TABLE OF CONTENTS
Page
Statement of Issue.............................................................................................. 1
Recommendations............................................................................................... 2
Findings of Fact.................................................................................................. 2
A. Applicant............................................................................................ 2
B. Procedural Summary.......................................................................... 3
C. Description of the Project.................................................................... 5
D. Routes Proposed in the Application...................................................... 5
E. Routes Considered in the DEIS............................................................ 5
F. Structure Types and Spans................................................................. 7
G. Route Widths..................................................................................... 8
H. Right-of-Way...................................................................................... 8
I. Project Schedule................................................................................ 8
J. Project Costs..................................................................................... 9
K. Substations........................................................................................ 9
L. Federal, State, and Local Agency Participation..................................... 9
1. Minnesota Department of Natural Resources................................. 9
2. Minnesota Department of Transportation..................................... 11
3. Local Agencies.......................................................................... 11
4. OES Environmental Review........................................................ 11
M. Public Comments.............................................................................. 13
Criteria for a Route Permit................................................................................. 13
Application of Statutory and Rule Criteria............................................................ 15
I. Application of Routing Factors to the 345 kV Transmission Line.................. 15
A. Effects on Human Settlement............................................................. 15
1. Displacement............................................................................ 15
2. Noise........................................................................................ 16
3. Aesthetics................................................................................. 17
4. Cultural Values.......................................................................... 18
5. Recreation................................................................................ 18
6. Public Services.......................................................................... 19
B. Effects on Public Health and Safety.................................................... 20
1. Electric and Magnetic Fields....................................................... 21
2. Stray Voltage............................................................................ 22
3. Interference with Natural Gas Pipelines....................................... 23
C. Effects on Land Based Economies..................................................... 25
D. Effects on Archaeological and Historic Resources............................... 26
E. Effects on Natural Environment.......................................................... 27
1. Air Quality................................................................................. 27
2. Water Quality and Resources..................................................... 28
3. Flora......................................................................................... 29
4. Fauna....................................................................................... 32
F. Effects on Rare and Unique Natural Resources................................... 33
G. Application of Various Design Considerations...................................... 34
H. Use or Paralleling of Existing Right-of-Way, Survey Lines, Natural Division Lines, and Agricultural Field Boundaries.............................................. 35
I. Use of Existing Transportation, Pipeline, and Electrical Transmission System Rights-of-Way...................................................................... 36
J. Electrical System Reliability............................................................... 36
K. Costs of Constructing, Operating, and Maintaining the Facility.............. 38
L. Adverse Human and Natural Environmental Effects Which Cannot be Avoided............................................................................................ 38
M. Irreversible and Irretrievable Commitments of Resources..................... 39
N. Consideration of Issues Presented by State and Federal Agencies....... 39
O. Evaluation of Alternatives................................................................... 39
II. Route Width Flexibility.............................................................................. 40
III. Notice..................................................................................................... 41
IV. Adequacy of FEIS................................................................................... 41
Conclusions....................................................................................................... 42
Notice ....................................................................................................... 43
Summary of Testimony...................................................................................... 44
Oral Testimony at the Public Hearings................................................................. 44
Written Comments............................................................................................. 48
|
OAH Docket No. 16-2500-21470-2 MPUC Docket Nos. ET-2/TL-09-1315 E-002/CN-08-992 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the
Matter of the Application for a Route Permit for the Pleasant Valley to Byron
161 kV Transmission Line Project and In the
Matter of the Application of Northern States Power Company, d/b/a Xcel Energy,
for a Certificate of Need for a 161 kV Transmission Line in Dodge, Olmstead,
and |
FINDINGS OF FACT, CONCLUSIONS, RECOMMENDATION, AND SUMMARY OF TESTIMONY |
Public and
evidentiary hearings were held before Manuel J. Cervantes, Administrative Law
Judge (“ALJ”), commencing at 2:00 p.m. and 7:00 p.m. on October 26, 2010, at
the American Legion Hall, 505 Frontage Road, Byron, Minnesota.
Valerie Herring,
Briggs and Morgan, P.A., appeared on behalf of Northern States Power Company, a
Karen Finstad
Hammel, Assistant Attorney General, appeared on behalf of the Minnesota Department
of Commerce, Office of Energy Security (“OES”).
STATEMENT OF ISSUE
Have Applicants
satisfied the criteria set forth in Minn. Stat. § 216E.03[1]
and Minn. R. Chapter 7850 for a Route Permit for the Pleasant Valley to Byron
161 kV Transmission Line Project, including necessary system connections. If so, what route complies best with
applicable statutes and rules?[2]
Based on the
Findings of Fact and Conclusions that follow, the ALJ makes the following:
RECOMMENDATIONS
1.
That the Minnesota
Public Utilities Commission (“Commission,” “PUC,” or “MPUC”) determine that all
relevant statutory and rule criteria necessary to obtain a Route Permit have
been satisfied and that there are no statutory or other requirements that
preclude granting a Route Permit based on the record.
2.
That the
Commission grant a Route Permit to Xcel Energy for the facilities described
below, to the effect of authorizing a 161 kV transmission line between Pleasant
Valley and Byron and Associated Facilities utilizing Route Alternative 3 as
identified in the Final Environmental Impact Statement, placed partially within
the right-of-way of an existing 345 kV line between the Pleasant Valley and
Byron substations.
3.
If Route Alternative 3 is not granted a Permit, the ALJ
recommends granting of a Route Permit for the Route Alternative 1 (
4.
That a route width of 400 feet be authorized, unless the
Commission selects the Preferred Route, in which case the route width be
authorized as 400 feet and increasing to 1,100 feet on the west side of that Route
for a one half mile segment west of 680th Avenue where the Preferred Route crosses
the North Branch Root River.[3]
5.
That Applicants
be required to take those actions necessary to implement the Commission’s
Orders in this proceeding.
Based on the Hearing
record, the ALJ makes the following Findings of Fact and Conclusions:
FINDINGS OF FACT
A.
Applicant
1.
Xcel Energy is a
2.
Applicant applied for a Route Permit to construct a 161 kV
transmission line project from
B.
Procedural Summary
3.
On December 3,
2009, Xcel Energy submitted a Route Permit Application (“Application”) for the
Project under Minn. R. 7850 and Minn. Stat. ch. 216E. The Project includes a 161 kV transmission
line between the
4.
Xcel Energy
filed an application for a Certificate of Need (CON) for the Project on
December 3, 2009.[7]
5.
On February 9,
2010, the Commission accepted the Applicant’s Route Permit Application as
complete and authorized the OES staff to process the Application under the full
review process of Minn. R. 7850.1700 to 7850.2700.[8]
6.
The Commission
accepted the Applicant’s CON application as complete on February 18, 2010. The Commission directed that the informal
review process under Minn. R. 7829.1200 be used for the CON determination and,
where possible, joint hearings be conducted in the CON and route permitting
process. The ALJ was directed to provide
the Commission with a summary of testimony in the CON Docket.[9]
7.
On January 8,
2010, Applicants filed Confirmation of Notice including Affidavits of Mailing
and Publication as required under Minn. Stat. § 216E.03, subd. 4; Minn. R.
7850.2100, subp. 2; and Minn. R. 7850.2100, subp. 4..[10]
8.
This matter was
assigned to ALJ Manuel J. Cervantes of the Office of Administrative Hearings
(“OAH”) and a prehearing conference was held on September 20, 2010. On September 23, 2010, the ALJ issued a
Prehearing Order establishing the schedule and procedures for intervention,
prefiled testimony, hearing, and other matters.[11]
9.
The Prehearing Order specified an intervention
deadline of October 11, 2010. No
petitions to intervene were filed.
10.
On March 8,
2010, the OES issued a Notice of Public Information and Environmental Impact
Statement (“EIS”) Scoping meetings.[12]
11.
On March 25, 2010,
OES held public information and EIS Scoping meetings at the American Legion
Hall in
12.
On July 9, 2010,
the OES issued its EIS Scoping Decision that set out the alternatives and
issues to be addressed in the Project’s EIS. [14]
13.
On October 11,
2010, Xcel Energy filed direct testimony by Tom Hillstrom, Jason Standing, and
Grant Stevenson.[15]
14.
On October 13,
2010, the OES issued the Draft Environmental Impact Statement (“DEIS”).[16]
15.
On October 14,
2010, the OES issued its Notice of Public Hearing, setting the public hearing
on the DEIS for October 26, 2010, to be conducted in conjunction with a public
hearing in the Route Permit Docket.[17]
16.
On October 26,
2010, the ALJ conducted public comment hearings and the evidentiary hearing at the
American Legion Hall in
17.
Public comments
on the Project were accepted by the ALJ until November 8, 2010. Nine written comments were received.
18.
On November 30,
2010, OES issued the Final EIS (“FEIS”).
19.
On December 13,
2010, notice of availability of the FEIS was published in the EQB Monitor.[18]
20.
The hearing
record closed for all purposes on December 8, 2010.
C.
Description of the Project
21.
The Project
primarily consists of a 16 to 18 mile long 161 kV transmission line running
between an existing substation in
22.
The first facility
is the 100 MW Grand Meadow wind farm, owned by Xcel Energy. The second facility is the 100 MW Wapsipinicon
wind farm, from which Southern Minnesota Municipal Power Agency purchases the
output. Both of these wind generators
are operational, but they are limited in the amount of power they deliver to
the system. Construction of the Project
will allow these facilities to operate at full capacity. The Project is also expected to provide
additional outlet capability to serve future generators in the Pleasant Valley
Substation area.[20]
D.
Routes Proposed in the Application
23.
In the Application, Xcel Energy identified Route Alternative
1 (
24.
The
25.
The
26.
The Connector Segment, identified by Xcel Energy to allow
flexibility in routing between the
27.
The
28.
