|
|
OAH 15-2500-20995-2 PUC E-002, ET-2/TL-09-1056 |
|
|
|
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Application for a Route Permit for
the |
TABLE OF CONTENTS |
Summary of the Position of the Parties
Preparation of the Environmental Impact
Statement
Description of the Proposed Project
Application of the Routing Criteria to the
Project as a Whole
Effects
on Public Health and Safety
Radio,
Television, Cellular Phone and Global Positioning System (GPS) Interference
Application of the Statutory and Rule
Criteria to the North Dakota to Alexandria Segment
Description
of the Route Alternatives
Effects
on Land-Based Economies
Effects
on Archaeological and Historical Resources
Effects
on Natural Environment
Effects
on Rare and Unique Natural Resources
Use
of Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural
Field Boundaries
Use
of Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
Costs
of Constructing, Operating and Maintaining the Facility
Adverse
Human and Natural Environmental Effects That Cannot Be Avoided
Irreversible
and Irretrievable Commitments of Resources
Recommendation
for the North Dakota to Alexandria Segment
Accommodation
for Rest Areas and Scenic Easements
Application of the Statutory and Rule
Criteria to the Alexandria to Sauk Centre Segment
Description
of the Route Alternatives
Effects
on Land-Based Economies
Effects
on Archaeological and Historical Resources
Effects
on Natural Environment
Effects
on Rare and Unique Natural Resources
Use
of Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural
Field Boundaries
Use
of Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
Costs
of Constructing, Operating and Maintaining the Facility
Adverse
Human and Natural Environmental Effects That Cannot Be Avoided
Irreversible
and Irretrievable Commitments of Resources
Recommendation
for the Alexandria to Sauk Centre Segment
Application of the Statutory and Rule
Criteria to the Sauk Centre to St. Cloud Segment
Description
of the Route Alternatives
Effects
on Land-Based Economies
Effects
on Archaeological and Historical Resources
Effects
on Natural Environment
Effects
on Rare and Unique Natural Resources
Use
of Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural
Field Boundaries
Use
of Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
Costs
of Constructing, Operating and Maintaining the Facility
Adverse
Human and Natural Environmental Effects That Cannot Be Avoided
Irreversible
and Irretrievable Commitments of Resources
Recommendation
for the Sauk Centre to St. Cloud Segment
Mitigation Recommended by the DNR
|
|
OAH 15-2500-20995-2 PUC E-002, ET-2/TL-09-1056 |
|
|
|
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Application for a Route Permit for
the |
FINDINGS OF FACT, CONCLUSIONS AND RECOMMENDATION |
This matter was assigned to Administrative Law Judge Beverly Jones
Heydinger (ALJ) to conduct a contested case hearing on the application by Xcel
Energy and Great River Energy for a route permit for the
Between November 16, 2010, and December 3, 2010, twelve public hearings
were held in ten communities. An
evidentiary hearing was held on December 6, 2010, and continued on December 7
through 10 and December 15, 2010, at the office of the Public Utilities
Commission (Commission) in
The parties filed post-hearing submissions. The hearing record closed on April 4, 2011, upon receipt of the Office of Energy Security’s response to a letter from the ALJ.
Appearances: Lisa M. Agrimonti, Michael Krikava and Elizabeth Brama, Briggs and Morgan, P.A., appeared on behalf of the Applicants, Northern States Power Company (Xcel Energy) and Great River Energy.
Carol A. Overland, Attorney at Law, appeared on behalf of NoCapX2020 (NoCapX), United Citizens Action Network (U-CAN) and North Route Citizens Alliance (NoRCA), collectively referred to as NoRCA.
Michael J. Ford and Cally R. Kjellber, Quinlivan & Hughes, P.A., and
Richard L. Pemberton, Stephen F. Rufer, H. Morrison Kershner, and Chad R.
Felstul, Pemberton, Sorlie, Rufer & Kershner, P.L.L.P., appeared on behalf
of
Gerald W. Von Korff and John C. Kolb, Rinke Noonan, Attorneys at Law,
appeared on behalf of
Karen Finstad Hammel, Assistant Attorney General, and David Birkholz, State Permit Manager, appeared on behalf of the Department of Commerce – Office of Energy Security, Energy Facility Permitting (OES).
David Seykora attended on behalf of the Minnesota Department of Transportation (MnDOT).
Bret Eknes and Bob Cupit, Commission staff, were present on behalf of the Commission.
Should the Commission issue a route permit to Applicants and, if so, for which of the routes under consideration and under what conditions?
The ALJ recommends that the Commission issue a route permit as follows, subject to the conditions set forth in this report:
Sauk Centre to St. Cloud Segment: Route G with Option 11 and the E-5 segment of Option 12.
Based on the information in the Route Permit Application to the Commission, the contested case hearing record, including public comments and exhibits, and the Environmental Impact Statement, the Administrative Law Judge makes the following:
1.
On October 1, 2009, the Applicants jointly
applied for a Route Permit to construct a 345 kV transmission line and
associated system connections from
2. The Commission issued a Certificate of Need for the Project in May 2009.[2]
3.
The Applicant stated that the length of the
4.
For purposes of analysis, the route was divided
into three segments: from
5.
Xcel Energy, a wholly owned subsidiary of Xcel
Energy, Inc. is a
6. NoCapX, U-CAN and NoRCA have joined together in this proceeding. NoCapX seeks to assure that the record is fully developed concerning each route option, the capacity of the transmission lines and related amperage and electromagnetic fields, and dissemination of the Draft Environmental Impact Statement to the public. U-CAN seeks to assure that landowners are well-informed about the proceedings and have sufficient information to effectively participate. NoRCA members are concerned about the proliferation of transmission lines and the impact of route selection on the environment.
7.
8.
Summary of the Position of the Parties
9.
For the segment of the route from
10.
For the segment of the route from
11.
For the segment of the route from
12.
In their Reply Brief, the Applicants stated that
the impact of Route E and Route G was quite similar, if not equal, that both
routes satisfy the routing criteria and are constructible, and both routes are
reasonable alternatives to the
13.
14.
NoRCA prefers either Route G or Route E with
Option 11, and asserts that both are prudent and feasible alternatives to the
15. No party advocated for the selection of Routes A, B, C, D, F or H, but some members of the public favored Route C and Route D, as more fully set forth in the Summary of Public Comment, largely because these alternatives more closely follow I-94 between Sauk Centre and St. Cloud.
16. Pursuant to Minn. Stat. § 216E.10, subd. 3, several state agencies were given the opportunity to participate in the routing proceeding. MnDOT and the DNR submitted comments at several points, and representatives testified at the evidentiary hearing.
17. MnDOT fully reviewed the proposed Project. Its primary areas of concern are: siting in the vicinity of four airports; the significant impact of construction along highways and, in particular, traffic disruption on I-94; the high number of proposed I-94 crossings; the siting limitations through areas classified by MnDOT as scenic easements or used as a Safety Rest Area, and the potential impact that underground construction on Route D could have on highway construction, operation and maintenance.[5]
18.
The Minnesota Department of Natural Resources (DNR)
offered comments addressing the impact of the route alternatives on lands it own
and manages, the impact of the route alternatives on the environment, and
mitigation. It requested that the
Applicants avoid identified high bird-use areas and migration corridors, state
managed resources and federally owned or managed resources, and the placement
of lines between these areas.
Recognizing that the route selection must take into account several
criteria, the DNR recommended selection of Route A for the
19. Both MnDOT and DNR recommended conditions on the permit to mitigate the Project’s impact.
20. OES fully participated in the public hearings and evidentiary hearings to assure that the Environmental Impact Statement was complete and responded to issues raised in the course of the proceeding.
21.
On October 1, 2009, Xcel Energy and Great River
Energy, the Applicants, filed an application for a route permit for a 345 kilovolt
(kV) transmission line from
22. On March 31, 2010, the ALJ issued a Notice of Prehearing Conference.
23. A Prehearing Conference was held on May 18, 2010. On May 25, 2010, the ALJ issued a Prehearing Order, establishing the schedule and procedures for intervention, prefiled testimony, hearing and other matters related to the contested case proceeding. The deadline for intervention was October 8, 2010.
24. Pursuant to Minn. Stat. § 216E.03, subd. 9, the Commission is directed to process an application for a Route Permit within one year from the date upon which the Commission finds that application complete, and the deadline may be extended for good cause. The Applicants agreed to the schedule set at the Prehearing Conference, recognizing that, due to the length of the proposed route and the complexity of the Project, a final decision would not be reached within one year from the date that the application was deemed complete.
25. Also on May 25, 2010, the ALJ sent a letter and copy of the Prehearing Order to representatives of the following Minnesota state agencies: Department of Agriculture, Board of Water and Soil Resources, Department of Natural Resources and Pollution Control Agency, notifying them of the proceeding and the requirements of Minn. Stat. § 216E.10, subd. 3.
26. On September 4, 2010, NoCapX, U-CAN and NoRCA filed a Petition to Intervene. The Petition was deficient and an Amended Petition for Intervention was filed on September 24, 2010. An Order Granting Intervention to NoCapX202, United Citizens Action Group and North Route Citizens Alliance was issued on November 6, 2010. The three groups will be referred to collectively as NoRCA.
27.
On October 7, 2010, Petitions to Intervene were
filed on behalf of
28.
On October 13 and 14, 2010, Applicants prefiled
the Direct Testimony of Darrin Lahr and Gerald Chezik. On October 29, 2010,
29. OES published notice of the contested case proceeding, including the dates, times and places of the public hearings, in legal newspapers of general circulation.[9]
30. OES sent notice of the contested case to persons on the project contact list maintained by the Commission on October 25, 2010.[10]
31. On November 1, 2011, OES sent notice of the contested case proceeding to local government officials. [11]
32.
On November 17, 2010, the Applicants filed
Rebuttal Testimony of Darrin Lahr;
33. On November 30, 2010, the Applicants filed Surrebuttal Testimony of Darrin Lahr, Daniel Kline and Dr. Peter Valberg. On December 3, 2010, NoRCA filed an objection to the Surrebuttal Testimony of Darrin Lahr, Dr. Peter Valberg and Motion to Strike, and Objection and Motion to Strike Direct Testimony of Darrin Lahr. The motions were denied on the record on December 6, 2010.[12] However, the related prefiled testimony of Dr. David O. Carpenter, and his cross-examination on the record in a prior proceeding before the Commission, were admitted into evidence.[13]
34. Public hearings were held as follows:
November 16, 2010 – Barnesville and Fergus Falls
November 17, 2010 –
Breckenridge and
November 18, 2010 –
November 30, 2010 –
December 1, 2010 –
December 2, 2010 –
35. The evidentiary hearing was held on December 6 through December 10, 2010, and December 15, 2010, at the Commission. In addition to the witnesses whose testimony was prefiled, David Birkholz testified on behalf of OES; David Seykora testified on behalf of MnDOT, and Jamie Schrenzel testified on behalf of the DNR.
36. The deadline for receipt of public comment was January 5, 2011. All written comments were reviewed and filed by the Office of Administrative Hearings with the Department of Commerce e-docket system. The public comments are summarized in Appendix A to this report.
37.
Also on January 5, 2011, comments were received
from the Applicants, MnDOT, the Federal Aviation Administration (FAA) and City
of
38.
The Applicants filed their initial post-hearing
brief on January 28, 2011; responsive briefs were filed by NoRCA,
39.
On March 23, 2011, the ALJ requested information
from the Applicants and OES concerning apparent discrepancies in the
information provided by them concerning the number of residences within 500
feet of the
40. By letter dated April 4, 2011, OES responded, clarifying information in the record concerning the location of residences in this segment. [17]
41.
42.
On June 29, 2009, and June 30, 2009, the
Applicants mailed letters to local governments within the Project area.[19] On October 1, 2009, the Applicants mailed
notice to landowners whose property was within or adjacent to proposed or
alternative routes and substations sites, and to persons on other mailing lists
maintained by the Commission.[20]
43.
Applicants sent copies of the Application to
public libraries within the Project area.[21]
44.
Between October 1, 2009, and October 6, 2009,
the Applicants published notice of the Application in newspapers throughout the
Project Area.[22]
45.
The Applicants gave notice to landowners
affected by Option 13 to the
Preparation of the Environmental Impact
Statement
46.
47. The scoping process is the first step in developing an EIS. OES “shall provide the public with an opportunity to participate in the development of the scope of the [EIS] by holding a public meeting and by soliciting public comments.” During the scoping process, alternative routes may be suggested for evaluation in the EIS.[25]
48. The scoping process “must be used to reduce the scope and bulk of an [EIS] by identifying the potentially significant issues and alternatives requiring analysis and establishing the detail into which the issues will be analyzed.”[26]
49. At the conclusion of the scoping process, OES must issue a scoping decision that addresses the following: 1) the issues to be addressed in the EIS; 2) the alternative sites and routes to be addressed in the EIS; and 3) the schedule for completion of the EIS.[27]
50. On December 21, 2009, OES issued a Notice of Public Information and Environmental Impact Statement (EIS) Scoping Meetings to provide information to the public about the Proposed Project. The purpose of the Scoping Meetings was to receive public comment and input on the draft route permit issued by the Commission, and to take public comment and input on the EIS. The public was invited to review the Application, learn more about the Commission review process, offer comments and ask questions.[28]
51.
Between January 19, 2010, and January 28, 2010,
OES held 12 Public Information and EIS Scoping meetings at six different
locations in the Project area.[29]
52.
OES appointed an Advisory Task Force (ATF) to
develop alternative routes that would be considered for the
53.
Public comments regarding the scope of the EIS
were accepted by OES until February 12, 2010.[31]
54.
On April 15, 2010, OES issued its EIS Scoping
Decision, responding to the public comments on the scope of the EIS and setting
forth the alternatives to be addressed.
The EIS Scoping Decision specified that an analysis of the potential
environmental and socio-economic impacts of certain routes, including those
proposed by the Applicants and identified by the ATF, would be performed.[32] OES issued an Amended Scoping Decision on July
25, 2010, incorporating some alternatives requested by Applicants on June 28,
2010.[33]
55.
On September 2, 2010, OES issued the Draft EIS
(DEIS) and notice of availability of the DEIS for the proposed project.[34]
56.
OES held eight public hearings on the DEIS from
September 27 through September 30, 2010, in seven different locations.[35]
57.
Minnesota Rules require OES to “respond to
timely substantive comments received on the [DEIS] consistent with the scoping
decision and prepare the final [EIS].”
OES may “attach to the [DEIS] the comments received and its response to
comments without preparing a separate document.”[36]
58.
On January 7, 2011, OES issued the final EIS
(FEIS), including its response to the comments received.[37]
Description of the Proposed Project
59.
The total length of the Proposed Project is
approximately 211 to 250 miles. The
estimated length is calculated from the planning engineers’ recommended
location for a new
60.
The Minnesota portion of the Proposed Project
will be approximately 151 to 189 miles long, extending from the Red River along
the Minnesota and North Dakota border between Clay and Wilkin counties, to the
existing Alexandria Switching Station located south of Alexandria and then to
the new Quarry Substation.[39] The North Dakota portion of the Proposed
Project from the Bison Substation to the
61.
On December 30, 2010, the Applicants filed a
Certificate of Corridor Compatibility with the North Dakota Public Services
Commission.[41]
62.
The Applicants’ process for developing and
selecting route alternatives, including their
63.
The Project connects to the Bison Substation in
64.
The new Quarry Substation, which is being
constructed as part of the
65.
The Project will also require modifications to
the existing Alexandria Switching Station to accommodate this Project and to
provide support to the underlying 115 kV transmission system. Expansion will include 345 kV and 115 kV
equipment, such as switches, a transformer, control panels, and circuit
breakers, and the additional foundations and structures to accommodate
them. The graded and fenced area
occupied by the substation will be enlarged.
AS-3, which has been incorporated into the
66.
The estimated cost of the Project in
67. The Power Plant Siting Act requires that route permit determinations “be guided by the state’s goals to conserve resources, minimize environmental impacts, minimize human settlement and other land use conflicts, and ensure the state’s electric energy security through efficient, cost-effective power supply and electric transmission infrastructure.”[49]
68. Under the Act, the Commission and ALJ must be guided by the following responsibilities, procedures and considerations:
(1) evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;
(2) environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;
(3) evaluation of the effects of new electric power generation and transmission technologies and systems related to power plants designed to minimize adverse environmental effects;
(4) evaluation of the potential for beneficial uses of waste energy from proposed large electric power generating plants;[50]
(5) analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;
(6) evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted;
(7) evaluation of alternatives to the Applicant’s proposed site or route proposed pursuant to Section 216E.03, subdivisions 1 and 2;
(8) evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way;
(9) evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;
(10) evaluation of future needs for additional high voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;
(11) evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and
(12) when appropriate, consideration of problems raised by other state and federal agencies and local entities.[51]
69. In addition to the Power Plant Siting Act, Minn. R. 7850.4000 provides that no route permit may be issued in violation of site selection criteria and standards found in Minnesota Statutes or Public Utilities Commission Rules. Power line permits must be consistent with state goals to minimize environmental impact and conflicts with human settlement and other land use. The Commission and ALJ are governed by Minn. R. 7850.4100, which provides for the following factors to be considered when determining whether to issue a route permit for a high voltage transmission line:
A. effects on human settlement, including, but not limited to, displacement, noise, aesthetics, cultural values, recreation, and public services;
B. effects on public health and safety;
C. effects on land-based economies, including, but not limited to, agriculture, forestry, tourism, and mining;
D. effects on archaeological and historic resources;
E. effects on the natural environment, including effects on air and water quality resources and flora and fauna;
F. effects on rare and unique natural resources;
G. application of design options that maximize energy efficiencies, mitigate adverse environmental effects, and could accommodate expansion of transmission or generating capacity;
H. use or paralleling of existing rights-of-way, survey lines, natural division
lines, and agricultural field boundaries;
J. use of existing transportation, pipeline, and electrical transmission systems or rights-of-way;
K. electrical system reliability;
L. costs of constructing, operating, and maintaining the facility which are dependent on design and route;
M. adverse human and natural environmental effects which cannot be avoided; and
N. irreversible and irretrievable commitments of resources.[53]
70. State agencies are required to consider environmental factors before making decisions, including the routing of high voltage transmission lines, that potentially have significant environmental effect, and shall not make a decision that is likely to cause pollution, impairment, or destruction of a natural resource so long as there is a feasible and prudent alternative consistent with the public health, safety and welfare.[54]
71. It is the State’s policy to recognize the impact of human activity on the natural environment, and the need to balance development with restoring and maintaining environmental quality, and to attempt to make decisions that create and maintain conditions under which human beings and nature can exist in productive harmony while fulfilling the social, economic, and other requirements of present and future generations.[55]
Application of the Routing
Criteria to the Project as a Whole
72. There is sufficient evidence in the record for the ALJ to assess the proposed routes and alternatives using the criteria set out above.
73. The application of various design considerations, electrical system reliability, costs of operating and maintaining the facility, and some health effects do not vary by route alternative. Those that vary will be addressed under each route segment.
74.
The Commission must evaluate future needs for
additional high-voltage transmission lines in the same general area and the
advisability of ordering the construction of structures capable of expansion in
transmission capacity.[56]
75.
The Commission must also consider the
application of design options that “maximize energy efficiencies, mitigate
adverse environmental effects, and could accommodate expansion of
transmission….”[57]
76.
For this Project, the Commission previously
approved the construction of double-circuit-capable structures to allow for
future transmission expansion. Both sets
of davit arms will be installed on the structures, but only one circuit will be
installed for this Project. The second
position will be available for a future additional circuit, in the event that
the Commission grants a second certificate of need.[58]
77.
The proposed structures will primarily include
single-pole, double-circuit capable, self-weathering or galvanized steel
structures that will range in height between 130 and 175 feet, typically placed
on a concrete foundation. Site-specific
conditions may require special structures.
For example, shorter structures may be needed in the area surrounding
the
78.
The span length between structures will
typically range from 600 to 1,000 feet, depending on site-specific
considerations.[61]
79.
At interstate crossings and where site
conditions may make it prudent to do so, the Applicants propose stringing three
additional bundled conductors (i.e., both circuits) during construction of this
Project. This will prevent disrupting
traffic at highway crossings and disturbance of sensitive areas at a later date
if the Commission approves installation of a second circuit. For this Project, the second set of
conductors will be tied to the first set to act as a single circuit, with no
change to the transmission capacity.[62]
80.
The Commission granted the Applicants permission
to string the additional conductors at highway crossings and in sensitive areas
for the 345 kV transmission line from
81.
MnDOT supports a condition on the Route Permit
that would require Applicants to string both circuits at the I-94 crossings.[64]
82.
The transmission line is made up of three
phases, each one consisting of a pair of 954,000 circular mills (954 kcmil,
approximately 1.2 inches in diameter) 54/7 Cardinal Aluminum Conductor Steel
Supported (ACSS) cables or conductors of comparable capacity, “bundled
conductors.” One bundled conductor is
installed on each of three davit arms.
