OAH 8-2500-20825-2
MPUC Docket Nos. E-017, E-015, ET-6 / TL-07-1327
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the
Application for a Route Permit for the |
FINDINGS OF FACT, CONCLUSIONS AND RECOMMENDATIONS |
This matter came before Administrative Law
Judge Eric L. Lipman during a series of public and evidentiary hearings on April
21, 22 and 23, 2010, in Blackduck,
The
following persons noted their appearance:
Thomas Erik Bailey, Briggs and Morgan, appeared on behalf of the
Applicants Otter Tail Power Company, Minnesota Power and Minnkota Power
Cooperative, Inc. (Applicants). Karen
Finstad Hammel, Assistant Attorney General, appeared on behalf of the
Department of Commerce Office of Energy Security (OES).
The
hearing record closed following the receipt of the Final Environmental Impact
Survey on September 2, 2010.
Have the Applicants satisfied the criteria
set forth in Minnesota Statutes § 216E.03 and Minnesota Rules Chapter 7850 for
a Route Permit for the Bemidji to Grand Rapids 230 kV Transmission Line Project?
Based upon the Findings and
Conclusions that follow below, the Administrative Law Judge makes the
following:
RECOMMENDATIONS
The Minnesota Public Utilities Commission
should:
1.
Determine
that all relevant statutory and rule criteria necessary to obtain a Route
Permit have been satisfied and that, on this record, there are no statutory or
other requirements that preclude granting a Route Permit.
2.
Grant a Route Permit to Applicants, on
behalf of themselves and Xcel Energy and Great River Energy, for:
(a)
The
Applicants’
(b)
Modifications
and additions to three existing substations (Wilton Substation, Cass Lake
Substation, and Boswell Substation) to accommodate the new transmission line
facilities; and
(c)
A new
115 kV breaker station at Nary Junction.
3.
Require
the Applicants to undertake such construction and maintenance practices so as
to minimize the impacts to natural resources within the Project Area.
4.
Require the Applicants to obtain all required
local, state, and federal permits and licenses, to comply with the terms of
those permits or licenses, and to comply with all applicable rules and
regulations.
5.
Require the Applicants to take those actions
necessary to implement the Commission’s Orders in this proceeding.
Based upon the hearing record,
the Administrative Law Judge makes the following:
FINDINGS OF FACT
A.
Introduction:
1.
The proposed
project is a 230 kV transmission line that would run primarily along existing
rights-of-way between the Wilton Substation (just west of Bemidji, Minnesota),
and the Boswell Substation in Cohasset, Minnesota.[1]
2.
The proposed line would traverse portions of
3.
The
Chippewa National Forest (CNF), the Leech Lake Reservation (LLR), the
Mississippi River, and the communities of
4.
Applicants
initially proposed two route alternatives, both of which are approximately 68
miles long:
·
Route 1 – This route generally follows the Great
Lakes pipeline right-of-way from the Wilton Substation to just east of
·
Route 2 – This alternative generally follows U.S. Highway
2 and the pipeline rights-of-way of Enbridge for its entire length between the
Wilton Substation and Boswell Substation.
There is one alternative route section for Route 2: 2C.[4]
5.
Following
analysis of information developed through the Draft Environmental Impact
Statement (DEIS) scoping process, the Applicants urged a combination of Routes
1 and 2 to establish Applicants’ Preferred Route. The west and east ends of Route 4 primarily
follow Route 1, while the central portion of Route 4 follows Route 2.[5]
6.
In the
Final Environmental Impact Statement (FEIS), the Applicants’
7.
Based
upon discussions among various governmental agencies and other stakeholders,
the OES concluded that the only route alternative that warranted study in
addition to Routes 1 and 2 was a route in the North Corridor that avoids the
boundaries of the Leech Lake Band of Ojibwe Reservation. This route was denominated as
“Route 3.” Route 3 bypasses the
Reservation by taking a route from
B.
Summary of Written Public Comments:
8.
Lynné Holt, of
9.
Robert
Harper, a Forest Supervisor for the
10.
Dean
Sedgwick, of
11.
