OAH 4-2500-20994-2
PUC IP-6728/CN-09-471
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISION
|
In the Matter of the
Application of Heartland Wind, LLC for a Certificate of Need for the Elm
Creek II Wind Project in Jackson and Martin Counties |
SUMMARY
OF PUBLIC TESTIMONY |
This proceeding began on August 28, 2009, when the Minnesota Public
Utilities Commission (Commission or MPUC) issued an Order directing an informal
review process of the application of Heartland Wind, LLC, for a Certificate of
Need (CON) for the Elm Creek II Wind Project and requesting the Office of
Administrative Hearings (OAH) to conduct a public hearing on the Project and provide a
summary of the public hearing testimony to the Commission.
Administrative Law Judge
NOTICE
This
report contains a summary of public testimony.
It is not a final decision. Pursuant
to Minn. R. 7850.3900, the Commission will make the final determination of the
matter after receiving the public hearing record from the ALJ.
Description of the Project
Heartland Wind, LLC (Heartland), which is
a wholly-owned subsidiary of Iberdrola Renewables, Inc. (Iberdrola), is
proposing to develop and construct the Elm Creek II Wind Project (the Project) as
a 150 megawatt (MW) large wind energy conversion system. The Project’s purpose will be to produce
renewable energy that will help meet the state’s renewable energy objectives. The Project will be located on approximately 30,339
acres in
The Project will consist of between 50
and 100 wind turbines, with rated outputs between 1.5 and 3.0 MW, in order to
yield 150 MW of electrical power. Each
turbine will be connected to a supervisory control and data acquisition (SCADA)
system via fiber optic cable to allow for real-time monitoring and control of
turbine operation. Other associated
facilities will include gravel access roads, expansion of an existing
substation, an expanded or new operation and maintenance building, two
meteorological towers, and an electrical collection system. The Project will interconnect to the
transmission grid at the existing Trimont Substation, which is connected to
Xcel Energy’s Lakefield Substation via an existing 345k transmission line.
Procedural History
1.
Heartland filed
an application with the Commission for a CON for the Project on June 8, 2009.[1]
2.
On June 26, 2009, the Commission issued an Order granting
certain exemptions from the CON filing requirements in accordance with
recommendations made by the Office of Energy Security of the Minnesota
Department of Commerce (the OES).[2]
3.
On August 4, 2009, the Commission found Heartland’s CON
application to be complete.[3]
4.
On August 28,
2009, the Commission authorized use of the informal process authorized by Minn. R.
7829.1200 and directed that an administrative law judge conduct a public
hearing on the application and provide the Commission with a summary of public
testimony.[4]
5.
On November 23,
2009, 2009, OES issued a Notice of Availability of the Environmental Report for
the Project.[5]
Hearing Notice, Public Hearing, and
Public Comment Process
6. On
November 30, 2009, the Commission issued a Notice of Public Hearing for a
public hearing to be conducted on December 15, 2009. On November 30, 2009, Heartland gave advance
notice of the public hearing to persons on the service list.
7. On
November 26, 2009, the Notice of Public Hearing was published in the Jackson
County Pilot, a local newspaper.[6] That Notice was also published on December 1,
2009, in the Fairmont Sentinel.[7]
8. The
ALJ conducted a public hearing on the Project on December 15, 2009, at 6:00
p.m. at the AmericInn of Jackson,
9. The
Commission will issue an order on Heartland’s application for a Certificate of
Need after examining this Summary, a copy of the digital recording of the
public hearing, and all filings and argument submitted by Heartland, the OES,
and other persons and entities interested in this matter.
Summary of Public Testimony
Bret
Eknes, a staff representative of the Commission, explained the Commission’s
role in considering Heartland’s CON application. Mr. Eknes also explained how members of the
public could gain web access to all documents filed in connection with this
docket.
Matthew Langan, Project Manager with the OES
discussed the OES’s responsibilities associated with processing the CON
application. He also stated that in
November 2009, the OES had issued an Environmental Report on the Project.[8] Mr. Langan explained that the
Environmental Report was a general document discussing the potential human and
environmental impacts of the Project, as proposed, as well as any alternatives
to the Project. That report also
assessed possible mitigation of potential adverse impacts of the Project.
Adam
Sokolski, representing Iberdrola and Heartland, is lead developer for the
Project. Mr. Sokolski provided
background on the need for and features of the Project. He indicated that the project was being
developed to help satisfy state and regional demands for renewable energy, as
well as to respond to the increasing regional demand for electric energy
generally. Mr. Sokolski also stated that
Heartland had also been the developer of the Trimont and Elm Creek I Projects
north of the City of
Kent Ringkob, a landowner and participant
in the Project, spoke in its favor.
Mr. Ringkob expressed his belief that the Project will be an
environmentally friendly way of providing electricity for a growing market in
the
Tim Stahl, the Jackson County Engineer,
indicated that he would prefer to have more information in greater detail about
the impacts that construction of the Project will have on county roads. He stated that although there was a
suggestion that the Project will have minimal impacts on existing
infrastructure, the County’s experience with earlier wind projects indicated
that the capacity limits for both county paved roads and township gravel roads
are likely to be exceeded during movements of construction equipment. Mr. Stahl wanted more information about how
that prospect would be addressed. He
also indicated that prior experience indicated the likelihood of other adverse
traffic impacts, such as road closures, detours, removal and replacement of
signage, and ensuring unimpeded access of emergency vehicles. Mr. Stahl believed that there needed to be
more specific plans to address those adverse impacts, and he looked forward to
working with representatives of Heartland to develop and implement those more
specific plans.