For the Proposed Project, the bundled conductors will be strung in a
vertical configuration, with one bundled conductor per davit arm on one side of
the structure.
83.
Shield wires will be installed and will include
fiber optic cable to allow substation protection equipment to communicate with
equipment at other terminals on the transmission line.[65]
84.
The Applicants’ proposed structure type and
spans are designed to meet future needs for high voltage transmission lines and
the proposed design will maximize energy efficiency, mitigate environmental
effects and accommodate expansion of transmission.
85.
In selecting a route the Commission must consider
the effect on electrical system reliability.[66]
86.
The Project has been approved by the Commission
for construction with double-circuit-capable structures, with a single circuit
to be strung initially, and with the capability of adding a second circuit if
subsequently approved by the Commission.
The reliability of the Project was fully evaluated in the Certificate of
Need proceeding.[67]
87.
When developing the route segments, the
Applicants analyzed the possibility of co-locating portions of the Project on the
same structures as existing facilities, but concluded that doing so was not
feasible because of reliability, safety, and the need for the line to be
double-circuit compatible. Applicants
applied the reliability criteria established by North American Electric
Reliability Corporation (NERC). In some
instances, where it was possible to parallel existing transmission lines, and
the parallel lines would not unduly decrease the system’s overall reliability,
parallel placements were incorporated into the proposed routes.[68]
88.
Because of reliability and safety concerns, the
Applicants do not propose adding an existing circuit as a third circuit to
these facilities. Triple-circuit
structures pose additional maintenance safety concerns for workers, which may
require de-energizing the line.
Triple-circuit construction is occasionally employed for a short
distance to minimize the potential for significant human or environmental
impact and minimize the need for new right-of-way.[69]
89.
The transmission line will be designed to meet
or surpass all relevant state and local codes, National Electric Safety Code
(NESC), NERC requirements and the Applicants’ standards.[70]
90.
There is no evidence that any of the route
alternatives will have a detrimental effect on the reliability of the electrical
system.
91.
The Power Plant Siting Act authorizes the
Commission to designate a route with a variable width of up to 1.25 miles.[71]
92.
The “route width” is the width included in the
Route Permit to allow the Applicants to vary the alignment of the transmission
line placement to accommodate construction and location-specific
conditions. For the Applicants’
93.
The Applicants are seeking route widths greater
than 1,000 feet in several areas. Many
of the broader route widths are intended to accommodate interstate freeway
exchanges.[73]
94.
In some areas, the Applicants request a route
width less than 1,000 feet, primarily to avoid lands held in fee by the USFWS,
which will not permit an overhead transmission line. In these locations, the Applicants request a
route width of 400 feet.[74]
95.
It is not clear in the record which of the route
width deviations the Applicants are still seeking.
96.
The “right-of-way” is the distance on each side
of the center line of the final alignment that is necessary for the Applicants
to access the transmission line for repair and maintenance. For overhead lines, the right-of-way assures
sufficient clearance from the transmission line to trees, buildings and other
objects, and takes into account the lateral movement of the transmission lines
due to the wind. Adequate right-of-way
also allows for safe tree maintenance.
97.
For underground lines, the right-of-way
requirements allow for construction and maintenance of the concrete duct and
splice vaults within which the transmission lines are installed. In addition, the clearance limits the
planting of vegetation that could interfere with installation or
maintenance. Some activities and
installations are allowed within the right-of-way.[75]
98.
For the type of pole structures the Applicants
plan to use, the transmission line will require a 150-foot right-of-way in most
locations. In some instances, the Applicants may be
able to share rights-of-way. For
example, when running parallel to a road, the Applicants typically place the
poles 20 to 25 feet off the existing road right-of-way, on the adjacent
property.[76] With this pole placement, the transmission
line shares the existing right-of-way, reducing the size of the easement
required from the adjoining landowner.
Similar sharing may be possible with railroads and utilities.[77] In the event that a second circuit is added
to the double-circuit capable pole structures at a later date, the Applicants
do not anticipate that they would need to seek additional right-of-way.[78]
99.
Typical construction techniques are set forth in
the Application.[79] For this project, Applicants are proposing to
use helicopters to install conductors and some hardware and have met with MnDOT
and the Minnesota State Patrol to discuss the feasibility of this approach
along highways, including I-94. Also,
Applicants are proposing to use implosive connectors to join conductors and
dead-end hardware rather than using hydraulic splices. Implosive connectors use controlled detonation
to fuse the conductors and hardware together.
The process creates noise equivalent to a clap of thunder or commercial
fireworks, lasting only an instant. The
process improves the strength and quality of the connections that can be a
potential failure point along the line. It
also takes less time to install than hydraulically-compressed connectors, and reduces
the number of areas required for set-up, which also reduces the amount of
ground disturbance along the route.[80]
100. Much
of the
101. Highway
crossings present additional challenges.
In addition to the interference with traffic during construction and
highway maintenance, crossings may restrict future development of overpasses,
interchanges or additional lanes, and increase the cost to the Trunk Highway
Fund of such improvements. Of special
concern, MnDOT noted that there could be 20 interstate highway crossings along
the
102. MnDOT
generally prohibits installation of utilities within Safety Rest Areas.
Selection of a route along I-94 may restrict the available options for the
location of future safety rest areas or require additional cost to relocate the
transmission lines.[83]
103. MnDOT
has a Utility Accommodation Policy, with specific provisions that govern
placement of utilities along an interstate highway. Typically, MnDOT requires that the poles and
davit arms are outside the interstate freeway right-of-way so that the utility’s
maintenance equipment does not need to enter the freeway right-of-way. The utility may be able to share some highway
right-of-way because line blow-out into the right-of-way poses fewer risks to
the highway operation.[84]
104. MnDOT
recommends that a condition be placed on the Route Permit to require that the
Applicants coordinate with MnDOT, local highway authorities, the State Patrol
and other appropriate agencies to manage the safe flow of traffic throughout
construction.[85]
105. Each
type of roadway has a “clear zone” requirement.
Transmission poles must be located a sufficient distance from the edge
of the traveled roadway so that they will not be a safety hazard. The safety
zone may vary with the level of traffic, surrounding topography and the road
speed. Typical roadway maintenance, such
as mowing, refuse removal, sign replacement and inspections, can take place in
proximity to the transmission line, but larger projects, including overpass or
bridge repair, repaving and road improvements, may require larger equipment and
greater clearance.[86]
106. Interstate
94 is a designated “super haul corridor,” which allows for higher height and
weight limits than standard roadways.
MnDOT must assure that the location of the transmission line preserves
these characteristics of the corridor.[87]
107. One
of the routes identified by the ATF for the
108. Underground
construction typically requires digging a trench and installing duct banks for
each circuit. Such construction requires
extensive ground disturbance, which may require considerable clearing and
grading, and increases noise, dust and traffic disruption. Concrete manholes or large splice vaults are
needed at recurring intervals.
Directional boring may be used to pass under a road, highway or
river. An underground line must be
routed to avoid other underground installations such as water, gas and sewer
lines. Transition structures are
required at each end of the underground segment.[89] Although Xcel Energy has some underground 115
kV lines, the Applicants do not have any 345 kV lines placed underground in
109. Transmission lines are designed to operate for decades and require little maintenance. Scheduled and unscheduled outages are rare; the average annual availability of transmission infrastructure exceeds 99 percent. The principal operating and maintenance cost is for inspection, usually done monthly by air. There are also costs for vegetation management, storm damage, and some replacement of materials as the lines age. The Applicants’ annual costs for inspection and maintenance of high voltage transmission lines are $300 to $500 per mile.[91]
110. For the substations, the cost of inspections is the single greatest operation and maintenance cost. Transformers, circuit breakers, batteries, protective relays and other equipment require periodic service. The site must be kept free of vegetation and drainage must be maintained.[92]
111. Generally,
underground transmission lines do not have routine maintenance and operation
costs. Visual inspections are not
possible. Underground transmission lines
are susceptible to two types of outages:
cable fault due to overloading the system and failure of the cable or
splices. The time and cost to repair an
underground transmission line is much greater than an overhead transmission
line, but fail far less frequently.[93] The right-of-way for an underground
transmission line is narrower than the right-of-way for overhead transmission
but requires more maintenance to assure that it remains clear of woody
vegetation.[94]
112. Costs
of the project will be addressed for each route segment, including the costs
for underground construction along the
113. The
figures for each segment do not include the cost to add a second circuit at
highway crossings. The estimated
additional cost to do so is $55,000 per crossing.[95]
114. The
Applicants anticipate that, if the route permit is issued, construction would
begin in the second quarter of 2012 and the transmission line would be placed
in service in the first quarter of 2015.[96]
Effects on
Public Health and Safety
115. The Commission must consider the impact of the route selection on public health and safety.[97] Impacts that are specific to route alternatives will be discussed under the appropriate route segment.
116. Applicants will ensure that all safety requirements are met during construction and operation of the proposed transmission line and associated facilities, and that appropriate signage is installed.[98] The Project will be designed and constructed according to state, local and NESC standards for ground clearance, crossing utilities clearance, building clearance, strength of materials and right-of-way widths. The proposed transmission lines will be equipped with protective devices, including breakers and relays at substations, to safeguard the public in the event of an accident, or in the event that a structure or conductor would fall. Substations will be properly fenced and accessible only by authorized personnel.[99]
117. The placement of high voltage transmission lines, including both structures and conductors, could impact the safe operation of an airport and hinder the maneuverability of aircraft. If close enough, the transmission line could also interfere with the operation of air navigation or weather systems. The Federal Aviation Administration (FAA) and MnDOT have established development guidelines on the proximity of transmission lines to public-use airports and heliports.[100] The location and likely impact of the airports in the Project Area will be discussed with respect to each of the affected route alternatives.
118. NoRCA and many members of the public expressed their concern about the effect that proximity to high voltage transmission lines may have on the health of people and animals.
119. Electric fields are measured in kilovolts per meter (kV/m). The intensity of the electric field is proportional to the voltage of the transmission line. While there is no federal standard for transmission line electric fields, the Commission has imposed a maximum electric field limit of 8 kV/m, measured at one meter above the ground. The maximum electric field associated with the Project, measured at one meter above the ground is calculated to be 4.3 kV/m.[101]
120. Magnetic
fields are measured in milliGauss (mG).
The intensity of the magnetic field is proportional to the current flow
through the conductors. While there are
no federal or
121. Applicants calculated the magnetic field levels for two conditions for the year 2015 (after the lines are operational), with average and with peak system-intact loading. The highest calculated magnetic field level during peak system-intact operations at 2015 projected load levels, with both circuits in service, occurs at the centerline of the right-of-way at 30.03 mG. With only one circuit in service, the highest calculated magnetic field level at the centerline would be 25.62 mG. Magnetic fields are not estimated to be higher than 11.10 mG at the edge of the right-of-way.[105]
122. The Applicants also calculated potential magnetic fields associated with maximum conductor capacity load levels, although the Applicants believe that such load levels are highly unlikely to occur. Such high load levels, 600 and 1500 MVA, would require more than 4,000 MW of new generation to be added to the west of the Project, and would also require a large, unplanned outage of another major facility, such as another 345 kV transmission line. Even with these assumptions, the Applicants could not reach flows of 1200 to 1500 MVA. Based on a theoretical assumption that 1200 and 1500 MVA could be reached, the maximum calculated magnetic field at the centerline would be 259.9 mG, which is significantly below the guidelines.[106]
123. Dr. Peter Valberg is a faculty member in the Department of Environmental Health at Harvard School of Public Health and has conducted research and taught toxicology, cell biology, environmental health, and public health. He has served on many advisory panels and remains current on the research concerning electromagnetic fields and health effects. Dr. Valberg explained that there are two types of magnetic fields, “radio frequencies” (RF), and “extremely low frequency” (ELF). Power-line magnetic fields operate at 60 Hz, ELF. The human body is virtually transparent to power-line magnetic fields, and compared to the continuous background level of approximately 100 watts of energy burning in human bodies, the maximum amount of energy delivered to the whole body by a 1,000 mG, 60-Hz magnetic field is less than 0.00000005 watt. In contrast, RF, created by cell phones, communication towers and cell phone towers at 900 MHz can heat tissue, depending on its intensity, because the RLF frequencies are more readily absorbed by biological tissue than ELF.[107]
124. Many common appliances, such as refrigerators, fans and electric ranges create fairly high magnetic fields close to them, but the strength of the field dissipates quickly as one moves away from the source. Transportation that runs on electric motors, such as some trains, may also have fairly high associated magnetic fields. A gasoline-electric hybrid car will also create a fairly high magnetic field, in the range of 20 to 40 mG.[108]
125. Over the past 30 years, many epidemiological studies have been conducted to determine if there is a correlation between childhood leukemia and proximity to electrical structures. Some studies have shown that there is an association and some have not. Although the epidemiological studies have been refined and increased in size, the studies do not show a stronger related effect. In addition, a great deal of experimental, laboratory research has been conducted to determine causality, and none has been found.[109]
126. Based on his training, experience and research, Dr. Valberg opined that the standards in the range of 2,000 to 9,000 mG are quite conservative and protect against health effects.[110]
127. Many members of the public commented that they are uncomfortable about the EMF and fear its health effects. Some members of the public believe that proximity to power lines has had a seriously detrimental effect on the health of their family members or livestock. Although some individuals may be electric sensitive, there is no research to support such sensitivity.[111]
128. NoRCA
offered the testimony of David O. Carpenter, which was part of the record in a
prior proceeding before the Commission.[112] Dr. Carpenter is a public health physician and
Director of the Institute for Health and the Environment at the
129. Although Dr. Carpenter’s recommendation has not been embraced by the Commission or the standard-setting organizations, it may provide some reassurance to the public that the effect of the magnetic field drops off quickly as one moves away from the source, and that few homes will be close enough to the transmission line to be affected in any way.[116]
Radio, Television, Cellular Phone and Global Positioning System (GPS) Interference
130. Many
members of the public expressed concern about the transmission line’s possible
interference with radio, television, cellular phones or GPS systems.
131. Some
landowners expressed concern that high voltage transmission lines could
interfere with electromagnetically guided cornering systems used for center pivot irrigation systems. A study published in the
132. The
Minnesota Pollution Control Agency (MPCA) sets daytime and nighttime noise
standards.[119]
133. Construction
activities will generate noise that is short-term and intermittent.
Construction will be limited to the hours of 7 a.m. to 10 p.m. With the exception of the use of explosions
to splice the conductors, the project noise will have little effect on the
surrounding area.[120]
134. The
Applicants propose to use implosive connectors rather than hydraulic splices to
join conductors. The process creates
noise equivalent to a clap of thunder or commercial fireworks.[121] Although no evaluation of the resulting noise
was included in the EIS, given the intermittent and widely dispersed explosions
that will be required, it is not likely that the MPCA noise limits would be
exceeded. Signs should be posted to warn
the travelling public of the possible detonations. Nearby residents should also be notified when
the explosions will occur in their area.
135. Transmission
lines produce noise under certain conditions.
The level depends on conductor conditions, voltage level and
weather. The noise during operation and
maintenance is minimal and does not exceed the MPCA Noise Limits outside of the
right-of-way. The estimated noise level
from the transmission lines is 48.5 dBA five percent of the time and 45.5 dBA
fifty percent of the time at the edge of the right of way. Under MPCA noise limits, the noise level at
the residences 1,000 feet away from the route may not exceed the quieter,
nighttime limits of 55 dBA for more than ten percent of the time, or 50 dBA for
more than fifty percent of the time.[122]
136. Members
of the public expressed dissatisfaction with the MPCA Noise Limits because the
rural area that the transmission line will cross is very quiet, with little
background noise.[123] An increase in the noise level will be
noticeable and will adversely affect their enjoyment of the rural setting. However, it is noted that the acceptable
noise level is measured at the edge of the right-of-way. Most residences along the selected route will
be at a much greater distance from the transmission line and experience a lower
noise level.
137. Transmission
lines can create a crackling sound in foggy, damp or rainy weather, caused by a
small amount of electricity ionizing the moist air near the conductors. The
noise is not audible during heavy rain, but may be audible during light rain,
dense fog, snow and other times when moisture is in the air. The audible noise is approximately equal to
household background noise. The noise
level at the edge of the right-of-way can not exceed the MPCA noise limits.[124]
138. The
Quarry Substation will be located in an area that is zoned municipal or
industrial and is not near noise-sensitive areas. The substation’s noise was reviewed in the
139. The
Alexandria Substation will be upgraded.
It is not in a noise-sensitive area and the upgrades are not expected to
significantly increase the noise.[126]
140. In
the event that Route D is placed underground in the
141. Noise associated with the operation of the transmission line is not predicted to exceed the noise limits set by the MPCA.[128]
Application of the Statutory and Rule
Criteria to the
Description of the Route Alternatives
142.
A map
depicting the route alternatives and route options for this segment is
reprinted in Appendix B to this report.
143.
For the
144. After
Applicants filed the Application, they incorporated two changes to the
145. AS-1
provides a
146. AS-1
is shorter and more compatible with the Diversion Project, but it affects a
personal use airstrip, the Lesmeister Flying Service, in
147. AS-2 was originally proposed to connect
the
148. The
Applicants’
149. Additional
options for this segment were considered.
Option 1 along the
150. Option 2A to the
151. During
the scoping of the DEIS, a short segment was added between Option 2A and the
152. The
DEIS analyzes Option 2B, not as depicted on the sheet maps, but as identified
in the DEIS at 1-10, Figure 1-5.[142] As analyzed, Option 2B begins at the point where
Option 2A runs south from the
153. The
DEIS compares Option 2A and Option 2B with the Modified Preferred Route from
the northern point where Option 2A deviates to the southern point where Option
2A and Option 2B rejoin it.
154. The
Applicants’ Tile Map E6 refers to Option 2A and 2B differently from either the
Sheet Maps or the discussion in the DEIS and will not be used as the basis for
comparison.[144]
155. Landowners
along the
156. Option 3 along the
157.
For
this segment, the Modified Preferred (including AS-1), Option 2a and 2b, and
Option 13, will be compared to Route A as proposed in the Application. AS-3, the area needed to expand the
Alexandria Switching Station, is included in both alternatives and will not be
separately evaluated. Because AS-2 is
not included in the
158. In
comparing the
159. The
Commission must consider the impact of the route on human settlement,
including, but not limited to, displacement, aesthetics, recreation, and public
services.[149]
160.
The record
does not show a clear comparison between the number of residential and
non-residential structures within the 1000-foot route for the
161.
The DEIS
includes a different measurement, the number of residences within specified
distances of the proposed right-of-way centerline.
162.
No residences
are located within the proposed rights-of-way for either the
|
Route |
Residences within Proximity of Alignment (Feet) |
||||
|
0-75 |
75-150 |
150-300 |
300-500 |
Total within 500 feet |
|
|
Modified Preferred |
0 |
8 |
21 |
27 |
56 |
|
Route A |
0 |
7 |
33 |
36 |
70 |
|
AS-1 |
0 |
0 |
1 |
2 |
3 |
163.
The
nonresidential structures include agricultural accessory buildings such as
barns and other farm buildings and commercial buildings near highways. There are 371 non-residential structures
within the
164.
There are no residential or non-residential
structures located along Option 13. The
comparative segment of AS-1 has four residential structures and 12
non-residential structures.[154] Thus, selection of Option 13 will reduce the
total number of residential and non-residential structures affected by the
165.
The
|
Route |
Residences within Proximity of Alignment (Feet)[155] |
||||
|
0-75 |
75-150 |
150-300 |
300-500 |
Total within 500 feet |
|
|
Modified Preferred – comparable to Route 2A and
2B |
0 |
2 |
4 |
3 |
9 |
|
Option 2A |
0 |
2 |
0 |
0 |
2 |
|
Option 2B |
0 |
0 |
2 |
3 |
5 |
166.
Although
a few more homes are within 500 feet of the alignment along Option 2B, the
landowners in the area prefer it because the affected homes are farther away
from the proposed centerline and fewer nonresidential structures used in
agricultural production would be affected.[156]
167.
Another way to evaluate displacement is to look
at the land zoned for residential and commercial development. The
type of land and the number of acres that could be impacted by the
|
Route |
Agriculture |
Residential |
Commercial |
Municipal |
Recreation |
Special Ag |
Transitional |
|
Modified Preferred ROW |
1,063 |
58 |
22 |
0 |
77 |
0 |
0 |
|
Modified Preferred No ROW |
1,620 |
88 |
33 |
0 |
117 |
0 |
0 |
|
Route A |
1,129 |
105 |
2 |
0 |
87 |
81 |
111 |
168.
Option
2A and Option 2B affect more agricultural land than the equivalent section of
the
169.
Option
13, like the comparable section of AS-1, affects only agricultural or
undeveloped land, and its use is not expected to change as a result of
construction and operation of the transmission line.[160] Option 13 affects less prime farmland than
the comparable section of AS-1.[161]
170.