Sally
Sedgwick, of
12.
Gary
and Juanita Metheny, of Blackduck, Minnesota, expressed concern that their
family farm would be taken from them, and that they would not be paid the true
value of their property, if Route 3 were selected.
13.
James
and Karol McCracken, of
14.
Linda
Bathen, landowner on
15.
Joanne
Mulbah, of
16.
Dan
Gartrell, on
17.
Jane
Johnson opposes the selection of Route 3 due to its greater cost, length
and amount of rights-of-way, when compared to Proposed Routes 1 and 2.
18.
Richard
Ludtke, of
19.
Diane
Plath, on behalf of Donald and Kristen Wagner of
20.
Jack
Haugen, a
21.
Dave
Baughn, of
22.
Gerald
and Eldora Solheim, of
23.
Rita
Velat, of
24.
Sheldon
Johnson, Chair of the Mississippi River Parkway Commission of Minnesota, expressed
the commission’s concerns that the qualities
of the
25.
Keith Pommerening,
of
26.
Jon
Eggers, of
27.
Jamie
Schrenzel, Principle Planner of the Environmental Review Unit of the Minnesota
Department of Natural Resources, reviewed the DEIS and determined
Proposed Route 2 to have the least potential for significant resource
impacts. The DNR, in its report to the
OES, requested further analysis of impacts
to waterfowl and water birds from the proposed routes and special attention
to protection of endangered
species.
28.
29.
Dale
and Jane Grasdalen, of
30.
Mike
Schmid, of
31.
Craig Affeldt, Supervisor of the Environmental
Review and Feedlot Section of the Minnesota Pollution Control Agency, provided
the Agency’s comments on the Draft Environmental Impact Statement. These comments highlighted features of the
DEIS that should be clarified or where additional or more appropriate planning
is required.
C.
Summary of Testimony at the Public Hearings:
Following brief presentations from Messrs.
Al Koeckeritz and Jason Weiers, of Otter Tail Power Company, Bob Lindholm, a
manager in the Environmental Services Department at Minnesota Power, and Dave
Seykora of the Minnesota Department of Transportation, at the beginning of each
hearing, testimony was received from members of the public.
32.
Harold and Jackie Ferdig, of
33.
Gerald Zeise of
34.
Troy Depew, of
35.
Ken Michalicek, of
36.
Mark Michalek, of
37.
Jerry Larson, of
38.
Dean Sedgwick, of
39.
Sally Sedgwick, of
40.
Gerald Zeise, of
41.
Jackie Ferdig, of
42.
Peter Guggenheimer, of
43.
Diane Plath, of
44.
Jarrett Lish, of
45.
Sharon Lish, of
46.
Lester Hiltz, of
47.
Doug Bjerke, of
48.
Jerry Solheim, of
49.
Karol Hendricks-McCracken, of
50.
Roy Williams, of
51.
Scott Dingman, of
52.
Shirley Moe, of
53.
Keith Pommerening, of
54.
Dan Reimer, of
55.
Cliff Westland, of
56.
Greg Chester, of
57.
Wanda Arenz, of
58.
Barry Babcock, of
59.
George Berbee, of
60.
Norley Hansen, of
D.
Certificate of Need:
61.
On
March 17, 2008, Otter Tail Power Company (Otter Tail Power), Minnesota
Power, and Minnkota Power Cooperative, Inc. (Minnkota Power), collectively
referred to as “the Applicants,” on behalf of themselves and Northern States
Power Company, a Minnesota corporation (Xcel Energy) and Great River Energy, a
Minnesota cooperative association, filed an application with the Minnesota
Public Utilities Commission (Commission) for a Certificate of Need to construct
a 230 kV transmission line between Bemidji, Minnesota and Grand Rapids,
Minnesota (Bemidji-Grand Rapids Line or the Project). The Applicants proposed locating the Project
along existing rights-of-way within a corridor that runs from
62.
The
Certificate of Need Application explained that the Project is needed to
effectively meet projected future customer demand in the
63.
On July
14, 2009, the Commission granted Applicants a certificate of need for the
Project.[38]
E.
