     34. The statute contains a list of 24 specific  exemptions,  which  are

applicable so long as three conditions are followed.  The conditions relate to

appropriate erosion control, not blocking fish passages in a watercourse, and

compliance with other applicable governmental requirements,  including  best

management practices.  While most of the exemptions drew no substantial

comment (other than comments directed at the statute, which will not be dealt

with here), there were some general provisions relating to exemptions and some

specific exemptions that did draw comments worthy of discussion below.

 

     35.  Exemptions 1, 2, 4, 7, 8, and 23 (known as the "agricultural

exemptions") all contain similar language, which reads as follows:

 

          Present and future owners can make no use of the wetland

          area after it is altered, other than as agricultural land

          for ten years, unless it is first replaced  . . . .  If

          the local government unit approves an exemption, the

          landowner must execute and the local government must

          record a notice of this restriction If the Wetlant II In

          a City.  [Emphasis added].

 

Discussion focused on whether recording should be required statewide, or just

in cities.  The theory behind requiring the recording of an exemption is that

a buyer purchasing land which had been drained using an agricultural exemption

might not know that the land could not be converted to non-agricultural  use

for ten years, unless the restriction was recorded.  During the rule drafting

process, persons argued that recording was a burdensome requirement to place

upon all landowners, and that it was most likely that conversion  to  non-ag

uses would occur in cities, rather than in unincorporated areas, and so  the

recording requirement ought to be limited to cities.  This was  the  position

adopted by the Board, but the Board did recognize it was  controversial  and

identified it as one of the five issues for particular attention during  the

public hearing process.

 

    36.  Public opinion was strongly in favor of imposing the reporting

requirement in all locations, not just in cities.  The general rationale  was

 

 

 

                                     -10-

 


that conversion to non-ag uses was likely to occur before incorporation or

annexation to a city, and not afterwards, and that the minimal cost and burden

of recording (estimated at an average of $17.00 around the State by the

Builders Association of Minnesota in a December 31 letter) was relatively

minor in comparison to the damages that could occur to an innocent buyer who

was unaware of the restriction.

 

     37.  In response to the public comments, the Board's post-hearing

submission recommended that the five agricultural exemptions all be modified

to require recording in all locations, not just in cities.  The Board

volunteered to make notice forms available locally, so that all a landowner

would have to do would be to fill in a property description and then take it

to the county recorder.  The Administrative Law Judge concludes that the Board

has justified the need for and reasonableness of its modified proposal.

 

     38.  The Board may wish to consider the comments of the Minnesota State

Bar Association's real property section, which proposed that the rule contain

minimum criteria for a proper notice.     The minimum criteria would be the

following:

 

          1.   the name or names of the land owners;

 

          2.   the name and address of the LGU granting the

               exemption;

 

          3.   a complete legal description (a tax description,

               street address or tax identification number is not

               adequate) of the real property affected by the

               restriction; and

 

          4.   the date on which the 10-year restriction expires.

 

The real property section recommended that all landowners named should sign

the notice, and that the notice be acknowledged so as to meet the requirements

of the recording act.  Letter dated December 31.  The Board's proposed rule

cannot be said to be inadequate or unreasonable without the real property

section's recommendations, but the Board should consider them to avoid any

problems with the forms it has offered to provide to landowners.

 

     39.  In addition to the change to require recording, the Board also

proposed that each of the five agricultural   exemptions receive a new sentence

which would provide that for ten years, the wetland could not be restored for

replacement credit.  This is really more of   an editorial change than a

substantive one, as the same prohibition is   contained in another part of the

rule, part 8420.0540, subpart 2.  That provision states:

 

          Wetlands drained or filled under an exemption may not be

          restored for replacement credit for ten years after

          draining or filling.

 

The wisdom of that restriction was another of the five Issues identified for

particular comment.

 

    40.  During the rule drafting process, some persons argued that if a

wetland is drained under an exemption (so that it is not rep I aced elsewhere) ,

 

 

                                       -11-

 


it should never be allowed to be restored  for  "credit"  so  that  some  other

wetland can be drained in its  place.  Other  persons  felt  that  an  absolute

prohibition was too severe, and that some  length  of  time  (ten  years  was

ultimately selected) would be long enough to discourage abuses of the

exemption provisions.     One of the most widely debated  topics  was  whether  or

not created wetlands were as good as  restored  wetlands  in  terms  of  providing

biological diversity and wetland  values.  Those  people  who  favored  a  ten-year

limitation, as opposed to an  absolute  prohibition,  pointed  out  that  restoring

an old wetland is often better than creating a new  one,  and  that  one  of  the

act's goals was to restore previously drained wetlands.

 

      41. The Board, in its Statement of  Need  and  Reasonableness  and  in  its

post-hearing comments, took the  position  that  a  ten-year  limitation  was

adequate to prevent abuse, yet still allow the use of previously drained

wetlands for replacement.  The Administrative Law Judge concludes that the

Board has demonstrated the need for  and  reasonableness  of  its  two  proposals

regarding these agricultural exemptions -- that  it  is  desirable  to  repeat  the

ten-year limitation in each exemption so that it is clearly understood,  and

that it is appropriate to record the fact that  an  exemption  has  been  taken  in

all locations, not just in cities.

 

      42. Exemption 3  relates  to  drainage  systems.  The  statutory  exemption

allows the following:    "Activities necessary to  repair  and  maintain  existing

public or private drainage systems as long as wetlands that have been in

existence for more than 20 years are  not  drained."  The  Board's  rule  goes  on

to specify how spoil material from the  repair  and  maintenance  activity  must  be

dealt with and what documentation is required.

 

      43. The bulk of the opposition to  the  Board's  rule  was  really  directed

at the statute, for it is the  statute  that  contains  the  20-year  wetland

provision.  The gist of the comments was that  if  a  landowner  had  paid  for  the

right to drain land, the landowner ought to be  able  to  exercise  that  right  at

any time, and if that requires repairing  or  maintaining  an  unused  ditch,  then

the landowner ought to be able to do  so  without  any  time  limitation.  See,  for

example, Tr. 55-56, 237, 248-49, 324.  The  pros  and  cons  of  this  question  will

not be discussed here, as the 20-year rule  merely  tracks  the  statute,  and  any

changes must come from the Legislature.

 

      44. A Marshall County commissioner  pointed  out  that  the  exemption  does

allow the filling of a wetland resulting  from  the  side  casting  of  spoil

materials when the wetland is located  within  the  right-of-way  acreage  of  the

ditch.  Some of the ditches in  Marshall  County  do  not  have  any  right-of-way

beyond the width of the ditch itself, and thus would  not  be  able  to  use  the

exemption for the efficient  placement  of  spoil  materials.  Tr.  293.  The  Board

acknowledged that its intent had been to  allow  for  side  casting,  and  proposed

the addition of language which would  allow  side  casting  either  within  the

right of way or within a one-rod width on either side  of  the  top  of  the  ditch,

whichever is greater, so long as  the  spoil  deposition  area  is  permanently

seeded into grass to avoid erosion problems.  The Administrative Law Judge

finds that this is a  reasonable  accommodation  for  those  ditches  without

rights-of-way, and that it is not a substantial change.

 

      45. Exemption 6 deals  with  activities  authorized  under  general  permits

issued by the United States Army  Corps  of  Engineers.  It  tracks,  verbatim,  a

statutory exemption.  The record suggests that  since  the  time  that  the  act  was

 

 

 

                                        -12-

 


passed in the spring of 1991, there have been changes to the Corps' program

and negotiations between the Corps and the  Minnesota  Pollution  Control  Agency

over appropriate regional conditions have caused the  language  in  the  act  and

the rule to be out of date.  There did not appear to  be  any  substantive

disagreement with the concept of the exemption; rather,  the  problem  occurs  as

a result of changes in the Corps program.    The Board may want to consider

seeking legislative amendment of the statute so that it  can  adopt  the  current

version of the Corps exemption.

 

     46.  Exemptions 7 and 8 are expected to be two of the most frequently

used exemptions, and the ones that triggered much of the debate over the

definition of "agricultural land".    Exemption 7 exempts activities in a  Type  I

wetland on agricultural land (except for bottomland hardwood  type  I  wetlands),

while Exemption 8 exempts activities in a Type 2  wetland  on  agricultural  land

that is two acres in size or less.  In the case of both exemptions,

Representative Marsh (Letter of December 28) recommended that the rule be

changed so that the local government unit would be required to  seek  the  advice

of the technical panel as to whether the wetland were a type I or  2  wetland  or

not, rather than the Board's permissive language which  merely  allowed  the  LGU

to seek the advice of the technical panel.  Marsh felt that it was a clear

violation of legislative intent not to require the use  of  the  technical  panel

for these two exemptions.   A similar issue arises  in  later  language  regarding

the role of the technical panel in connection with replacement plans.

 

     47. There is a statutory provision which discusses the  role  of  the  panel

in connection with replacement plans, but the Administrative Law Judge does

not read that provision as extending to exemptions.  There  is  no  corresponding

statutory directive regarding the technical panel's use for exemptions.

Therefore, the Administrative Law Judge does not  believe  the  Board's  proposed

language for these exemptions conflicts with the statute.