The
171. The
proposed transmission line will be constructed on single-pole, double circuit
capable, self-weathering or galvanized steel structures approximately 135 to
175 feet high. The transmission line
will introduce new vertical forms or lines in largely rural areas. In flat or rolling terrain, common in the
Project area, the structures can be visible for a mile or more. On agricultural lands, the pole structures
may be visible for up to two miles. In
addition to the structures, the right-of-way will require vegetation removal
and may have a dramatic effect on the visual appearance. All of the routes will require some corner
structures, breaking the linear nature of the line and having a greater visual
impact.[164]
172. Placement
of an overhead high voltage transmission line will have a significant aesthetic
effect on nearby homeowners and persons who see the transmission line while
travelling or engaging in recreational activities. Sensitive view points include locations from
which a significant number of people who enjoy the scenery would view an
affected landscape. These viewpoints
include transportation corridors, designated scenic byways, existing residences
in close proximity and with an unobstructed view of the transmission line, and
recreational use areas. The proposed
routes have similar impacts on aesthetics.[165]
173.
Between
174.
The
175.
Recreational
resources are also located near the
176.
Option
2A affects less recreational land than the
177.
Each of
the route alternatives pass through a roadway network consisting of various
interstate, state, county, city and other local roadways. The
178.
MnDOT
expressed concern about the high number of freeway crossings (20) along the
179.
Except
to the extent that Option 2B follows I-94 along the
180. There
are three full-service rest areas along I-94 in this segment, which will be
affected by the
181. Southeast
of
182.
There
are three public airports located along the
183.
If the
184.
Applicants
analyzed the requirements that would be in place if the Lesmeister Flying Service
were subject to the specific clearances set by the FAA for regulated
airports. The Applicants determined that
the
185.
Applicants
proposed Option 13 to avoid the airport.
Option 13 would place the transmission line far enough from the
Lesmeister Flying Service so that the restrictive FAA clearances would be
met. Option 13 would avoid the runway by
approximately one mile to the south and .5 mile on the east and west.[182]
186.
Many
other private use airports were identified within five miles of the
Effects on
Land-Based Economies
187. The
Commission must consider the effect of the route alternatives on land-based
economies including agriculture, forestry, tourism and mining.[184]
188.
The
primary land-based economy in the Project Area is agriculture. Fifty-five percent of lands occurring within
the
189.
There
are 5,002 acres of prime farmland within the
190.
Option
2B includes approximately the same number of acres of prime farmland as the
191.
The
Project will cause permanent and temporary impacts to farmland. Permanent impacts will occur as a result of
structure placement along the route centerline.
The temporary impacts occur during construction. Applicants estimate that the permanent
impacts to agricultural fields will be 1,000 square feet per pole. In this route segment, the
192. The
Applicants have developed an Agricultural Impact Mitigation Plan with the
Department of Agriculture that identifies measures the Applicants must take to
avoid or mitigate any negative impact to farmland that may occur from
transmission line construction, including restoration of damaged drainage tile,
restoration of soil and removal of debris.
It requires the Applicants to retain an inspector who reports directly
to the Minnesota Department of Agriculture.
It also addresses any impact that construction may have on interruption
of irrigation.[192]
193. Appendix
B to the Agricultural Impact Mitigation Plan addresses
194. Pole
placement may interfere with center pivot irrigation systems. After a route is selected, pole placements
can be negotiated with the landowner during the right-of-way acquisition
process.[194]
195.
There
is one center pivot irrigation system in use within Route A. There are no center pivot irrigation systems
used within the
196.
The
197.
There
are 48 acres of wooded land within the
198. There
is no evidence of potential impact to mining resources along this segment of
the
199. Neither
the
Effects on
Archaeological and Historical Resources
200. The
Commission must consider the effect of the route alternatives on archaeological
and historic resources.[201]
201. Archaeological
and historical resources represent the visible or otherwise tangible record of
past human activity on the landscape. An
archaeological resource refers to a surface or buried resource and an historic
architecture resource refers to a building or structure, constructed since
settlers came in contact with indigenous people.[202]
202. There
are three archaeological sites within the
Effects on
Natural Environment
203. The
Commission must consider the effect of the route alternatives on the natural
environment including effects on air and water quality resources and flora and
fauna.[205]
204.
Where
possible, all rivers, streams and ditches along the proposed routes will be
spanned by transmission structures or avoided to minimize the impact. A limited number of structures could be
located within surface waters.[206]
205.
Wetlands
are present at several points along the proposed routes. The USFWS National Wetlands Inventory (NWI)
was used to identify wetlands throughout the proposed routes and route options. Some surface waters are designated as Public
Waters by the State of
206.
Route A
has 54 acres of NWI wetlands and 10 acres of PWI lakes and wetlands within the
right-of-way. The
|
NWI Wetland Type |
Modified Preferred Route |
Route A |
Option 2A[211] |
Option 2B |
|
Freshwater Emergent |
588 |
387 |
45 |
63 |
|
Freshwater Forested/Shrub |
40 |
31 |
1 |
1 |
|
Freshwater Pond |
92 |
21 |
1 |
12 |
|
|
215 |
35 |
5 |
25 |
|
Riverine |
26 |
5 |
|
|
207.
Temporary
and permanent wetland impacts will occur as a result of the Project. Temporary impacts to wetlands may occur if
they need to be crossed during construction of the transmission line. Permanent impacts to wetlands would occur
where structures must be located within wetland boundaries. Structure placement would result in
approximately 55 square feet of permanent impact per standard single-pole
structure. Temporary impacts would total
approximately 20-foot-wide by length of the transmission line span of the
wetland, which is the assumed width of a temporary access road.[212]
208.
The
Applicants estimated that the
209.
The
210.
The Applicants would need a National Pollution
Discharge Elimination System Permit (NPDES) from the MPCA for the discharge of storm
water generated during construction.
Construction practices can mitigate soil erosion and disturbed soil can
be restored.
211.
DNR
rules require that utilities in public waters should ordinarily be placed
underground. In order to receive
approval for an overhead placement, the applicant must “explain the economic,
technological, or land characteristic factors, which make underground placement
infeasible. Economic considerations
alone shall not be the major determinant.”[216]
212.
The
rules also direct utilities to avoid crossing PWI lakes, but if there is no
feasible and prudent alternative, to minimize encroachment by crossing under
the water.[217]
213.
At this
point in the process, the Applicants and DNR have not determined whether any
portion of the alignment would require an underground portion. Thus, no costs for underground placement in
any specific location have been included in the Project costs. Rather, there is general information about
underground construction and costs.[218]
214.
There
would be no pole placements in NWI or PWI wetlands in Option 2A or Option 2B.[219] However, the Option 2A right-of-way would
include two acres of USFWS wetland easements and Option 2B right-of-way would
include ten acres of USFWS wetland easements.
The
215.
Twenty-six
Waterfowl Protection Areas (WPAs), seven Wildlife Management Areas (WMAs) and
one Scientific Natural Area (SNA) are within one mile of the
216.
There
are 56 acres of USFWS wetland and grassland easements within the
217.
There
are no SNAS, WMAs or WPAs in the
218.
Critical
habitat is the natural environment that supports species. Designated habitat or conservation areas
include unmanaged areas such as the
219.
The Minnesota County Biological Survey (MCBS)
attempts to locate, organize and rank sites with significant biodiversity. There are three levels: moderate, high, and outstanding. Areas with moderate biodiversity significance contain significant occurrences
of rare species and/or moderately disturbed native plant communities and
landscapes that have a strong potential for recovery. Areas with high biodiversity significance contain sites with high quality
occurrences of the rarest plant communities and/or important functional
landscapes. Areas with outstanding biodiversity significance contain
the best occurrence of the rarest species; the most outstanding example of the
rarest native plant communities and/or the largest, most intact functional
landscapes present in
220.
In this
segment, there are three acres of MCBS sites of moderate biodiversity
significance within the right-of-way of Route A and one acre of MCBS sites of moderate
biodiversity significance within the right-of-way of the
221.
The DNR
prefers Route A for this segment of the Project because the
Effects on Rare and Unique Natural Resources
222.
The Commission must consider the effect of the
route alternatives on rare and unique natural resources.[228]
223.
Six
species listed as endangered, threatened, or special concern by the State of
224.
The DNR
and its partners have developed
225.
The DNR
and USFWS identified two areas of special concern along the
226.
Route A
would avoid the areas of concern along the
227.
Although
it parallels more existing right-of-way, the
228.
Most of
the effects of the transmission line can be mitigated with careful attention to
construction location and techniques.
The greatest impact on natural resources in this area will be to
waterfowl and migratory birds. The
Applicants have developed an Avian Protection Plan and will attempt to avoid
major flyways or migratory resting spots, avoid high quality wildlife habitat
and add shield wires or avian diverters to the degree possible. However, the prevalence of the habitat within
the
Use of Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural Field Boundaries
229.
The Commission must consider the extent to which
the route alternatives use or parallel existing rights-of-way, survey lines,
natural division lines and agricultural field boundaries.[236]
230.
For the
231.
Option
13 follows a field boundary for 100% of its distance.[238]
232.
Options
2A and 2B parallel existing linear features for 100% of their distance. Option 2a parallels 6.4 miles of roadway and
2.8 miles of field. Option 2B parallels
7.6 miles of roadway and 1 mile of field.[239]
Use of
Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
233.
The Commission must consider the extent to which
the route alternatives use existing transportation, pipeline and electrical
transmission system rights-of-way.[240]
234.
In People
for Environmental Enlightenment and Responsibility (PEER) v. Minnesota
Environmental Quality Council,[241]
the Minnesota Supreme Court discussed the value of selecting transmission
options that avoid proliferation of new right-of-way if a feasible and suitable
alternative exists.
235.
The Legislature has also directed the Commission
to make specific findings that it considered locating a high voltage
transmission line on an existing high voltage transmission line route or
parallel to existing highway right-of-way, and to state its reasons if it did
not select such a route.[242] The statute does not apply to this proceeding
because the Route Permit was filed prior to the statute taking effect, but the
principle established in PEER applies.
236.
The extent to which a proposed route will follow
existing transmission lines, highways and other established rights-of-way is a
factor to be considered in the decision. Although this factor alone is not
determinative of the routing decision, its principle, frequently referred to as
“non-proliferation,” has merit and must be considered. Once a party has made a showing that the
proposed route will adversely affect natural resources, one must determine
whether there is a feasible and prudent alternative. If there is a feasible and prudent
alternative that will better promote the public health, safety, or welfare,
that option should be selected.[243]
237.
The selection of a pre-existing route:
minimizes the impact of the new intrusion
by limiting its effects to those who are already accustomed to living with an
existing route. More importantly,
however, the establishment of a new route today means that in the future, when
the principle of non-proliferation is applied, residents living along this
newly established route may have to suffer the burden of additional power line
easements.[244]
238.
Because of the desirability of
non-proliferation, this factor is given greater weight than the factor which
includes not only rights-of-way, but also survey lines, natural division lines
and agricultural field boundaries.
Although such features are helpful for siting the proposed line,
following such lines and boundaries does not avoid proliferation.
239. It is likely that homes will be affected by running transmission lines along highway rights-of-way because homes are typically placed close to roads. Thus, it is necessary to balance the desirability of following existing rights-of–way, the number of homes in proximity to the alternatives, the impact on the environment, cost, and the other routing factors to determine which route best meets the routing criteria.
240.
For this
segment, 77% of the
241. The Modified Preferred Route parallels less existing right-of-way and linear features than the Preferred Route Applicants initially proposed, but the Applicants prefer the Modified Preferred Route because it allows for a river crossing that is farther south of the Fargo area, which addresses the concerns raised by local officials.[246]
242.
By
comparing the distance that Option 2A and Option 2B follow roads, rails, trails
or transmission lines, one can calculate the approximate corridor sharing for
the options. Option 2A follows roads for
approximately 69 percent of its length; Option 2B follows roads for
approximately 88 percent of its length.
The comparable section of the
Costs of
Constructing, Operating and Maintaining the Facility
243. The Commission must consider the costs of constructing, operating, and maintaining the facility that are dependent on design and route.[248] The costs of operation and maintenance are based on a per-mile figure.
244.
For this segment, the estimated cost of construction
of the
245.
Option 2A will add approximately $15.7 million
to the cost of the
246.
Despite its shorter length, Route A is more
expensive to construct than the
247.
Both the
Adverse
Human and Natural Environmental Effects That Cannot Be Avoided
248.
The Commission must consider the adverse human
and natural environmental effects that cannot be avoided.[252]
249.
The
unavoidable adverse impacts associated with the Project include the physical
impacts to the land, primarily agricultural land, caused by the construction of
the Project. The agricultural impacts
are discussed in detail above. The
250.
Applicants
intend to work with the USFWS and DNR to minimize the impact of construction,
restore disturbed land, and avoid major flyways or migratory resting spots.
Irreversible
and Irretrievable Commitments of Resources
251.
The Commission must consider whether the
irreversible and irretrievable commitment of resources will be affected by
route selection.[254]
252.
Construction resources, such as concrete, steel
and hydrocarbon fuels, will be irreversible and irretrievably committed to this
Project. The use of resources is
relative to the length of each route.
Within
Recommendation
for the
253.
The
254.
The permanent impact on the environment from the
placement of structures can be mitigated with careful attention to construction
techniques and restoration. The most
difficult impact to mitigate will be the effect on the birds in flight. Sharing the I-94 right-of-way will help
reduce impact on habitat, but care must be taken to avoid adverse consequences
caused by the location and length of the conductors.
255.
Option 2B is a feasible and prudent alternative
to either the
256.
Option 13 is a feasible and prudent alternative
to one portion of the
Accommodation for Rest Areas and Scenic Easements
257.
The Applicants seek a broader route width at two
points in
258.
Further south, at section 32 of
259. The residents of River Oaks support an alignment that crosses the MnDOT scenic easement.[258] Although MnDOT typically prohibits crossing scenic easements, it has an exception process, which would require the Applicant to address certain criteria set forth in the federal regulations and the MnDOT Accommodation Policy.[259]
260. The Applicants do not object to seeking an exception to move the alignment closer to I-94 in this area.[260]
261.
Further south in
262.
Although no final determination has been made,
MnDOT is evaluating the possibility of eliminating the Iverson Rest Area
because of the rising water. However,
because the land was purchased with federal funds, MnDOT must follow specific
procedures to dispose of the property.
In light of the procedures to be followed, MnDOT was uncertain whether
the land would be available for a transmission line crossing.[263] If the
263.
In
Application of the Statutory and Rule
Criteria to the
Description
of the Route Alternatives
264.
A map
depicting the route alternatives and route options for this segment is
reprinted in Appendix B to this report.
265.
The Applicants proposed the Modified Preferred Route and an alternative, Route A, for this segment. The
266.
AS-3
includes 4.3 acres along the
267.
For this segment, the
268.
Option 4
is approximately five miles long and deviates from Route A, parallel to and
north of Route A, about two miles northeast of Forada. This option would require an aerial crossing
of
269.
Option 5
is approximately three miles long and deviates from the
270.
Option 6
is approximately 1.5 miles long and connects the Modified Preferred Route and
Route A about 2 miles west of Sauk Centre to allow selection of a portion of
each of the two routes.[273] It does not follow an existing right-of-way.[274]
Option 6 would allow a switch to Route A from the
271.
Option 7
is approximately two miles long and is a shorter alignment option within Route
A about five miles west of Sauk Centre. It
would cross the Victor Winter Wildlife Management Area, but it would affect
fewer homes, center pivot irrigation systems and less wooded land than a more
northerly alignment within Route A.[276]
272.
For this segment, the
273.
The
following table shows the number of residential and nonresidential structures
within the 1,000-foot routes for each route alternative. Twenty more residences are located within the
|
Route |
Residences |
Nonresidential Structures |
|
Modified Preferred |
57 |
246 |
|
Route A |
37 |
98 |
274.
The
following table shows the number of residential structures within 500 feet of
the proposed right-of-way centerline for each route. There are seven more homes within 500 feet of
the centerline for the
|
Route |
Residences within Proximity of Alignment (Feet) |
||||
|
0-75 |
75-150 |
150-300 |
300-500 |
Total
within 500 feet |
|
|
Modified Preferred |
0 |
12 |
13 |
16 |
41 |
|
Route A |
0 |
8 |
13 |
13 |
34 |
275.
The
Option 7 alignment will affect four fewer homes than Route A. Option 6 will decrease the number of affected
homes on the
276.
Route A
has 23 fewer non-residential structures within 150 feet of the alignment than
the
277.
Another way to evaluate the effect of the
transmission lines on human settlement is to look at the acres of land zoned
for residential use within the right-of-way proposed for each route.
278.
The
type of land and the number of acres within the right-of-way that could be
impacted by the
|
Route |
Agriculture |
Residential |
Commercial |
Municipal |
Recreation |
Special
Ag |
Transitional |
|
Modified
Preferred ROW |
213 |
77 |
31 |
0 |
44 |
0 |
0 |
|
Modified
Preferred No ROW |
322 |
117 |
46 |
0 |
66 |
0 |
0 |
|
Route
A |
482 |
104 |
15 |
0 |
41 |
40 |
0 |
279.
Both the
280.
Option 6 crosses more land zoned for
agricultural use than the
281.
Option 7 crosses only land zoned for agriculture
but because it is shorter than the comparable section of Route A, it affects
less agricultural land.[286]
282.
The
283.
As set forth more fully above, placement of an
overhead high voltage transmission line will have a significant aesthetic
effect on nearby homeowners and persons who see the transmission line while
travelling or engaging in recreational activities. The number of residences within 500 feet of
the proposed alignment of the two alternatives is not significantly different. Route A has seven fewer homes than the
Modified Preferred route and 11 fewer homes if the Option 7 alignment is selected.[288]
284.
Recreational
resources in the project area from Alexandria to Sauk Centre include WPAs,
WMAs, lakes, boat launches, local and regional trails, a golf course, and other
recreational uses.[289]
285.
From
286.
The
Central Lakes Trail is a 55-mile paved trail between
287.
MnDOT owns the Lake Wobegon Trail between Osakis
and
288.
The Applicants’ estimated costs of the Project
do not include costs associated with crossing or running parallel to the Lake
Wobegon Trail.[293]
289.
There
are no state parks, state forests or SNAs within one mile of either route.[294]
290.
One
scenic byway, the Glacial Ridge Trail, runs within one mile of both the
291.
The
Lynx National Golf Course is located within the Route A right-of-way, east of
Highway 71 and south of the
292.
Both
the
293.
Visitors
to the recreational areas may view the transmission line, which distracts from
the attractiveness of the area, but the transmission lines are not expected to
interfere with recreational use.
294.
The
295.
MnDOT expressed concern about the unusually high
number of freeway crossings close to
296.
There are two public airports in this segment of
the Project. One, Chandler Field, can be
avoided, but proper notice must be given to the FAA.[300] The other airport,
297.
The
298.
The City of
299.
The
300.
Runway 08/26 is a secondary, unpaved crosswind
east/west runway that is 2,270 feet long and 140 feet wide. It is located at the north end of the Runway
14/32, not far from I-94. The ALP
reflects the City’s intention to upgrade Runway 08/26 to a paved runway, 2,500
feet by 60 feet. There is no timeline
for the City’s proposed upgrades.[304]
301.
MnDOT and the FAA have rules that govern runway
clearance, including airspace and land use restrictions. The FAA rules require notice and review of
any object that may affect the navigable airspace. MnDOT also regulates obstructions in the
airspace and prescribes airport approach and turning standards. The most significant airspace requirements
applicable to this proceeding are the “departure slopes,” which extend upward
and outward from each runway. There are
also relevant land use safety requirements.
Within Safety Zone A, the area that extends beyond the end of the runway
for approximately two thirds the runway length, certain structures, including
transmission lines, are restricted.
Within Safety Zone A, an aerial transmission line is prohibited,
regardless of its height.[305]
302.
The City of
303.
Throughout this proceeding, the Applicants,
MnDOT, and City representatives discussed the impact of the airport on the
routing. On December 28, 2010, they met
with FAA officials to review possible design modifications that would address
concerns about interference with runway clearance and the City’s objection to
running the transmission line on the north side of I-94 along
304.
The Applicants believe that an alignment north
of I-94 could be developed to address the current airport configuration and
safety standards and avoid the downtown portion of
305.
The Applicants requested flexibility to develop
an alignment in consultation with MnDOT, the FAA and the City of
306.
In the event that the Modified Preferred Route cannot
be aligned to comply with federal and state aviation standards and address the
City’s objections to alignment along 12th Street, an alternative is
to follow the Modified Preferred Route to Option 6, then follow Option 6 and
Route A to the point where Route A rejoins the Modified Preferred Route at the
end of this segment. This would add
about 3.5 miles to the length of the
307.
During the hearing, questions were raised about
the feasibility of placing the transmission line underground through the airport
clearance zone, a distance of about 2,400 feet.
This would require construction of both circuits under the
308.