During this
process, Applicants gathered environmental data, held open houses and work
group meetings, collected public comments, and analyzed the statutory and rule
factors set forth in the Power Plant Siting Act (“PPSA”), Minn. Stat. ch. 216E,
and Minn. R. 7850 to develop the Preferred Route and the Alternate Route
for the Project.[27]
E.
Routes Considered in the DEIS
29.
A third route alternative (Route Alternative 3) was
identified during the EIS Scoping process.
Route Alternative 3 is approximately 16.3 miles in length and would
parallel the existing Pleasant Valley–Byron 345 kV line to the east for its
entire length between the
30.
In addition to Route Alternative 3, there were three route
segment alternatives (Alternative Segment A, Alternative Segment B, and Alternative
Segment C) that were proposed during the EIS Scoping process. From the Byron Substation, Alternative
Segment A runs south adjacent to the existing Pleasant Valley–Byron 345 kV
transmission line for approximately 1.85 miles. At
31.
Alternative Segment B follows the
32.
Alternative Segment C was proposed during the scoping
process as an alternative that would co-locate the Project’s crossing of Salem
Creek with an existing crossing by the Pleasant Valley–Byron 345 kV line. Alternative Segment C uses the
F.
Structure Types and Spans
33.
Applicant
proposes to construct the majority of the 161 kV transmission line as a single
circuit line using single-pole, weathering steel structures with brace post insulators.
The height of the single circuit
structures will range from 70 to 90 feet.
The spans between structures will range from 400 to 650 feet with a
right-of-way width of 80 feet.[33]
34.
Xcel Energy
requested the flexibility to use double circuit structures for a 1.5 mile
portion of the
35.
The proposed 161
kV transmission line will be constructed with single 795 kcmil 26/7 Aluminum
Core Steel Supported (“ACSS”) conductor per phase.[35]
G.
Route Widths
36.
Xcel Energy has
requested a route width of 200 feet on each side of the route alignment (400
feet total width) with the exception of two areas. One of these areas is along the
H.
Right-of-Way
37.
The right-of-way
required for the proposed 161 kV transmission line along either the
38.
For Route
Alternative 3, the Project transmission line structures could be aligned five
feet within the existing right-of-way for the 345 kV transmission line such
that the western 40 feet of the Project right-of-way and the eastern five feet
of the Project right-of-way would overlap with the existing 345 kV transmission
line right-of-way of 150 feet. Placement of the Project structures within the
existing 345 kV transmission line right-of-way would reduce the width of the
new right-of-way required to approximately 35 feet. If Route Alternative 3 were
constructed, the total combined right-of-way for the Project and the existing
345 kV transmission line would be 185 feet.[39]
I.
Project Schedule
39.
Xcel Energy
expects to begin right-of-way acquisition in the first quarter of 2011 and
estimated that the Project will be complete by the first quarter of 2012.[40]
J.
Project Costs
40.
Xcel Energy
estimated that the Project cost, if constructed along the
K.
Substations
41.
The associated
facilities for the Project include modifications to and equipment additions at
the existing
L.
Federal, State, and Local Agency Participation
42.
In developing
the Route alternatives, Xcel Energy consulted with local, state and Federal
agencies associated with the Project Area. Xcel Energy indicated that these agencies
generally responded by requesting to be updated on further Project developments
and informing Xcel Energy of required permits for the Project along with
specific applicable guidelines, rules, and regulations. Xcel Energy committed to maintaining communications
with these agencies throughout the routing process.[44]
1.
Minnesota Department of Natural Resources
43.
On November 9, 2010, the Minnesota Department of Natural
Resources (“MnDNR”) submitted comments regarding the Project and its potential
impact on natural resources. These
comments included the following:
Considering route comparisons provided in the DEIS, Alternative 1
appears to have the least overall impact to natural resources. Specifically,
Alternative 1 has the least effect on wetlands, the least tree removal at Salem
Creek, and avoids a crossing of the South Fork Zumbro River Wildlife Management
Area (WMA). Impacts to rare species were described in the DEIS as comparable,
with the exception of potential impacts to the state and federally listed
threatened Prairie Bush Clover along Alternative 1. Further consideration of
rare species will be important for all routes, and particularly important for
Alterative 1.
The DEIS Table S-2 titled Summary of Potential Mitigation Measures includes
the measure of surveying all likely habitat for Prairie Bush Clover, American
Ginseng, and Valerian so that structure placement can be sited to avoid known
occurrences. The DNR concurs with this
recommendation for any of the routes considered. As stated in previous comment letters, if it
is possible that the project will impact waterways, then impacts to aquatic
organisms should also be addressed. The DEIS states that wetlands and waterways
could be spanned. Impacts to rare
species would be minimized provided the transmission line spans waterways and
wetlands. This would include
floodplains, which are potential habitat for the Wood Turtle. Given the presence of rare species (Wood
Turtle, Ellipse, and Ozark Minnow) that are vulnerable to deterioration in
water quality, especially increased siltation, it is important that effective
erosion prevention and sediment control practices be implemented and maintained
near the rivers and creeks. The DNR
encourages continued project planning to span waterways, wetlands and
floodplains as much as possible. If
spanning these areas is not possible, then botanical and mussel surveys should
be completed in all likely wetland and waterway rare species habitats.
Surveys for rare species are recommended prior to a routing decision.
The DNR encourages coordination regarding rare species surveys as early as
possible in the route permitting process to (I) provide the most robust
comparison of rare species along routes during environmental review and
permitting, and (2) plan appropriate scheduling for any needed rare species
surveys (some mussel and botanical surveys may be required by the DNR) because
survey scheduling may be dependent on species-specific timeframes.
The DNR recommends that the FEIS include a description of potential
direct and indirect impacts specific to the South Fork Zumbro River WMA.
Descriptions of site-specific potential impacts and potential mitigation
measures for public lands are recommended for this project and in all
applicable transmission line environmental review documents to help inform
agency and public review and to inform the License to Cross Public Lands and
Waters Permit.
The DNR supports mitigation offsetting lost functions and values for
wetland impacts resulting from conversion of forested wetlands to non-forested
wetlands.[45]
2.
Minnesota Department of Transportation
44.
On November 8,
2010, the Minnesota Department of Transportation (“Mn/DOT”) submitted a comment
letter regarding the DEIS. Mn/DOT expressed
continuing concerns about the limitations on any future design for the possible
interchange at US Highway 14 and
3.
Local Agencies
45.
On October 8, 2008,
Xcel Energy met with
46.
Xcel Energy met
with the City of
4.
OES Environmental Review
47.
48.
The scoping
process is the first step in developing an EIS.
OES “shall provide the public with an opportunity to participate in the
development of the scope of the environmental impact statement by holding a
public meeting and by soliciting public comments.”[50] During the scoping process, alternative
routes may be suggested for evaluation in the environmental impact statement.[51]
49.
The scoping
process “must be used to reduce the scope and bulk of an environmental impact
statement by identifying the potentially significant issues and alternatives
requiring analysis and establishing the detail into which the issues will be
analyzed.”[52]
50.
At the
conclusion of the scoping process, OES must issue a scoping decision which
shall address at least the following: 1) the issues to be addressed in the EIS;
2) the alternative sites and routes to be addressed in the EIS; and 3) the
schedule for completion of the EIS.[53]
51.
On July 9, 2010,
OES issued its Scoping Decision for the EIS.
The Scoping Decision identified the topics to be covered in the Project
EIS: Project engineering and design; Project construction; and human and
environmental resources affected by the Project and each considered route
alternative.[54]
52.
The next step in
OES’s environmental review required OES to publish the DEIS and to schedule
informational meetings, which provide an opportunity for the public to comment
on the DEIS.[55]
53.
On October 6,
2009, OES published the DEIS which included a discussion of all of the
alternatives and topics required by the Scoping Decision.[56]
54.
The OES
published notice of the public meeting to be held on the DEIS in the Byron Review, the
55.
56.
Written and oral
comments were received by OES during the DEIS comment period. Included in this group are comments from the
MnDNR and Mn/DOT.[60]
57.
On November 30,
2010, OES published the FEIS.[61]
M.
Public Comments
58.
Oral and written
comments were received until November 8, 2010.
Generally, persons with residences, buildable lots, or farms along the
Criteria for a Route Permit
59.
The PPSA requires that route permit determinations “be
guided by the state’s goals to conserve resources, minimize environmental
impacts, minimize human settlement and other land use conflicts, and ensure the
state’s electric energy security through efficient, cost-effective power supply
and electric transmission infrastructure.”[62]
60.
Under the PPSA,
the Commission and ALJ must be guided by the following responsibilities,
procedures, and considerations:
(1) evaluation
of research and investigations relating to the effects on land, water and air
resources of large electric power generating plants and high voltage
transmission lines and the effects of water and air discharges and electric and
magnetic fields resulting from such facilities on public health and welfare,
vegetation, animals, materials and aesthetic values, including baseline
studies, predictive modeling, and evaluation of new or improved methods for
minimizing adverse impacts of water and air discharges and other matters
pertaining to the effects of power plants on the water and air environment;
(2) environmental
evaluation of sites and routes proposed for future development and expansion
and their relationship to the land, water, air and human resources of the
state;
(3) evaluation
of the effects of new electric power generation and transmission technologies
and systems related to power plants designed to minimize adverse environmental
effects;
(4) evaluation
of the potential for beneficial uses of waste energy from proposed large
electric power generating plants;[63]
(5) analysis
of the direct and indirect economic impact of proposed sites and routes
including, but not limited to, productive agricultural land lost or impaired;
(6) evaluation
of adverse direct and indirect environmental effects that cannot be avoided
should the proposed site and route be accepted;
(7) evaluation
of alternatives to the applicant’s proposed site or route proposed pursuant to
subdivision 1 and 2;
(8) evaluation
of potential routes that would use or parallel existing railroad and highway
rights-of-way;
(9) evaluation
of governmental survey lines and other natural division lines of agricultural
land so as to minimize interference with agricultural operations;
(10) evaluation
of future needs for additional high voltage transmission lines in the same
general area as any proposed route, and the advisability of ordering the
construction of structures capable of expansion in transmission capacity
through multiple circuiting or design modifications;
(11) evaluation
of irreversible and irretrievable commitments of resources should the proposed
site or route be approved; and
(12) when
appropriate, consideration of problems raised by other state and federal
agencies and local entities.[64]
61.