Barbara Jordi stated that she and her
husband own a six-acre homestead within the Project area, and that they operate
a business that is heavily dependent on internet connectivity. They currently receive internet service from
an internet service provider (ISP) that delivers their service via a line-of
sight microwave signal, and they are concerned about the extent to which noise created
by the Project, as well as movement of turbine blades, might disrupt their
business by disrupting their internet service.
She also expressed concern how the Project might impact a potential sale
of their home.
Mr. Sokolski indicated that Heartland had
already contacted Mr. and Mrs. Jordi’s ISP and had identified the tower from
which they receive the transmission for their internet service. Consulting with engineers employed by the
ISP, Heartland determined that a couple of the proposed sites for the Project’s
wind turbines needed to be shifted to ensure that turbine blades would not
interrupt the line-of-site transmission of the Jordi’s internet service. Those siting adjustments have been
incorporated into Project plans. With
regard to operational noise, Mr. Sokolski stated that in developing the
Project, Heartland is strictly complying with the standards set forth in the Minnesota
Pollution Control Agency’s noise abatement rules. More specifically, ongoing noise studies
indicate that noise levels everywhere on Mr. and Mrs. Jordi’s six-acre
homestead will be well below applicable noise standards. Finally, Heartland provided Mr. and Mrs.
Jordi with copies of studies made of property value impacts from wind turbines.
Mr. Stahl inquired whether turbine siting
is being coordinated with deployment by the Department of Transportation
(MnDOT) of the ARMER emergency communications system, which will allow
interconnection of communications between various regional emergency services
responders. More specifically, Mr. Stahl
asked whether there has been coordination to avoid disruption of the high
frequency line-of-sight transmissions between the towers that will be
constructed to interconnect emergency transmissions in
Commissioner Tusa went on to comment more
generally that the Project is expected to result in the creation of jobs and to
promote future economic development within
Summary of Written Comment
On December 23, 2009, Adam Sokolski
submitted written comments to the ALJ on behalf of Iberdrola Renewables, Inc., by
efiling them in this docket. In his
comments, Mr. Sokolski requested the Commission to grant a CON for the Project
as soon as possible. He noted that no
party or member of the public objected to the Project, disputed that the
Project was needed, or recommended that the CON be denied. Mr. Sokolski went on to note what he
considered to be some minor discrepancies in the Environmental Report. His comments also raised more substantive
criticisms of the following statement in Section 6.10 of the Environmental
Report:
Wind
turbines produce audible, low frequency sound and sub-audible sound
(infrasound). These sounds can have a
rhythmic modulation due to the spinning of the turbine blades. Impacts due to these sound characteristics are
subjective, i.e., human sensitivity, especially to low frequency sound, is
variable. However, in general, low frequency sounds can cause annoyance and
sleep disturbance.
The above language summarizes what Iberdrola
considers to be a controversial portion of the Minnesota Department of Health
(MDH) White Paper, “Public Health Impacts of Wind Turbines.” Responding to that white paper, Mr. Sokolski
included the following attachments to his written comments, which expressed
conclusions about the health effects of wind turbines that varied from those
expressed in MDH’s white paper:
a. Written
comments submitted by Iberdrola to the MPUC on September 16, 2009, in PUC Docket E999/CI-09-845, In the Matter of the Commission Investigation
into Large Wind Energy Conversion System Permit Conditions on Setbacks and the Minnesota Department of Health
Environmental Health Division’s White Paper on Public Health Impacts of Wind
Turbines;[9]
b. Review of Minnesota Department of Health’s "Public Health Impacts of Wind Turbines" prepared by
Mark Bastasch, P.E., on September 16, 2009;[10]
and
c. Wind Turbine Sound and Health Effects: An
Expert Panel Review, prepared by W. David Colby, M.D., Robert Dobie, M.D.,
Geoff Leventhall, Ph.D., Geoff Leventhall, Ph.D., David M. Lipscomb, Ph.D., Robert
J. McCunney, M.D., Michael T. Seilo, Ph.D., and Bo Søndergaard, M.Sc.[11]
Finally,
Mr. Sokolski also included some comments on the draft site permit.[12]
No other written comments
from the public were received.
Dated: January 12, 2010
s/Bruce
H. Johnson
|
BRUCE H. JOHNSON Assistant Chief
Administrative Law Judge |
Digitally
recorded; no transcript prepared.
[1] Application for a Certificate of Need
( https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=20096-38322-01)
[2] Order on Exemption and Variance Request (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=20096-38953-01
)
[3] Order Finding CON Application to be Complete
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=20098-40454-01
)
[4] Order Authorizing Informal Process
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=20098-41275-01)
[5] Notice of Availability of Environmental Report
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-44561-01 )
[6] Affidavit of Publication.
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-45315-01)
[7] Exs. 1 (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-44726-01
); Ex. 2.
[8] Environmental Report
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200911-44359-01)
[9] Attachment A, Part 1 of 2
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-45360-04 )
[10] Attachment A, Part 2 of 2
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-45360-08 )
[12] Applicant Comments
(https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=200912-45360-06 )