There are no 345 kV transmission lines
underground in
Effects on
Land-Based Economies
309.
Within
this Project segment, 58 percent of the land within the
310.
The
311.
The
312.
The
Project will cause permanent and temporary impact to farmland. Permanent impact will occur as a result of
structure placement along the route centerline.
Applicants estimate that the permanent impact to agricultural fields
will be 1,000 square feet per pole, and the temporary impact will be one acre
per pole.[318]
313.
The
314.
Ninety-six
percent of the lands within the Option 6 right-of-way are zoned for
agriculture. There are no center pivot
irrigation systems in the Option 6 right-of-way. The permanent impact to agricultural lands is
minimal but still higher for the Option 6 alignment than the
315.
One
hundred percent of Option 7 is zoned for agriculture as is the Route A
right-of-way at this location. There is
one center pivot irrigation system within the Option 7 area and six within the
equivalent segment of Route A.[321]
316.
The
proposed routes are located primarily in grassland and cultivated land. The wooded areas within or near the routes
are located primarily on privately held lands.
There was no evidence of commercial forestry operations.[322]
317.
There
are 295 acres of wooded lands within the
318.
Information
on mining was taken from MnDOT’s Aggregate Source Information System, based on
319.
The
Effects on
Archaeological and Historical Resources
320.
This section
of the
321.
This
section of Route A does not contain any previously recorded archaeological or
historic architecture resources.[328]
Effects on
Natural Environment
322.
A total
of 414 acres of wetlands occur within the
323.
The
324.
The
following chart shows the types of NWI wetlands and acres within the proposed
routes and Option 6. [331]
|
NWI Wetland Type |
Modified Preferred Route |
Route A |
Option 6 |
|
Freshwater Emergent |
303 |
552 |
174 |
|
Freshwater Forested/Shrub |
73 |
155 |
4 |
|
Freshwater Pond |
8 |
4 |
1 |
|
|
17 |
8 |
|
|
Riverine |
12 |
0 |
|
325.
As set
forth fully above, permanent structure placement would result in approximately
55 square feet of permanent impact per standard single-pole structure. The temporary impact is approximately 20 feet
wide, the assumed width of a temporary access road, for the distance that the
transmission line spans the wetland. The
Applicants estimated that the
326.
Route A
has approximately 40 acres more of NWI wetlands within the right-of-way and
would have three times as many poles in NWI wetlands as the
327.
Both
Route A and the
328.
Option
6 would have little effect on any natural resources. It contains one acre of wetland and no poles
would need to be placed in that wetland.[336]
329.
The
330.
For
this segment, the
331.
Option
6 would include 6.5 acres of land designated in the MCBS as “moderate” within
its right-of-way.[339]
332.
Route A
crosses seven USFWS easements, three WMAs, six MCBS sites of biodiversity
significance, two BWSR RIM Easements, and five Native Plant Communities. Route A does not cross any WPAs, SNAs, or
MCBS Railroad Prairies.[340] Route A would cross the Sauk River WMA and
the Wild and Scenic River District east of the
333.
The
following table summarizes the number of sensitive management areas within the
right-of-way of the
|
Type of Area |
Modified Preferred Route |
Route A |
|
Number of USFWS Easements within ROW |
1 |
2 |
|
Total Acres of USFWS within ROW |
7 |
3 |
|
Number of MCBS Sites of Biodiversity Significance
within ROW |
0 |
2 |
|
Total Acres of MCBS Sites of Biodiversity
Significance within ROW |
0 |
12 |
|
Number of WMAs within ROW |
0 |
1 |
|
Acres of WMAs within ROW |
0 |
12 |
|
Number of MCBS Native Plant Communities within
ROW |
0 |
2 |
|
Acres of MCBS Native Plant Communities within ROW |
0 |
5 |
334.
The
impact of Option 6 is similar to Route A.[343]
335.
The
Lake Osakis Important Bird Area is located in this segment, near
336.
To
avoid impact to waterfowl and migratory birds, DNR recommends Route A from
337.
The DNR
concurs with the Applicants’ alignment of the
Effects on
Rare and Unique Natural Resources
338.
In preparing the DEIS, OES coordinated with the
USFWS and DNR and did not identify any areas of concern within this
segment. The impact on habitat was also
evaluated. Although both alternatives
have relatively little impact, Route A impacts a WMA (220 acres within the
Route, 12 within the right-of-way), an MCBS Site designated as Moderate (56
acres within the Route, 10 within the right-of-way), and five native plant
communities (32 acres with the Route, 5 within the right-of-way). There are none within the
339.
The DNR has identified Species of Greatest
Conservation Need, those with rare, declining or vulnerable populations, at
levels below what is desirable to ensure long-term health and stability
(including threatened and endangered species).
Of the five identified species that occur within one mile of the
Use of
Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural
Field Boundaries
340.
For the
Use of
Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
341.
For the
Costs of
Constructing, Operating and Maintaining the Facility
342.
For the
Adverse Human and Natural Environmental Effects That Cannot Be Avoided
343.
The DEIS and FEIS offer suggestions to mitigate
the effect of the transmission line, including adjustment of the alignment and
placement of the structures to avoid or span sensitive areas or to increase the
distance from homes and non-residential structures. Applicants have expressed their intention to employ
best practices and work with the USFWS, DNR and other agencies to minimize the
impact of construction, restore disturbed land, and avoid major flyways or
migratory resting spots.
Irreversible
and Irretrievable Commitments of Resources
344.
Construction resources, such as concrete, steel
and hydrocarbon fuels, will be irreversible and irretrievably committed to this
Project. The use of resources is
relative to the length of each route.
Since Route A is longer than the
Recommendation
for the
345.
Overall, the
346.
The DNR would prefer to follow Route A to Option
6 and then go north to the
347.
If MnDOT, the FAA and the City can not find an acceptable
alignment for the Modified Preferred Route, the transmission line should follow
the Modified Preferred Route south from Alexandria to Option 6, along Option 6
to Route A, and follow Route A to the point of reconnection with the Modified
Preferred Route south of Sauk Centre. This
selection would avoid the airport, the developed part of the City and
significantly reduce the number of freeway crossings. If this alternative is selected, the Route
Permit should require the Applicants to coordinate with the DNR to mitigate the
alignment’s impact.
348.
Option 7 is shorter and would affect fewer
homes, less wooded land and agricultural operations than the comparable portion
of Route A. However, Option 7 would cut
across a field and WMA and increase the number of poles placed in
wetlands. In the event that Route A is
selected, the Applicants should work with the DNR and the landowners to find an
alignment that will have the least effect on human settlement and the natural
resources in this area.
Application of the Statutory and Rule
Criteria to the
Description of the Route Alternatives
349.
A map
depicting the route alternatives and route options for this segment is
reprinted in Appendix B to this report.
350.
This segment of the Project was the most
controversial. An ATF was appointed and
many route alternatives were developed for study in the EIS. The Applicants’
351.
For ease of comparison, each of the nine routes
is compared from a point east of
352.
In order to more fully analyze the many
alternatives for this section, the DEIS assigned route segment identifiers.
353.
This segment of the Project is in proximity to
the Avon Hills Conservation Area, which is a part of the Stearns County
Comprehensive Plan.[355]
The Conservation Overlay District includes lands in Collegeville, St. Wendel,
354.
Avon Hills is ecologically significant because
it encompasses a rare complex of undeveloped forest, native plant communities
and wildlife representative of the region’s historic environment. A majority of the Avon Hills lies within the
Hardwood Hills ecological subsection, which was predominantly forested in 1850
and still includes key habitats. It is
surrounded by an area that was historically prairie and savanna but is now
cropland.[357]
355.
Many of the forests in the region (
356.
The intervenors, the DNR, and many members of
the public seek a route that will have the least possible effect on the Avon
Hills Conservation Area.
357.
The Applicants’ Modified Preferred Route
begins east of the intersection of State Highway 4 and I-94 and is made up of
segments that run generally east, north of I-94 to a point south of the city of
358.
Option 8
is a diagonal alignment within the
359.
Option 9
deviates to the north of the
360.
Route A
starts at the same point as the
361.
Option 10
is a slight deviation from Route A, approximately 1.5 miles long north of Saint
Rosa. It avoids a home but bisects
parcels.[366]
362.
Route B
begins east of State Highway 4 and I-94, follows Route A east to approximately
4.5 miles west of St. Stephen, and then turns south for 17 miles, west of St.
Joseph and then southeast to the Quarry Substation. Route B is approximately 46 miles long.[367] The ATF identified a portion of the route
west of
363.
Route C
begins east of State Highway 4 and I-94, follows the
364.
Route D
is approximately 38 miles long and follows I-94 the most closely of any route
alternative. It begins east of State
Highway 4 and I-94 and follows the
365.
There are sections along Route D where placement
of the transmission line is quite constrained.
To address this, the Advisory Task Force identified specific portions of
Route D that could be constructed underground.
Those segments are: through Freeport and Albany, each about 1.5 miles
long, and at Avon, underground for approximately ten miles, between Big Spunk
Lake and Middle Spunk Lake, skirting Collegeville and the western and southern
city limits of St. Joseph. The last
underground segment would also affect Route B.[370]
366.
Route D generated
a great deal of public comment. Those
who favored running the transmission line along I-94 generally favored this alternative,
but those who lived along it or recognized the significant impact the route
would have on the cities of
367.
Route E
begins east of State Highway 4 and I-94 and follows the
368.
Option 11
is approximately three miles long and deviates from Route E one mile west of
369.
Option 12
is a small segment of Route E, approximately 1.2 miles long, and two segments
of Route B, approximately 1.8 miles southeast of
370.
AS-4
is a broadened section of Route E, south of
371.
AS-5
is approximately two miles long, paralleling State Highway 138, at the southern
end of the Project Area near the Quarry Substation. It offers an alternative method for the last
portion of Routes B, C, D, E, G or H to connect to the Quarry Substation.[378]
372.
Route F
begins east of the intersection of State Highway 4 and I-94 and is
approximately 49 miles long. It follows
the
373.
Route G
begins just east of the intersection of State Highway 4 and I-94 and is
approximately 44 miles long. It follows
the
374.
Route H
begins just east of the intersection of State Highway 4 and I-94 and is
approximately 45 miles long. It follows
the
375.
The Applicants support the
376.
377.
There was some public support for Route C and
Route D because those two routes most closely follow I-94. However, based on the record as a whole, and
as elaborated in these findings, it is clear that neither Route C nor Route D is
a prudent and feasible alternative to the
378.
MnDOT expressed reservations about whether Route
D could be built without interfering with the operation of I-94 and also
expressed reservations about Route F.[382]
379.
There was no significant support for Route A, B,
F or H, and no evidence that any one of them was a more prudent and feasible
alternative to the
380.
Option 8 is an alignment within the
381.
For this segment, Option 9 is an adjustment to
the
382.
Option 11 affects Route G after Route G rejoins
Route E. Thus, Option 11 will be
compared to Route E.
383. The following table shows the number of residential and nonresidential structures within the 1,000 foot routes for each route alternative.[384]
|
Structures |
Modified Preferred Route |
Route C |
Route D |
Route E |
Route G |
Option 11 |
Option AS-4 |
|
Residences |
191 |
85 |
220 |
91 |
98 |
4 |
5 |
|
Nonresidential Structures |
409 |
146 |
210 |
279 |
251 |
1 |
26 |
384. The FEIS identified residences within 500 feet of the proposed alignment for each route.[385]
|
Route |
Residences within Proximity of Alignment (Feet) |
||||
|
0-75 |
75-150 |
150-300 |
300-500 |
Total within 500 |
|
|
Modified Preferred Route |
1 |
7 |
50 |
34 |
92 |
|
Route C |
2 |
8 |
42 |
27 |
79 |
|
Route D |
9 |
20 |
75 |
75 |
179 |
|
Route E |
0 |
12 |
37 |
27 |
76 |
|
Route G |
0 |
9 |
49 |
30 |
88 |
|
Rte. E comp. to Option 11 |
0 |
1 |
7 |
3 |
11 |
|
Option 11 |
0 |
1 |
2 |
1 |
4 |
385.
There are no homes within 75 feet of the
proposed alignment of Routes E and G or Option 11. The FEIS identified one home within 75 feet of
the Modified Preferred Route Alignment, but the Applicants could not verify the
location based on its data. Route C has two
homes and Route D has nine homes within 75 feet of the proposed alignment.[386]
386.
Within 500 feet of the proposed alignment, the
387.
Routes C, D, E and G have significantly fewer
nonresidential structures within the 1,000-foot route than the
388.
Option 11 would have seven fewer residences
within 500 feet of the alignment than the comparable distance of Route E, and
there is only one nonresidential structure located within Option 11.[389]
389.
The construction and operation of transmission
lines can impact existing and planned land uses and local zoning. For this segment, most of the land along the
routes is used for agriculture or zoned for agricultural use. Modified Preferred Route - 92%; Route C – 91%; Route D – 80%; Route E –
92%; Route G – 94%.[390]
390.
Similarly, most of the land within the
right-of-way for each route is also zoned for agriculture.[391]
|
Acres |
Modified
Preferred ROW Occup |
Modified
Preferred No ROW Occup |
Route
C |
Route
D |
Route
E |
Route
G |
Route
E Comp to Option 11 |
Opt
11 |
Opt
12-B |
Opt
12-E |
|
Agriculture |
533 |
813 |
649 |
527 |
768 |
781 |
57 |
53 |
18 |
22 |
|
Residential |
6 |
9 |
19 |
57 |
10 |
9 |
0 |
0 |
10 |
0 |
|
Commercial-Industrial |
25 |
33 |
34 |
64 |
4 |
3 |
0 |
0 |
4 |
0 |
|
Municipal |
3 |
4 |
10 |
30 |
4 |
4 |
0 |
0 |
0 |
0 |
|
Recreation |
5 |
7 |
5 |
6 |
1 |
.05 |
0 |
0 |
0 |
0 |
|
Special
Ag. |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
11 |
0 |
0 |
|
Transitional |
0 |
0 |
0 |
0 |
10 |
10 |
0 |
0 |
0 |
0 |
391.
Route D would affect the greatest number of
acres of residential land within the 150-foot right-of-way. With the exception of Route D, the number of
affected acres is low. Modified
Preferred Route – 9 (with no I-94 right-of-way sharing; 6 if there is shared
right-of-way); Route C – 14; Route D – 57; Route E – 10; Route G – 9.[392]
392.
The acres of land zoned for commercial and
industrial use within the right-of-way is also a measure of possible
displacement. Modified Preferred Route –
33 acres without right-of-way sharing, and 25 with it; Route C – 34; Route D –
64; Route E – 4; and Route G – 3.[393] Because Route D passes closest to developed
areas, it will affect more potential commercial development than the other
alternatives.[394]
393.
Routes C and D are located within several
municipalities and therefore cross more urban zoning and land uses than the
other routes, which affect predominantly rural areas. Route D follows I-94 and crosses the edges of
394.
The
395.
Route D would have the greatest effect on human
settlement. Route E would have the least
effect, and Routes C, E and G would all have less effect than the
396.
Overall, there will be little direct
socioeconomic impact from construction and operation of the transmission
line. The highest concentration of
population in the Project area is in this segment, between
397.
Dennis Sand, Mayor of Albany, objected to the
impact of Route E on Wells Concrete. He
did not comment on AS-4, which is intended to accommodate Wells Concrete. Mayor Sand also objected to Route D,
asserting that the transmission line would effectively destroy the Albany Golf
Course, regardless of which side of the interstate was selected for alignment,
and would adversely affect several commercial businesses and an industrial park
on the south side of I-94.[398]
398.
Two pipelines cross Route E; one pipeline
crosses Route G. No pipelines cross the
other alternatives or route options.[399]
399.
As set forth more fully above, placement of an
overhead high voltage transmission line will have a significant aesthetic
effect on nearby homeowners and persons who see the transmission line while travelling
or engaging in recreational activities.[400]
400.
There are a wide variety of recreational options
within the Project area, including lakes, rivers, trails, a state forest, WPAs,
WMAs, SNAs, and local and county parks, golf courses and other recreational uses. Visitors to these recreational use areas may
view the transmission line.[401]
401.
Route D and the
402.
Placing the transmission line underground would
decrease the aesthetic impact to the homes along Route D.[403]
403.
To the extent that a route alternative has fewer
homes within 500 feet, it will have less negative aesthetic impact on
homeowners. Homes within 500 feet of the
alignment will be most directly affected, depending to a degree upon pole
placement and topography. Although the transmission
line will be visible for over a mile, the aesthetic impact at any point will
vary significantly with the terrain and other land features.
404.
Portions of each route parallel I-94, a
pre-disturbed major transportation corridor that includes scenic easements. Motorists along roadways that parallel a
route would view the transmission line.
Traffic volumes are heavier along major roads such as I-94 and
405.
Land owned by
406.
The DNR manages “water trails” for canoeing and
kayaking along
407.
There is less park, open space or recreational
land use within the rights-of-way of Route E (1 acre) and Route G (0.05 acre)
than there is along the
408.
As displayed in the table above, there are few
acres of recreational land within the rights-of-way for any alternative. The
409.
The FEIS concluded that, apart from the
aesthetic impact discussed above, none of the routes will significantly alter
or limit the recreational use of the land nearby.[411]
410.
The Lake Wobegon Trail is a significant regional
trail that is crossed by several potential routes.[412] Members of the public strongly objected to
running the transmission line along the trail.
411.
Route D parallels the Lake Wobegon Trail within
the 150 right-of-way for approximately eight miles. The
412.
The privately-owned Hemker Park & Zoo is
located in
413.
Route D could have a significant effect on
recreational use. In addition to running
along the Lake Wobegon Trail, Route D
also travels through
414.
Route C was criticized because it would cross
the Lake Wobegon Trail three times, and it passes through the Collegeville Game
Refuge, crossing over the unique wooden covered pedestrian bridge that connects
415.
It is not likely that the transmission line
would alter or significantly limit the recreational use of the land along the
416.
Interstate 94 runs through this portion of the
Project. The
417.
There are two full-service Rest Areas along I-94
in this segment: Big Spunk Lake Rest Area
for eastbound traffic and Middle Spunk Lake Rest Area for westbound traffic. Route D, which follows I-94 in this area, goes
south of I-94 to avoid these rest areas. At this point, I-94 follows a narrow strip of
land that runs between two lakes and near the City of
418.
Construction of Route D underground could
adversely affect maintenance and operation of I-94. Restrictions on activity above the 60-foot
right-of-way required for underground construction may prohibit sharing of the
highway right-of-way or expanding the highway for further development.[419] Placing Route D underground could affect
access to the frontage road near
419.
The intersection of I-94 and Highway 75 near
420.
There are no public use airports within five
miles of these route alternatives, except the
Effects on Land-Based Economies
421.
The primary land-based economy in the Project
area is agriculture. The majority of the
land within each of the route alternatives is zoned for agriculture, with the
percent varying from Route D at 77 percent to Route E at 94 percent.[424] The percentage of agricultural land within
the alignment rights-of-way is similar.[425]
422.
The United States Department of Agriculture has
provided detailed soil data and designated “prime farmland” most desirable for
agricultural production. The
423.
Once the alignment is selected, the number of
acres taken out of production in the right-of-way will be a substantially lower
number, 1000 square feet per pole, approximately 4.82 acres for the
424.
One of the reasons that the ATF selected Route G
for study was because it impacts primarily large-tract farmland. This may make it easier to place structures
farther from residences and to have less impact on farm operations.[428]
425.
There are more center pivot irrigation systems
along Route E and Route G (11) than along the other routes. The
426.
The proposed routes include some forested areas
adjacent to farmsteads, waterways and within DNR managed lands. Also,
427.
Because the wooded areas have negligible
commercial forestry operations, and no townships within the proposed routes
have timber harvest plans, selection among the other alternatives is not
expected to impact commercial forestry operations. The
428.
To determine the location of aggregate resources
for the DEIS, the MnDOT Aggregate Source Information System, a database based
on county pit maps completed in 2003, was reviewed. All of the routes under consideration have five
or six aggregate sources, except Route D, which has nine aggregate sources.[433] Within the right-of-way of the proposed
alignments, most of the routes include the same aggregate pit near
429.
The majority of tourism along the proposed
routes is associated with recreational uses, discussed above.
Effects on Archaeological and Historical Resources
430.
Regardless of the Route selected, the DEIS
recommends that the Applicants conduct an inventory of resources that follows
the State Historic Preservation Office protocol. Information in the DEIS was taken from the
Application for the
431.
The
432.
Impact to the identified archaeological and
historic resources can be largely avoided by designation of the area and
adjustments to construction, but some may be sensitive to visual
intrusion. If a resource cannot be
avoided, evaluation and planning should be coordinated with the State Historic
Preservation Office, Office of the State Archaeologist, and the OES to mitigate
the adverse impact.[437]
433.
If the underground options along Route D were
selected, the potential impact on archaeological resources would be
significantly higher and would require a specialist to assess and document the
impact.[438]
434.