In addition to
the PPSA, Minn. R. 7850.4000 provides that no route permit may be issued in
violation of site selection criteria and standards found in Minnesota Statutes
or Public Utilities Commission Rules.
Power line permits must be consistent with state goals to minimize
environmental impacts and conflicts with human settlement and other land use. The Commission and ALJ are governed by Minn.
R. 7850.4100, which provides for the following factors to be considered when
determining whether to issue a route permit for a high voltage transmission line:
A. effects
on human settlement, including, but not limited to, displacement, noise,
aesthetics, cultural values, recreation, and public services;
B. effects on public health and safety;
C. effects
on land-based economies, including, but not limited to, agriculture, forestry,
tourism, and mining;
D. effects on archaeological and historic
resources;
E. effects
on the natural environment, including effects on air and water quality
resources and flora and fauna;
F. effects on rare and unique natural resources;
G. application
of design options that maximize energy efficiencies, mitigate adverse
environmental effects, and could accommodate expansion of transmission or
generating capacity;
H. use
or paralleling of existing rights-of-way, survey lines, natural division lines,
and agricultural field boundaries;
J. use
of existing transportation, pipeline, and electrical transmission systems or
rights-of-way;
K. electrical system reliability;
L. costs
of constructing, operating, and maintaining the facility which are dependent on
design and route;
M. adverse human and natural environmental
effects which cannot be avoided; and
N. irreversible and irretrievable
commitments of resources.
62.
There is sufficient
evidence on the record for the Commission to assess the proposed routes and
alternatives using the criteria set out above.
Application of Statutory and
Rule Criteria
I. Application
of Routing Factors to the 345 kV Transmission Line
A.
Effects on Human Settlement
63.
Minnesota
statutory and rule routing criteria for high voltage transmission lines require
consideration of the proposed transmission line route’s effect on human
settlement, including displacement of residences and businesses; noise created
during construction and by operation of the Project; and impacts to aesthetics,
cultural values, recreation, and public services.[66]
1.
Displacement
64.
Safety standards
set out in the National Electric Safety Code (“NESC”), and adopted by Xcel
Energy, require certain clearances between transmission line facilities and
buildings. Xcel Energy has committed to acquiring
a right-of-way for the proposed transmission line that is sufficient to
maintain these clearances. Xcel Energy
has identified a feasible centerline and right-of-way for each Route
Alternative such that all existing residences would be outside the right-of-way
and no demolition of residences or displacement of residents would be required.[67]
65.
For the
66.
For the
67.
For the Route
Alternative 3, there are no homes located within 200 feet of the route
centerline and only one home is located within 300 feet of the route
centerline. [70]
68.
Route Alternative
3 has the least impact on human habitation.
2.
Noise
69.
The Minnesota
Pollution Control Agency (“MPCA”) has established standards for the regulation
of noise levels.[71]
70.
For residential,
commercial and industrial land, the MPCA noise limits are 60-65 A-weighted decibels
(“dBA”) during the daytime and 50-55 dBA at night.[72]
71.
Transmission
lines produce noise under certain conditions.
The level of noise depends on conductor conditions, voltage level, and
weather conditions. Generally, activity
related noise levels during the operation and maintenance of transmission lines
are minimal and do not exceed the MPCA Noise Limits outside the right-of-way.[73]
72.
The Applicant
estimated the noise that would be emitted by the 161 kV line using the transmission
line noise level algorithms developed by the Bonneville Power Administration. The Applicant has predicted that the L5 and
L50 level of noise measured at the edge of the ROW would be 35.0 and 31.5 dBA,
respectively. These predicted noise
levels are below the lowest MPCA nighttime L50 limit of 50 dBA for Noise Area
Classification 1.[74]
73.
The audible
noise levels for each of the three Route Alternatives are not predicted to
exceed the MPCA Noise Limits outside the right-of-way and “during fair weather .
. . [would] likely be very low and seldom noticeable, even when standing
directly under the line.”[75]
3.
Aesthetics
74.
Construction of
the proposed facilities will likely affect visual quality and area aesthetics
within close proximity of the transmission line. Such effects can occur where any of the Route
Alternatives cross creeks or rivers, are located near recreational resources,
and are placed near residences, particularly those within 300 feet of the
right-of-way centerline.[76]
75.
Land use within
the Project area is primarily agricultural.
Also present in the Project area are residential uses, wind power
projects, and industrial land uses. The
aesthetic impact of the Project is likely to be only incremental, because there
are existing transmission lines within the viewshed in the Project area. These include a 69 kV line owned by Peoples
Cooperative, a 69 kV line and 161 kV line owned by Southern Minnesota Municipal
Power Agency, a 161 kV line owned by Great River Energy, and a 345 kV line
owned by Xcel Energy. Potential
aesthetic impacts include disruption to the existing landscape from the
addition of transmission lines; loss of trees; and devaluation of high-value or
sensitive scenic resources.[77]
76.
Xcel Energy
recognized that the transmission lines will be a contrast to the surrounding
land. The only mitigative measures
identified in the Application were siting the transmission line along existing
corridors and avoiding residences.[78]
77.
The transmission
lines will be visible by some residents near the Project for the Preferred and
78.
The potential
for aesthetic impacts differ among the three route alternatives. Both the
79.
In light of the
factors noted in the preceding Finding, the record confirms that Route Alternative
3 will have fewer aesthetic impacts compared to the Preferred and Alternate
Routes.
4.
Cultural Values
80.
The communities
in the vicinity of the Project have cultural values arising from agricultural practices
(typically corn, soybeans, and grazing), with some manufacturing and tourism. Many residents value their rural or semi-rural
lifestyle, the existing farming operations, and agricultural history, and have
high-standards for health and safety.[81]
81.
Xcel Energy
proposed to mitigate impacts on cultural values by reducing any impacts on the
community.[82] Of the three route alternatives, Route Alternative
3 poses the least impact on cultural values.
5.
Recreation
82.
Recreational
resources near the
83.
The EIS analysis
noted that there are no MnDNR designated trout lakes or trout streams within
the Study Area, but Salem Creek is considered a popular fishing resource. Salem Creek and other waterways may be used
for recreational swimming by the residents of the Study Area. There are no public water access points maintained
by local or State governments within the Study Area, and use of these waterways
by non-residents is not expected to be significant.[84] Salem Creek is crossed by all three Route
Alternatives at different locations.
84.
In addition, eight
state wildlife management areas (WMA) are located within the vicinity of the
Study Area. These WMAs provide public
land for hunting deer, small game, pheasants, waterfowl, and turkeys. Hunting may also occur on private lands.[85] Neither the
85.
There are no
designated federal, state, or local parks, located within the Study Area. There are several bicycle trails in
86.
The EIS concluded
that the Project will not have any long-term direct impacts on the recreational
resources near the
6.
Public Services
87.
Public services
in the Project Area include sewer and water services and existing and future
transportation corridors and projects. In
the City of
88.
Construction of
the Project along any of the three routes is not anticipated to directly or
indirectly affect the operation of any existing public services A proposed highway project includes an
interchange on either State Highway 14 at
89.
Xcel Energy maintained
that a compatible design can be developed prior to construction such that the
proposed transmission structures would not interfere with this possible future interchange,
if the
90.
Despite Xcel
Energy’s proposed adjustments, Mn/DOT continued to express concerns about potential
limitations on future design presented by the presence of a transmission line
at this location. Mn/DOT supported
crossing Highway 14 where the existing HVTL crosses the highway (Route
Alternative 3 or the Preferred Route using Segment A).[93]
91.
Construction of
the Project along Route Alternative 3, the
B.
Effects on Public Health and Safety
92.
93.
The Project will
be designed in compliance with local, state, National Electric Safety Code (“NESC”),
and the Xcel Energy standards regarding clearance to ground, clearance to
crossing utilities, clearance to buildings, strength of materials, and
right-of-way widths.[95]
94.
Xcel Energy
construction crews and/or contract crews will comply with local, state, and NESC
standards and Xcel Energy policies regarding installation of facilities and compliance
with standard construction practices both during and after installation of the
transmission lines. Xcel Energy will
post plainly visible unambiguous signage during all construction activities.[96]
95.
The proposed
transmission lines will be equipped with protective devices (circuit breakers
and relays located in the substation where the transmission lines terminate) to
safeguard the public if an accident occurs, such as a structure or conductor
falling to the ground. In the event of
such an accident, the protective equipment will de-energize the transmission
line. [97]
1.
Electric and Magnetic Fields
96.
The Commission
is required to consider of the effects of electric and magnetic fields
resulting from the Project on public health and welfare.[98]
97.
Electric and
magnetic fields (“EMF”) are produced by natural sources and by the voltages and
currents associated with the use of electric power. Electric and magnetic fields also exist near
wherever electricity is being generated and transmitted. The amount of electric charge on a metal
wire, which is expressed as voltage, creates an electric field on other nearby
charges. When electric charges in the
conductor are in motion, they produce an electric current, which is measured in
amperes, and a wire with an electric current creates a magnetic field (“MF”)
that exerts forces on other electric currents. MF levels become lower farther away from the
source.[99]
98.
The electric and
magnetic fields associated with power lines are often designated as
extremely-low-frequency EMF (“ELF-EMF”).
