|
|
OAH 7-2500-21394-2 IP-6829/CN-09-1046 IP-6829/WS-09-1239 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Applications of Lakefield Wind
Project, LLC for a Certificate of Need and Site Permit for a Large Wind
Energy Conversion System in |
SUMMARY OF PUBLIC TESTIMONY |
A public hearing was conducted in this
matter at the
Kate O’Hair, Regional Project Developer, appeared on behalf of the Applicant. Larry B. Hartman, State Planning Director, and Jamie MacAlister, Senior Planner, appeared on behalf of the Minnesota Department of Commerce (DOC). Brett A. Eknes, State Planning Director, appeared on behalf of the staff of the Minnesota Public Utilities Commission (PUC).
1.
The Lakefield Wind Project has been in the
planning and development stages for approximately seven years. Construction of the wind turbines which are
designed to convert wind energy to electricity is scheduled to begin in the Fall
of 2010. The project consists of 137
1.5 mw turbines (a total of 205.5 mw (renewable)), located in four
townships in
2. For the first 20 years of the project (which is scheduled to go “online” in September, 2011) the energy produced by the Lakefield project turbines will be purchased by Indianapolis Power and Light.
3. The General Electric turbines (Model GE SLE) will stand up to 408 feet high, when the blade on the rotor is at its apex. The mast of each turbine is approximately 268 feet high. Each turbine will be made of rolled steel, and have a circular diameter of approximately 20 feet at its base, surrounded by a circular gravel pad (skirt) extending another 15 feet around the outside of the base of the turbine. Taken together, the turbine and its skirt will be approximately 50 feet in diameter. Small access roads will be constructed through fields, connecting each turbine and its skirt to roads or landowners’ driveways. The access roads will be between 15 and 20 feet wide. The area occupied by the turbine pads and access roads for each turbine will be approximately one-quarter acre. During the construction phase of each turbine, approximately eight acres will be granted by easement to enXco to allow sufficient room for the transport, layout and construction of the turbine components and related equipment needed to build and erect each structure.
4.
The developer of the project, EDF-EN (Electricitie
de France-Energie Nouvelles), is the renewable energy division of the French national
electric company. In
5. Transformer boxes will be constructed adjacent to each turbine, from which boxes the electric energy will be transmitted by cable to the intermediate collection points described above. In response to a question from Mike Handzus, Ms. O’Hair clarified that the lines from each transformer to each intermediate collection point will stay on the private property of the participating landowner. Ms. O’Hair pointed out also that reports regarding impacts on cultural resources, an ecological risk assessment, and a bird survey were filed as part of the Applications.
6. Local landowner John Nauerth, a supporter of the project, urged commencement of construction as soon as possible.
7. Mr. Handzus, Thomas Hotzler and Richard Klima raised questions regarding the positioning and setback requirements for each turbine. Mr. Hotzler was concerned about whether any public money was to be spent on the Lakefield project, and Ms. O’Hair clarified that only private funds would be used in the development of the project.
8. Mr. Hartman explained that the State’s noise standard, relevant to the wind turbines proposed for construction, is for a limit of 50 decibels (which can be exceeded for a maximum of 10 minutes each hour). In order meet the standard, each turbine must be placed at least five rotor diameters (approximately 1,250 feet) from each other along the prevailing wind axis (north-south) and three rotor diameters (approximately 750-800 feet) apart on the nonprevailing wind axis (east-west). Ms. O’Hair noted that enXco is locating the turbines at a minimum setback of 1,000 feet from any road, and that the developer intends to place its turbines far enough from any occupied building to meet the applicable noise standard.
9. In response to a question from Mr. Hotzler, Ms. O’Hair explained that the 137 turbines planned currently will completely fill the area planned for the project. No other turbines are planned in connection with this development.
10. In response to Richard Klima and Mike Handzus, Ms. O’Hair clarified that the turbines will be positioned, so far as possible, perpendicular to the prevailing winds, which are from the northwest during the winter, and from the southeast during the summer. Mr. Klima asked whether landowners could build homes closer to the turbines than the distance allowed for the State noise standard, and Mr. Hartman explained that the distance required to meet the noise standard could not be waived.
11. Mr. Handzus expressed concern that the project may lead to the construction of additional high voltage transmission lines in the area in order to transmit the electricity converted from wind energy in the Project. His concern was that landowners may end up having more of their property confiscated by eminent domain in order to build the High-Voltage Transmission Lines.
12. Richard Klima raised concerns about emergency situations, such as collapse of any of the turbines or their components, and fires. Mr. Klima and Milton Fricke also raised concerns about possible difficulties associated with farming in the areas where interconnecting cables would be laid in the ground. The two major issues are whether tile lines would be cut during construction of the trenches for the interconnection cables, and whether excessive weight on the soil underneath the areas on which heavy equipment will operate during the construction phase would result in soil compaction which could stunt the growth of crops grown in those areas in the future.