 

     48.  Substantial criticism was directed at the exemption for road and

bridge maintenance.   The statute, at section 103G.2241, subd.  l(a)(16)  exempts:

 

          Activities associated with routine maintenance of

          existing public highways, roads, streets, and bridges,

          provided the activities do not result in additional

          intrusion into the wetland and do not result in the

          draining or filling, wholly or partially, of a wetland.

 

The rule explains that this exemption does not prevent repairing washouts or

adding material to the driving surface so long as the  road's  occupancy  of  the

wetland does not increase.

 

    49. Many comments were received to the effect  that  this  exemption  is  too

limited, and that it ought to allow for upgrades to Improve the safety of

roads without having to go through the entire process  of  the  rules.  A  number

of persons pointed out that forest roads were treated better than  public

roads, even though forest roads often went through more "pristine" areas and

were for private profit, rather than the public good.  The  Board's  basic

reaction to the testimony was to point out that there was another exemption

available for the maintenance of existing roads -- the use  of  Corps  Nationwide

Permit 14, which the Legislature did allow to be used for maintenance  of

existing roads, but not for new roads.  Pursuant to Exemption 6  of  these

 

 

 

                                     -13-

 


rules, work which is done in conformity with Corps Permit 14 (except for  new

roads) would be exempt.  Tr. 120.

 

     50.   The Administrative Law Judge finds that the complaints regarding

road maintenance must be  directed  to  the  Legislature,  not  to  the  Board.   The

Board has in no way restricted the availability of the exempti on as it is

written in the statute, and if it is  going  to  be  changed,  it  must  be  changed

by statute.

 

     51.  An interesting alternative is proposed by Wright County.  The county

pointed out that its highway department has worked with the local soil and

water conservation district to restore wetlands along highways and create

additional wetlands.     The County proposes that if  a  wetland  is  the  result  of

highway construction, then  some  reasonable  intrusion  ought  to  be  allowed  for

highway maintenance.     The County points out that if maintenance is going to

require mitigation in   the future, then the County may not make such an effort

to create new wetlands in the future.      Tr. 857.

 

     52.  A question has arisen as to whether or not a person draining or

filling a wetland under an exemption must obtain an exemption certificate from

the LGU, or whether the exemption certificate process is merely voluntary.

The statute is silent on the question.      The Board's proposed rule makes it

voluntary on the part of the landowner, but specifies that if a landowner does

request a certificate of exemption, and is entitled to one, then the local

government unit must issue one.      The rule specifies, however, that an

exemption applies whether or not the LGU chooses to issue certificates of

exemption or not.

 

     53.  Representative  Munger  urged  that  certification  be   mandatory.   He

pointed out that a formal  certificate  would  make  it  easier  for  owners,

contractors and enforcement officers  to  deal  with  the  legitimacy  of  an

action.  Tr. 813.  Others,  however,  urged  that  there  was  no  reason  to  have  a

certificate in each case, and it was  appropriate  to  leave  it  up  to  the

landowner as to whether or not one was obtained.  The utility industry, for

example, felt comfortable without obtaining one in each case, feeling it would

be a waste of time for both them and the LGUs.  Letter of January 8.  The

Association of Minnesota Counties thought the current language was just right,

because it did allow the landowner the option.  Letter of January 8.  The

Builders Association of Minnesota urged that the rule be clear in setting

forth whether or not a certificate was required.       Letter  of  December  31.

 

    54. The  Administrative  Law  Judge  concludes  that  the  Board  has  justified

its rule  as  reasonable.   As will  be  discussed  below,  there  were  numerous

complaints from LGUs regarding the  cost  of  this  program,  and  requiring  a

certificate in each case would only add to the cost for both LGUs and

landowners.   Giving the landowner an option to obtain one or not is a

reasonable approach.

 

 

                            Minimis Prgvision

 

    55.   The Act does not contain any de minimts provision.        The  Board  felt,

however, that it must specify some amount of impact that is so small as to not

warrant attention.  The Board picked 100 square feet as that amount, reasoning

that it was small enough not to conflict with the Legislature's decision to

 

 

 

                                        -14-

 


put no minimum size in the Act, and yet not so small as to be totally

meaningless.  The Board coupled that with restrictions to avoid cumulative

impacts that would exceed that amount.  The proposed rule reads as follows:

 

          A landowner unsure if proposed work will result in a loss

          of wetland may apply to the local government unit for a

          determination.  The local government unit shall issue a

          no-loss certificate if  . . .  the draining or filling will

          be minimal and not warrant replacement.  This item is

          applicable  if the total wetland loss will be less than

          100  square  feet per year per landowner, and the

          cumulative  impact on a wetland over time without

          replacement after January 1, 1992, of draining and

          filling by all persons does not exceed five percent of

          the wetland's area.

 

    56.  This provision drew a host of negative comments, and only a few

supportive ones.   Most commentators said 100 square feet was too small.

Recommendations were made for one-tenth of an acre, one-half an acre, one

acre, two acres, three acres, all the way up to five acres.      The basic concept

expressed was that the administrative time and money, both for the landowner

and the LGU, to deal with very small wetlands was simply out of proportion to

their value, and there should be some realistic de mintmis provision.      One

commentator pointed out (advocating four or five hundred square feet "as a

bare minimum") that the law should generally follow ordinary peoples'

perception of what is minor and what is not minor, and 100 square feet was

simply too small.   Tr. 22.   Cass County, which has been operating under the

interim rules, has  71 open files, and 80% of them deal with areas less than

2,000 square feet.   The County noted that jurisdictional Size is a statutory

issue, but if there is no change in the statute, then there must be some

streamlining of the process for very small parcels.     Tr. 413.   Representative

Munger pointed out that the Legislature did not include any minimum impact

provision, and urged that any attempt to enlarge the size from the 100 square

feet should be discouraged.  Tr. 810.

 

    57.  In its post-hearing submission, the Board pointed out that the

difficulty with setting any particular limit is the fact that the Legislature

elected not to:  The Legislature rejected the Corps' Nationwide Permit No. 26,

which exempts isolated wetlands less than one acre in size, and the

Legislature did not extend its one-half acre exemption for utility lines even

so far as to include public roads.  In light of this history, both the Wetland

Heritage Advisory Committee and the Rule Working Group accepted 100 square

feet as the maximum that could be allowed without encroaching on the

legislative judgment.   The Board pointed out that the Act was passed in order

to protect wetlands that were not protected by other agencies, and thus

proposals to increase the Ye minimis amount to the same amount as the Corps of

Engineers or other existing permit programs would be pointless.     As will be

discussed more fully below, the Board did propose a change in an attempt to

streamline some of the procedural requirements applicable to small wetlands,

but left the 100-square de minimis amount intact.

 

    58.  The Administrative Law Judge agrees with those who claim that it is

for the Legislature, not the Board, to determine the scope of the law.  The

general rule is that the Legislature may confer discretion on an agency

regarding the execution or administration of the law, but it may not give an

 

 

 

                                      -15-

 


agency the authority to determine what the law shall be or supply a

substantive provision of  the  law  which  the  agency  believes  the  Legislature

should have included in the first place.   Wallace v. Commissioner, 184 N.W.2d

588, 594 (Minn. 1971).     An agency cannot limit its jurisdiction through

rulemaking.  The Legislature, not the agency, determines the scope of the

agency's jurisdiction.    leisure HillS of  Grand  Rapids,  Inc.  v.  Levine,  366

N.W.2d 302, 304 (Minn.  App. 1985).      On the other hand, it is absurd to believe

that the Legislature intended that every square centimeter of wetland be

protected.   State , Kulvar, 266 Minn. 408, 123 N.W.2d 699 (1963).          It is

permissible for an agency to draw a "line of absurdity", but any more

substantial limitation on its  jurisdiction  must  be  drawn  by  the  Legislature,

not the agency.    The Administrative Law Judge believes that 100 square feet is

a reasonable choice for a de minimis provision based on a "line or absurdity"

rationale.    It is up to the  Legislature  to  decide  if  some  more  substantial

number ought to be used.

 

     59.  Minnesota Power, on behalf of the utility industry, pointed out that

the language regarding issuance of a  no-loss  certificate  was  not  as  clear  as

the language regarding an exemption certificate, and that it ought to be clear

that a certificate was not required in each case, as that would be a waste of

LGU time.   The Administrative Law  Judge  agrees  that  the  language  is  not  as

clear, but that the outcome of the two is the same.       To avoid confusion,

however, he suggests that the  Board  consider  taking  language  from  the  first

paragraph of part 8420.0210, the exemption provision, and use it in the

no-loss provision, so that there is no question but that a certificate is not

required.  The  existing  no-loss  determination  is  not  unreasonable  or  illegal

without the change, but clarification would assist readers.

 

 

Replacement Plan Procedurel

 

    60.   A person desiring to drain or fill  who  does  not  qualify  for  one  of

the exemptions or no-loss provisions  is  required  to  replace  the  lost  wetland

values.  The statute requires that  the  process  for  this  replacement  is  to  be

the preparation of a  replacement  plan,  followed  by  approvals  from  the  LGUs

involved.   The details of that process drew substantial criticism as being too

complicated, too onerous, and too time consuming, particularly for small

impacts.   After noting its belief that  it  could  not  increase  the  de  minimis

impact without a legislative change, the Board did propose to modify the

procedures so as to minimize the work required for small impacts.        Some    of

those changes are discussed below.