Although there is no federal regulation, the Minnesota PUC has imposed a
permit condition of 8 kV/m for the maximum electric field for previously
permitted high voltage transmission lines (HVTLs) (measured at centerline and
at 1 meter above ground). There are no
federal or
99.
The maximum
electric field associated with Applicants’ proposal, measured at one meter
above the ground, is calculated to be 1.46 kV/m.[101]
100.
The highest
projected MF level that will be created by the Project is approximately 15 mG
at the edge of the right-of-way during peak operation.[102]
101.
The FEIS
contains a thorough discussion of the issues of EMF-ELF exposure and a related
issue, stray voltage. Regarding the
impact of electric fields, the FEIS states:
A viable cause and effect relationship between the
exposure to EMFs and adverse health effects has not been established. The
calculated electric fields for the Project at 1 meter (approximately 3.28 feet)
above ground are displayed in Table 6.1.6-3. Estimates of the anticipated
strength of the magnetic field associated with the Project routes are displayed
in Table 6.1.6-4.
The maximum electric field associated with the
Project (1.46 kV/m) would be significantly less than the maximum limit of 8
kV/m, which would be a permit condition imposed by the PUC.
The maximum calculated peak magnetic field strength
at 1 meter aboveground would be 53.43 mG. The Commission does not impose permit
conditions that limit magnetic field strength.[103]
102.
The FEIS
suggests that EMF-ELF impacts, to whatever extent such impacts exist, can be
mitigated through distance from the HVTL, compaction between transmission line
phases, and phase cancellation along the HVTL.[104]
103.
The absence of
any demonstrated impact by EMF-ELF exposure supports the conclusion that there
is no demonstrated impact on human health and safety that is not adequately
addressed by the existing State standards for such exposure. The record shows that the current exposure
standard for EMF-ELF is adequately protective of human health and safety. There is no difference in impacts between the
three Route Alternatives.
2.
Stray Voltage
104.
Stray voltage is
a condition that can occur at the electric service entrances to structures from
distribution lines, not transmission lines. More precisely, stray voltage is a voltage
that exists between the neutral wire of the service entrance and grounded
objects in buildings such as barns and milking parlors. Transmission lines do not, by themselves,
create stray voltage because they do not connect to businesses or residences. Transmission lines can induce stray voltage
on a distribution circuit that is parallel to and immediately under the transmission
line.[105]
105.
The FEIS
addressed the issue of stray voltage remediation, stating:
The Applicant would address stray voltage issues on a case by case basis
(Xcel Energy, 2009a). The three primary methods to reduce or eliminate stray
voltage are cancellation, separation, and enhanced grounding. Cancellation
entails the arranging of transmission line phase conductors in a configuration
to minimize EMF levels, bonding distribution neutral and transmission shield
wires together, and bonding an under-built transmission shield wire to
distribution neutral wires rather than a normal overhead shield wire.
Separation entails increasing the distance between transmission and distribution
lines through re-locating distribution lines underground, placing the transmission
line on the opposite side of the road as existing distribution lines, or increasing
the vertical distance between the transmission line phase conductor and under-built
distribution line. Enhanced grounding would reduce stray voltage potential through
connecting counterpoises to the distribution neutral wire and/or transmission shield
wire.[106]
106.
Stray voltage
that is induced by the proposed HVTL can be remedied by the Xcel Energy. Conditioning the issuance of a Permit on the
remediation of stray voltage conditions caused by the 161 kV line is supported
by the record.
3.
Interference with Natural Gas Pipelines
107.
The southernmost
end of the
108.
Steel pipelines
which are buried in the earth must be protected from corrosion. This is typically
accomplished by applying a protective coating on the pipe and using a cathodic
protection system. The NNG pipeline along
109.
Xcel Energy
commissioned an AC interference study to understand the interactions between
the pipeline and transmission line so that the possibility of these situations can
be eliminated. The study results
conclude that separating the transmission line and natural gas pipeline by at
least 42 feet and taking several corrective measures will greatly reduce potential
interference and shock potential. These measures
include installing a lower impedance shield wire between
110.
The initial OES
analysis of safety regarding the proximity of the NNG pipeline stated:
Although low in probability, a
simultaneous leak on a pipeline and fault on the transmission line could result
in ignition if the Project is not located at a minimum safe distance from natural
gas pipelines. The National Association of Corrosion Engineers (NACE) develops
standards to ensure pipeline safety and integrity. The NACE standards do not
specify a safe separation distance between a pipeline and transmission line,
but require analysis to determine the safe separation distance. In
111.
Xcel Energy
disputed the DEIS finding regarding pipeline safety, contending that:
Xcel Energy would like to emphasize that the
possibility of this type of ignition situation is extremely uncommon due to the
safety mechanism installed on the pipeline to prevent leaks and on the
transmission line to prevent faults. In the rare event that a pipeline leak
goes undetected, a transmission line is not a likely source of ignition. Xcel
Energy requests that this section of the DEIS be revised to state that an
undetected pipeline leak is very rare and that a transmission line is not a
likely source of ignition.[111]
112.
OES noted that
pipelines are equipped with safety mechanisms to prevent leaks. OES acknowledged that the possibility of a
simultaneous gas leak and line fault was “extremely low in probability,” but
noted that “Ignition could also occur if natural gas is released from a pressure
relief valve located at a pipeline compressor station.” [112]
113.
The potential
for interference or an accident involving the NNG pipeline only arises if the
C.
Effects on Land Based Economies
114.
115.
The Project will
result in permanent and temporary impacts to farmland. Working from an estimated foundation diameter
of eight feet, Xcel Energy suggested that each Project structure (pole) would
displace up to approximately 50 square feet of soil. Estimating that the poles would be placed at an
average distance of 400 feet apart, long-term loss of farmland was calculated
to be up to 0.28 acres for the
116.
Temporary
impacts during construction may include soil compaction, disruption of
agricultural practices (e.g., center pivot irrigation or drain tile) and crop damage
within the right-of-way.[115]
117.
Prime farmland
is located along all three routes, along with ditches and other noncultivated farmland. Within the proposed rights-of-way, Route
Alternative 3 has 93 acres of prime farmland, compared to 116 acres for the
118.
Xcel Energy
intends to limit springtime construction to the extent possible to minimize
agricultural impacts. If construction is
necessary during the springtime, Xcel Energy has proposed minimizing
disturbance by using the shortest access location and possibly constructing
temporary driveways where necessary to limit traffic on fields. [117]
119.
The only
identified tourism site in the Project Area is Tweite’s Pumpkin Patch, located
along the Preferred Route, south of the intersection of U.S. Highway 14 and
280th Avenue. This business is open to
the public six weeks a year (September through October 31) and includes corn
mazes, pumpkin patches and other agri-tourism amusement activities. At other times, the premises are open for
private events. In 2009, approximately
30,000 people attended events on the premises.[118]
120.
Xcel Energy
maintained that the placement of structures associated with the
121.
There will be no
significant impact on tourism if the Project is constructed along Route
Alternative 3 or the
122.
No forestry resource
impacts other than removal of individual trees have been identified along any
of the routes under consideration in this proceeding.[120] No impacts on mining resources are expected
as Xcel Energy has proposed to avoid gravel pits, rock quarries, and commercial
aggregate sources during detailed design of the transmission line.[121]
123.
The record demonstrates that Route Alternative 3 has the
least impact on land-based economies when compared to the
D.
Effects on Archaeological and Historic Resources
124.
125.
The Study Area
was evaluated in a records search and review of existing records contained at
the Minnesota State Historic Preservation Office (SHPO) conducted in 2008 by
10,000 Lakes Archaeology, Inc. The records
search was conducted to determine if significant archaeological, architectural,
or tribal resources have been documented within the Study Area. Both archaeological and historic sites were
documented within 0.5 miles of each of the Route Alternatives.[123]
126.
The records
search of existing cultural resources identified three previously recorded archaeological
sites and nine historic structures within 0.5 mile of the
127.
The records
search of existing cultural resources identified one previously recorded archaeological
site and three historic structures within 0.5 mile of the
128.
The records
search of existing cultural resources identified two previously recorded archaeological
sites and three historic structures within 0.5 mile of Route Alternative 3. One non-registered historic structure was
identified within 0.5 mile of Route Alternative 3.[126]
129.
Xcel Energy
committed that, if an artifact is discovered during construction, consultation
would be conducted with the SHPO to determine whether or not the resource would
be eligible for listing in the National Registry of Historic Places (NRHP). Phase I or Phase II surveys would be conducted
in the event that a potentially eligible artifact is discovered and cannot be
spanned.[127]
130.
It is
appropriate for the Commission to condition a permit on any archaeological
sites identified by investigation or during Project construction, being avoided
through flexibility in siting of the Project structures and right-of-way. Where a discovered site cannot be avoided, such
a site should be evaluated for significance and potential listing, and subsequent
mitigation performed as needed. Potential
visual impacts to the viewshed to/from historic sites should be reduced through
coordinating pole placement with the land owner(s) and other interested
parties.[128]
131.
The record demonstrates that there are fewer archaeological
and historic sites within the Route Alternative 3 and the
E.
Effects on Natural Environment
132.
1.
Air Quality
133.
Construction of
the Project will result in temporary air quality impacts caused by, among other
things, construction-vehicle emissions and fugitive dust from right-of-way
clearing.[130]
134.
Xcel Energy will
implement the appropriate dust control and vehicle idling measures during
construction.[131]
135.
The operation of
the Project along any of the three Routes is not anticipated to cause any
long-term impacts to air quality.[132]
2.
Water Quality and Resources
136.
Water resources
in the Project area include surface waters, groundwater, and floodplains.[133]
137.