13.
Regarding safety procedures, Ms. O’Hair that
each turbine could be controlled separately from the Project’s office in
Lakefield, and also from enXco’s regional center in
14. The developer is committed to fixing any tile that may be cut during the process of digging trenches for the collection system of electrical cables, and will also finance evaluation by local Agricultural Extension Agents to determine whether or not crop lands have been damaged permanently due to soil compaction that occurs during the construction phase of the Project. In that connection it was noted that 125-foot easements for road construction would be acquired in order to haul turbines and associated equipment in and out of the building sites.
WRITTEN COMMENTS ON THE LAKEFIELD PROJECT
1. Written comments on the Project were received from Jamie Schrenzel, Principal Planner with the Environmental Review Unit of the Minnesota Department of Natural Resources (DNR), and local landowner Mike Handzus.
2. Ms. Schrenzel’s filing indicates that the DNR has reviewed the Site Permit Application, Draft Site Permit, and Avian Survey documents, including the survey protocol and results for the Project. Attached to Ms. Schrenzel’s submission is a “Final Bird Survey Protocol for the Lakefield Wind Project”, issued by Debra R. Pile of the Office of Energy Security.
3. Ms. Schrenzel notes that, pursuant to a Commission Order on March 9, 2010 to the effect that the Applicant work with the DNR to identify and conduct studies assessing the need for exclusion areas and avian and bats-specific permit conditions, the appropriate staffs of the DNR, United States Fish and Wildlife Service (USFWS) and OES met to discuss pre-construction survey protocols. Subsequent to the meeting, Ms. Pile issued her April 20, 2010 letter, referenced above.
4. Ms. Schrenzel noted that while the DNR and the Applicant generally agreed on survey locations, the Final Protocol included less observation time and fewer field visits than what the DNR and USFWS had recommended.
5. Ms. Schrenzel wrote that the Applicant has completed surveys as required by the Final Protocol and submitted a Pre-Construction Avian Survey Report, dated July 7, 2010. She notes that no bat surveys had been conducted to date.
6.
Ms. Schrenzel stated the purpose of conducting
surveys and possible flyways and breeding bird habitats near wildlife
management areas, a
7. Ms. Schrenzel’s comment notes that the season for acoustic monitoring of bat activity ends soon (late September), but suggests that the DNR has provided information on the conduct of bat surveys and will be available for consultation regarding the procedures for any studies.
8. Due to the density of conservation lands and avian and bat habitat features within and near the Project area, the DNR considers the site to be at high risk for avian and bat mortality due to turbine strikes or habitat avoidance.
9. The DNR recommends also mortality monitoring, to be included as a permit condition for the site permit, requiring post-construction mortality surveys for two years (developed with DNR consultation), for the purpose of understanding actual impacts and what may be necessary to develop the best adaptive management techniques if rare or migratory species takings or high avian mortality occurs despite avoidance efforts taken in response to pre-construction data.
10.
The DNR is concerned also with the possible
disruption in the viewshed of the
11. The DNR notes also that System Site Permits currently do not include guidance or requirements addressing the prevention of invasive plant species introduction to areas that are temporarily disturbed, specifically during periods of construction when larger areas of soil will be exposed. The DNR suggests adding prevention methods to limit the introduction of invasive species in the Soil Erosion and Sediment Control Plan.
12.
The comments filed by Mr. Handzus expand on the
concerns he raised orally at the Public Hearing about emergency situations such
as the toppling of the turbines and the possible fire hazards. In addition, his filing includes information
on the possible “ice-throwing” hazard that could result from pieces of ice
being hurled from the ends of the turbine rotors. Mr. Handzus’s data relates an incident in
13. Mr. Handzus’s data includes also accounts of serious fires and heavy damage inflicted by the collapse of turbines. He details also the health hazards involved with constant exposure to the noise generated by the turbines and the “flicker effect” (shadow flicker and strobing flicker). People exposed to the constant low-frequency noises emitted by wind farms can demonstrate a range of symptoms from headaches, migraines, nausea, dizziness, palpitations and tinnitus to sleep disturbance, stress, anxiety and depression. These symptoms affect persons activities of daily living, causing poor concentration, irritability and an inability to cope. The data submitted by Mr. Handzus indicates also that the most severe health risk associated with shadow flicker and strobing is seizure. Other risks include headache, loss of balance, nausea and disorientation. If a person is driving a car or operating a piece of farm equipment when stricken with a seizure, the result could be devastating.
Dated this _30th_ day of August, 2010.
/s/ Richard C. Luis
|
RICHARD
C. LUIS Administrative
Law Judge |
Reported: Court Reported
Transcript
Prepared by Christine Simons, Shaddix & Associates