 

    The initial draft of  the  rule  imposed  the  same  notice  requirements  for

applications on all replacement plans, regardless of size.        A number of

commentators recommended that  this  be  changed,  to  more  appropriately  tailor

the notice requirements to the size of the impact.  The Dakota Soil and Water

Conservation District and the Builders Association of Minnesota, along with a

number of others, all recommended that there be some streamlining of the

notice for smaller projects.     The Board has  now  proposed  that  the  procedures

be different depending on the size of the project.  The Board divided projects

into three classes:   0.1 acres or less; 0.1 acres to 0.5 acres; and 0.5 acres

or more.   With regard to  notice,  for  example,  the  largest  impacts  (one-half

acre or more) would have to give notice to  all  of  the  entities  listed  in  the

statute, including publishing in the EQB Monitor and a local newspaper.

However, for impacts between .1 and .5 acres, the requirement for publication

 

 

 

                                       -16-

 


  in the EQB Monitor would be dropped.       For the smallest class of impacts, only

  those agencies who requested notice would have to receive it, and there would

  be no notice to the Board itself  or  publication  in  a  local  newspaper  or  the

  EQB Monitor.    Instead, the governing Board of the LGU and the technical

  evaluation panel and the watershed district or watershed management

  organization would be the only required notifications.

 

       61. The  statute,  in  section  103G.2242,  subd.  6,  requires  that  certain

  notif I cation and pub I I cation occur whenever a replacement plan is filed  with

  an LGU.  The statute makes no exceptions for small impacts or medium sized

  ones.  It treats all of them the same.  In the face of clear statutory

  language requiring that something  occur,  the  Board  cannot  adopt  a  rule  which

  Imposes the requirements on some applicants but not all.        Presumably the Board

  would advocate the same "line of absurdity" rationale that was adopted

  earlier, but it does not apply in this kind of a situation.        If the

  Legislature wants the Board to  receive  a  copy  of  every  replacement  plan,  no

  rule can vary that requirement.      If the Legislature wants notice published in

  the EQB Monitor or wants  neighbors  notified  by  publication  in  a  newspaper  of

  general circulation, it can require that.       None of  those  requirements  are  so

  absurd as to place them beyond the "line of absurdity".        The Board's proposed

  modifications to the notice provisions of part 8420.0230 (page 25, line 6

  through 19, along with lines 23 and 27) conflict with the statute, and cannot

  be adopted.    In order to cure this defect, the Board must either return to its

  original proposal, as published in the State Register, or propose language

  which does not conflict with the statute.

 

 

  Technical  Evalvation Panel Makeup

 

       62.  The statute, in section 103G.2242, subd. 2, specifies the following:

 

            Questions concerning the public value, location, size, or

            type of a wetland shall be submitted to and determined by

            a technical evaluation panel after an on-site

            inspection.    The technical  evaluation  panel  shall  be

            composed of a  technical  professional  employee  of  the

            board, a technical professional employee of the local

            soil and water conservation district or districts, and an

            engineer for the local government unit.       The panel shall

            use the "Federal Manual For Identifying and Delineating

            Jurisdictional Wetlands" (January 1989).       The panel shall

            provide the wetland determination to the local government

            unit that must approve  a  replacement  plan  under  this

            section, and may recommend  approval  or  denial  of  the

            plan.   The authority must consider and include the

            decision of the technical evaluation panel in their

            approval or denial of a plan.

 

While a great deal of controversy focused upon the role of the technical

panel, an initial matter which  must  be  discussed  is  the  makeup  of  the  panel.

 

      The Board has proposed the following rule:

 

            For each local government  unit,  there  is  a  technical

            panel of three persons:  A technical professional

 

 

 

                                         -17-

 


          employee of the board, a technical professional employee

          of the soil and water conservation district of  the  county

          in which the activity is occurring, and an engineer or

          their designee for the local government  unit.  One  member

          selected by the LGU shall act as the contact person and

          coordinator for the panel.  Two members of  the  panel  must

          be knowledgeable and trained in applying  methodologies  of

          the [federal manual], and evaluation of public values.

          The technical panel may invite additional  wetland  experts

          to help the panel in its work.

 

     63.  Several counties complained that the rule constituted "micro

management", and that they ought to be allowed to have a variety of people on

their panels.   Lake County, for example, has placed other persons  on  interim

panels, and intends to continue to do so for "grass roots"  input.  Tr.  438.

St. Louis County has a wetland coordinator, a DNR hydrologist, a  county  land

department specialist, etc., that they would like to be able to place on their

panels.   Tr. 470.   Both want the flexibility to name their own panels.

 

     64. The Board responded to these suggestions by pointing  out  that  the

statute mandates the membership of the committee, and that adding other voting

members of the panel raises the possibility of the panel being  "stacked"  one

way or the other.  The Board noted that adding additional members as technical

advisors or ex-officio members is a good way to involve local citizens,

resource managers, scientific experts, etc., but that limiting  voting  rights

to the three members prescribed in the statute is appropriate.

 

    65.  The Administrative Law Judge finds that the Board has justified its

proposal as reasonable.   The statute binds the Board, and the Board's rule is

reasonable.  The Board did make other minor changes in response to public

input, but none of them are substantial.

 

 

Technical Evaluation Panel Role

 

    66.  One of the five issues identified by the Board for particular

attention was the question of the Technical Evaluation Panel's  role.

 

    The basic question is whether or not the panel must be  used  whenever  a

replacement plan is submitted to a local unit of government, or  whether  the

technical panel need only be used when a local unit of government has

questions.  The Board's Rule Working Group was unable to  reach  consensus  on

this issue, but the Wetland Heritage Advisory Committee elected to  have  the

panel review all plans and make recommendations on those plans to the LGU.

That was the position set forth in the second paragraph of part 8420.0240.

When it made that decision, however, the Advisory Committee did not notice

that it also needed to adjust language in another section in order to keep the

two consistent.   That other section is part 8420.0510, subp. 3, which proposes

using the panel only when questions arise.  Therefore, the rules  as  published

in the State Register contained an inconsistency, but the Board's notice of  a

hearing alerted people to this issue so that a great deal of comment was

received.

 

    67. The weight of the comments supported the optional use  of  the  panel,

primarily because of perceived difficulties of cost and time if the panel were

 

 

 

                                     -18-

 


to be used in each case.  Todd County, for example, indicated that between

April I and December 7 of 1992, it received 70 applications for replacement

plan approvals.  It pointed out that in the summertime,  spring  and  fall,

county engineers are really busy, and that the Board conservationist  who  must

also be on the panel, has to cover more than one county.  Tr.  46.  The  City  of

Breezy Point, in Crow Wing County, suggested it might take three  or  four

months to convene the panel, given the workload of the various people

involved.  Tr. 374.  Even the American Society  of  Civil  Engineers,  whose

members might be  hired  to staff technical panels in particularly busy areas,

believes that it  would  be impractical to have a panel in every case.

Tr. 433.  The  Gun  Club  Lake Watershed Management Organization  (in  Dakota

County) indicated  that  its experience is that the majority of wetland

replacement issues  can  be addressed in a technically sound manner without

going through the  time  and expense of convening the panel.  The

Ramsey-Washington Watershed Board said a large majority of impacts  are  clear,

and no questions arise.  Both urged that LGUs be given the  discretion  of  when

the panel should be used.

 

     On the other hand, there were persons who urged that the panel  should  be

used in every case, and never be bypassed.  The Minnesota Wildlife Society

indicated that the purpose of the panel was to ensure that  technical  decisions

are based on scientific analysis, and the technical panel was  clearly  designed

to provide just that.  Tr. 40.  The Wetland Conservation Coalition, a

coalition of environmental and sports groups, urged that using the panel in

each case would result in fair and uniform decisions across the State.  It

argued that this was a compromise between those who wanted  a  centralized

program and those who wanted a decentralized one, and that using the  panel  in

all cases would at least provide some objective input into a decision that

might otherwise be driven by the temptation for development and tax revenue.

Tr. 88 and letter dated December 31.  Representative Munger  indicated  that  the

panel should be used in every case so that the LGU decisions are based  on  the

most information possible.  Tr. 809.

 

     68. After considering all of the comments, the Board chose  to  modify  the

rule to clarify that the panel need only participate on an as-needed basis,

but that it had to be used upon request of the LGU, the landowner, or any

member of the panel itself.  The Board felt this arrangement provided checks

and balances, but placed responsibility with the LGU for making decisions on

routine projects without requiring another level of review.

 

    69.  The Administrative Law Judge finds that the statute is not clear

with regard to whether the LGU was to be used in all situations, or  only  when

there were questions.  He further finds that the Board's modification is a

reasonable one, and may be adopted.  It is not a substantial change In light

of the notice which was given.

 

 

Appeals

 

    70.  The statute contains a definite procedure for appealing an LGU's

approval or denial of a replacement plan.  But the statute does  not  deal  with

appeals from other LGU decisions, such as exemptions and no-loss

determinations.  Initially, the Board had proposed that all appeals of

decisions based on the rules go to the Board, but that appeals of exemption  or

no-loss determinations must first be appealed to a local government's board  of

adjustment or appeals or to the governing body of the LGU.