Public Water
Inventory (“PWI”) rivers and streams within or adjacent to the Route
Alternatives are shown in Table 6.2.3-1 and Figure 7 in the FEIS. At 10 crossings, Route Alternative 3 has more
river and stream crossings than the
138.
Should pole
placement occur within a water basin (e.g., lakes and ponds) or watercourse
(e.g., rivers and streams), temporary direct impacts could include soil erosion
along the shoreline and sedimentation caused by construction. The deposition of sediment could result in a
long-term impact to water turbidity. Xcel Energy designed the Project to span
surface water bodies in order to avoid such impacts. Indirect impacts are expected and will be
avoided and minimized using the appropriate construction practices.[135]
139.
Using the
National Wetlands Inventory, OES analyzed the impact on forested wetlands as
follows:
Acreage of wetlands that would be crossed by the
Project are similar for Route Alternatives 1 [
140.
The Project could require a number of water and
wetland-related permits, including coverage under the General Permit for Storm
Water Discharges Associated with Construction Activities and associated Storm
Water Pollution Prevention Plan (“SWPPP”), National Pollution Discharge
Elimination System Permit (“NPDES”), License to Cross Public Waters, Public
Waters Work Permit, and Section 404 Clean Water Act permit. The placement of transmission line pole
structures, land clearing that involves soil disturbance, or placement of
construction mats may be considered a discharge of fill material that would
require a permit from the Department of the Army,` pursuant to Section 404 of
the Clean Water Act. These permits would require the Applicant to develop and
implement Best Management Practices (“BMPs”) for sediment and erosion control
during construction and operation of the Project to protect topsoil and
adjacent wetlands and surface water resources.
Appropriate BMPs for the Project include:
• When possible,
construction would be scheduled during frozen ground conditions;
• Crews would attempt to
access a wetland with the least amount of physical impact to the wetland (i.e.,
shortest route);
• The structures would be
assembled on upland areas before they were brought to the site for
installation, when practical; and
• When construction during
winter was not possible, construction mats would be used where wetlands would
be affected.[137]
141.
The record demonstrates that there are fewer potentially
affected water resources within the
3.
Flora
142.
The Project Area
is located in an area of southeastern
143.
The FEIS
identified direct impacts from the Project as primarily the loss of individual plants
through disturbance from construction or related right-of-way clearing, and
ongoing losses of flora through disturbance from maintenance activities.[139]
144.
MnDNR expressed
its overall assessment of impacts to the environment and specific effects on
flora in the right-of-way, stating:
Considering route comparisons provided in the DEIS, Alternative 1 appears to have the least overall impact to natural resources. Specifically, Alternative 1 has the least effect on wetlands, the least tree removal at Salem Creek, and avoids a crossing of the South Fork Zumbro River Wildlife Management Area (WMA). Impacts to rare species were described in the DEIS as comparable, with the exception of potential impacts to the state and federally listed threatened Prairie Bush Clover along Alternative 1. Further consideration of rare species will be important for all routes, and particularly important for Alterative 1.
The DEIS Table 8-2 titled Summary of Potential Mitigation Measures includes the measure of surveying all likely habitat for Prairie Bush Clover, American Ginseng, and Valerian so that structure placement can be sited to avoid known occurrences. The DNR concurs with this recommendation for any of the routes considered. …[140]
145.
As set out in
the FEIS, minimizing long-term impacts to flora can be achieved by utilizing
the following methods:
·
Restoring the
disturbed area to its original vegetative state to the extent possible
throughout the Project right-of-way, lay down areas, access roads, and temporary
work spaces.
·
Limiting tree
removal to only those trees located within the permitted right-of-way that
would affect the safe operation of the transmission line.
·
Washing or
manually removing material from construction vehicles prior to the start of
construction where that equipment has traveled from an area contaminated by noxious
weeds.
·
Planting cover
crops or other stabilizing vegetation (in nonagricultural areas) following
construction to prevent disturbed areas from becoming available to weed species.[141]
146.
Route Alternative 3 would cross the South Fork Zumbro River
Wildlife Management Area (“WMA”) east of the 345 kV transmission line, near the
narrow northeastern edge of the WMA. The
400-foot route width requested for Route Alternative 3 would allow for
flexibility in placement of the transmission line and poles, such that impacts
to the WMA could be reduced or avoided. The length of Route Alternative 3 that
would cross the WMA would be 465 feet, which is less than the maximum distance
between Project structures of 650 feet. Given
the potential distance between structures, the WMA could be spanned and poles
placed outside the WMA, thereby minimizing impact on flora in the WMA.[142]
147.
The right-of-way for Route Alternative 3 would overlap with existing
right-of-way for the existing 345 kV transmission line, reducing to 35 feet the
new right-of-way width required for Route Alternative 3. If the transmission line follows the proposed
centerline of Route Alternative 3, additional right-of-way of 35 feet
traversing a distance of 465 feet would result in approximately 0.37 acres of
new right-of-way required through the WMA.[143]
148.
The
149.
All three Route alternatives would require tree removal at Salem
Creek and the transmission line would be visible to recreational users of the
waterway. The
150.
The record demonstrates that the greatest impact upon flora
would occur by utilizing the
4.
Fauna
151.
The Project
would be located primarily along existing rights-of-way in a cultivated agricultural
environment with patches of natural areas present. These natural areas include habitat such as
grasslands, upland and lowland deciduous forests, emergent wetlands, and
riparian woodlands.[146]
152.
These habitats
provide forage, nesting, and breeding habitat for resident wildlife, as well as
stopover habitat for migratory species. Resident
species common to south-east
153.
Throughout the
Project area, there are several areas where high-quality wildlife habitat
occurs naturally or is being managed, including the South Fork Zumbro River WMA,
the Tri-cooperative WMA, and the Rock Dell WMA.
Of these areas, only the South Fork Zumbro River WMA is crossed by a
proposed route, Route Alternative 3. [148]
154.
There are no Scientific
Natural Areas, National Wildlife Refuges or Waterfowl Production Areas located
within 1 mile of the Project. The
closest wildlife refuge is the Upper Mississippi River National Wildlife and
Fish Refuge, located approximately 50 miles south of the Project.[149]
155.
Due to the
similarity in length, impacts to terrestrial wildlife would be similar for all Route
and Segment Alternatives. Construction
noise and increased activity levels would temporarily limit the use of the
habitat along the routes. The clearing
of trees along the ROW could displace nesting or burrowing wildlife. Due to the availability of adjacent habitat,
displacement of any species is expected to be short-term.[150]
156.
MnDNR expressed
its overall assessment of impacts to fauna in the right-of-way, stating:
The DEIS states that wetlands and waterways could be spanned. Impacts to rare species would be minimized provided the transmission line spans waterways and wetlands. This would include floodplains, which are potential habitat for the Wood Turtle. Given the presence of rare species (Wood Turtle, Ellipse, Ozark Minnow) that are vulnerable to deterioration in water quality, especially increased siltation, it is important that effective erosion prevention and sediment control practices be implemented and maintained near the rivers and creeks. The DNR encourages continued project planning to span waterways, wetlands and floodplains as much as possible. If spanning these areas is not possible, then botanical and mussel surveys should be completed in all likely wetland and waterway rare species habitats.
Surveys for rare species are recommended prior to a routing decision. The DNR. encourages coordination regarding rare species surveys as early as possible in the route permitting process to (1) provide the most robust comparison of rare species along routes during environmental review and permitting, and (2) plan appropriate scheduling for any needed rare species surveys (some mussel and botanical surveys may be required by the DNR) because survey scheduling may be dependent on species-specific timeframes.
The DNR recommends that the FEIS include a description of potential direct and indirect impacts specific to the South Fork Zumbro River WMA. Descriptions of site-specific potential impacts and potential mitigation measures for public lands are recommended for this project and in all applicable transmission line environmental review documents to help inform agency and public review and to inform the License to Cross Public Lands and Waters Permit.[151]
157.
To ensure mitigation
of possible impacts to wildlife, imposing conditions on the Permit to require Xcel
Energy to span designated habitat or conservation areas wherever feasible is
appropriate. In the event complete
spanning is not possible, requiring Xcel Energy to minimize the number of
structures placed in high quality wildlife habitat and to work with the MnDNR
to determine appropriate mitigation is appropriate.
158.
The evidence demonstrates that none of the three routes will
have a significant impact on fauna.
F.
Effects on Rare and Unique Natural Resources
159.
160.
The FEIS
prepared for this Project lists the species found within the Project Area that
are threatened, endangered, or of special concern.[153] The species listed include those identified
by the MnDNR in the discussion above regarding flora and fauna. The FEIS describes the route impact on these
species as follows:
In general, potential impacts to sensitive species would be similar for all Route and Segment Alternatives. However, Route Alternative 1 would cross known occurrences of prairie bush clover, which are avoided by Route Alternatives 2 and 3.
As described in Section 6.2.4, Route Alternative 3 would cross more wetland acreage than Route Alternatives 1 and 2. As such, it has a greater potential to impact sensitive wetland species through construction and structure placement within wetlands.
Each of the three Route Alternatives would cross Salem Creek and adjacent wooded area surrounding the creek that provides suitable habitat for species. Route Alternative 1 would cross the shortest length of wooded area surrounding Salem Creek of the three Route Alternatives and could result in fewer impacts to sensitive species near Salem Creek.[154]
161.
Xcel Energy proposed
to span, where possible, rivers, streams and wetlands, and any habitats where listed
species have been recorded or are likely to occur. Wherever it is not feasible to span, a survey
will be conducted to determine the presence of special status species or suitability
of habitat for such species. Where the
survey shows such species or habitat, Applicants will coordinate with MnDNR to
avoid and minimize any impact.[155]
162.
The record demonstrates that there are equivalent impacts to
threatened and endangered species within all three Route options, provided that
Route Alternative 3 is aligned to span the South Fork Zumbro River WMA (without
placement of poles within the WMA boundaries).