Route Permit Application:
64.
On June
4, 2008, Otter Tail Power, Minnesota Power, and Minnkota Power filed an
application for a Route Permit for the
65.
On June
30, 2008, the Commission found the Route Permit Application complete and
authorized the Application to be processed under the full review process (Minn.
R. 7850.1700‑ 7850.2700).[40]
66.
On July
2, 2008, the OES appointed eight persons to an Advisory Task Force that would
render advice on the issues to be addressed in the Environmental Impact
Statement.[41]
67.
Public
information meetings on the Project and the scope of its environmental review
by OES were held in Blackduck,
68.
On
September 24, 2008, the Advisory Task Force issued its report.[43]
69.
On
April 2, 2009, OES issued its Notice of Scoping Decision and Intent to
Prepare an Environmental Impact Statement for the Project jointly with the Rural
Utilities Service of the U.S.
Department of Agriculture (RUS). Minnkota
Power is seeking federal funding for its portion of the Project from the RUS.[44]
70.
The
closing date on the period for intervention in this matter was February 10,
2010. In the Matter of the Application for a
Route Permit for the Bemidji – Grand Rapids 230kV Transmission Project, Second Prehearing Order, OAH Docket
No. 8-2500-20825-2 (December 28, 2009).
71.
On February
11, 2010, OES issued its Notice of Revised Environmental Impact Statement
Scoping Decision.[45]
72.
On
February 23, 2010, OES issued its Notice of Availability of Draft Environmental
Impact Statement (DEIS) and Notice of Public Information Meetings. The DEIS public information meetings
were held on March 16-18 in
73.
Combined
public and evidentiary hearings on the Project were held on April 21 through
April 23, 2010 in Blackduck,
· The post-hearing public comment period closed on May 3, 2010.[48]
·
On
August 8, 2010, NoCapX 2020 and United Citizens Action Network petition
for intervention as parties in this matter and for an adjustment of the
timelines set forth in the Third and Fourth Prehearing Orders. The undersigned denied the requests on the
grounds that the requests were untimely and the requested relief
unnecessary. In the Matter of the Application for a
Route Permit for the Bemidji – Grand Rapids 230kV Transmission Project, Order on Intervention,
OAH Docket No. 8-2500-20825-2 (August 12, 2010).
74.
On
September 2, 2010, OES issued its Notice of Availability of Final Environmental
Impact Statement (FEIS).[49]
F.
Project and Associated Facilities 230 kV
Transmission Line:
75.
The Project
will use predominantly H-frame 230 kV structures. These structures are suitable for
single-circuit construction in rugged terrain and for areas which require longer
spans – such as areas that are adjacent to wetlands or waterways. H-frames will range in height between 70 to
90 feet and be placed approximately 600 to 1,000 feet apart. A typical H-frame structure has two 24- to
36-inch diameter poles placed approximately 19.5 feet apart from each other.[50]
76.
Single-pole
self-supporting structures may also be used for single circuit portions of the
transmission line in areas where the available width of the right-of-way is
limited by existing infrastructure or development. While Applicants do not know precisely how wide the right-of-way will
need to be in these areas, for planning purposes, they are using a
right-of-way width of 75 feet.[51]
77.
The height of
single-pole single circuit structures would range from approximately 80 to 100
feet, with the span between structures approximately 400 to 800 feet apart.[52]
78.
For each phase
of the 230 kV circuit, 954 kcmil aluminum conductor steel reinforced (ACSR) is
proposed. The use of 3/8-inch diameter
extra high strength steel (EHS) and fiber optic ground wire (OPGW) is proposed
for the shield wires. The conductor size
and shield wire selection are subject to change pending completion of
additional electrical optimization studies.[53]
79.
The
typical right-of-way needed to support a 230 kV transmission line is
approximately 125 feet wide. However,
the width of the right-of-way that is needed in a particular location depends upon
topography, existing features and recommended clearances between the conductor
and other facilities adjacent to the route.
Applicants seek permanent easements providing the right to construct,
operate, and maintain the transmission line along the full width and length of
the proposed right-of-way.[54]
80.