 

 

 

                                     -19-

 


     7 1 .  During   the  comment process, criticisms came  from  those  who  pointed

out that  any  citizen  would have the right to appeal and block a project,

probably for  a  whole  construction season, and there was no provision for

separating   frivolous  appeals from serious ones.   Letter of Urban Wetland

Management   Coalition  dated December 31.   Others pointed out that some  LGUs  did

not have boards of adjustment and appeals and that  a  variety  of  structures

must be  accommodated.   Association of Minnesota Counties, December 30.

 

     72.   In its post-hearing submission, the Board  made  proposals  for  changes

to respond to these comments.  First of all, the Board noted that the

statutory appeal provisions apply only to replacement  plans,  not  all  appeals,

and so the Board tried to adopt the statutory requirements only for

replacement plans.    For exemptions and no-loss determinations, the Board

established a procedure whereby only the landowner had  an  absolute  right  to

appeal an exemption or no-loss determination, and before doing so, the

landowner must exhaust all local administrative appeal options.      Others  who

might want to appeal an exemption or no-loss  determination  were  limited  to

those required to receive notice of replacement plan decisions, and those

persons did not have an absolute right to appeal.     They were granted  the  right

to petition the Board to hear an appeal, but the Board  was  empowered  to  grant

or deny the  petition.

 

     73. There are two problems with  the  Board's  modified  plan.  First  of

all, the statute specifies that appeals from replacement  plan  decisions  may  be

made by any of the following people: "the  wetland  owner,  by  any  of-those  to

whom notice in required to be mailed under [103G.2242]  subdivision  7,  or  by

100 residents of the county in which the majority of  the  wetland  is  located."

The Board has attempted to restrict appeals to the following:     "the  landowner,

any of those required to receive notice of the decision  as  provided  for  in

part 8420.0230, or by 100 residents of the county in  which  a  majority  of  the

wetland  Is  located."  The rule reference, however, refers to the list of

people which the Board sought to reduce as described in Finding 61 above.      In

other words, by attempting to change that list of  people,  the  Board  has  also

changed the list of people who would be entitled to  appeal  a  replacement  plan

decision.   That is contrary to the statute.     The statute sets forth the

required list, and the Board cannot alter  that.  Therefore,  in  order  to  cure

this defect, the Board must modify its proposed language for  page  28,  lines  14

through 16, to comport with Minn.  Stat.   103G.2242,  subd.  9.  The  Board  may

use whatever stylistic device it chooses to  deal  with  the  cross-references

between subdivision 7 and subdivision 9, but it cannot  alter  the  substance  of

the statute.

 

    74.   The other problem raised by the Board's proposal  is  that  the  rule

allows the Board to grant or deny an appeal petition from an exemption or

no-loss determination, but there are no standards in the  rule  to  guide  its

decision.   It is well settled in the  law that a rule which grants

discretionary authority to an administrative  officer  must  have  a  "reasonably

clear policy or standard of action" so that it is clear  that  the  action  is

occurring by virtue of its own terms, and not according to  the  whim  or  caprice

of the administrative officer.   lee v. Delmont, 228 Minn. 101,  113,  36  N.W.2d

530, 538 (1949); Andersn v, Commissioner of Highways,  126  N.W.2d  778,  780

(Minn. 1964); Beck, Bakken & Muck,  Minnesota  Administrative Procedure,    24.4

(Butterworths,  1987).   In order to cure this defect,  the  Board  must  either

return to a position whereby all appeals are accepted by  the  Board,  or  provide

 

 

 

                                       -20-

 


reasonable standards to guide the Board's discretion.  An example of such

limiting language might be the following:

 

          The  Board shall grant the petition unless it finds that

          the  appeal is meritless, trivial, or brought solely for

          the  purposes of delay.    In determining whether to grant

          the  appeal, the Board shall also give consideration to

          the  size of the wetland, other factors in controversy,

          any  pattern of similar acts by the LGU, the landowner or

          the  petitioner, and the consequences of the delay.

 

The Administrative Law Judge does not mean to  suggest  that  those  are  the  only

factors which the Board might want to enumerate, or that all of them are

appropriate.  Rather, he is attempting  to  give  some  guidance  to  the  Board  in

understanding the kind of restrictions that must be Imposed on the Board's

discretion.

 

 

Enforcement Procedures

 

    75. Part 8420.0920,  subp.  2,  includes  a  provision  for  delayed  effective

dates on cease and desist orders.     It provides that  a  cease  and  desist  order

with a delayed effective date (three weeks  from  the  date  of  issuance)  can  be

issued when it is not readily apparent whether an  activity  Is  exempt  or  within

the no-loss provisions, and continued  drain  or  fill  activity  would  not  cause

irreparable harm to the wetland.     The rule  requires  the  enforcement  authority

to advise the landowner that an application  should  be  made  Immediately  to  the

LGU and that if the LGU determines that the activity is not appropriate,

restoration may be required.    The rule goes on to  provide  that  in  those  cases

where an application for exemption certificate or no-loss determination is

triggered by a cease and desist order, the LGU must make a decision "within

three weeks from the date of the application or sooner if the landowner

requests."

 

    76.  This provision received a number of comments.  A Goodhue County

official pointed out that giving the landowner the option to request a

decision "sooner" places an unnecessary burden on the LGU.      She  asked   whether

there was any limitation on "sooner", so that an unreasonable request would

not have to be honored.    Tr. 949-50.   A  Todd  County  administrator  asked   what

happens if the decision is not issued within three weeks -- is the violator

"off the  hook"?  Tr. 45.   The Administrative Law Judge  believes  that  since  the

rule fails to state the penalty for  not  meeting  the  three-week  period,  it  is

discretionary, not mandatory, and the party  seeking  action  would  be  forced  to

go to court for a writ.    The Board may want to  consider  specifying  an  outcome,

but given the variety of circumstances which can occur, it may be best to

leave it for a case-by-case  determination.  The  rule  is  not  defective  without

specifying an outcome.  The  first  comment,  however,  does  point  out  a  problem

which must be dealt with.

 

    77.  The provision that requires the LGU or technical panel to make a

decision within three weeks from the date of the  application  "or  sooner  if  the

landowner requests" has not  been  demonstrated  to  be  reasonable.  There  is  no

defense of it in the SONAR or hearing record,  and  common  sense  suggests  it  is

unreasonable.  This defect can be cured by  either  deleting  the  last  phrase,  so

that the decision would have to be made within three weeks.      Another way to

 

 

 

                                       -21-

 


cure the defect would be to add limiting language to make sure that the

request for "sooner" is reasonable under the circumstances.        The

Administrative Law Judge recommends that the phrase "or sooner if the

landowner requests" be deleted, as it  would  be  difficult  to  draft  language

that would cover all the possible eventualities.

 

 

Replacement Plans:    part 8420.050O_to 8420.0630

 

     Sequencing.

 

     78.   The Act makes it clear that  impacting  one  wetland  and  replacing  it

with another is to be the last  resort  solution  to  a  problem,  The  problem  must

be first addressed by  avoiding  the  impact,  minimizing  the  impact,  rectifying

the impact, and reducing or eliminating the impact over time.        The  Act  directs

that these principles are to be used  "in  descending  order  of  priority",  and

that replacing or providing a substitute wetland  is  to  be  the  last  option.

The rules on sequencing  reflect  that  legislative  priority.  They  require  an

applicant who wants to impact one wetland  and  replace  it  with  another  to  first

demonstrate attempts to avoid, minimize, rectify, etc.       The  detailed   showing

required, however, was characterized as "silly", "excessive", "unreasonable",

and "impractical".    Commentators were  particularly  concerned  when  the  full

sequencing procedures were applied  to  small  impacts,  believing  that  the  time

and expense required to document the  required  steps  was  out  of  proportion  to

the impact.

 

     79. The Board responded  to  these  criticisms  by  proposing  to  delete  the

requirement for written documentation in the case of projects impacting

wetland areas less than 0.1 acres.  The  Board  proposed  that  in  those  cases,

the local government unit  could  provide  an  on-site  sequencing  determination

without the written documentation.     The Board  proposed  exceptions  to  that,

however, for projects  within  certain  distances  of  outstanding  resource  value

waters, trout streams, and trout lakes.  The Board's proposal for small

wetlands would not remove the requirement  that  the  LGU  must  assure  itself  that

avoidance, minimization,  etc.  has  occurred.  That  requirement  would  still

apply.   All the Board's modification  would  do  is  remove  the  documentation

requirements for those small wetlands less than 0.1 acres.

 

     80.  The Administrative Law Judge finds that the Board has justified its

proposed change.    Although the change  was  drafted  in  connection  with  changes

to the notification requirements which  were  found  to  conflict  with  the  statute

(see Finding 61 above), the change to reduce the documentation does not

conflict with any statutory requirement.      What the statute  requires  is  that

the LGU be guided by the principles of avoidance, minimization, etc.         The

statute does not specify what documentation is required.       The Board's

modification on documentation may be adopted.