The
G.
Application of Various Design Considerations
163.
164.
As stated
previously, the 161 kV transmission line is proposed to be constructed as a
single circuit line using single-pole, weathering steel structures with brace
post insulators. The height of the
single circuit structures will range from 70 to 90 feet. The spans between structures will range from
400 to 650 feet with a right-of-way width of 80 feet.[157]
165.
The transmission
line is designed to meet current and projected needs. In addition, both the Pleasant Valley
Substation and Byron Substation were designed and constructed to accommodate
future transmission line interconnections.[158]
166.
The design
options of the facilities along all the Route options maximize energy efficiencies,
mitigate adverse environmental effects, and accommodate future expansion.[159]
H.
Use or Paralleling of Existing Right-of-Way, Survey
Lines, Natural Division Lines, and Agricultural Field Boundaries
167.
Minnesota high
voltage transmission line routing criteria require consideration of the
proposed route’s use or paralleling of existing rights-of-way, survey lines,
natural division lines, and agricultural field boundaries.[160]
168.
The
169.
Route
Alternative 3 parallels the existing Pleasant Valley–Byron 345 kV transmission
line rights-of-way for nearly 100 percent of its length.[162]
170.
The record demonstrates that Route Alternative 3 maximizes
the use of parallel existing rights-of-way for electrical lines.
I.
Use of Existing Transportation, Pipeline, and
Electrical Transmission System Rights-of-Way
171.
172.
As discussed in
the foregoing Findings, the
J.
Electrical System Reliability
173.
174.
Xcel Energy
contended that, when compared to the
175.
All three Route
alternatives satisfy the applicable North American Electric Reliability
Corporation (“NERC”) criteria and meet the Project need of providing additional
generation outlet.[166] In addition,
the primary purpose of the proposed 161 kV line is for generation outlet rather
than system or regional reliability.[167]
176.
OES carefully
analyzed the issue of reliability in the FEIS.
On that issue, the FEIS states:
The Applicant has expressed reliability concerns over
co-locating the Project’s 161 kV transmission line with the existing 345 kV
transmission line on overlapping ROW.
The existing 345 kV transmission line serves multiple functions,
including local load serving, regional power transfer, and providing generation
outlet capacity from the Pleasant Valley Substation (Standing, 2010). The
stated need of the Project is to provide generator outlet from the Pleasant
Valley Substation Area, specifically from the Grand Meadow and Wapsipinicon
Wind Farms and future generators. Although both the Project transmission line
and existing 345 kV line would provide generation outlet capacity from the
Pleasant Valley Substation, the Project was proposed to interconnect the two
wind farms and was not proposed to provide reliability or redundancy to the
existing 345 kV transmission line. Further, the Project’s 161 kV transmission
line alone would not be able to physically serve as full back-up of the 345 kV
transmission line if the 345 kV transmission line segment between the
It should be noted that single contingency events with
the potential to disrupt service on both lines are not limited to pole
collapse. The Applicant has stated that lightening strikes or wind blown debris
are more likely causes of outage events (Standing, 2010). However, the
Applicant has been unable to provide recent examples of such events occurring
or the probability of a single contingency event occurring for the Project. The
Project would be designed to meet or exceed the requirements of NESC, including
withstanding wind and other extreme weather conditions. In the past five years, none of the
Applicant’s steel poles in
177.
The record
demonstrates the each of the three routes will support the reliable operation
of the electrical transmission system.
K.
Costs of Constructing, Operating, and Maintaining the
Facility
178.
179.
The
180.
The record
demonstrates that it will cost less to construct the Route Alternative 3 than
the Preferred or
L.
Adverse Human and Natural Environmental Effects Which
Cannot be Avoided
181.
182.
Unavoidable
adverse impacts include the physical impacts to the primarily agricultural
land, due to the construction of the Project.[173]
183.
Xcel Energy identified
mitigation measures to address adverse environmental effects during construction
of the Project and committed to working with public agencies to minimize the
unavoidable adverse environmental effects that may arise during construction of
the Project.[174]
184.
Approximately 0.28
acres of permanent agricultural land impacts are anticipated for the
185.
Approximately 0.25
acres of permanent agricultural land impacts are anticipated for Route Alternative
3.[176]
186.
The least impact
through unavoidable adverse human and natural environmental effects is achieved
through the use of Route Alternative 3.
M.
Irreversible and Irretrievable Commitments of
Resources
187.
188.
Only
construction resources, such as concrete, steel, and hydrocarbon fuels, will be
irreversibly and irretrievably committed to this Project. The impacts are similar in extent for the
189.
The commitment
of these resources is slightly less, due to the shorter distance of the route,
for Route Alternative 3 when compared to the
N.
Consideration of Issues Presented by State and
Federal Agencies
190.
191.
Mn/DOT, MnDNR,
and OES expressed concern with various aspects of the
O.
Evaluation of Alternatives
192.
193.
The three route
options, the crossover route, and three segment alternatives were studied by
the OES in the draft EIS.[181]
194.
Generally
speaking, the segment alternatives are suitable for addressing specific adverse
impacts in the event of the selection of either the Preferred or the
195.
The PPSA directs
the Commission to locate transmission lines in a manner that “minimize[s]
adverse human and environmental impact while ensuring continuing electric power
system reliability and integrity and ensuring that electric energy needs are
met and fulfilled in an orderly and timely fashion.”[182]
196.
The PPSA further
authorizes the Commission to meet its routing responsibility by designating a
“route” with a “variable width of up to 1.25 miles.”[183]
197.
Xcel Energy
requested a route width of 400 feet for the 161 kV transmission line, and a
1,000-foot route width would extend 500 feet on either side of buildings within
an industrial area located south of the Byron Substation.[184]
198.
Subsequently, Xcel
Energy also requested additional route width up to 1,100 feet on the west side
of the Route Alternative 1 for a one half mile segment west of
199.
The proposed
route width is consistent with prior Route Permits issued by the Commission.[186]
200.
The landowner at
the potentially double circuited location supported the wider route width,
should the
201.
Applicants’
request for a route width of 400 feet, and where necessary up to 1,000 feet for
a limited portion of the
202.
Xcel Energy’s request
for a 400 foot-wide route width, including an area where a width of 1,100 feet is
necessary for the
III. Notice
203.
204.
As set out in
the Procedural Summary in this Report, Xcel Energy provided notice to the
public and local governments in satisfaction of
205.
IV. Adequacy of FEIS
206.
The Commission
is required to determine the adequacy of the FEIS.[193] An FEIS is adequate if it: (A) addresses the
issues and alternatives raised in scoping to a reasonable extent considering
the availability of information and the time limitations for considering the
permit application; (B) provides responses to the timely substantive comments
received during the DEIS review process; and (C) was prepared in compliance
with the procedures in Minn. R. 7850.1000 to 7850.5600.[194]
207.
The record demonstrates
that the FEIS is adequate because it addresses the issues and alternatives
raised in the Scoping Decision, provides responses to the substantive comments
received during the DEIS review process, and was prepared in compliance with Minn.
R. 7850.1000 to 7850.5600.
CONCLUSIONS
1.
The Public
Utilities Commission and Administrative Law Judge have jurisdiction to consider
Applicant’s Application for a Route Permit. [195]
2.
The Commission
determined that the Application was substantially complete and accepted the
Application on February 9, 2010.
3.
OES has
conducted an appropriate environmental analysis of the Project for purposes of
this route permit proceeding and the FEIS satisfies Minn. R. 7850.2500. Specifically, the FEIS addresses the issues
and alternatives raised through the scoping process in light of the
availability of information and the time limitations for considering the permit
application, provides responses to the timely substantive comments received
during the DEIS review process, and was prepared in compliance with the
procedures in Minn. R. 7850.1000-7850.5600.
4.
Applicants gave
notice as required by Minn. Stat. § 216E.03, subd. 3a; Minn. Stat. § 216E.03,
subd. 4; Minn. R. 7850.2100, subp. 2; and Minn. R. 7850.2100, subp. 4.
5.
OES gave notice
as required by Minn. Stat. § 216E.03, subd. 6; Minn. R. 7850.2300, subp.
2; Minn. R. 7850.2500, subp. 2; Minn. R. 7850.2500, subp. 7; Minn. R.
7850.2500, subp. 8; and Minn. R. 7850.2500, subp. 9.
6.
Public hearings
were conducted in a community located along the proposed high voltage
transmission line routes. Xcel Energy
and OES gave proper notice of the public hearings, and the public was given the
opportunity to speak at the hearings and to submit written comments. All procedural requirements for the Route
Permit were satisfied.
7.
The record
demonstrates that Route Alternative 3, and its Associated Facilities, satisfies
the route permit criteria set forth in Minn. Stat. § 216E.03, subd. 7 and
8.
The record establishes
that the Preferred and Alternate Routes also satisfy the route permit criteria
set forth in Minn. Stat. § 216E.03, subd. 7 and
9.
The record
demonstrates that Route Alternative 3 is the best alternative for the 161 kV
transmission line between the Pleasant Valley Substation and the Byron
Substation.
10.
The record
demonstrates that it is appropriate to grant a Route Permit for the 161 kV
transmission line, and Associated Facilities, along Route Alternative 3.
11.
The record
demonstrates that it is appropriate for the Route Permit to provide the
requested route width of 400 feet with a route width of 1,000 feet requested
immediately south of the Byron Substation. In the event that the Commission selects the
12.
It is
appropriate for the Route Permit to require Applicant to obtain all required
local, state, and federal permits and licenses, to comply with the terms of
those permits or licenses, and to comply with all applicable rules and
regulations.
13.
Any Findings
more properly designated Conclusions are incorporated herein by reference.