435.
The Sisters of the Order of Saint Benedict were
also concerned that Route C or Route D may adversely affect their property,
which is south of St. John’s. Like
436.
Several members of the public commented on
Century Farms located along the proposed route alternatives. In 1976, the Minnesota State Fair and the
Minnesota Farm Bureau formally recognized longstanding family farm ownership through
a program known as Century and Sesquicentennial Farms. Since the inception of the program, 8,500
437.
There is insufficient evidence upon which to compare
the effect of the route alternatives on archaeological and historic resources.
Effects on
Natural Environment
438.
The entire route, including this segment,
includes many protected areas, including WMAs, SNAs, National Wildlife Refuges
(NWRs), WPAs, and state game refuges, as well as conservation easements, flora,
fauna, rare and unique natural resources and critical habitat. The ecological significance of the Avon Hills
area is described above.
439.
The DEIS evaluated surface water (lakes, rivers
and streams), ground water, wetlands and floodplains within the routes and the
planned alignments.[443]
440.
Because all rivers, streams and ditches would be
spanned by transmission structures, the impact on surface water would be
minimal for any of the route alternatives.
Each of the routes would require a number of stream crossings, but there
are no significant differences in the number of crossings.[444] None of the route alternatives will have a
significant impact on the surface waters.[445] The following table shows wetland type and
acreage for each of the proposed routes and route options.[446]
|
NWI Wetland Type |
Modified Preferred Route |
Route C |
Route D |
Route E |
Route G |
Option 11 |
Option 12B |
Option 12E |
Option AS-4 |
|
Total NWI Wetland Acreage |
2267 |
873 |
799 |
1229 |
967 |
17 |
152 |
72 |
128 |
|
Freshwater Emergent |
1561 |
716 |
661 |
1015 |
808 |
14 |
134 |
67 |
96 |
|
Freshwater Forested/Shrub |
592 |
88 |
65 |
128 |
112 |
0 |
17 |
6 |
32 |
|
Freshwater Pond |
85 |
49 |
29 |
55 |
39 |
3 |
1 |
0 |
0 |
|
|
6 |
13 |
16 |
22 |
0 |
0 |
0 |
0 |
0 |
|
Riverine |
24 |
8 |
8 |
8 |
8 |
0 |
0 |
0 |
0 |
441.
Wetlands will be affected by pole placement,
particularly during construction, but there will be virtually no permanent loss
of wetlands from any of the route alternatives.
Route E and Route G require the fewest pole placements in wetlands; the
442.
The temporary impact on the wetlands can be
mitigated by scheduling construction when the ground is frozen and accessing
the wetland from a point with the least physical impact.[448]
443.
Many members of the public and NoRCA were
concerned about the effect that the
444.
Each of the route alternatives will cross the
FEMA 100-year floodplain. The number of
poles that would be placed within the floodplain varies from three in Route E
and Route G to nine in the
445.
None of the alternatives under consideration
will cross a WPA or SNA. Route E will
cross Legacy Marsh WMA, although the proposed alignment runs on the western
edge of it.[451] Route E also runs next to and between several
lakes, particularly along
446.
The 2,430-acre Collegeville Game Refuge is part
of the land privately held by
447.
Evaluation of the affected acreage alone does
not provide a complete picture of environmental impact from placement of the
transmission line. Fragmentation of
forests can have a disproportionate effect on some species, particularly since
the forest clearing is permanent within the transmission line right-of-way. Widening existing rights-of-way will further
replace forest habitat with grassland or edge habitat, which may increase predation
on the forest species.[455]
448.
The
449.
The acres within the proposed rights-of-way are
more similar, but the
450.
None of the alternatives will have a major
permanent impact on non-agricultural vegetation except where wooded lands are
permanently removed from the right-of-way. Placing Route D underground would impact more
wooded lands because only grasses and low shrubs would be permitted within its
60-foot right-of-way.[458]
451.
Throughout the area between
452.
Many members of the public were concerned that
the selected route should have as little effect on the Avon Hills as possible.
453.
Also,
454.
455.
Development along Route C or Route D would
increase the “edge effect,” the effect of clearing land at the edge of the
forest. Edge effect has several
components: warming the air and soil
shifts the plant species within 100 meters of the forest edge; non-native
invasive plants may move from disturbed areas into adjacent natural areas; and
predators may move from the grassland and edge habitat up to a quarter mile
into the adjacent forests. It is costly
in both time and money to mitigate the effects of this intrusion on the forest,
and more difficult to mitigate than wetland disturbance.[466]
456.
Route E and Route G skirt the large wooded areas
and would decrease the edge effect, particularly if Option 11 is selected.[467]
457.
Agricultural lands are not key habitats for the
species of greatest concern. Since
farming can continue within the rights-of-way, transmission line construction
will have less permanent impact to natural resources than construction in
wetlands and, especially, in forested areas.[468]
Effects on
Rare and Unique Natural Resources
458.
Rare and unique natural communities and habitats
occur throughout the area between
459.
Route C and Route D bisect the Avon Hills
Conservation Design Overlay District and run closest to several rare features
that may be adversely affected by further habitat fragmentation. The
460.
MCBS sites are present between
461.
The
462.
The next highest level of impact is Route G,
which has 51 acres of high biodiversity significance (8 acres in the
right-of-way), as well as 60 acres with moderate biodiversity significance (6
in the right-of-way), and 56 acres of Native Plant Communities (7 in the
right-of-way).[473]
463.
Route E would have less impact than Route G, 20
acres of high biodiversity significance (2 in the right-of-way); 42 acres of
moderate biodiversity significance (6 in the right-of-way), and 37 acres of
Native Plant Communities (3 in the right-of-way). Selection of Option 11 would decrease the
acres with high biodiversity significance and Native Plant Communities within
Route E and Route G.[474]
464.
Route C is the only route alternative that
includes land designated as outstanding biodiversity significance, 57 acres, within
the
465.
Route D would have the least impact on rare and
unique natural resources, with only one acre of outstanding or high
Biodiversity Significance and 15 Native Plant Communities.[476]
466.
The
467.
Perhaps because of its narrower right-of-way, placing
a portion of Route D underground would have slightly less impact on Sites of
Biodiversity Significance, Native Plant Communities and the Avon Hills IBA than
Route D above ground.[479]
468.
The DNR and other organizations have developed a
State Wildlife Action Plan (SWAP), “Tomorrow’s Habitat for the Wild and Rare,”
to protect key habitats that are susceptible to population growth and
development for “Species of Greatest Conservation Need” (SGCN). There are very few occurrences of these
species within the 1000-foot route for any of the alternatives under
consideration (one incidence of the Cerulean Warbler on Route G; one incidence
of the Pugnose shiner on Route C).[480]
469.
It is not anticipated that any protected species
will be directly displaced by the proposed rights-of-way as there are few
incidences of protected plants or animals within any of the routes. Transmission line alignment and structure
locations may be able to span sensitive flora or vegetation, further minimizing
the impact. Construction may reduce some
wetland and agricultural habitat but the effect diminishes when vegetation is
reestablished after construction. Timing
construction to avoid breeding or nesting seasons would also mitigate the
impact. It is more difficult to mitigate
the effect of removing forest land since reforestation within the right-of-way
is not possible.
Use of
Existing Right-of-Way, Survey Lines, Natural Division Lines and Agricultural
Field Boundaries
470.
Virtually all of the route alternatives run
along existing rights-of-way, survey lines, natural division lines, or
agricultural field boundaries. Some of
these geographic demarcations, such as survey lines and natural division lines,
are not visible, but attention to them decreases diagonal property crossings. The
Use of
Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
471.
The ATF, which was appointed to consider the
route alternatives from Freeport to St. Cloud, ranked nonproliferation as its
top priority in selecting routes for evaluation.[482]
472.
Of the five alternatives under consideration for
this segment of the Project, the
473.
The
474.
475.
Option 11 follows more field lines than the
comparable section of Route E, which follows more roads. The Route B segments of Option 12 follow roads
and the E-5 segment follows a rail line.[486]
Costs of
Constructing, Operating and Maintaining the Facility
476. The estimated costs of each route alternative are based on a standard per-mile figure of $1.7 million, and take into account pole locations, spotted to minimize impact to wetlands, areas of cultural significance, residential structures and other sensitive areas. The estimated cost per mile for underground construction is approximately $20 million per mile for single circuit construction and $40 million per mile for two circuits.[487]
Modified
Route C $60.9
million
Route D $60.3
million
Route D, inc. underground segments $608.0 million
Route E $64.7
million
Route G $65.2
million
477.
Selection of Option 11 will reduce the length of
Route E and Route G by one mile and the cost by $1.7 million.[488] AS-4 will increase the cost of Route E by
$850,000.[489] Since Option 12 does not affect the route
length by a mile or more, it does not affect the cost for Route E or Route G.[490]
478.
Either Route E or Route G with Option 11 is
slightly less expensive than the
479.
Although Route C is shorter than the other
routes, it requires more angle structures than the
480.
The cost of Route D with segments placed
underground is approximately ten times the cost of any other route
alternative. In addition to the
construction costs, maintenance and repair of an underground transmission line may
be greater than maintenance and repair of an overhead transmission line.[492]
Adverse
Human and Natural Environmental Effects That Cannot Be Avoided
481.
The DEIS and FEIS discuss mitigation for adverse
effects. Some of the adverse effects can
be diminished by careful consultation with landowners, right-of-way adjustment,
and pole placement. The DNR offered several proposals to mitigate the
environmental impact, as set forth below.
Irreversible
and Irretrievable Commitments of Resources
482.
Construction resources, such as concrete, steel
and hydrocarbon fuels, will be irreversible and irretrievably committed to this
Project. The use of resources is
relative to the length of each route.
Since the
Recommendation
for the
483.
The
484.
The
485.
The costs of the
486.
Although the relative merits of Route E and
Route G are quite similar, Route G follows more road right-of-way than Route E,
and the roads are more heavily travelled.
Route G with Option 11 skirts the Avon Hills and will have less
environmental impact than Route E, which runs beside a WMA and between a series
of five lakes.
487.
Option 11 is a more feasible and prudent
alternative than the equivalent portion of Route E or Route G. The E-5 segment of Option 12 is a more
feasible and prudent alternative than the Route B segments of Option 12.
488.
Overall, Route G with Option 11 and the E-5
segment of Option 12 best meets the routing criteria.
489.
Because of displacement, difficulty of construction
and the impact on the Avon Hills, Route D is not a feasible and prudent
alternative to the
Mitigation Recommended by the DNR
490.
This Project will run through important habitat
for waterfowl and migratory birds, particularly from
491.
The DNR lacked sufficient information concerning
avian use and mortality risk to compare the route alternatives and identify
appropriate mitigation methods. For
example, waterfowl are more susceptible to collision with transmission lines
running between fields and water, but the DEIS did not identify where such
transitions occur along each route alternative.[493] Also, a transmission line will affect
different bird species in different ways.
The type of mitigation, including the type, placement and spacing of
bird diverters, may vary. The DNR
recommended that the Route Permit require the Applicants to develop an avian
protection plan, with specific monitoring and mitigation measures, for review
and approval by the DNR prior to construction.[494]
492.
The DNR recommended that the Route Permit
require habitat for wildlife along riparian corridors, and shading of
streams. Woody vegetation is not only
beneficial to wildlife, but it also inhibits erosion and deters damaging all-terrain
vehicle access to streams.[495] The DNR requested that the Applicants delineate
and mark all wetlands and rare plant communities prior to construction, and
where it is feasible, avoid construction activities within 50 feet of the
marked areas.[496]
493.
The DNR requested that the transmission line
span water bodies and wetlands wherever possible to avoid increased
sedimentation and soil erosion and the associated degradation of the
resource. Where this cannot be avoided,
the DNR requested that the Applicants be required to confer about structure
type and placement.[497]
494.
The Project will also come close to a large,
highly valued forested area within the Avon Hills, a critical habitat for many
species. The DNR encouraged the
Applicants to manage the rights-of-way to benefit wildlife and to avoid or
minimize establishment of invasive species and encourage native plant
establishment. It pointed out that care
should be given when using herbicides where sensitive bird or insect species
are known to occur.[498]
495.
As a condition for the Route Permit, the DNR
recommended that the Applicants complete an overall Construction Environmental
Control Plan (CECP) to ensure compliance with all required permits and project
plans, including an Environmental Mitigation Plan. Because of the large scope of the Project,
and the environmental sensitivity of the areas through which portions of the
Project will pass, the DNR also recommended that the Route Permit require
selection of a third-party monitor to assure compliance with the CECP and to
avoid or minimize damage to protected resources.[499]
496.
The Commission is required to determine the
adequacy of the FEIS. To be adequate,
the FEIS must, among other things, address the issues and alternatives
identified in the Scoping Decision “to a reasonable extent considering the
availability of information and the time limitations for considering the permit
application.”
497.
The evidence on the record demonstrates that the
FEIS is adequate because it addresses the issues and alternatives raised in the
Scoping Decision, as amended, provides responses to the substantive comments
received during the DEIS review process, and was prepared in compliance with
Minnesota Rules 7850.1000 to 7850.5600.
Based on these Findings of Fact, the Administrative Law Judge makes the following:
1. The Public Utilities Commission and the Administrative Law Judge have jurisdiction to consider the Applicants’ Application for a Route Permit.[500]
2. The Commission determined that the Application was substantially complete and accepted the Application on November 9, 2009. The Applicants and other parties agreed to extend the twelve-month timeframe for a decision on the permit.
3. OES conducted an appropriate environmental analysis of the Project for purposes of this route permit proceeding and the FEIS satisfies Minn. R. 7850.2500.
4.
Applicants gave notice of the proceeding as
required by Minn. Stat. §§ 216E.03, subds. 3a and 4, and
5. Minnesota Statutes § 216E.03, subd. 6, and Minn. R. 7850.2600 set out the notice requirements for the contested case hearing on the routing for a proposed high voltage transmission line. The content of the notices issued in this matter fully complied with Minn. R. 1405.0500 and the applicable statute and rules.
6.
OES gave notice as required by Minn. Stat. §
216E.03, subd. 6;
7. Public hearings were conducted in the Project Area. Applicants and OES gave proper notice of the public hearings and the public was given the opportunity to speak at the hearings and to submit written comments. All procedural requirements for the Route Permit were satisfied.
8.
For the North
Dakota to Alexandria segment of the Route, the Modified Preferred Route with Option 13 and 2B satisfies the route permit criteria set forth in Minn. Stat.
§ 216E.03, subd. 7 (a), 7(b), and
9.
Applicants should work with MnDOT to seek
approval to cross the Iverson Rest Area so that the alignment is placed closer
to I-94, and to cross the scenic easement on the south side of I-94 near
10.
For the Alexandria
to Sauk Centre segment of the Route, the Modified Preferred Route satisfies the route permit criteria set
forth in Minn. Stat. § 216E.03, subd. 7 (a), 7(b), and
11. In the event that the Modified Preferred Route cannot be aligned to meet MnDOT airport clearance requirements and avoid 12th Street in Sauk Centre, the Modified Preferred Route should be followed from Alexandria to Option 6 and then follow Route A to the point where it rejoins the Modified Preferred Route.
12.
For the Sauk
Centre to St. Cloud segment of the Route, based on an evaluation of the
routing criteria, construction of the
13.
For the
14. The Route Permit should include the associated facilities, expansion of the Quarry Substation and the Alexandria Switching Station.
15. The Route Permit should provide the Applicants with a route width of up to 1,000 feet. The record is unclear as to the areas where the Applicants continue to seek a wider route width or narrower route width and that information should be provided to the Commission.[501]
16. The Route Permit should allow the Applicants to install six conductors at highway crossings and interchange locations to facilitate the addition of a second circuit at a later date, upon approval of the Commission.
17. It is appropriate for the Route Permit to require Applicants to obtain all required local, state, and federal permits and licenses, to comply with the terms of those permits and licenses, and to comply with all applicable rules and regulations.
18. As a condition of the Route Permit, the Applicants should coordinate with MnDOT, local highway authorities, the State Patrol and other appropriate agencies to manage the safe flow of traffic throughout construction.
19. As a condition of the Route Permit, the Applicants should give notice to the travelling public and landowners when explosions will be used to splice conductors.
20. As a condition of the Route Permit the Applicants should seek approval from the Commission to place a portion of the transmission line underground if necessary to comply with restrictions imposed by the DNR or USFWS, consistent with Minn. R. 6135.1100 and 6135.1200.
21. As a condition of the Route Permit, the Applicants should develop a Construction Environmental Control Plan, which shall include an Agricultural Impact Mitigation Plan, Avian Protection Plan, Environmental Management Plan, Re-vegetation and Restoration Plans, Pollution Prevention Plan, Environmental Mitigation Plan and all policies, permits, plans, and protocols, to minimize and mitigate the potential impact associated with the construction and operation of the transmission line. The control plan shall require the Applicants to consult with the DNR concerning right-of-way management, use of bird diverters, and construction near water bodies, wetlands, native plant communities and breeding areas. The Applicants should also be required to fund an environmental monitor to oversee implementation and compliance with the Construction Environmental Control Plan.
22. Any Findings of Fact more properly designated Conclusions are adopted as such.
Based upon these Conclusions, and for the reasons explained in the accompanying Memorandum, the Administrative Law Judge makes the following:
1. That the Commission issue Applicants a Route Permit for the Modified Preferred Route from North Dakota to Sauk Centre, with Option 13 and 2B, and for Route G with Option 11 and the E-5 segment of Option 12 from Sauk Centre to St. Cloud, subject to conditions as more fully set forth in the conclusions.
2. The Route Permit shall include the Applicants’ requested modifications to the Quarry Substation and expansion of the Alexandria Switching Station.
Dated: April 25, 2011
s/Beverly Jones Heydinger
|
Beverly Jones Heydinger Administrative Law Judge |
Reported: Shaddix & Associates
Summary of Public Comments
Modified Preferred Route – General Comments
1.
Many
people supported the
2.
Many
people favored using the I-94 corridor for the entire route. Many people believed that following the
freeway would reduce costs and further the State’s nonproliferation policy.[506]
3.
The
Lien Township Board of Supervisors and Jerald and Celine Brudvik supported the
4.
Terry
Giese, who lives in
5.
A
number of people supported the
6.
Lynn
Haagenson supported the
7.
Many
people opposed the
8.
Robert
and Jeanine Henneman and nine other residents of
9.
Gary
and Sharon Behrens of
Route A
10.
Many
people supported Route A.[514] The City of Fergus Falls passed a resolution
in support of Route A, or in the alternative, for the
11.
Jerome
Cichosz and sixty-eight others from the River Oaks Housing Development near the
City of Fergus Falls signed a petition expressing concern with the location of
the
12.
In a
letter filed later in the proceeding, Mr. Cichosz restated his preference for
Route A around
13.
Dean
Sillerud of
14.
Matthew
Valan supported Route A because it goes through an area that is less populated
than the area crossed by the
15.
If
Route A is selected, Arthur Isackson requested that the Commission include a
condition that would allow realignment in Section 36 of Holmes City Township so
that the line would not run diagonally through his property.[520]
16.
Others
opposed Route A, including Verlyn Bruzak,[521]
Gerald and Celine Budvik,[522]
and Jeff and Rebecca Christiansen.[523]
Option 3 to the Modified Preferred Route
17.
Alan
Zeithamer opposed Option 3 because it would impact 30 homes, but the
18.
Michael,
Jeanne and Paul Wittrock opposed Option 3 because it would cross countless
farms, hundreds of homes and established neighborhoods.[525]
19.
Wayne
Summer, who lives near
Option 13 to Modified Preferred Route
20.
Richard
Thompson supported Option 13 to avoid the Lesmeister Flying Service
airstrip. Thompson estimated that the
owner of the Flying Service uses the airstrip to spray approximately
60,000-100,000 acres of farmland each year, and that he believes the airstrip
might be busier than the
21.
Craig
Hanson spoke in opposition to the
22.
Marv
Sawtell, Judith A. Johnson, Julie and Brad Kimball, Mark and Marcia Dufty,
Tonya Bergren, Daniel and Mary Beth Schindler and the Cedar Park Board of
Directors also stated that the
23.
Raymond
Rogers also opposed the
24.
Others,
including Mary Jane Olson, Brian Kotschevar, Mark Waisanen and Michael Smith,
favored running on the south side of I-94, through the Iverson Rest Area.[531]
25.
The
Swan Lake Association similarly opposed the routing along
26.
Ryan
Hanson, who lives in the
27.
The
City of
Option 4 –
28.
David
Walsh, who lives in
Modified Preferred Route
29.
Bob
Harren of
30.
The
City of
31.
Joan
Hemker opposed the
32.
The
Nature Conservancy opposed the
33.
Dave
Simpkins opposed the
34.
Leroy
Gondringer opposed the
35.
Robin
Heinen suggested that the costs of undergrounding along some sections of the
route have not been fully analyzed or compared to the costs of purchasing the
easements necessary to utilize any of the route alternatives or options.[542]
Route A
36.