 

     81. The Board had proposed  to  insert  its  language  relating  to  wetland

areas less than 0.1 acres on page 44, at  line  3.  This  would  seem  to  "bury"

the language in the middle of a paragraph relating to alternatives.        It would

make more sense if the proposed  insertion  were  a  stand-alone  paragraph,  so

that it was clearly seen by persons not familiar with the rules.       This   is

solely an editorial suggestion, however, not a requirement.

 

                                        -22-

 


Replacement Plan Components

 

     82.  The amount and detail of information required In a replacement plan

application was attacked as "onerous and expensive" by groups such as the

Urban Coalition (Letter of December 31), the Douglas Soil and Water

Conservation District (which questioned cost effectiveness at Tr. 28) and the

Todd County Administrator, who labeled them "unreasonable".  Tr. 46.

 

     83.  In response, the Board has reduced the amount of information

required for plans utilizing the wetland bank.  The Board has also proposed a

number of more detailed changes in an attempt to make the application more

"user friendly".   The Board has committed to the development of standardized

forms and procedures to be contained in an administrative manual (post-hearing

submission, at p. 19).  The Administrative Law Judge finds that the Board has

justified the amount of detail required in the replacement plan provision.

Since many of the smaller impacts are likely to be mitigated by the wetland

bank, simplifying the application paperwork for projects utilizing the bank

will alleviate some of the concern expressed.

 

 

Replacement Plan Evaluation CriteriA

 

     84.  Another of the five major issues identified by the Board is a

provision which prohibits the use of a previously drained wetland, which was

drained pursuant to an exemption from the replacement requirements, as the

replacement for a new impact, for a period of ten years from the time that the

original wetland was impacted.   An example may help explain this somewhat

complicated idea.   A landowner has two wetlands on his property, one of which

is exempt from the Act, the other one is not.  This rule would prohibit the

landowner from draining the first wetland under the exemption, and then

turning around and using it as replacement for draining the second wetland.

The Board has proposed that the restriction against using an exempted wetland

for replacement extend for ten years from the time that it was originally

drained or filled.   However, the Board recognized that there were some who

believed that such wetlands should never be allowed for use as replacement

wetlands because it would be contrary to the no net loss goal of the Act.  The

argument in favor of the ten-year limitation is that one of the Act's goals is

to restore natural wetlands, and ten years is long enough to deter those

"schemers" who would attempt to abuse the law by taking advantage of the

exemption.   See, for example, Tr. 320.   Indeed, some argued that ten years was

too long, and that it ought to be reduced to five years.   Tr. 418.   Both the

MPCA (letter of December 30) and the Urban Wetlands Management Coalition

(letter of December 31) supported the ten-year compromise, arguing that it

will prevent "deals", but will also allow the use of natural wetlands for

restoration.

 

    85.  The Administrative Law Judge believes that the Agency has

demonstrated the need for and reasonableness of its proposed rule which would

allow wetlands drained under an exemption to be used as replacement wetlands

after ten years had passed.   While it does allow for a loss, the 2:1 ratio on

many replacements should make up for that loss, so there will not be a net

loss.  Moreover, the arguments favoring restoration of natural wetlands, as

opposed to created ones, support this provision.   It is unlikely that many

people will bother to drain an exempt wetland now so it will be available for

 

 

 

                                     -23-

 


restoration ten years from now.  The benefits outweigh the risks, and the

Board has justified its position.

 

     86.  Both the statute and the rule require that replacement of wetland

values must be completed prior to or concurrent with the actual draining or

filling of a wetland, unless an irrevocable bank letter of credit or other

security acceptable to the local government unit is submitted to guarantee

successful completion of replacement.  However, one of the goals of

replacement is the replacement of impacted plant life, and a later rule,

part 8420.0550, subp. 2 E. states that when feasible, organic soil used for

backfill of a restored wetland should be taken from the impacted wetland.  One

commentator thought these two provisions were irreconcilable, particularly

when it may take weeks or even months for a drained wetland to dry out enough

to allow earthmoving equipment to be used.  Letter of Dennis Miller,

December 29.  The Administrative Law Judge does not believe the two are

fatally irreconcilable, because of the flexibility inherent in terms like

"concurrent with" and "when feasible".  However, the Board may want to

consider asking the Legislature to allow a reasonable period of time, say one

or two months, to allow for the transfer of organic soil from the old wetland

to the new.   While a bank letter of credit could be used to facilitate this,

it seems an unnecessary penalty to place on the landowner who is attempting to

comply with the soil transfer rule.

 

     87.  An error occurred in the preparation of the final draft of

part 8420.0540 so that two sentences were omitted from the version as

published in the State Register and mailed out to interested persons.  This

error was announced at the start of each hearing session except for the first

two sessions in Alexandria.  The first announcement of the error occurred at

the start of the afternoon session in Thief River Falls (Tr. 206) and was made

at all subsequent sessions.  In addition, an errata sheet describing the

omission was distributed at each of the hearing sessions except for

Alexandria.  Ex. 19.  The question arises as to whether the Board's proposed

insertion of the omitted language into the rule without its being published

and distributed in advance is mere harmless error, or whether it constitutes a

substantial change.

 

    88.  The language at issue is to be added to part 8420.0540, subp. 6,

which is on page 55, at line 12.  That section deals with the required size of

replacement wetlands, and contains a statement that for wetlands on

non-agricultural land, the minimum replacement ratio is 2:1, but for wetlands

on agricultural land, the minimum replacement ratio is 1:1.  The omitted

language reads as follows:

 

         Present and future owners may make no use of the wetland

         after it is altered, other than as agricultural land for

         a period of ten years unless future replacement to

         achieve a 2:1 ratio occurs.  The landowner must execute

         and the LGU must record a notice of this restriction.

 

As explained during the hearing sessions, and in the Board's post-hearing

submission, this provision is parallel with other 10-year provisions which are

designed to avoid abuses of the Act.  For example, as discussed above, a

wetland which has been drained or filled under an exemption cannot be used as

a restoration credit for ten years after it has been drained or filled.

Secondly, a wetland that has been drained or filled under an agricultural

 

 

 

                                    -24-

 


 exemption (so that no replacement is required) must stay in  agricultural  use

 for ten years.  If it is converted to another use, then it must be replaced at

 that point, as if the land had been converted before the draining had

 occurred.  The omitted language quoted above provides that if a wetland on

 agricultural land is drained but not under an exemption, but is replaced at a

 1:1 ratio rather than at a 2:1 ratio, and then the land is converted to

 nonagricultural use during ten years, the rule requires that  the  replacement

 must be increased to a 2:1 ratio, as if the conversion had occurred  prior  to

 the draining.  The Department argues that because the omitted language is

 logically consistent with the other two rules, persons should not be surprised

 to see it, even though it was omitted from the rule as  published.

 

      89.  The provision was adopted by the Wetland Heritage Advisory Committee

 and accepted by the Board prior to the hearing.  It  was  apparently  suggested

 by DNR to the Wetland Rule Working Committee, but the affected section of the

 rule did not receive final review by the committee, and thus the suggestion

 was left to the Heritage Advisory Committee and the Board for their

 consideration.

 

      90.  The Board points out that all persons who attended the hearings,

 except for those on the first day, had the opportunity to comment on the

 proposed language, and none expressed any concern with the fact that it had

 not been published.

 

      91.  No persons submitting written comments criticized the proposed

 language as a substantial change, although it was criticized on other grounds.

 

      92.  Minn.  Stat.  14.05, subd. 2 provides as follows:

 

           An agency may modify a proposed rule in accordance  with

           the procedures of the Administrative Procedure Act.

           However, an agency may not modify a proposed rule so that

           it is substantially different from the proposed rule  in

           the Notice of Intent to Adopt Rules.

 

      93.  Minn.  Rule pt. 1400.1100, subp. 2 provides as follows:

 

           In determining whether a proposed final rule or a rule as

           adopted is substantially different, the Administrative

           Law Judge or the Chief Administrative Law Judge shall

           consider the extent to which it affects classes of

           persons who could not have reasonably been expected to

           comment on the proposed rules at the rulemaking  hearing

           or goes to a new subject matter of significant

           substantive effect, or makes a major substantive  change

           that was not raised by the original Notice of Hearing in

           such a way as to invite reaction at the hearing, or

           results in a rule fundamentally different in effect from

           that contained in the Notice of Hearing.

 

      94. The test quoted above has four elements.  The  omitted  language  does

not affect classes of persons who could not have been expected to comment on

the rules at the hearing.  The classes of persons affected, landowners who

would take advantage of the 1:1 ratio for impacts on agricultural land, were

well represented at the hearings.  The added language does not go to a new

 

 

 

                                      -25-

 


subject matter of significant substantive effect.  The concepts of special

treatment for agricultural land, and assuring that special status is not

abused, were discussed at length.  What was not  discussed,  however,  was  the

concept of having to go out to acquire additional mitigation within a  ten-year

period if the land were converted.  That is so close to the idea of  having  to

mitigate if an agricultural exemption is used, that it certainly cannot be

labeled "new subject matter".  Nor does the additional language  make  a  major

substantive change that was not raised by the original Notice of  Hearing.  The

impact of the new language is simply not "major" in the sense of these  rules,

and the two other parallel provisions would be likely to evoke the same

response as this one.