Applicants
have agreed that when approaching landowners regarding the purchase of right-of-way
easements, the Applicants’ agents will provide written disclosures regarding
the protections found in Minn. Stat. § 216E.12, subd. 4.[55]
1. Substations
81.
The Project
requires modifications at the Wilton Substation near
82.
At the Wilton
Substation, the Applicants propose to install a new line termination structure,
two new 230 kV circuit breakers, five new 230 kV switches, and associated
foundations, steel structures, and control panels. None of these modifications will require
physical expansion beyond the limits of the existing fenced perimeter of the
substation.[57]
83.
The Applicants
propose similar modifications to the Boswell Substation. The Applicants propose utilizing an unused
line position in the substation and installing one new 230 kV circuit breaker,
a 230 kV “dead-end structure,” two new 230 kV switches, associated foundations,
steel structures and control panels.[58]
84.
Additionally, the
power lines that now run into the substation will need to be relocated so as to
accommodate the addition of another line.
This relocation and addition may require additional 230 kV dead-end
structures to be installed.[59]
85.
The Applicants
do not anticipate requiring additional land, beyond the Boswell Substation’s
current 1.3 acre parcel, to complete the needed modifications.[60]
86.
Locating the
Project along Route 4 also requires upgrading the existing 115 kV Cass
Lake Substation to 230 kV.[61]
87.
While the
Applicants do not propose to acquire land in order to accommodate the needed
improvements, the Applicants do propose substantial upgrades to the existing Cass
Lake Substation site. The Applicants
propose extending the existing fence line around the Substation approximately
320 feet west, so as to establish a new 230 kV switchyard; installing a new 230
kV three-breaker ring bus with line switches, a new 230/115 kV transformer and
associated 115 kV facilities; establishing a new 115 kV four-breaker ring bus
with switches; and placement of a new control house, relay panels, foundations,
steel structures, and switches.[62]
88.
Applicants
likewise propose that a Breaker Station
be constructed at Nary Junction so as to improve the reliability of the 115 kV
system in the
89.
The
addition of a Breaker Station at Nary Junction would connect three 230 kV
sources of electric power (from the
90.
Installation
of a Breaker Station at Nary Junction would improve reliability by
sectionalizing the local 115 kV system and providing fault-interrupting
capability at an important point in the transmission system.
These upgrades would minimize the number of customers that would be
affected in the event of a fault on the transmission system between
91.
Installation
of a Breaker Station at Nary Junction would also improve operational flexibility
of the 115 kV system. Equipment at such
stations can be remotely-controlled from dispatch centers – a feature that
reduces both the amount of time that is needed to restore power following a
fault on the transmission line and the length of periods of
“de-energizing” of the line during facility construction and maintenance. Remote control of switches can operate faster
than manual switching by field personnel. This greater speed thus minimizes the impact
of outages to customers along the existing 115 kV system.[65]
92.
The Applicants
propose to establish this new 115 kV breaker station adjacent to the existing
Nary Junction switch, and within the existing 5-acre site. The proposed breaker station will consist of
three 115 kV circuit breakers;
nine new 115 kV switches; communications, relay and control equipment; three
115 kV line termination structures; and a control house. An improved access road and small parking lot
will also be required to move this equipment to the site.[66]
2. 115
kV Line Thermal Improvements
93.
The Applicants
propose upgrades to improve the thermal limits of the existing
94.
Increasing
the thermal limit of the Cass Lake-Nary 115 kV line requires replacing the
existing 115 kV conductor with a larger 115 kV conductor.[68]
95.
Moreover,
to increase the thermal limit of the Nary-Helga-Bemidji 115 kV line, its conductor-to-ground clearances
must be increased by either replacing the existing structures or by using a
technique known as “phase raising.”
Phase raising involves cutting through the existing structures and
placing steel spacers in them for added height and structural integrity.[69]
96.
The
Applicants propose to raise the structures along the Nary-Helga-Bemidji 115 kV
line (which now reach between 65 and 70 feet tall) by 5 feet. No additional right-of-way would be required
to complete the phase raising.[70]
3. Project
Cost
97.