Dale
and Janet Skroch opposed Route A because it would affect 43 Century Farms and
because 32% of Route A creates new transmission corridors.[543] Mike Kuklok similarly opposed Route A because
of the proliferation of new transmission right-of-way. He supported the use of the I-94 corridor.[544]
37.
Tim and
Kerrie Kerfeld opposed Route A because of its proximity to
38.
John
Huls opposed Routes A and B because the Routes would cross his property and he
is worried about the health effects and the ecological impact to
Route B
39.
Bruce
Braun opposed Route B because there are more homes within 500 feet of the
alignment than any other route alternative and because it would affect the most
acres of farm land. He supported the
Routes C and D
40.
Many
people opposed Routes C and D because they cross through the community of
Collegeville, which was established in the late 1800s, and because the area
endured the construction of I-94 in the 1960s and 1970s.[549]
41.
Forty-four
people from the Collegeville community submitted a petition in opposition to
Routes C and D. They stated that the
Collegeville area and the Lake Wobegon Trail are valued resources for those who
live and visit there. The community is
proud of the way it has been able to preserve its history despite the I-94
corridor and it worries that Route C or Route D would ruin the vibrancy of the
community.[550]
42.
John
Grutsch, Mayor of Avon, opposed Route D because of the number of residences and
commercial businesses in proximity to the route as it travels along I-94. There are over 90 homes located in the
Stratford Addition of Avon that would be affected by the selection of Route D. Because of the density of the population of
43.
Jeff
Manthe, President of the Stratford Association, a neighborhood association in
44.
Thomas
Fisher, Dean of the
45.
Peggy
Roske opposed Routes C and D because they would go through the Collegeville
wetlands and because the I-94 corridor through
46.
Terence
Check opposed Route D because it runs parallel to the Lake Wobegon Trail for
approximately three miles. The trail is
used extensively by bikers, joggers, rollerbladers, snowmobilers and
pedestrians, and it offers views of prairie grasslands, woodlands and
marshlands.[555]
47.
John
Wittrock opposed Route D because it would require the removal of a field stone
barn built in 1902 and a grove of 100-year-old trees.[556]
48.
Audubon
49.
The
Minnesota Forestry Association opposed Route D because it would transect the
forest land owned and managed by
50.
Dave
Blenker opposed Route D because it would it would cross the Albany Golf Course
and effectively destroy its operation.[559]
51.
Dennis
Sand, Mayor of Albany, opposed Route D because the route would affect a number
of residences, commercial businesses, an industrial park and the Albany Golf
Course. The City would not object if the
line were placed underground.[560]
52.
A
number of people supported Route D because they believed the line should follow
the I-94 corridor.[561] Kevin Heim supported Route D because it costs
less than the
53.
Thomas
and Margaret Klecker supported the use of the I-94 corridor with undergrounding
through the City of
Route E
54.
Jean
Didier opposed Route E because of its adverse effect on natural resources,
property values, and human settlement and because it violates the policy of
nonproliferation. She prefers Route D or
the
55.
Patricia
Gorecki similarly opposed Route E. She
stated that the area through which Route E would pass is just as pristine and
worthy of protection as the Avon Hills area.[565]
56.
Dennis
Sand, Mayor of Albany, opposed Route E because it could potentially impede
business at Wells Concrete, which recently completed construction of a $25
million manufacturing plant located on 80 acres of land within the City’s
industrial park. Wells Concrete uses
33-foot high cranes, which use would be prohibited if the line were routed near
the manufacturing plant. The City would
not object to Route E if the route were moved further south to accommodate the
plant.[566]
57.
Ann
Marie Stock and David Campagna opposed Route E because of the rare and fragile
ecosystem along the route. The wetlands
in this area of
58.
Todd
and Sarah Theisen oppose Route E because it would impact the Watab Creek,
wildlife, homeowners and farming operations.[568]
59.
Terra
O’Neil opposed Route E because of the environmental impact to the wildlife and
wetlands in that area. She said the area
is home to eagles, hawk, deer, fox, coyotes, sandhill cranes, and trumpeter
swans. The line would require clearing
of many trees, some 100-year-old oak trees.
She supports the selection of Route A or Route F.[569]
60.
Myron
and Lenore Felix opposed Route E, which they believe to be “the path of least
resistance” because many of the landowners cannot afford legal
representation. They support the
selection of Route D.[570]
61.
Tom
Vouk, Ron Eikmeier and Ken Eikmeier opposed Route E because of the number of
trees that would need to be removed.[571] Eikmeier supported the selection of the
62.
Neil
Franz opposed Route E because of its proximity to
63.
Route F
64.
Lynn
Carlson opposed Route F because it would prohibit the operation of his aviation
business, which operates within a half mile of the Route.[575]
Routes G and H
65.
Alice
Doubek opposed Routes G and H because they are too close to dairy farms and the
electro-magnetic fields will be detrimental to the cows’ health and the
farmers’ livelihood.[576]
66.
Stephen
Platenberg, former chair of the Avon Township Planning Board, supported Route G
with Option 11 because it has minimum contact with river, lake and natural
wetland buffer zones; follows existing county roads, which have larger setback
requirements than township roads; minimizes the fragmentation of the
countryside; does not impact the Stearns County Natural Resource Overlay
District; avoids SNAs in St. Wendel, Avon and Farming Townships; and because it
avoids the future growth areas of the County’s major cities of St. Stephen,
Sartell, St. Joseph and St. Cloud. He
pointed out that homes along Route G typically sit farther back from the road
than along other routes.[577]
Option 8 to Modified Preferred Route
67.
Glen
Klaphake supported Option 8 even though it will cross his property. The route is shorter than the other
alternatives and it would allow him to expand his feedlot.[578]
68.
Nicholas
and Erwin Klaphake supported Option 8 because it is shorter than the
alternatives and because it would cross meadowlands.[579] Paul Primus also supported Option 8 because
it is shorter.[580]
Option 11 to Route E or Route G
69.
Twenty-four
homeowners opposed Option 11 because the line would run along County Road 2 in
front of their homes. They are concerned
with EMF, interruption of communication services, aesthetics, and decreasing
property values. They worry the lines
will destroy their neighborhood.[581]
Electro-Magnetic Fields
70.
Many
people expressed concern regarding the health effects of the electro-magnetic
fields.[582] Matt Valan wondered whether the cumulative
effects of exposure were properly taken into account, especially for children
who might be exposed for lengthy periods of time.[583]
71.
Ken
Schindele expressed concern that the data in the record does not accurately
account for the EMF levels if a second set of lines is added in the
future. He also expressed concern
regarding the noise the lines generate and whether the noise would affect the
livability of the area.[584]
72.
Robin
Heinen questioned the accuracy of the EMF measurements. She stated that it seemed that the EMF charts
she has seen are inconsistent, and a small difference in the milliGauss (mG)
number can yield a large difference in health and environmental effects.[585]
73.
Todd
Theisen stated that there are many inconclusive and conflicting studies, and
that the results regarding EMF health effects appear to be swayed by industry studies
to support or rationalize their quest to sell more power.[586]
74.
Alice
Doubek and many others expressed concern about the effect of EMF on farm
animals. Ms. Doubek had to leave her
farm and give up her farming livelihood because the ill-effects of the EMF on
her cows. Many others also gave
anecdotal evidence of the harmful effects of EMF on their livestock and
production levels.[587]
Interference with Electronic Equipment
75.
Renee
Nicklay owns a business near Barnesville that is within or near the
76.
Doug
Christensen of
Agriculture
77.
Many
people expressed concern that the transmission line will interfere with their
agricultural operations. In addition to
the concern about EMF, they were concerned that the proposed alignments will
run diagonally across some farmland, which will make fieldwork more difficult
and limit the installation or use of irrigation systems.[591]
78.
Robin
Heinen and John Hellerman expressed concern that the construction of a
transmission line would affect farms that are certified organic or in the
process of becoming certified organic.[592]
Dissatisfaction with the Process
79.
Dave
Ebaugh stated during the public hearings that the Applicants did not use
accurate maps in their analyses to determine the preferred route. He stated that the 1999 DNR map used by the
Applicants does not generate reliable data.
The Applicants used the map beyond the limitations of its design to
support invalid conclusions. He stated
that the Applicants used information from 1980 to support its conclusions
regarding uncommon species found in the Project Area. He questioned the objectivity of the DEIS and
the makeup, diligence and accuracy of the Advisory Task Force. He concluded that the errors and omissions
will result in an FEIS that is not reflective of the scoping activities. He recommended further analysis of Route G
and Option 11.[593]
80.
Joe
Farry questioned the comprehensiveness of the DEIS. He stated that there was a lot of information
about the local regions that was not included in the DEIS. According to Farry, six of the eighteen homes
in Collegeville were not identified in the DEIS.[594]
81.
Some
people from the Collegeville community expressed concern that they were not
invited to participate in the Advisory Task Force.[595]
82.
David
Heinen questioned the accuracy of the DEIS and stated that some homes were not
identified or included in the DEIS.[596] Peggy Roske also stated that the DEIS did not
include two of her neighbors’ homes, even though Route C went right over them.[597] Ray Vouk also stated that his home was not
included in the DEIS.[598] Derek Iverson of
83.
Faith
Fischer expressed frustration at the number of route options under
consideration. She stated there were so
many it was difficult to know which one to comment on.[600]
Maps of Route Alternatives
Ex. 228, DEIS Appx. H at H-3

Ex. 18 at 11 of 17 (Scoping Decision)

Ex. 18 at 15 of 17 (Scoping Decision)

[1] Ex. 1a at 1-1 (Application).
[2] Order Granting Certificates of Need with Conditions, In the Matter of the Application of Great River Energy, Northern States Power Co. (d/b/a/ Xcel Energy) and others for Certificates of Need for the CapX 345-kV Transmission Project, Docket No. ET-2,E-002. et al; CN-06-1115 (May 22, 2009, as modified Aug. 9, 2009).
[3] Ex. 1a (Application) at 6-6.
[4] Ex. 1a (Application) at 1-1.
[5] Ex. 41 (MnDOT Comments to DEIS); Tr. Vol. 4 at 77-80 (Seykora).
[6]
Ex. 43 (Letters to David Birkholz from Jamie Schrenzel, DNR Environmental
Review Unit, Oct. 18, 2010 and Feb. 11, 2011). The DNR was unable to fully
evaluate the
[7] Ex. 51 (Letter to ALJ from Jamie Schrenzel, DNR Environmental Review Unit, Dec. 14, 2010).
[8]
Notice and Order for Hearing Under
[9] Ex. 27.
[10] Ex. 25a.
[11] Ex. 26.
[12] Tr. Vol. 1 at 142-145.
[13] Exs. 49 and 50.
[14]
ALJ Steve Mihalchick presided at the public hearings in
[15] Exs. 55, 56, 57 and 58.
[16] eDocket Doc. No. 20113-60562-01 (eFiled Mar. 23, 2011).
[17] eDocket Doc. No. 20114-60984-01 (eFiled Apr. 4, 2011).
[18]
[19]
[20]
[21]
[22]
[23] Ex. 52.
[24] Minn. R. 7850.2500, subp. 1; Minn. Stat. § 216E.03, subd. 5.
[25]
[26]
[27]
[28] Exs. 14, 15a.
[29] Ex. 16A; Ex. 18 at 3 (EIS Scoping Decision).
[30] Ex. 17 (ATF Report).
[31] Ex. 18 at 3 (EIS Scoping Decision).
[32] Ex. 18 (EIS Scoping Decision).
[33] Ex. 21 (Amended Scoping Decision).
[34] Exs. 22a, 22b, 23a, 23b, 24a, and 24b.
[35] Ex. 23a, 24a, and 24b.
[36]
[37]
FEIS, eDocket Doc. Nos. 20111-58289-01 through 20111-5829-07 and 20111-58294-01
through 20111-58294-08 (filed Jan. 7, 2011).
[38]
Ex. 1a (Application) at ES-2; Ex. 2 at 6 (Lahr Direct); Order, In the Matter of the Application of a Route
Permit for the
[39] Ex. 2 at 6 (Lahr Direct).
[40] Ex. 1a (Application) at ES-2.
[41] Ex. 1a (Application) at ES-2.
[42] Ex. 1a (Application) at Section 4.0.
[43] Ex. 1a (Application) at 4-13 – 14 and Section 6.
[44] Ex. 1a (Application) at ES-7, 5-7 – 5-12.
[45] Ex. 18 at 13, 16 (EIS Scoping Decision).
[46]
Order, In the Matter of the Application
of a Route Permit for the
[47] Ex. 1a (Application) at 2-14, 3-5; Ex. 2 at 10, 11 (Lahr Direct).
[48] Ex. 3 at 10 (Chezik Direct).
[49]
[50] This subfactor is inapplicable because Applicant has not applied for a route permit for a large electric generating plant.
[51]
[52] This criterion is inapplicable because the Applicant has not applied for a permit for a large electric generating plant.
[53]
[54]
[55]
[56]
[57]
[58] Ex. 1a (Application) at ES-2; FEIS at 3-1; see Order Granting Certificates of Need With Conditions, In the Matter of the Application of Great River Energy, Northern States Power Co. (d/b/a/ Xcel Energy) and others for Certificates of Need for the CapX 345-kV Transmission Project, Docket No. ET-2,E-002. et al; CN-06-1115 (May 22, 2009, as modified Aug. 9, 2009).
[59] Ex. 1a (Application) at 3-1.
[60] Ex. 3 at 6 (Chezik Direct).
[61] Ex. 1a (Application) at ES-2; FEIS at 3-1.
[62] Ex. 3 at 6-7 (Chezik Direct); Ex. 1a (Application) at 3-4; Vol. 1 at 28-47 (Chezik).
[63]
Ex. 3 at 6-7 (Chezik Direct); Order, In
the Matter of the Application of a Route Permit for the
[64] Tr. Vol. 4 at 94-95 (Seykora).
[65] Ex. 3 at 7 (Chezik).
[66]
[67] Order Granting Certificates of Need with Conditions, In the Matter of the Application of Great River Energy, Northern States Power Co. (d/b/a/ Xcel Energy) and others for Certificates of Need for the CapX 345-kV Transmission Project, Docket No. ET-2,E-002. et al; CN-06-1115 (May 22, 2009, as modified Aug. 9, 2009).
[68] Ex. 1a (Application) at 3-25.
[69] Ex. 1a (Application) at 3-26.
[70] Ex. 1a (Application) at 3-3.
[71]
[72] Ex. 1a (Application) at ES-2-3 and 2-6.
[73] Ex. 22A, DEIS at 1-31, Table 1.5-1.
[74] Ex. 22A, DEIS at 1-34, Table 1.5-2.
[75] Ex. 22A, DEIS at 4-6.
[76] Ex. 1a (Application) at 3-3 - 3-4; Ex. 22A, DEIS at 7-62.
[77] Ex. 1a (Application) at 3-3 - 3-4.
[78] Ex. 1a (Application) at 3-5.
[79] Ex. 1a (Application) at 3-7 - 3-15.
[80] Ex. 3 at 8 (Chezik Direct).
[81] Ex. 41 at 2; Tr. Vol. 4 at 69-71 (Seykora).
[82] Ex. 41 at 3; Tr. Vol. 4 at 68-69, 123-125 (Seykora).
[83] Ex. 41 at 3-4.
[84] Tr. Vol. 4 at 48-49 (Seykora).
[85] Ex. 41 at 3.
[86] Ex. 22A, DEIS at 7-64 - 7-65.
[87] FEIS at 3-42.
[88] See
[89] Ex. 22A, DEIS at 4-5 – 4-7
[90] Tr. Vol. 1 at 96-97, 104-105, 107 (Chezik).
[91] Ex. 22A, DEIS at 4-3 – 4-4.
[92] Ex. 22A, DEIS at 4-4.
[93] Ex. 22A, DEIS at 4-5 – 4-6.
[94] Ex. 22A, DEIS at 7-2.
[95] Ex. 44.
[96] Ex. 1a (Application) at 2-15; Ex. 3 at 8 (Chezik Direct).
[97]
[98] Ex. 1a (Application) at 6-3.
[99] Ex. 1a (Application) at 7-2.
[100] Ex. 1a (Application) at 7-2 – 7-3.
[101] Ex. 1a (Application) at 3-16; Ex. 2 at Sched. 6 (Lahr Direct).
[102] Ex. 1a (Application) at 3-16; Ex. 22A, DEIS, at 5-19; Ex. 35 at 6-8 (Valberg Surrebuttal); Tr. Vol 3 at 20 (Valberg).
[103]
The ICNIRP is an independent body of scientists based in
[104] Ex. 35 at 8 (Valberg Surrebuttal); Ex. 22A, DEIS, at 5-19.
[105] Ex. 2 at Sched. 6 at 2 (Lahr Direct); FEIS at 3-12 – 3-13, Table 3.4-3.
[106] Ex. 29 at 7-8 and Sched. 2 (Kline Surrebuttal); FEIS at 3-13.
[107] Ex. 35 at 4-5 (Valberg Surrebuttal).
[108] Tr. Vol. 3 at 12-13 (Valberg).
[109] Tr. Vol. 3 at 13-15, 17-23 (Valberg).
[110] Tr. Vol. 3 at 23 (Valberg).
[111] Tr. Vol. 3 at 34-35 (Valberg).
[112]
Ex. 49, Testimony of David O. Carpenter, In
the Matter of the Route Application by
[113] Ex. 49 at 17.
[114] Ex. 50 at 45, In the Matter of the Route Application by Great River Energy and Xcel Energy for a 345 kV Transmission Line from Brookings County, South Dakota to Hampton, Minnesota, PUC Docket No. ET2/TL-08-1474, Tr. Vol. 3.
[115] Ex. 50 at 75.
[116] Ex. 50 at 129: Question: Dr. Carpenter, …you’re not advocating the route for this line assure that there is no residents (sic) within proximity to the line that would experience four milligauss of magnetic fields, are you? Answer: No, I’m not advocating that. But I’m advocating strongly that the line be routed to reduce the number of those homes as much as possible. The ideal would be to impact no home at values more than four milligauss. That may not be unrealistic.
[117] Ex. 1A at 7-16 – 7-18 (Application).
[118] Ex. 22A, DEIS at 7-75, citing study conducted by Olsen and Heins, 1998.
[119] Ex. 22A, DEIS at 5-14 – 5-15.
[120] Ex. 22A, DEIS at 5-14.
[121] Ex. 3 at 8 (Chezik Direct).
[122] Ex. 22A, DEIS at 5-14 – 5-15, 6-5 – 6-6, 7-7 – 7-8.
[123] See Ex. 22A, DEIS at 5-7, Table 5.1-6, Noise Levels Associated with Common Sources, 30 dBA for secluded woods, compared with 40 dBA in a bedroom and 50 dBA in a library.
[124] Ex. 22A, DEIS at 5-14.
[125]
FEIS at 3-25; Order, In the Matter of the
Application of a Route Permit for the
[126] FEIS at 3-25.
[127] Ex. 22A, DEIS at 7-19.
[128] Ex. 22A, DEIS at 5-15, 6-13, 7-17.
[129] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[130] Ex. 2 at 11-12 (Lahr Direct).
[131] Tr. Vol. 6 at 122-123 (Lahr); Ex. 4b.
[132]
Ex. 2 at Sched. 4, depicting Option 13; see
also Ex. 4b, showing the initial
[133] Ex. 4b; Ex. 2 at 17 (Lahr Direct); Ex. 21.
[134] See Ex. 2 at Sched. 2 (Lahr Direct) and Ex. 4p.
[135] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[136] Some of the options were referred to as Alternative Route Segments, with different numbers, in the Application. The references here are to the designations assigned in the DEIS.
[137] Ex. 2 at 17 (Lahr Direct); FEIS, Appx. C, Sheet 18. In the Application, Option 1 is referred to as Applicants Preferred Alternative Route Segment 5.
[138]
Ex. 1a (Application) at ES-11 (delineated as Applicants Preferred Route Segment
Alternative 5); Tr. Vol. 6 at 116 (Lahr).
[139] Ex. 1a (Application) at ES-10 (delineated as Applicants Preferred Route Segment Alternative 4).
[140] Ex. 2 at 17 (Lahr Direct); FEIS, Appx. C, Sheets 19, 20 and 21.
[141] Ex. 22A, DEIS at 1-16.
[142] Ex. 22A, DEIS at 1-27.
[143] This description is not set forth in the DEIS, but is the best assessment of the option that can be made to reconcile the maps and data in the DEIS.
[144] See Ex. 4m, Applicants’ Tile Map, refers to both the 2B segment and the eastern part of 2A as 2B.
[145] Public Ex. 1, Letter from Robert and Jeanine Henneman with Attachments; FEIS, Appx. C, Sheets 19-21.
[146] Tr. Vol. 6 at 118-119 (Lahr).
[147] FEIS Appx. C at Sheet 24; Ex. 1a at ES-9 (delineated in the Application as Preferred Route Segment Alternative 3).