 

    95. The most troublesome of the four tests is  the  last  one  --  whether

the new one results in a rule fundamentally different in effect from that

contained in the Notice of Hearing.  The Administrative Law Judge does not

believe that adding the proposed language creates fundamentally different

effects.  A great deal of testimony was directed to the idea of recording

exemptions, for example, so that buyers would know limitations  on  what  they

were purchasing.  Much comment was devoted to the question of whether or  not  a

wetland drained under an exemption could be used as a  replacement  after  ten

years.  The concept of requiring additional mitigation if a  conversion  occurs

within ten years after draining a nonexempt wetland is similar  in  effect  to

the others that the omission does not result in a rule that is  "fundamentally

different in effect".

 

    96. The conclusion is buttressed by the fact that  no  commentator  raised

the substantial change issue, even though the omission was announced and

explained at the start of each hearing session except for the first  two,  and

the fact that it was highlighted by a separate handout available at each

hearing session except the same two.  In addition, the language must  have  been

the subject of a specific discussion at the Heritage Commission review of  the

Rule Working Committee's report in order for it to have been included  in  the

rule as adopted by the Heritage Commission.  The Heritage  Commission  is  made

up of persons with a broad range of views.  Some members of the  Commission  did

testify during the hearings, but none of them raised this as  a  concern.  All

this buttresses the judgment that this is not a substantial change.

 

    97.  MNDOT (which was aware of the potential for a substantial change

issue, but did not raise it) is opposed to the rule because, they  allege,  it

conflicts with the statute.  MNDOT points out that Minn.  Stat.   103G.222  (f)

and (g) provide as follows:

 

         (f)  for a wetland located on nonagricultural land,

         replacement must be in the ratio of two acres of replaced

         wetland for each acre of drained or filled wetland.

 

         (g)  for a wetland located on agricultural land,

         replacement must be in the ratio of one acre of replaced

         wetland for each acre of drained or filled wetland.

 

MNDOT argues that the statute does not reference activity as the  prerequisite

for a 1:1 replacement ratio, rather, it references the location of the

wetland.  MNDOT argues that the omitted language  exceeds  statutory  authority

by limiting the 1:1 replacement ratio to only agricultural activities

impacting wetlands on agricultural land.  They argue that  the  only  rationale

 

 

 

                                     -26-

 


for limiting the 1:1 ratio to agricultural activi ties is that of retri bution

on the nonagricultural community, by arbitrarily increasing the amount, and

therefore cost, of their required wetland replacement.         The nature of  the  loss

itself, not the type of activity causing the loss , they believe, should be  the

deciding factor.

 

      98. The  Administrative  Law  Judge  cannot  accept  MnDOT's  argument.  It  is

true that the determinative factor in all of the exemptions and other special

benefits is whether or not the wetland is located on agricultural  and .  It  is

true that it is not the purpose for which the activity is undertaken that

determines whether or not the exemption occurs.        But it is the change in the

status of the land which triggers the increased ratio.         It is converting the

land from agricultural land to some other  kind  of  land  that  is  at  issue  here,

and thus the proposed language is not in conflict with the statute.

 

      99.  The final issue which must be raised in connection with these two

sentences is whether or not the failure of the agency to mention them in its

Statement of Need  and  Reasonableness  violates  Minn.  Rule  pt.  1400.0500,  which

is designed to allow persons to be able to fully prepare any testimony or

evidence in favor of or opposition to a rule.        The rule provides that if an

agency presents evidence or testimony not summarized in the SONAR, and any

interested person so requests, the Administrative Law Judge may recess the

hearing to allow the public time  to  prepare  their  own  testimony  or  evidence  in

opposition to the agency.  No person made such a request, despite the fact

that at all the sessions (except Alexandria) the matter was specifically

called to their attention by Attorney Clapp, the rationale explained, and

comment was solicited.     The absence of any such comment (except from MNDOT)

suggests that the provision simply was not of interest to the hundreds of

organizations and individuals who did comment on the rules.        Under the

circumstances, no remedial action is required.

 

 

Circular 39, the Cowardin System, and the Replacement Ratios

 

     100.  Subpart 10 of Rule 8420.0540 was one of the most complicated

portions of the rules because it tackles the difficult task of dealing with

wetland functions and values.      It is a response to the statutory requirement

that the rules must:

 

           address the criteria, procedure, timing, and location of

           acceptable replacement of wetland values; [and] may

           address  . . .  the methodology to be used in identifying

           and evaluating wetland functions . . . .

 

Section 103G.2242, subd. l(a).

 

     101.  These are very difficult assignments, as there is no universally

accepted methodology for dealing with values and functions.        There are

numerous alternatives available from various international and national

organizations, as well as from other states.

 

     102.  The United States Fish  &  Wildlife  Service  has  published  two  separate

systems for describing wetlands.      The first, published in 1956, is known as

Circular No. 39.    It described wetland basins by type (type 1 , type 2 type 3,

etc. ) based primarily upon their use by waterfowl and wildlife.      Water depth,

 

 

 

                                        -27-

 


salinity, and/or generalized vegetative descriptions (wooded swamps, shrub

swamps, etc.) were the primary criteria for typing the wetlands.    However, the

Fish & Wildlife Service believes that the Circular 39 system is currently

outdated and, in fact, is now out of print.  Letter of Decemberr 30.

 

     103.  The Circular 39 system was replaced by the Fish & Wildlife Service's

Coward in system, first published in 1979, which is not based solely on

waterfowl or wildlife values.  It is more detailed than  the  Circular  39

system, and is asserted to be based upon ecological concepts and

state-of-the-art knowledge of wetlands.  It is the basis for the national

wetlands inventory maps, and the computerized wetland data base that is being

developed from those maps.  It provides the basis for the 1989 federal manual

which is referenced in section 103G.2242, subd. 2, as the manual which must be

used by technical evaluation panels in reviewing replacement plans.

 

     104  Many people who commented on the rule objected to the use of the

Cowardin system at all.  Many of them, particularly professionals who have

worked with the Circular 39 system for some years, objected to the departure

from Circular 39.  The Board, in response, has proposed to include a

conversion chart for the two classification systems.  This chart is designed

to allow users to determine Circular 39 wetland types based upon the Cowardin

inventory maps and on-site field inspections.

 

     105.  The Administrative Law Judge concludes that the use of the Cowardin

system is an appropriate response to the Legislature's requirement that the

Board identify and develop a system based on functions and values.  While

there are legitimate complaints that the Cowardin system doesn't go as far as

it ought to, and that there may be better systems available to meet the

legislative goal, the Administrative Law Judge believes that the  Board's

choice of Cowardin is a reasonable one.  The Board has submitted into the

record a variety of documents illustrating various systems which are in the

literature and in use in various locations.  The Board is not  unaware  of

them.  However, the Board was concerned about the practicalities of using a

system in the field, and chose a relatively simple one over more  complex

ones.  One of the criticisms labeled at the Board was that it attempted to

simplify the Cowardin system too far in order to make it workable in  the

field.  Practicality of application is a legitimate factor for the Board to

consider, and so long as a system meets the minimum criteria of the statute,

the Administrative Law Judge will not disturb it.  See, Manufactured Housing

Institute v. Pettersen, 347 N.W.2d 238 (Minn. 1984).

 

    106.  The basic outline of the Board's approach to evaluating replacement

wetlands is as follows:  A replacement wetland should be as similar to the

impacted wetland as possible, not only in terms of size, but also in terms of

function and value.  There must be flexibility, however, in designing

replacement wetlands if they are to be used at all.  There are three

characteristics which, taken together, represent a reasonable assurance of

similar functions and values.  These are (1) the type of wetland  per  the

Cowardin system, (2) the location in terms of watershed units, and the

(3) inlet/outlet characteristics.  If these three factors are the same for

both the impacted wetland and the replacement wetland, then it can be said

that the two are similar and one is a reasonable replacement for the other.

But if any of the three characteristics are different, then the two wetlands

are not similar, and it is necessary to consider whether or not some

adjustment to the replacement wetland is necessary in order to at least bring

 

 

 

                                     -28-

 


it closer to the impacted  one,  in  terms  of  replacing  the  functions  and  values

which have been lost.

 

     107.  Much of the  complexity  of  the  rule  results  from  these  adjustments.

They are like the Income Tax Code in  that  the  Code  attempts  to  tax  people  in

similar situations the same amount, but the Code gets very complex in

attempting to make the situations similar.       For example, one  person  may  have  a

very high salary,  but  an  uninsured  catastrophic  medical  expense  may  take  much

of it away in a particular year.      His neighbor may have  a  low  salary,  but  no

catastrophic medical expenses.     If we assume that the two have relatively

similar abilities to pay, then a fair  tax  system  would  be  one  which  provided  a

deduction for the medical expenses  so  that  the  two  paid  roughly  equal  taxes.