THIS REPORT IS
NOT AN ORDER AND NO AUTHORITY IS GRANTED HEREIN. THE
Based on the
Findings of Fact, Conclusions, and the entire record herein, the Administrative
Law Judge makes the Recommendations set forth above in this Report.
Dated: January 7, 2011
s/Manuel J. Cervantes
|
MANUEL
J. CERVANTES Administrative
Law Judge |
Recorded: Janet Shaddix and Associates
Transcripts
Prepared
NOTICE
Under the PUC’s Rules of Practice and
Procedure, Minn. R. 7829.0100 to 7829.3200, exceptions to this Report, if any,
by any party adversely affected must be filed within 15 days of the mailing
date hereof with the Executive Secretary of the PUC, 350 Metro Square Building,
121 Seventh Place East, St. Paul, Minnesota 55101-2147. Exceptions must be specific, relevant to the
matters at issue in this proceeding, and stated and numbered separately. Proposed Findings of Fact, Conclusions, and
Order should be included, and copies thereof served upon all parties.
The PUC shall make its determination on the
applications for the Certificate of Need and Route Permits after expiration of
the period to file Exceptions as set forth above, or after oral argument, if
such is requested and had in this matter.
In accordance with Minn. R. 4400.1900, the PUC shall make a final
decision on the Route Permits within 60 days after receipt of this Report.
Notice is hereby given that the PUC may
accept, modify, condition, or reject this Report of the Administrative Law
Judge and that this Report has no legal effect unless expressly adopted by the
PUC.
SUMMARY
OF TESTIMONY
Oral
Testimony at the Public Hearings
Over 60 people attended the two public
hearings held in
Michael Madery, a resident of
Mr. Madery also expressed his
concern with stray voltage, noting that the
Mr. Madery supported adoption of
Route Alternative 3, stating :
Alternative
route three is the shortest route. It
disturbs the fewest acres of prime farmland.
It has the least impact on aesthetics and tree removal in the area. It has the least impact for safety and health
to humans and animals. It has the fewest
residents within 300 feet of the right-of-way.
It has fewer residential property value impacts. It's definitely, when this line runs in front
of our place, going to reduce the value of my property.
And
I couldn't read anywhere in the impact statement concerning cost, but it has to
be the least expensive route. And for
those reasons, I support route alternative number three.[196]
Jared Snyder described property
that he is clearing on
Arlin Scharberg, a resident of
Rock Dell Township in Olmsted County, described his experience with stray
voltage when working in his farm field underneath the existing 345 kV line,
stating:
When
I drive my old John Deere underneath the lines, there's no cab on it or
nothing, the old tractor, and if I'm not careful, the three spokes in the
steering wheel are hot. I get a shock. So there's stray voltage coming through those lines when I'm right underneath the
lines. I can prove it because anytime
you go out, I drive 100 feet away, and it’s fine.
Mr. Scharberg expressed concern that, if Route Alternative 3 is selected,
he will experience more problems with stray voltage. He suggested that it would be more
appropriate to distribute the impact around the community. Mr. Scharberg supported routing the HVTL
along the
Todd Humphrey expressed his
support for Route Alternative 3 as having the least impact on residents as
assessed in the DEIS. He suggested that
the costs for that alternative could not be significantly higher than the costs
for the
Mr. Humphrey urged consideration of the aesthetic impact of the proposed line on rural residents, who have chosen to live “in the middle of nowhere, if you will.” These residents have chosen to live apart from busy roads and do not desire to have utilities located there.
Mr. Humphrey noted that the
Regarding effects on land-based
economies, Mr. Humphries noted that he rents out farmland that would be
affected by the
As to effects on the natural
environment, Mr. Humphrey urged that potential impact of the
Mr. Humphrey suggested that
either the
Timothy Horvei, a resident near the
Mr. Horvei contended that Xcel Energy's need for redundancy would be met
by using separate structures along Route Alternative 3. He asked what
information Xcel Energy was relying on in drawing its conclusions on
redundancy. He expressed his opinion
that the odds of an event affecting both lines at the same time were
"slim." Mr. Horvei also
pointed out that the
Kendall Boyum, a property owner along the
Jerry Holecek objected to the
Bruce Ludwig questioned why Xcel
Energy could not run the
Mr. Ludwig also questioned whether induction from the HVTL would affect
facilities of KM Telecom (Kasson Mantorville Telephone Company). KM Telecom has facilities running from County
Road 14 to Highway 30.[203]
Joseph Wieners, a resident along
the
Corey Carlson, a resident along
the
Theresa Horvei noted that the
Written
Comments
Written comments regarding the
Project were accepted until November 8, 2010.
The ALJ has not reproduced the written comments in their entirety, as much
of the commentary offered is similar in substance and often recites information
from other sources (such as the DEIS) which is analyzed in the Findings above.
Tim Clemens, Greenway Co-op
General Manager, indicated that the Co-op has a corn bunker on its property
that is located approximately 50 feet from the existing 345 kV line, near its
entry into the Byron Substation. Mr.
Clemens expressed concern that either the
Todd Rauen disputed Xcel Energy's assertions regarding
reliability for selecting the
Peter Reinarts, P.E., of
Corey Carlson submitted a
written comment that restated his oral comments and questioned whether the
Todd Humphrey submitted a written comment that restated his oral
comments. He also maintained that:
Power
lines are dangerous, affect property values and are ugly. They should not should be located near people
and traffic, or where future homesteads will be. They should be hidden as much as they can
within reason. In this case there is no reason.
There are viable and feasible alternatives. Options 2 or 3 (or bypassing
county line road/650 street) meets this criteria.[212]
Michael Madery and Anita Madery submitted a written comment that restated
Mr. Madery's oral comments. They also
identified potential impacts to their property and to the historic property
owned by Mr. Madery's mother arising from the selection of the
Joseph Weiners restated his oral comments in a written comment. He also restated a number of points from the
DEIS that supported the adoption of Route Alternative 3. Mr. Weiners suggested that the aesthetic
impact of the
Lorraine Ludwig expressed
concern over the potential impact of routing the power line along the
Warren Fay, a resident of
M.
J. C.
[1] Unless
otherwise noted, the statutes and rules are cited to the 2009 edition.
[2] While
this proceeding includes a Certificate of Need component (PUC Docket No.
08-992), there are no issues presented, as the ALJ’s role in that proceeding is
solely to provide a summary of testimony as discussed in Findings, below.
[3] Ex. 5 (Map
of Route Width Request)
[4] Ex. 1 at
12 (Application)
[5] Ex. 1, at
1 (Application).
[6] Ex. 1
(Application).
[7] In the
Matter of the Application of Northern States Power Company, d/b/a Xcel Energy,
for a Certificate of Need for a 161 kV Transmission Line in Dodge, Olmstead,
and
[8] In the
Matter of the Application for a Route Permit for the Pleasant Valley to Byron
161 kV Transmission Line Project, Docket No. ET2/TL-09-1315, Commission Order
(February 18, 2010), eDocket Document No. 20102-47181-01 (generally, Route
Docket).
[9] CON Docket,
Commission Order Accepting Application as Substantially Complete, Authorizing
Informal Review Process, and Encouraging Joint Proceedings (Feb. 18, 2010),
eDocket Document No. 200912-44684-02.
[10] Ex. 2
(Applicant Mailed and Published Notices of Application Filing).
[11] ALJ
Prehearing Order (Sept. 23, 2010) eDocket Document No. 20109-54722-01.
[12] Ex. C
(Notice of Public Information and EIS Scoping Meetings).
[13]
[14] Ex. D
(Scoping Decision).
[15] Ex. 3 (Hillstrom
Direct), Ex. 6 (Standing Direct), and Ex. 7 (Stevenson Direct).
[16] Ex. E
(DEIS).
[17] Exs. G
and H (Notices of Public Hearing).
[18] EQB
Monitor Vol. 34 No. 25 (December 13, 2010) at p. 4
(http://www.eqb.state.mn.us/documents/EQB%20Monitor%2012-13-2010.pdf).
[19] Ex. 1 at
3 (Application).
[20] Ex. 1 at 1
(Application).
[21] Ex. 1 at
23-24 (Application).
[22] Ex. 3 at
8 (Hillstrom Direct).
[23] Ex. 3 at
6-7 (Hillstrom Direct).
[24] Ex. 3 at
7 (Hillstrom Direct).
[25] Ex. 3 at 8
(Hillstrom Direct).
[26] Ex. 1 at 24-25
(Application).
[27]
[28] Ex. E at
S-1-S-2 (DEIS).
[29] Ex. E at
S-2 (DEIS).
[30] Ex. E at
S-2 (DEIS).
[31] Ex. E at
S-2 (DEIS).
[32] Ex. E at
S-2 (DEIS).
[33] Ex. 1 at
37 (Application).
[34] Ex. 6 at
3 (Stevenson Direct).
[35] Ex. 1 at
37 (Application).
[36] Ex. 1 at 15
(Application).
[37] Ex. 4
(Route width map).
[38] Ex. 1 at
39 (Application).
[39] Ex. E at
17 (DEIS).
[40] Ex. 8
(Project Schedule).
[41] Ex. 1 at
17 (Application).
[42] Xcel
Energy Nov. 5, 2010 Letter, eDocket Document No. 201011-56267-01.
[43] Ex. 1 at
16 (Application).
[44] Ex. 1 at 27
(Application).
[45] Ex. I
(MnDNR Letter, November 9, 2010).
[46] Mn/DOT
Nov. 8, 2010 Letter, eDocket Document No. 201011-56293-01.
[47] Ex. 1 at 27
(Application).
[48]
[49] Minn. R.
7850.2500, subp. 1.
[50] Minn. R.
7850.2500, subp. 2.
[51] Minn. R.
7850.2500, subp. 3.
[52] Minn. R.
7850.2500, subp. 4.
[53] Minn. R.
7850.2500, subp. 4.