[148] Tr. Vol. 6 at 119-120 (Lahr); Ex. 2 at 17 (Lahr Direct).
[149]
[150] Ex. 22A, DEIS at 5-6.
[151] Ex. 22A, DEIS at 5-11 and 5-12; Ex. 30 at
Sched. 8 (Lahr Rebuttal); Letter to ALJ from Karen Finstad Hammel, Apr. 4,
2011.
[152] Ex. 22A, DEIS at 5-6, Table 5.1-5.
[153] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[154] FEIS at 3-6, Table 3.3-1.
[155] Ex. 22A, DEIS at 5-12, Table 5.1-11.
[156] Ex. 22A, DEIS at 5-6, Table 5.1-5.
[157] FEIS at 3-10, Table 3.4-1.
[158] See
FEIS at 3-10; Ex. 22A, DEIS at
5-9.
[159] FEIS at 3-11, Table 3.4-2.
[160] FEIS at 3-6, Table 3.3-1.
[161] FEIS at 3-9, Table 3.3-2.
[162] Ex. 22A, DEIS at 5-13; Ex. 30 at Sched. 8 at 2 (Lahr Rebuttal).
[163] Ex. 22A, DEIS at 5-15.
[164] Ex. 22A, DEIS at 5-35 – 5-37.
[165] Ex. 22A, DEIS at 5-37.
[166] Ex. 22A, DEIS at 5-35 and 5-38.
[167] Ex. 30 at Sched. 8 (Lahr Rebuttal); FEIS at
3-18, Table 3.4-6.
[168] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[169] Ex. 22A, DEIS at 5-27.
[170] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[171] FEIS at 3-11, Table 3.4-2.
[172] Ex. 22A, DEIS at 5-40 – 5-41, Tables 5.4-1 and 5.4-2. Based on the information provided, it is
difficult to evaluate Option 2A and 2B, except that to the extent that they
deviate from I-94, they will affect less traffic. DEIS at 5-43.
[173] Ex. 41 at 3.
[174]
Ex. 22A, DEIS at 5-43, Table 5.4-3. It
is noted that the DEIS text on this page incorrectly describes the options. Option 2A follows all four roads listed.
Option 2B follows I-94,
[175] FEIS, Appx. C, Sheets 15, 16, 17.
[176] Ex. 4j; FEIS, Appx. C, Sheet 14; Tr. Vol. 6 at 127 (Lahr).
[177] Tr. Vol. 4 at 55-56; 104-05 (Seykora).
[178] Tr. Vol. 6 at 128 (Lahr).
[179] Ex. 30 at 10 (Lahr Rebuttal); Ex. 41 (MnDOT
DEIS Comment Letter); Vol. 5 at 12 (Seykora).
[180] Ex. 2 at 12-13 (Lahr Direct); FEIS at 3-7 -
3-8.
[181] Ex. 2 at 13-14 and Sched. 4 (Lahr Direct).
[182] Ex. 2 at 14 and Sched. 4 (Lahr Direct);
FEIS at 3-8.
[183] Ex. 22A, DEIS at 5-51, Table 5.4-5.
[184]
Minn. Stat. § 216E.03, subd. 7 (b)(5);
[185] Ex. 22A, DEIS at 5-59; Ex. 30, Sched. 8 at 2 (Lahr Rebuttal).
[186] Ex. 30 at Sched. 8 at 2 (Lahr Rebuttal).
[187]
Ex. 22A, DEIS at 5-60.
[188] Ex. 22A, DEIS at 5-61, citing 7 C.F.R. § 657.5.
[189] Ex. 22A, DEIS at 5-61.
[190] Ex. 22A, DEIS at 5-69, Table 5.7-10.
[191] Ex. 22A, DEIS at 5-66; Ex. 30 at Sched. 8 at 2 (Lahr Rebuttal).
[192] Ex. 2 at 27-28 (Lahr Direct); Ex. 1c, Appx. I to the Application (Agricultural Impact Mitigation Plan).
[193] Ex. 1c, Appx. I to the Application (Agricultural Impact Mitigation Plan, Appx. B)
[194] FEIS at 2-42.
[195] Ex. 22A, DEIS at 5-60, Table 5.7-3.
[196] Ex. 22A, DEIS at 5-61-5-62.
[197] Ex. 1a (Application) at 7-31.
[198] Ex. 22A, DEIS at 5.7-11. Note that these numbers do not match those in Ex. 30 at Sched. 8 (Lahr Rebuttal).
[199] Ex. 30 at Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 5-62.
[200] Ex. 22A, DEIS at 5-71.
[201]
Minn. Stat. § 216E.03, subd. 7 (b)(1);
[202] Ex. 22A, DEIS at 5-54 – 5-55.
[203] Ex. 30 at Sched. 8 at 2 (Lahr Rebuttal): see also Ex. 22A, DEIS at 5-54 – 5-57.
[204] Ex. 30 at Sched. 8 at 2 (Lahr Rebuttal); see also Ex. 22A, DEIS at 5-55 – 5-56.
[205]
Minn. Stat. § 216E.03, subd. 7 (b)(1) and (2);
[206] Ex. 22A, DEIS at 5-79.
[207] Ex. 22A, DEIS at 5-73, 5-76.
[208] Ex. 22A, DEIS at 5-76.
[209] Ex. 30 at Sched. 8 at 1 (Lahr Rebuttal).
[210] Ex. 22A, DEIS at 5-77.
[211]
Here, Option 2A and Option 2B can only be compared to each other and not to the
comparable section of the
[212] Ex. 22A, DEIS at 5-81.
[213] Ex. 30 at Sched. 8 at 1 (Lahr
Rebuttal).
[214] Ex. 22A, DEIS at 5-82, Table 5.8-9.
[215] Ex. 22A, DEIS at 5-80, Table 5.8-7.
[216]
[217]
[218] Ex. 3 at Sched. 1 (Chezik Direct).
[219] Ex. 30 at Sched. 8 at 1 (Lahr Rebuttal).
[220] Ex. 22A, DEIS at 5-95.
[221] Ex. 22A, DEIS at 5-33.
[222] Ex. 30 at Sched. 8 at 3 (Lahr Rebuttal).
[223] Ex. 30 at Sched. 8 (Lahr Rebuttal); DEIS at
5-93.
[224] Ex. 22A, DEIS at 5-86.
[225] Ex. 22A, DEIS at 7-113 – 7-114.
[226] Ex. 30 at Sched. 8 at 3 (Lahr Rebuttal);
Ex. 22A, DEIS at 5-94.
[227] Letter, Jan. 5, 2011, Jamie Schrenzel.
[228]
[229] Ex. 1a (Application) at 7-63; Ex. 22A, DEIS
at 5-95 and Tables 5.9-4, 5.9-5 and 5.9-6; FEIS at 3-20, Table 3.4-7.
[230] Ex. 1a (Application) at 7-63; Ex. 22A, DEIS
at 5-95.
[231] FEIS at 3-20, Table 3.4-7.
[232]
See Exs. 4k and 4m; and FEIS, Appx. C
at Sheets 16 and 17.
[233] Ex. 22A, DEIS at 5-92 – 5-93.
[234] Ex. 22A, DEIS at 5-93.
[235] Ex. 22A, DEIS at 5-94.
[236]
[237] Ex. 30 at Sched. 8 (Lahr Rebuttal); FEIS at
3-3, Table 3.2-2.
[238] Ex. 30 at Sched. 11 (Lahr Rebuttal); FEIS
at 3-3, Table 3.2-2.
[239] FEIS at 3-3, Table 3.2-2.
[240]
Minn. Stat. § 216E.03, subd. 7 (b) (8);
[241]
266 N.W.2d 858 (
[242]
[243] PEER at 867-868.
[244] PEER at 868-869.
[245] Ex. 30 at Sched. 8 (Lahr Rebuttal); Ex.
22A, DEIS at 5-41, Table 5.4-1 and 5-42, Table 5.4-2; see also FEIS at 3-3, Table 3.2-2.
[246] Applicants’ Post-Hearing Brief at 22.
[247] FEIS 3-3, Table 3.2-2, applied to estimated length of 9 miles for Option 2A and estimated length of 8.6 miles for Option 2B.
[248]
[249] Ex. 1a (Application) at 6-6; Tr. Vol. 1 at 132-133 (Chezik).
[250] FEIS at 3-2, Table 3.2-1.
[251] Tr. Vol. 1 at 123-125 (Chezik); Exs. 4b, 4d, 4e and 4f (Modified Preferred Route) and Exs. 4c, 4g and 4h (Route A).
[252]
Minn. Stat. § 216E.03, subd. 7 (b) (5);
[253] Ex. 1A at 6-6 (Application); Ex. 30 at
Sched. 8 (Lahr Rebuttal). The number of
acres affected is proportional to the length of the route.
[254]
[255] Ex. 22A, DEIS at 5-41, Table 5.4-1 and 5-42, Table 5.4-2.
[256] Tr. Vol 6 at 123-125 (Lahr); Ex. 4i.
[257] Ex. 30 at 15 and Sched. 14 (map depicting the location of alignment and River Oaks)(Lahr Rebuttal).
[258] Tr. Vol. 6 at 125-126 (Lahr); Ex. 4j; Cichosz, Public Hearing, Fergus Falls, Nov. 16, 2010, 6:30 p.m. at pp. 31-32; Public Ex. 3.
[259] See 23 C.F.R. § 645.209 (h); Tr. Vol. 4 at 101-102 (Seykora).
[260] Tr. Vol. 6 at 125-126 (Lahr).
[261]
Ex. 4j.
[262] Exs. 4j and 4k; Tr. Vol. 6 at 127-129 (Lahr).
[263]
Tr. Vol. 4 at 55-56 (Seykora).
[264] Vol. 6 at 128 (Lahr).
[265] Ex. 4n.
[266] Ex. 4n; Comment, Hegg, Nov. 18, 2010, evening, at 28-31; Public Exs. 7-8; Comment Lahr, Nov. 18, 2010, evening, at 32-33; Vol. 6 at 132 (Lahr).
[267] Ex. 22A, DEIS at 1-12; Ex. 30, Sched. 8 (Lahr Rebuttal).
[268] Ex. 4p; FEIS, Appx. C at Sheet 44; Ex. 2 at 11, 15 (Lahr Direct).
[269] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[270] FEIS, Appx. C at Sheet 53.
[271] Ex. 22A, DEIS at 1-27; 6-34; 6-52, Table 6.7-3, 6-57; Ex. 2 at 18 (Lahr Direct).
[272] Ex. 22A, DEIS at 1-27; FEIS Appx. C at Sheet 48; Ex. 2 at 18 (Lahr Direct).
[273] Ex. 22A, DEIS at 1-27; FEIS Appx. C at Sheet 49. Ex. 1a (Application ) at ES-8 (delineated as Preferred Route Segment Alternative 2); Tr. Vol. 6 at 120-121 (Lahr).
[274] Ex. 30 at Sched. 8 at 5 (Lahr Rebuttal);
[275] FEIS, Appx. C at Sheets 51, 57 and 58.
[276] Ex. 2 at 18 (Lahr Direct); Ex. 30, Sched. 8 at 5, 6 (Lahr Rebuttal); Ex. 22A, DEIS at 1-27; 6-10; 6-57; 6-61; FEIS Appx. C at Sheet 56.
[277] Ex. 22A, DEIS at 6-1.
[278] Ex. 22A, DEIS at 6-5, Table 6.1-5. Since
Option 7 is an alignment option, it is included within Route A.
[279] Ex. 22A, DEIS at 6-10; Tables 6.1-10 and 6.1-11; Ex. 30 at Sched. 8 (Lahr Rebuttal).
[280] Ex. 22A, DEIS at 6-10; Table 6.1-11; FEIS, Appx. C at Sheet 50. Ex. 30 at Sched. 8 (Lahr Rebuttal) reflects fewer homes for Option 6 because it does not include the homes along Route A that would be followed if this option were selected. See FEIS, Appx. C at Sheets 50, 51 and 57.
[281] Ex. 22A, DEIS at 6-9.
[282] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[283] FEIS at 3-23 - 3-25, Table 3.5-2.
[284] FEIS at 3-25, Table 3.5-2.
[285] FEIS at 3-25, Table 3.5-2.
[286] FEIS at 3-25, Table 3.5-2.
[287] Ex. 22A, DEIS at 6-12.
[288] Ex. 22A, DEIS at 6-34, Table 6.3-4.
[289] Ex. 22A, DEIS at 6-25.
[290] Ex. 22A, DEIS at 6-26; 6-29 – 6-30. It is
not clear why Table 6.3-1 (Recreational Land Use Impact Evaluation for Routes)
shows zero acres for Option 6 while Table 6.3-2 (Recreational Land Use Within
Each Route and Route Option Alternative ROW) shows one acre for Option 6.
[291] Ex. 22A, DEIS at 6-29 - 6-30.
[292] Tr. Vol. 4 at 83-84, 120-121 (Seykora); Minn. Stat. § 222.63; Minn. R. parts 8830.5810-8830.5860.
[293] Tr. Vol. 6 at 135 (Lahr).
[294] Ex. 22A, DEIS at 6-26.
[295] Ex. 22A, DEIS at 6-27.
[296] Ex. 22A, DEIS at 6-28.
[297] Ex. 22A, DEIS at 6-29 – 6-30.
[298] Ex. 22A, DEIS at 6-36 – 6-37, Table 6.4-1 and Table 6.4-2, 6-43.
[299] Ex. 41 at 3.
[300] Ex. 22A, DEIS at 6-39.
[301] FEIS, Appx. C at Sheets 50 and 51.
[302] Public Ex. 10; Ex. 57.
[303] Ex. 55 (Letter to ALJ from MnDOT, Jan. 5, 2011).
[304] Ex. 55 (Letter to ALJ from MnDOT, Jan. 5, 2011).
[305] Ex. 55 (Letter to ALJ from MnDOT, Jan. 5, 2011), Map showing Airspace Zones, attached.
[306] Public Ex. 10; Ex. 57.
[307] Ex. 55 at 3; Exs. 56 and 57.
[308] Exs. 55, 56 and 57.
[309] Ex. 58.
[310] Ex. 58.
[311] Ex. 55 at 6.
[312] Ex. 44 at 2 (Letter from Applicants to ALJ, dated Dec. 13, 2010); Ex. 3 at Sched. 1 (Chezik Direct).
[313] Ex. 44 at 2-3; Tr. Vol. 1 at 100-101 (Chezik).
[314] Ex. 22A, DEIS at 6-51.
[315] Ex. 22A, DEIS at 6-52, Table 6.7-3.
[316] Ex. 22A, DEIS at 6-53.
[317] Ex. 30 at Sched. 8 at 5 (Lahr Rebuttal).
[318] Ex. 22A, DEIS at 6-55.
[319] Ex. 30 at Sched. 8 at 5 (Lahr Rebuttal).
[320] Ex. 22A, DEIS at 6-59.
[321] Ex. 22A, DEIS at 6-60.
[322] Ex. 22A, DEIS at 6-53.
[323] Ex. 22A, DEIS at 6-54, Table 6.7-5.
[324] Ex. 22A, DEIS at 6-54, Table 6.7-6, 6-63.
[325] Ex. 22A, DEIS at 6-54.
[326] Ex. 22A, DEIS at 6-48. The DEIS did not
provide additional detail.
[327] Ex. 30 at Sched. 8 at 5 (Lahr Rebuttal).
[328] Ex. 22A, DEIS at 6-48.
[329] Ex. 22A, DEIS at 6-66, Table 6.8-5.
[330] Ex. 30 at Sched. 8 at 4 (Lahr Rebuttal).
[331] Ex. 22A, DEIS at 6-66, Table 6.8-5.
[332] Ex. 30 at Sched. 8 at 4 (Lahr Rebuttal).
[333] Ex. 22A, DEIS at 6-70, Table 6.8-9.
[334] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[335] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[336] Ex. 30 at Sched. 8 (Lahr Rebuttal).
[337] Ex. 22A, DEIS at 6-68.
[338] Ex. 30 at Sched. 8 (Lahr Rebuttal); Ex.
22A, DEIS at 6-80 (but no MCBS sites
included in Table 6.9-3).
[339] Ex. 22A, DEIS at 6-82, Table 6.9-4.
[340] Ex. 22A, DEIS at 6-80.
[341] Ex. 30 at 11 (Lahr Rebuttal); FEIS Appx. C
at Sheets 50 and 51.
[342] Ex. 30 at Sched. 8 at 6 (Lahr Rebuttal).
[343] Ex. 22A, DEIS at 6-82.
[344] Ex. 43, Letter of Oct. 18, 2010, at 3: Ex. 6 at 12 (Kroll Direct).
[345] Letter, Jan. 5, 2011, Jamie Schrenzel; FEIS, Appx. C at Sheets 49, 50 and 51.
[346] Letter, Jan. 5, 2011, Jamie Schrenzel;
FEIS, Appx C at Sheet 50 and 51.
[347] Ex. 22A, DEIS at 6-80 – 6-82, Tables 6.9-3 and 6.9-4.
[348]http://www.google.com/imgres?imgurl=http://www.ejphoto.com/images_of_the_month/CA_MarbledGodwit04.jpg&imgrefurl=http://www.ejphoto.com/photos_of_the_month_page.htm&h=506&w=750&sz=195&tbnid=Dn2ViidgpiAbtM:&tbnh=95&tbnw=141&prev=/search%3Fq%3DMarbled%2BGodwit%26tbm%3Disch%26tbo%3Du&zoom=1&q=Marbled+Godwit&hl=en&usg=__rTH_lLuYpGPqoLvM9BsI00e3AIE=&sa=X&ei=UieeTcfyGZCP0QGhuJjBBA&ved=0CD0Q9QEwAg (A photo of the Marbled Godwit).
[349] FEIS at 3-4, Table 3.2-3.
[350] FEIS at 3-4, Table 3.2-3.
[351] Ex. 1a (Application) at 6-6.
[352] FEIS at 3-2, Table 3.2-1 (costs for the options based on $1.7 million per mile).
[353] Tr. Vol. 5 at 63 (Schrenzel).
[354] See DEIS Scoping Document, with attached maps, reprinted in DEIS Appx. A at 15 of 17.
[355]
Ex. 5 at Sched. 5 (
[356] See map attached to letter from Nature Conservancy to ALJ, December 1, 2010, eDocket Doc. No. 201012-57785-01 (eFiled Dec. 22, 2010).
[357]
Ex. 11 at 4 (
[358] Ex. 11 at 4, Scheds. 3, 4 and 5 (Avon Township Chapman Direct); eDocket Doc. No. 201012-57503-01 (efiled Dec. 15, 2010) ( Letter from Peter Dwyer, Avon Hills Initiative Chair, Member of ATF).
[359] Ex. 22A, DEIS at 1-16.
[360] Ex. 30, Sched. 8 (Lahr Rebuttal).
[361] FEIS, Appx. C, Sheets 66, 80, and 92. The reason for this broad route width is not explained.
[362] Ex. 22A, DEIS at 1-27; FEIS, Appx. C, Sheet 68.
[363] Ex. 22A, DEIS at 1-27; FEIS, Appx. C, Sheets 68, 69.
[364] Ex. 22A, DEIS at 1-16,17.
[365] Ex. 30, Sched. 8 (Lahr Rebuttal).
[366] Ex. 22A, DEIS at 1-28; FEIS, Appx. C, Sheet 61; Ex. 2 at 24 (Lahr Direct).
[367] Ex. 22A, DEIS at 1-17; Ex. 30, Sched. 8 (Lahr Rebuttal).
[368] FEIS, Appx. C, Sheets 79 and 91 (showing the underground segment).
[369] Ex. 30, Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 1-17.
[370]
Ex. 22A, DEIS at 1-22 (Fig. 1-11); 1-17; FEIS Appx. C, Sheet 69 (
[371] Ex. 30, Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 1-17; 1-23 (Fig. 1-12).
[372] Ex. 1a (Application) at ES-7 (designated as Preferred Route Segment Alternative 1); Ex. 18 at 13 (EIS Scoping Decision).
[373] Ex. 22A, DEIS at 1-23 (Fig. 1-12), 1-28; Ex. 4w; FEIS Appx. C, Sheet 90.
[374] Ex. 22A, DEIS at 1-28; FEIS Appx. C, Sheet 98; Ex. 4w.
[375] See Ex. 18 at Figure 4 (EIS Scoping Decision); Ex. 21 at Map 5 (EIS Amended Scoping Decision); Ex. 2 at 24 (Lahr Direct); Ex. 22A at Fig. 1-10; Applicants’ Reply Brief at 1.
[376] Ex. 22A, DEIS at 1-28; DEIS at 1-23 (Fig. 1-12); FEIS Appx. C, Sheets 76 and 77 (showing broader route width). A high resolution map was attached to the EIS Scoping Decision Amendment, DEIS, Appx. A at Map 5.
[377] Applicants’ Post-Hearing Brief at 6; Applicant’s Reply Brief at 1.