When adjustments are  made  not  only  for  catastrophic  medical  expenses  but  also

for  home  mortgage  payments,  charitable  contributions,  investments  in  capital

equipment, child  care  expenses,  legitimate  business  expenses,  etc.,  the  Code

does get complex.    The same kind  of  complexity  occurs  in  connection  with  the

various adjustments required by these rules.       The more accurate  a  system  is  in

replicating the functions and values between the impacted wetland and the

replacement one, the more complex it is going to be, and the harder it is

going to be to administer in the field.  The Urban Wetland Management

Coalition, for  example,  recommended  an  approach  (referred  to  as  the  "Peterson

approach") which would replace the Board's matrix and ratios with a

descriptive narrative system.     In this  system,  the  impacted  wetland  would  be

examined for its functions and its values (separately) that needed to be

replaced, then the community would be reviewed to see whether any of those

could be  adequately  addressed  by  other  permitting  or  approval  processes,  then

each of the remaining unreplaced functions would be evaluated against

narrative criteria, which may  or  may  not  be  quantitative  depending  on  what  is

known about them.    The Administrative Law Judge believes that such a system

(if well written and well applied) might yield a more accurate replacement

than the Board's system.    But he also agrees with those who complained that

the Peterson  approach  requires  highly  training  personnel  and  time  (and  money)

for analysis.  Letters from DNR of December 31 and January 8.  The

Administrative Law Judge notes that for projects of unusual complexity or

replacement plans that have been denied and are on appeal, the LGU may

evaluate  the  replacement  plan  using  Minnesota  wetland  evaluation  methodology

or any other scientific methodology approved by the Board.  Therefore, the

Peterson approach could be used (if approved) for unusual projects.

 

    108.  Another criticism leveled  at  the  Board's  index  system  is  that  it  has

the potential to require more  than  a  1:1  or  2:1  replacement  for  each  impacted

acre.   The Urban Coalition  submitted  an  example  that  ended  up  with  more  than

four acres of replacement for each acre lost.      The  Board's  response  is  that  if

it is necessary to go above 1:1 or  2:1  in  order  to  replace  the  wetland  values,

then the rules may require it.     SONAR, pp. 30-31.     The Administrative Law

Judge finds that the increased ratios reflect an attempt to compensate for

lost values in a rough, but practical manner.      As  discussed  above,  the   costs

of recreating values on a strict acreage basis would require a level of

technical expertise and sophistication which neither the State nor the LGUs

can afford.  The tradeoff for a reduced level of values protection is an

increased quantity of acreage.  The Board recognizes this tradeoff and the

Administrative Law Judge accepts  their  rationale  as  a  reasoned  one,  which  is

not in conflict with the acreage ratios in statute.

 

                                        -29-

 


Wetland Banking

 

     109.  Many persons objected to the "one size fits all" aspects of  some  of

the rules proposed by the Board.  They stated that the  geography,  soil  and

historic drainage differences between northwestern  Minnesota,  northeastern

Minnesota, southwest, southeast, and metro areas required more  flexibility

than the rules allowed.  The Board's attempt to  accommodate  these  differences

included a number of items, but one of the primary ones was the ability to  use

a wetland bank to mitigate impacts from draining or filling.  The  Board  is

authorized by Minn.  Stat.  130G.2242 to adopt rules to establish a  wetland

banking program, and the Board has done so.  The basic idea behind the  bank  is

that it provides an alternative procedure for replacing lost wetland  values

when project-specific replacement is impossible or impractical.

 

    110.  The major issue in connection with wetland banking is whether  or  not

created wetlands ought to be allowed for deposit into the bank, or whether  the

bank should be limited to accepting only restored wetlands.  This  issue  was

one of the five issues highlighted by the Board for particular  attention,  and

a high percentage of all of the comments included statements about this  Issue.

 

    111.  The statute does not provide any limitation on the use  of  created

wetlands for the bank.

 

    112.  Initially, the Board proposed that only restored wetlands would be

eligible for deposit into the bank, and created wetlands would not be

eligible, The underlying reason for this limitation was the belief that  it  is

extremely difficult to create a truly functioning wetland where  no  wetland

previously occurred, and that it is ecologically better to restore an old

wetland than to try to create a new one.  The Board reasoned that  since  the

whole idea of a bank was optional, it was not illogical to limit it  to  the

more promising type of wetlands.  SONAR, p. 39.  Representative Munger

indicated that wetland banking was discussed by the Legislature as a  system

for banking restored wetlands only.  He did not support the  use  of  created

wetlands for banking because they do not function well as  wetlands.  Tr.  809.

Other reasons for avoiding created wetlands are that it makes it very  easy  to

convert numerous small losses into one large replacement ("clumping"),

particularly when a dam or dike is built to impound a watercourse.  DNR  letter

of January 8. In oral testimony, the DNR argued that there are more  than  nine

million acres of drained wetlands available for restoration, and restoration

should be favored.  Tr. 841.  The Department went on to  state  that  if  created

wetlands were allowed to be banked, they should be limited  to  excavations,

rather than impoundments, because impoundments often inundate existing

wetlands and also have the undesirable "clumping effect".

 

    113.  Testimony at the hearings, and in written comments,  favored  the  use

of created wetlands as a major relief valve for mitigation in certain parts  of

the State.  Urban real estate, for example, may be difficult to  acquire  and

extremely expensive; taking lands away from woodlands or open spaces is a

public detriment which should be weighed in the balance.  Letter of  Raymond  D.

Haik on behalf of Minnesota Association of Watershed Districts dated

December 23.  Counties with very high percentages of their wetlands never

having been drained (counties like Lake and Cook have had less than five

percent of their presettlement wetlands drained), have very  few  opportunities

to restore wetlands locally, and thus would be forced to  purchase  restoration

credits from the south and western parts of the State where there  are  many

 

 

 

                                    -30-

 


opportunities for restoration.  Many argued that allowing  created  wetlands  to

be banked would be fairer to all counties.  Advocates also  argued  that  the

statute specifically allows created wetlands to be used in  replacement  plans,

and since banking is simply an alternative process for  achieving  replacement,

creation should not be excluded from the bank.  MNDOT,  along  with  virtually

every county highway department, argued that there have been  numerous  examples

of successful wetland creations and that many of the Board's own wetland

replacement standards are taken from MNDOT design guidelines.  Letter of

December 24.  Proponents of created wetlands also argued that  there  will  be

thorough, site-specific review by the LGU, the technical evaluation  panel,  and

other interested parties, and this should heighten the chances  for  success.

They point to the limitations in the proposed rules which require  that  only

functioning wetlands can be deposited in the bank to begin with,  and  suggest

that nonfunctioning created wetlands can be avoided by that mechanism.

 

     114.  In its post-hearing submission, the Board proposed  a  compromise,

essentially based on the DNR position.  The Board pointed out  that  the  record

did contain actual examples of good created wetlands, as well as a  number  of

suggestions for limiting the use of created wetlands so as to  maximize  the

chances for their success.  The Board recommended allowing  created  wetlands  to

be banked, but proposed limitations on the use of created wetlands.  The

primary one is that they would either have to be constructed by  excavation  or,

if they were constructed by impoundment, they would have to be limited  to  less

than ten acres in size, The Board also proposed to impose  a  longer  "waiting

period" for created wetlands before they could be approved (by  the  technical

panel) for deposit in the bank.

 

     115.  The Administrative Law Judge concludes that the Board has

demonstrated the reasonableness of its position to allow banking  of  created

wetlands.  There is no question but that there have been  some  created  wetlands

in other states which have been environmental failures, but with the

limitations and safeguards present in these rules, the risk of  that  occurring

here have been reduced.  The equities to some parts of the State, and the

efficiencies for mitigating very small impacts, outweigh the small risk

remaining that created banking will be a detriment to the  biological  diversity

required by the Act.

 

     116.  Another typographical error occurred in the rules at page 77,

line 10.  It is part of a provision designed to avoid "clumping" which

provides that as an incentive to encourage the restoration of  small  wetlands,

the LGU shall "devalue" restored acreages greater than ten acres by ten

percent, while restorations of zero to ten acres would receive 100%  credit  for

their acreage.  The rule as published went on to provide:

 

          The local government unit may modify the credit given, up

          to a maximum of 100%, if unanimously agreed to by the

          technical panel.

 

The word "unanimously' should have been removed from the version of  the  rule

as published, but it was not.  Both the Board and the utility industry

(Tr. 766 and Minnesota Power letter of December 30) noted that  the  Wetland

Heritage Advisory Committee had stricken the word, but that  it  inadvertently

had reappeared in the Revisor's draft of the rule.  The  Administrative  Law

Judge has reviewed the minutes of the Advisory Committee meeting,  and  agrees

that those minutes reflect that the word was removed.  It  is  appropriate  that

 

 

 

                                      -31-

 


it be removed from the final version of the rule in light of this history.  It

is a harmless error, and its removal is not a substantial change.

 

     117.  There were complaints registered about the "devaluation", primarily

because it is not in the statute.  MNDOT letter of December 24.  The

Administrative Law Judge reads the statutory provisions for banking to be

extremely general, granting the Board a greater degree of latitude than  some

of the detailed statutory provisions in other sections.  Therefore,  the  fact

that the "devaluation" is not mentioned in the statute does not prohibit  its

use in the rule.  Moreover, in light of the concerns over clumping  which  can

result from the use of created wetlands and banking, this ten percent

devaluation is not unreasonable.  The Board did consider some of the

alternatives proposed during the hearing, but could not agree with any of

them.  Under the circumstances, the Board's position is reasonable.