[54] Ex. D (Environmental Impact
Statement Scoping Decision).
[55] Minn. R.
7850.2500, subps. 6-7.
[56] Ex. 23
(DEIS).
[57] Ex. J (Affidavit of Publication).
[58] Minn. R.
7850.2500, subp. 9.
[59]
[60] Ex. I.
[61] See FEIS.
[62] Minn.
Stat. § 216E.03, subd. 7.
[63] This criterion
is not applicable since Applicants have not applied for a route permit for a
large electric generating plant.
[64] Minn.
Stat. § 216E.03, subd. 7.
[65] This
criterion is inapplicable since Applicants have not applied for a permit for a
large electric generating plant.
[66] Minn.
Stat. § 216E.03, subd. 7(b);
[67] FEIS, at 25,
eDockets Document No. 201011-57001-02.
[68] FEIS, at 23,
Table 6.1.1-1, eDockets Document No. 201011-57001-02.
[69] FEIS, at 23,
Table 6.1.1-1, eDockets Document No. 201011-57001-02.
[70] FEIS, at 23,
Table 6.1.1-1, eDockets Document No. 201011-57001-02.
[71]
[72]
[73]
[74]
[75]
[76] FEIS, at
26-27, eDockets Document No. 201011-57001-02.
[77] FEIS, at
26, eDockets Document No. 201011-57001-02.
[78] Ex. 1, at
65 (Application).
[79] Ex. 1, at
65 (Application).
[80] FEIS, at
28.
[81] Ex. 1 at
p. 65-66 (Application).
[82]
[83] Ex. 1 at 66
(Application).
[84] FEIS, at 100-101.
[85] FEIS, at 99-100.
[86] FEIS, at 102.
[87] FEIS, at 100.
[88] FEIS, at 102.
[89] FEIS, at 69.
[90] Ex. 1 at 66
(Application).
[91] Ex. 1 at 66
(Application).
[92] Ex. 4 (Xcel
Energy DEIS Comment Letter).
[93] Mn/DOT
Nov. 8, 2010 Letter, eDocket Document No. 201011-56293-01.
[94] Minn.
Stat. § 216E.03, subd. 7(b)(1);
[95] Ex. 1 at
p. 58 (Application).
[96] Ex. 1 at
p. 58 (Application).
[97] Ex. 1 at
p. 58 (Application).
[98] Minn.
Stat. § 216E.03, subd. 7.
[99] FEIS, at 41.
[100] FEIS, at 41.
[101] Ex. 1 at 48
(Application).
[102] Ex. 1 at 55
(Application).
[103] FEIS, at
47.
[104]
[105] Ex. 1 at 55
(Application).
[106] FEIS, at
48.
[107] Ex. 7 at 4
(Stevenson Direct), as amended by errata eDockets Document No. 201011-56615-06.
[108] Ex. 7 at 5
(Stevenson Direct).
[109] Ex. 7 at 5
(Stevenson Direct); Ex. 4, Attachment 1 (Xcel Energy DEIS Comment Letter).
[110] Ex. E, at
46 (DEIS).
[111] Xcel
Energy DEIS Comment Letter (October 26, 2010) eDockets Document No. 201010-55882-01.
[112] FEIS, at
46.
[113] Minn.
Stat. § 216E.03, subd. 7(b)(5);
[114] Ex. E, at
85 (DEIS).
[115] Ex. 1 at
69 (Application).
[116] Ex. E at
S-8 and Table 6.3.3-3 (DEIS); Ex. 1 at 69 (Application).
[117] Ex. E, at
88 (DEIS); Ex. 1, at 71 (Application).
[118] Ex. E, at
85-88 (DEIS); Ex. 1, at 71-72 (Application).
[119] FEIS, at 88.
[120] FEIS, at 88.
[121] FEIS, at 90.
[122] Minn.
Stat. § 216E.03, subd. 7(b)(1);
[123] FEIS, at
37.
[124] FEIS, at
37.
[125] FEIS, at
38.
[126] FEIS, at
38-39.
[127] Ex. 1, at
74 (Application).
[128] FEIS, at
74.
[129] Minn.
Stat. §§ 216E.03, subd. 7(b)(1) and (2);
[130] FEIS, at
S-6.
[131]
[132] FEIS, at
53.
[133] FEIS, at
55.
[134] FEIS, at
56.
[135] FEIS, at
59.
[136] FEIS, at
62-63.
[137] FEIS, at
64-65.
[138] FEIS, at
65.
[139] FEIS, at
66.
[140] Ex. I
(MnDNR Letter, November 9, 2010).
[141] FEIS, at
67.
[142] FEIS, at 69.
[143] FEIS, at 68-69.
[144] FEIS, at 28.
[145] See FEIS at S-7 (Table S-1: Summary of Impacts
and Comparison of Route Alternatives).
[146] FEIS, at 67.
[147] FEIS, at 67.
[148] FEIS, at 67.
[149] FEIS, at
68.
[150] FEIS, at
68.
[151] Ex. I (MnDNR Letter, November 9,
2010).
[152] Minn.
Stat. § 216E.03, subd. 7(b)(1);
[153] FEIS, at 71.
[154] FEIS, at 72-73.
[155] FEIS, at
73; Ex. 1, at 84-88 (Application).
[156] Minn.
Stat. §§ 216E.03, subd. 7(b)(3) and (10);
[157] Ex. 1, at
37 (Application).
[158]
[159] Ex. 2 at
pp. 3-5, 3-6 (Application).
[160] Minn.
Stat. § 216E.03, subd. 7(b)(9);
[161] Ex. 1, at
5, 7 (Application).
[162] FEIS, at
18.
[163] Minn.
Stat. § 216E.03, subd. 7(b)(8);
[164] Minn.
Stat. § 216E.03, subd. 7(b)(10);
[165] Ex. 6, at
9 (Standing Direct).
[166] Byron Evidentiary Hearing Transcript
at 36.
[167] Byron Evidentiary Hearing
Transcript at 28.
[168] FEIS, at
19.
[169]
[170] Xcel
Energy Cost Letter (November 5, 2010) eDockets No. 201011-56267-01.
[171] Ex. 1, at
47 (Application).
[172] Minn.
Stat. § 216E.03, subd. 7(b)(5) and (6);
[173] Ex. 1 at
91 (Application).
[174] Ex. 1 at
57-84 (Application).
[175] FEIS, at 89.
[176]
[177] Minn.
Stat. § 216E.03, subd. 7(b)(11);
[178] Ex. 1 at
p. 92 (Application).
[179] Minn.
Stat. § 216E.03, subd. 7(b)(12).
[180] Minn.
Stat. § 216E.03, subd. 7(b)(7).
[181] Ex. E, at
§ 5 (DEIS).
[182] Minn.
Stat. § 216E.02, subd. 1.
[183] Minn.
Stat. § 216E.02, subd. 1.
[184] Ex. 1, at
8, Appendix A, Figure A-4 (Application)(denoted “Wider Route Area”).
[185] Ex. 7, Schedule
2 (Stevenson Direct).
[186] See In the Matter of the Application for a
[187] Byron Evidentiary Hearing
Transcript at 21-24 (Gronseth).
[188] Minn.
Stat. § 216E.02, subd. 1.
[189]
[190] Minn.
Stat. § 216E.03, subd. 3a; Minn. Stat. § 216E.03, subd. 4; Minn. R. 7850.2100,
subp. 2; Minn. R. 7850.2100, subp. 4.
[191] See generally Ex. 2..
[192] Minn.
Stat. § 216E.03, subd. 6; Minn. R. 7850.2300, subp. 2; Minn. R. 7850.2500,
subp. 2; Minn. R. 7850.2500, subp. 7; Minn. R. 7850.2500, subp. 8; and Minn. R.
7850.2500, subp. 9.
[193] Minn. R.
7850.2500, subp. 10.
[194]
[195] Minn. Stat. §§ 14.57-.62 and 216E.02, subd.
2.
[196] Byron Afternoon Public Hearing
Transcript at 16-19.
[197] Byron Afternoon Public Hearing
Transcript at 20-24.
[198] Byron Afternoon Public Hearing
Transcript at 24-30.
[199] Byron Evening Public Hearing
Transcript at 15-21.
[200] Byron Evening Public Hearing
Transcript at 22-29, 61-66.
[201] Byron Evening Public Hearing
Transcript at 30-34.
[202] Byron Evening Public Hearing
Transcript at 36-37, 40.
[203] Byron Evening Public Hearing
Transcript at 44-47.
[204] Byron Evening Public Hearing
Transcript at 48-52.
[205] Byron Evening Public Hearing
Transcript at 52-54.
[206] Byron Evening Public Hearing
Transcript at 56-60.
[207] eDockets No. 201011-56359-02 (eFiled November 9, 2010).
[208] eDockets No. 201011-56359-02 (eFiled November 9, 2010).
[209] This comment appears to be a
reference to the outage that occurred on June 25, 1998, when lightning strikes
resulted in two 345 kV lines (Prairie Island–Byron and King-Eau Claire) and one
161 kV line (Alma-Rock Elm) being taken out of service, with an overall outage
period of 19 hours.. See .1998
System Disturbances, at 13 (North American Electric Reliability Council,
May 2001) (http://www.nerc.com/files/disturb98.pdf).
[210] eDockets No. 201011-56359-02 (eFiled November 9, 2010).
[211] eDockets No. 201011-56614-02 (eFiled November 17, 2010).
[212] eDockets No. 201011-56614-02 (eFiled November 17, 2010).
[213] eDockets No. 201011-56642-02
(eFiled November 17, 2010).
[214] eDockets No. 201011-56642-02 (eFiled
November 17, 2010).
[215] eDockets No. 201011-56642-02
(eFiled November 17, 2010).
[216] eDockets No. 201011-56642-02
(eFiled November 17, 2010).