[378]
Ex. 30, Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 1-6 (Fig. 1-4); 1-22 (Fig.
1-11); 1-28; FEIS, Appx. C, Sheet 98 (AS-5 is mistakenly identified on the
Sheet Map as AS-3).
[379] Ex. 22A, DEIS at 1-17, 18; FEIS Appx. C, Sheets 94, 95 and 96.
[380] Ex. 30, Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 1-18; 1-25 (Fig. 1-14).
[381] Ex. 30, Sched. 8 (Lahr Rebuttal); Ex. 22A, DEIS at 1-18; 1-26 (Fig. 1-15).
[382] Tr. Vol. 4 at 72-80 (Seykora).
[383] Ex. 4t.
[384] FEIS at 3-33, Table 3.4-2 and 3.6-3, combined.
[385] FEIS at 3-34, Table 3.6-4 and Table 3.6-5, combined.
[386] Compare FEIS at 3-34, Table 3.6-4 with Ex. 30 at Sched. 8 at 9 (Lahr Rebuttal); Applicants’ Post-Hearing Brief at 52.
[387] FEIS at 3-34 – 3-35, Tables 3.6-4 and 3.6-5; Ex. 30 at Sched. 8 at 9 (Lahr Rebuttal).
[388] FEIS at 3-33, Table 3.6-2: Modified Preferred Route - 409; Route C - 146; Route D - 210; Route E - 279 and Route G - 251.
[389] FEIS at 3-33, Table 3.6-3, and 3-35, Table 3.6-5.
[390] Ex. 22A, DEIS at 7-74, Table 7.7-2; Ex. 30 at Sched. 8, page 8 of 9 (Lahr Rebuttal).
[391] FEIS at 3-36, Table 3.6-6, and DEIS at 7-11, Table 7.1-10, combined.
[392] FEIS at 3-36, Table 3.6-6.
[393] FEIS at 3-36, Table 3.6-6.
[394]
A late-filed public comment from the City of Waite Park expressed a preference
for the
[395] FEIS at 3-37.
[396] FEIS at 3-37.
[397] Ex. 22A, DEIS at 7-3.
[398] Letter from Sand to ALJ, edocket Doc. No. 20111-58106-01 (eFiled Jan. 4, 2011).
[399] Ex. 22A, DEIS at 7-16.
[400] Ex. 22A, DEIS at 7-46.
[401] Ex. 22A, DEIS at 7-34.
[402] Ex. 22A, DEIS at 7-48, Table 7.3-4.
[403] Ex. 22A, DEIS at 7-49.
[404] Ex. 22A, DEIS at 7-34.
[405] FEIS at 3-38 and 3-60.
[406]
FEIS at 3-42 and Appx. C, Sheet 79, showing the proximity of Route C and Route
D to
[407] FEIS at 3-39.
[408]
Ex. 22A, DEIS at 7-35. The number of acres along the
[409] FEIS at 3-36, Table 3.6-6; Ex. 30 at Sched. 8 at 8 (Lahr Rebuttal).
[410] Ex. 22A, DEIS at 7-32, Table 7.3-1 and 7-36, Table 7.3-2.
[411] FEIS at 3-42.
[412]
FEIS at 3-38. As explained in the
discussion of the
[413] Ex. 22A, DEIS at 7-43 – 7-44, Table 7.3-3.
[414]
FEIS, Appx. C at Sheet 69, near intersection of CSAH 39 and
[415] Ex. 22A, DEIS at 7-44.
[416] FEIS at 3-41; Ex. 22A, DEIS at 7-44.
[417] Ex. 22A, DEIS at 7-51 – 7-57
[418] Ex. 22A, DEIS at 7-54; FEIS, Appx. C at Sheets 77 and 78.
[419] Ex. 41 at 5; Tr. Vol. 4 at 77-80 (Seykora); FEIS at 3-42.
[420] Ex. 22A, DEIS at 7-49.
[421] Ex. 22A, DEIS at 7-55, Table 7.4-6.
[422] Tr. Vol. 4 at 80-81 (Seykora); FEIS Appx. C, Sheet 79.
[423] Ex. 22A, DEIS at 7-66.
[424] Ex. 22A, DEIS at 7-74, Table 7.7-2.
[425] Ex. 30, Sched. 8 (Lahr Rebuttal): Route D at 77%, Route C at 90%, Modified Preferred Route at 94% and Route E and Route G at 96%. See also FEIS at 3-36, Table 3.6-6.
[426] Ex. 22A, DEIS at 7-74,Table 7.7-2 and 7-78, Table 7.7-4.
[427] Ex. 22A, DEIS at 7-85, Table 7.7-9.
[428] Ex. 17 at 7, 18 (referring to ATF alternative Group 3, Alt. 1); Tr. Vol. 5 at 132 (Birkholz).
[429] Ex. 22A, DEIS at 7-76, Table 7.7-3.
[430] Ex. 22A, DEIS at 7-84, Table 7.7-8.
[431] FEIS at 3-44 – 3-45.
[432]
Ex. 22A, DEIS at 7-78 – 7-79;
7-94 - 7-95, Table 7.7-12 (Wooded Lands in Proposed ROW). Ex. 30 at Sched. 8, page 8, shows lower acres
of wooded lands within the right-of-way for each of the alternative
routes. Modified
[433] Ex. 22A, DEIS at 7-81.
[434] Ex. 22A, DEIS at 7-96 - 7-97; Table 7.7-13.
[435] Ex. 22A, DEIS at 7-70.
[436] Ex. 22A, DEIS at 7-70.
[437] Ex. 22A, DEIS at 7-71.
[438] Ex. 22A, DEIS at 7-70; FEIS at 3-44.
[439] Ex. 6 at 8 (Kroll Direct).
[440] FEIS at 3-44.
[441] Letter to ALJ, eDocket Doc. No. 20111-58106-01 (Efiled Jan. 4, 2011).
[442] FEIS at 2-53.
[443] Ex. 22A, DEIS at 7-97 – 7-112.
[444] Ex. 22A, DEIS at 7-105, Table 7.8-6.
[445] Ex. 22A, DEIS at 7-111 – 7-112.
[446] Ex. 22A, DEIS at 7-103, Table 7.8-4.
[447] Ex. 22A, DEIS at 7-108 – 7-110, 7-112; Table 7.8-8.
[448] Ex. 22A, DEIS at 7-112.
[449] Ex. 47 at 23 (Hyllla Direct); FEIS, Appx. C at Sheet 65.
[450] Ex. 22A, DEIS at 7-110 – 7-112.
[451] FEIS at 3-55 – 3-58, Table 3.6; FEIS, Appx. C, Sheet 88.
[452]
FEIS, Appx. C, Sheets 84 and 88; Exs. 4t and 4u (
[453] FEIS at 3-47.
[454] FEIS at 3-44 – 3-49.
[455]
Ex. 5 at 6-7 (
[456] Ex. 22A, DEIS at 7-78 – 7-79.
[457]
FEIS at 3-46, Table 3.6-8. Ex. 30 at
Sched. 8 at 8 shows lower acres of wooded lands within the right-of-way for
each of the alternative routes than the FEIS.
FEIS: Modified
[458] Ex. 22A, DEIS at 7-117 – 7-119; FEIS at 3-51 and Table 3.6-9.
[459] Ex. 6 at 12 and Scheds. 5 and 8 (Kroll Direct).
[460] FEIS at 3-49.
[461] Ex. 8 at 4-7 (McGee Direct).
[462]
[463] Ex. 6 at 5-7 (Kroll Direct).
[464] Ex. 6 at 14 (Kroll Direct), quoting Michael Lee, DNR botanist.
[465] Tr. Vol. 3 at 117-118 (Chapman).
[466]
Ex. 11 at 6-8 (
[467] Tr. Vol. 3 at 133 (Chapman). Although FEIS at 3-36, Table 3.6-8, shows that the acres within the rights-of-way do not differ for Option 11, the maps show the relative location of the wooded areas. FEIS, Appx. C at Sheet 90.
[468]
Ex. 5 at 4, 6-7 (
[469] Ex. 22A, DEIS at 7-120 – 7-121.
[470]
Ex. 5 at Scheds. 4, 5 (
[471] Ex. 22A, DEIS at 7-113 – 7-114.
[472] FEIS at 3-51 – 3-61; Table 3.6-10.
[473] FEIS at 3-51 – 3-61; Table 3.6-11.
[474] FEIS at 3-51 – 3-61; Table 3.6-11 and Table 3.6-13.
[475] FEIS at 3-51 – 3-61; Table 3.6-10 and Table 3.6-11; Ex. 6 at 14 (Kroll Direct).
[476] FEIS at 3-51 – 3-61; Table 3.6-10 and Table 3.6-11.
[477] FEIS at 3-51 – 3-61; Table 3.6-10, 3.6-11 and 3.6-13.
[478] FEIS at 3-51 – 3-61; Table 3.6-11.
[479] Ex. 22A, DEIS at 7-127.
[480] FEIS, Table 3.6-15.
[481] FEIS at 3-5, Table 3.2-4. But compare Ex. 30, Sched. 8 at 8 (Lahr Rebuttal): The Modified Preferred Route follows such designations for 97 percent of its length; Route C – 95%; Route D – 97%; Route E – 100 %; Route G – 100%.
[482] Ex. 17, Appx. D.
[483] FEIS at 3-5, Table 3.2-4. See also Ex. 30, Sched. 8 at 8 (Lahr Rebuttal), with some differences.
[484] FEIS at 3-5, Table 3.2-4.
[485]
[486] FEIS at 3-5, Table 3.2-4.
[487]
Ex. 3 at 11 (Chezik). The Applicants
explained why it would be prudent to install both circuits in the underground
segments to avoid future cost and disruption.
[488] Ex. 3 at 10, f.n. 5 (Chezik Direct); Tr. Vol. 1 at 133 (Chezik).
[489] Ex. 22A, DEIS at 1-40, Table 1.6-1.
[490] Ex. 3 at 10, f.n. 2 (Chezik Direct).
[491] Ex. 2 at 20 (Lahr Direct).
[492] Ex. 3 at 10 (Chezik Direct).
[493] Ex. 43 at 2-3.
[494] Ex. 43 at 4-5.
[495] Ex. 43 at 4.
[496] Ex. 43 at 5.
[497] Ex. 43 at 4.
[498] Ex. 43 at 3.
[499] Ex. 43 at 6.
[500]
[501] Several areas with broader route width, many to skirt freeway interchanges, were identified in the Application, and included in Ex. 22A, DEIS at 1-31 – 1-33, Table 1.5-1. Apparently some are no longer needed. Some areas with decreased route width are also identified. Ex. 22A, DEIS at 1-34, Table 1.5-2.
[502] See
e.g., Comment, David Thingvold, Trans. Nov. 16, 2010, afternoon, p. 28-30,
Comment, Sylvester Goerdt, Trans. Nov. 16, 2010, evening, p. 47; Comment, Larry
Schneeberger, Trans. Nov. 17, 2010, evening, p. 26-27; Comment, Chad Beste,
Trans. Nov. 30, 2010, afternoon, p. 27-28; Comment, Justin Markell of RES
America, Trans. Dec. 2, 2010, afternoon, p. 33-34.
[503] Trans. Nov. 16, 2010, evening, p. 20.
[504] Trans. Nov. 18, 2010, afternoon, p. 38.
[505] Trans. Nov. 18, 2010, evening, p. 37-38.
[506] See
e.g., Letter, Jan Kaeter, Jan. 2, 2011; Letter, Anna Jonas, Jan. 3, 2011,
Letter, Margaret Boatz, undated; Letter, Tony and Nancy Schwalbe, Jan. 5, 2011,
Letter, Derek Iverson, Jan. 5, 2011; Letter, Duane and Jane Scepaniak, Jan. 5,
2011; Letter, Michael Zimmer, Dec. 30, 2010; Letter, John Ruprecht, Dec. 28,
2010; Letter, Leo Pohl, Dec. 7, 2010; Letter, Tim and Mary Drake, Nov. 24,
2010; Letter, Christy Morgel, received Dec. 2, 2010.
[507] Trans. Nov. 17, 2010, afternoon, p. 18;
Public Ex. 6; see also Comment, Harry
Whitehead, Nov. 17, 2010, afternoon, p. 21 (stating same); Comment, Helmer
Wright, Nov. 18, 2010, afternoon, p. 21-24 (stating same); Comment, Purves
Todd, Trans. Dec. 1, 2010, afternoon, p. 35-36; Comment, Art Kerfeld, Trans.
Dec. 1, 2010, afternoon, p. 48.
[508] Trans. Nov. 18, evening, p. 34-35; Letter,
Jan. 5, 2011.
[509] See
Letters, Casey Miller, Scott Miller, Dan Miller, Jan. 5, 2011.
[510] Trans. Nov. 16, 2010, evening, p. 22.
[511] Trans. Nov. 16, 2010, afternoon, p. 56-57.
[512] Public Ex. 1.
[513] Public Ex. 5.
[514] See
e.g., Comment, Mark Carr, Trans. Nov. 16, 2010, afternoon, p. 58-59;
Comment, Trail Vosberg, Nov. 16, 2010, evening, p. 36-37.
[515] Public Ex. 2.
[516] Trans., Nov. 16, 2010, evening, p. 26-32;
Public Ex. 3.
[517] Letter, Dec. 12, 2010.
[518] Trans. Nov. 16, 2010, afternoon, p. 40-44.
[519] Trans. Nov. 16, 2010, afternoon, p. 45.
[520] Trans. Nov. 18, 2010, afternoon, p. 26-32.
[521] Letter, Dec. 15, 2010.
[522] Letter, Dec. 20, 2010.
[523]
Public Exhibit 4.
[524] Trans. Nov. 18, 2010, afternoon, p. 34-36.
[525] Letter, Jan. 1, 2011.
[526] Trans. Nov. 18, 2010, evening, p. 35-37.
[527] Trans. Nov. 16, afternoon, p. 49.
[528] Trans. Nov. 17, 2010, evening, p. 18-25.
[529] Trans. Nov. 17, 2010, evening, p. 27-28;
Letters Dec. 22, 2010.
[530] Trans. Nov. 17, 2010, evening, p. 28-29.
[531]
Letters rec’d Nov. 29, 2010.
[532] Letter, Richard Baker, Tim Atkinson, Nov.
24, 2010.
[533] Trans. Nov. 17, 2010, evening, p. 40-41.
[534] Trans. Nov. 30, 2010, afternoon, p. 17-22;
Public Ex. 10; Letter, Jan. 5, 2011.
[535] Trans. Nov. 18, 2010, evening, p. 19-22.
[536] Trans. Dec. 1, 2010, afternoon, p. 52.
[537] Letter, Dec. 22, 2010.
[538] Trans. Nov. 30, 2010, evening, p. 16-19. Although the zoo has endangered species,
animals in captivity do not typically have endangered species status. Tr. Vol. 3 at 61-62 (Restani).
[539] Letter, Dec. 8, 2010 (Margaret Ladner,
State Director).
[540] Trans. Nov. 30, 2010, afternoon, p. 21-22.
[541] Trans. Dec. 1, 2010, afternoon, p. 20;
Public Ex. 15.
[542] Trans. Dec. 1, 2010, afternoon, p. 38-44.
[543] Letter, Jan. 4, 2011; see also Letter, Shawn Vouk, Jan. 5, 2011.
[544] Letter, Jan. 4, 2011; see also Letter, Michelle Gohl, Jan. 5, 2011.
[545]
Letter, Nov. 29, 2010.
[546] Letter, Jan. 5, 2011; see also Letter, Carrie Kerfeld, Jan. 5, 2011.
[547] Letter, Jan. 3, 2011.
[548] Letter, Dec. 28, 2010.
[549] See
e.g., Letter, Terence Check, Jan. 5, 2011; Letter, Sisters of the Order of
Saint Benedict, Dec. 28, 2010; Letter, Avon Hills Initiative, Dec. 2, 2010.
[550] Letter, Dec. 29, 2010.
[551] Public Ex. 10; Letter, City of Avon, Dec.
15, 2010; see also Comment, Jodi
Austing-Traut, Trans. Dec. 2, 2010, afternoon, p. 19 (stating same).
[552] Trans. Dec. 1, 2010, afternoon, p. 64.
[553] Letter, Nov. 26, 2010.
[554] Trans. Dec. 2, 2010, evening, p. 60-61.
[555] Letter, Jan. 5, 2011.
[556] Letter, Jan. 5, 2011.
[557] Letter, Jan. 5, 2011 (Mark Martell).
[558] Letter, Dec. 30, 2010.
[559] Letter, Dec. 31, 2010.
[560] Letter, Dec. 29, 2010.
[561] See
e.g., Comment, Todd Theisen, Trans. Dec. 1, 2010, evening, p. 27-30;
Comment, Tom Vouk, Trans. Dec. 2, 2010, afternoon, p. 39-40; Comment Paul
Eisenschenk, Trans. Dec. 2, 2010, afternoon, p. 47; Comment, Ken Schindele,
Trans. Dec. 2, 2010, afternoon, p. 56-57; Public Ex. 21.
[562] Trans. Dec. 2, 2010, evening, p. 22-24.
[563] Letter, Dec. 22, 2010; Letter, Jan. 5,
2011, citing Dakota County, 2006 WL
618903 (Minn. App 2006) and PEER, 266
N.W2d 858 (
[564] Letter, Jan. 3, 2011.
[565] Letter, Jan. 4, 2011.
[566] Letter, Dec. 29, 2010.
[567] Letter, Jan. 5, 2011.
[568] Trans. Dec. 2, 2010, afternoon, p. 19-23;
Letter, Sarah Theisen, Jan. 4, 2011.
[569] Trans. Dec. 2, 2010, afternoon, p. 29-32.
[570] Letter, Dec. 20, 2010.
[571] Trans. Dec. 2, 2010, afternoon, p. 41-44;
Public Ex. 19; Trans. Dec. 2, 2010, evening, p. 61-67.
[572] Trans. Dec. 2, 2010, evening, p. 61-63.
[573] Trans. Dec. 1, 2010, afternoon, p. 70-74;
Letter, Jan. 3, 2011.
[574] Letter, Dec. 17, 2010.
[575] Letter, Dec. 5, 2010.
[576] Trans. Dec. 1, 2010, afternoon, p. 57-62.
[577] Public Ex. 18.
[578] Letter, Jan. 1, 2011.
[579] Letters received Jan. 5, 2011.
[580] Letter, received Dec. 13, 2010.
[581] Letter, Jan. 5, 2011; Letter, Cindy Mehr,
Jan. 4, 2011.
[582] See
e.g., Comment, Mr. Arnhalt, Nov. 17, 2010, afternoon, p. 23; Comment, Tom
Vouk, Trans Dec. 1, 2010, p. 25-27; Comment, Joan Hemker, Trans. Dec. 2, 2010,
evening, p. 38-39; Public Ex. 26, Comment, Jeff and Rebekah Christensen, Public
Ex. 4.
[583] Trans., Nov. 16, 2010, afternoon, p.
45-46.
[584] Public Ex. 27.
[585] Trans. Dec. 1, 2010, afternoon, p. 38-39.
[586] Trans. Dec. 2, 2010, afternoon, p. 23.
[587] Trans. Dec. 1, 2010, p. 59-60; see also Comment, Terra O’Neil, Trans.
Dec. 2, 2010, afternoon, p. 30-31 (expressing concern regarding EMF effects on
farming output); Comment, Joe Kenning, Trans. Dec. 2, 2010, afternoon, p.
48-56; Public Ex. 20; Comment, David Heinen, Trans. Dec. 2, 2010, evening, p.
54-56; letter, Arthur and Sharon Salzer, undated.
[588] Trans. Nov. 16, 2010, afternoon, p. 52-53.
[589] Trans. Nov. 16, 2010, evening, p. 19;
Public Ex. 6 (Comment of Lien Township).
[590] See
e.g., Comment, Arthur Isaackson, Trans. Nov. 18, 2010, afternoon, p. 30-31.
[591] See
e.g., Comment, Cliff Borgerding, Trans. Dec. 2, 2010, evening, p. 76;
Public Ex. 15.
[592] Trans. Dec. 1, 2010, afternoon, p. 40-42; see also Comment, Todd Theisen, Trans.
Dec. 1, 2010, p. 27-29 (stating same); Letter, Jan. 3, 2011.
[593] Trans. Dec. 1, 2010, afternoon, p. 28-32,
76-86; Ex. 11A-11D.
[594] Trans. Dec. 2, 2010, afternoon, p. 69-78;
Letter, Dec. 29, 2010.
[595] Letter, Dec. 29, 2010.
[596] Trans. Dec. 2, 2010, evening, p. 56.
[597] Trans. Dec. 2, 2010, evening, p. 58-60.
[598] Trans. Dec. 2, 2010, evening, p. 78.
[599] Letter, Jan. 5, 2011.
[600] Trans. Dec. 1, 2010, afternoon, p. 46-47.