 

     118.  Some counties and municipalities have implemented their own  banks

under the interim rules, and some have positive balances.  The Cass Soil &

Water Conservation District introduced into the record a memo dated  November

23, 1992, from a Board employee which stated that any positive balances in

local banks would have to be "zeroed out" by July 1, 1993.  Ex. 27.  Cass

County had established a local bank pursuant to a county board resolution, and

urged that any wetland acres banked using the criteria in the permanent rules

be allowed to carry over into the new state bank without penalty.  Tr.  415.

See also, Tr. 858.

 

     119.  The Board responded with a proposal that would allow certain

replacement credits into the bank under limited conditions.  The proposal

would allow the following:

 

          Also, wetland replacement that has been completed and

          deposited in a local government unit bank prior to the

          effective date of these rules and after January 1, 1992

          is eligible for deposit into the statewide banking system

          if the project meets all of the criteria in subpart

          8420.0700 to 8420.0760 based on a site inspection and

          review by the board and the commissioner.

 

The Administrative Law Judge finds that given the limitations in the proposed

rule, the rule is reasonable and not a substantial change.

 

     120.  Criticisms were made that the Statement of Need and  Reasonableness

failed to properly analyze the impact on agricultural land, as required by

Minn.  Stat.  17.83.  That statute provides that if an agency proposes to

adopt a rule "which it determines may have a direct and substantial  adverse

effect on agricultural land", then it must include notice of the adverse

effects in the Notice of Hearing and include certain material in the Statement

of Need and Reasonableness.  The term "action which adversely affects" is

further defined, however, to be limited to acquisition, permitting, leasing or

funding for nonagricultural uses.  The thrust of the statute is one of notice,

both to the public and to the commissioner of agriculture.

 

    121.  The Administrative Law Judge concludes that this statute  has  been

satisfied, both as to its letter and as to its spirit.  From a technical

standpoint, the statute does not apply at all.  These rules do not involve

acquisition, permitting, leasing or funding within the meaning of the

 

 

 

                                     -32-

 


statute.  But more importantly, as a practical matter, the agricultural

community and the commissioner of agriculture have been deeply involved in the

drafting and commenting process.  The record, for example, contains

recommendations from the Commissioner (letter of October 1) which indicates

that the Department of Agriculture participated in both the Heritage Advisory

Committee and the Rule Drafting Committee.  The spirit of the statute has been

satisfied, as well as the letter.

 

     122.  Criticisms were also leveled at the Board's estimate of the fiscal

impact of the rules.  See, for example, letter from the Association of

Minnesota Counties dated December 30.  The law requires that if the adoption

of a rule will require the expenditure of public money by local public bodies

and the estimated total cost exceeds $100,000 in either of two years

immediately following adoption of the rule, then a fiscal note must be

prepared.  There is no question but that these rules will require the

expenditure of substantial sums of money by LGUs.  The Board did prepare a

fiscal note.  The Board estimates that the total statewide cost for LGU

implementation will be four million dollars per year for each of the next two

years, or a total of eight million dollars for the biennium.  Some entities

have criticized this as being a gross underestimate, and provided examples of

their own estimates.  The Administrative Law Judge concludes, however, that

the law has been satisfied because the Board has provided a fiscal note which

is in within the realm of reasonableness.  The Board asked LGUs to document

the cost of implementing the interim phase of the Act, and then selected a

geographically representative sample to get a representative estimate of the

actual costs.  The average for 13 LGUs who responded to the Board's request

was $14,000.  The LGUs noted, however, that the interim program was simpler

than the final program, and that more money would be required to administer

the final one.  The Board added $6,000 to adjust for this change, coming up

with a total of $20,000 as an annual average cost per LGU.  Based on the

assumption that approximately 200 LGUs would be involved in the program, the

Board computed its four million dollar total.  This is based on an average,

which ranges from LGUs that may only have three or four or five applications

per year to LGUs which will have to deal with more than a hundred applications

per year.  Since it is based on such a wide variation of activity, it must be

viewed as only a rough estimate.  But it is adequate for the Legislature and

others to get an idea of the fiscal impact of the rule.

 

 

General Comments

 

    123.  Compensation to landowners for the restrictions imposed upon them by

the statute and these rules was a topic brought up by many persons throughout

the hearing process.  The concept expressed is essentially as follows:

 

         If preserving wetlands is such a great societal benefit,

         then society ought to compensate those who are burdened

         by restrictions on the use of their land.

 

Many people claimed that the statute and rules were unconstitutional in that

they failed to provide such compensation.  The Attorney General's Office,

however, has studied the matter and is of the opinion that neither the statute

nor the rules are unconstitutional on their face.  Tr. 345.  There may be

particular situations where particular pieces of land and particular

administrative actions may cause an unconstitutional taking requiring

 

 

 

                                    -33-

 


compensation, but those must await resolution on a case-by-case basis.     The

Administrative Law Judge is not empowered to rule on the facial

constitutionality of a rule.  Neeland v. Clearlater Memorial Hospital, 257

N.W.2d 366, 368 (Minn. 1977).    Such a claim must be directed to  the  judicial

branch.

 

 

     Based upon the foregoing Findings of Fact, the  Administrative  Law  Judge

makes the following:

 

                                  CONCLUSIONS

 

     1. That the Board gave proper notice of the hearing  in  this  matter.

 

     2.  That the Board has fulfilled the procedural requirements of Minn.

Stat.  14.14, subds. 1, la and 14.14, subd. 2, and all  other  procedural

requirements of law or rule, except as noted at Finding 7.

 

     3.  That the Board has demonstrated its statutory authority to  adopt  the

proposed rules and has fulfilled all other substantive requirements of  law  or

rule within the meaning of Minn.  Stat.  14.05, subd. 1, 14.15,  subd.  3  and

14.50 (i)(ii), except as noted at Findings 61, 73 and 74.

 

     4. That the Board has documented the need for and  reasonableness  of  its

proposed rules with an affirmative presentation of facts in the  record  within

the meaning of Minn.  Stat.  14.14, subd. 2 and 14.50 (iii), except  as  noted

at Findings 30 and 77.

 

     5.  That the amendments and additions to the proposed rules which were

suggested by the Board after publication of the proposed rules in the State

Register do not result in rules which are substantially different from the

proposed rules as published in the State Register within the meaning  of  Minn.

Stat.  14.15, subd. 3, and Minn.  Rule 1400.1000, subp.  I and 1400.1100.

 

     6. That the Administrative Law Judge has suggested action  to  correct  the

defects cited in Conclusions 3 and 4, as noted at Findings 30, 73, 74  and  77.

 

     7. That due to Conclusions 2, 3, 4 and 6, this Report  has  been  submitted

to the Chief Administrative Law Judge for his approval pursuant to  Minn.  Stat.

 14.15, subd. 3.

 

     B.  That any Findings which might properly be termed  Conclusions  and  any

Conclusions which might properly be termed Findings are hereby  adopted  as

such .

 

     9. That a finding or conclusion of need and reasonableness  in  regard  to

any particular rule subsection does not preclude and should not  discourage  the

Board from further modification of the proposed rules based upon an

examination of the public comments, provided that no substantial change is

made from the proposed rules as originally published, and provided that the

rule finally adopted is based upon facts appearing in this rule hearing

record.

 

     Based upon the foregoing Conclusions, the Administrative Law  Judge  makes

the following:

 

 

 

                                     -34-

 


                                  RECOMMENDATION

 

     It is hereby recommended that the proposed rules be adopted except where

specifically otherwise noted above.

 

Dated this 11th  day of February, 1993.

 

 

 

                                          ALLAN W. KLEIN

                                          Administrative Law Judge

 

 

Reported:  Tape Recorded; Transcript Prepared.

 

 

                                    MEMORANDUM

 

     It should be stressed that this Report  deals  with  legal  questions,  not

policy ones.   The only way a policy question is discussed  is  in  the  context  of

whether or not the Board has demonstrated the  need  for  and  reasonableness  of

its proposed rules.    Therefore, a person should not look  to  this  Report  for

policy guidance.    The fact that a rule is found to be  reasonable  does  not  mean

that it is the "best rule" from a policy standpoint.      It may or may not  be  the

best rule.   Policy decisions are left for the Legislature and the Board.        Many

of the  written  submissions and some of the oral statements at the hearings

suggested  that  people thought the Administrative Law Judge would force the

Board to  adopt  whatever rule the Judge thought was the best one.  That is not

the case, and it should be clear that the only question which has been

answered with regard to policy is whether or not  the  Board  has  justified  its

policy choices as reasonable.    There is a "range  of  reasonableness"  that  is

broad enough to include many different ideas of how a rule ought to read.  So

long as the Board's proposal is within that range,  the  Judge  will  declare  it

to be reasonable.

 

     There were numerous suggestions for improvements  in  the  rule  which  are

not mentioned in this Report.    This is because discussing them was not

necessary to determine the reasonableness of  the  Board's  rule.  Many  of  them

are, however, desirable changes and, to the extent  the  Board  staff  has  time,

it would be worthwhile to review the record (particularly the written

submissions) to determine which of them it thinks improve the clarity or

working of the rule.    As noted in the final conclusion, there are limitations

on this process , but there is still a great deal of room for the Board to take

advantage of the comments.

 

 

                                      A.W.K.

 

 

 

 

                                       -35-