The
cost of constructing the 230 kV transmission line as proposed by Applicants is
approximately $55.8 million. This total
includes the estimated construction costs associated with each mile of wetland
and forestland crossed, and the double circuiting of the Project with an
existing 115 kV line at the Wilton Substation.[71]
98.
The
construction costs for the Project’s associated facilities (substation
modifications at
G.
Route Alternatives:
99.
In
their Route Permit Application, the Applicants identified Route 1 as their
preferred route.[73]
100.
Based upon
discussions among several federal agencies and other stakeholders – including the Rural Utilities Service (RUS),
Chippewa National Forest (CNF), Army Corps of Engineers (ACE), and the Department
of Resource Management (DRM) of the Leech Lake Band of Ojibwe (LLBO) – four additional
corridors for the Project were identified:[74]
·
The North Corridor is an approximately 116-mile
long corridor that connects the
·
The Central Corridor is approximately 69 miles long
and from two to eight miles wide. It
runs parallel to U.S. Highway 2 between
·
The South Corridor is an approximately 100-mile
long corridor that connects the
·
The Non-CNF Corridor is an approximately 126-mile
corridor that connects the
101.
The EIS
scoping process also revealed that, with respect to the central portion
of the CNF and LLR, both the CNF and
the LLBO favor Route 2 over Route 1.
Route 2 follows the Enbridge pipeline right-of-way near U.S. 2 and
includes more previously-disturbed land than Route 1. In addition, locating the Project along Route
2 avoids areas of special cultural and biological significance – specifically,
the Ten Section area of the CNF and the
H.
Applicants’ Route:
102.
Based upon
the information developed through the EIS scoping process, and the colloquies
with various agencies, the Applicants combined segments of Routes 1 and
2 so as to create Applicants’
103.
Beginning
at the Wilton Substation west of
104.
Route 4
follows Route 1 at the point that it crosses the
105.
An
H-frame design allows longer spans between structures, requires fewer structures and therefore
reduces the direct impacts to floodplain wetlands. While having the Project adjacent to Great
River Energy’s 69 kV line increases the number of horizontal planes of wire
that birds moving along the river will encounter (i.e., three conductor
levels and one shield wire level), the risk of avian collisions can be
effectively minimized by the Applicants’
plan to incorporate visual flight diverters to these multiple planes.[78]
106.
Route 4
avoids crossing on, or over, any tribal trust lands of the LLBO or the
Minnesota Chippewa Tribe.[79]
Applicants have reviewed with the Bureau of Indian Affairs (BIA) the
parcels within Route 4, and the BIA has confirmed that Applicants’
right-of-way can be aligned so as to
avoid crossing on, or over, tribal trust lands.[80]
I.
Route Permitting Statutes and Rules:
107.
The
Power Plan Siting Act requires that route permit determinations “be guided by
the state’s goals to conserve resources, minimize environmental impacts,
minimize human settlement and other land use conflicts, and ensure the state’s
electric energy security through efficient, cost-effective power supply and
electric transmission infrastructure.”[81] The
statute then identifies twelve criteria for the Commission to consider when making a route designation:
(1) evaluation of research and investigations
relating to the effects on land, water and air resources of large electric
power generating plants and high-voltage transmission lines and the effects of water and air discharges and
electric and magnetic fields resulting from such facilities on public health
and welfare, vegetation, animals, materials and aesthetic values, including
baseline studies, predictive modeling, and evaluation of new or improved
methods for minimizing adverse impacts of water and air discharges and other
matters pertaining to the effects of power plants on the water and air
environment;
(2) environmental evaluation of sites and
routes proposed for future development and expansion and their relationship to the land, water, air and human
resources of the state;
(3) evaluation of the effects of new electric
power generation and transmission technologies and systems related to power
plants designed to minimize adverse environmental effects;
(4) evaluation of the potential for beneficial
uses of waste energy from proposed large electric power generating plants;
(5) analysis of the direct and indirect
economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or
impaired;
(6) evaluation of adverse direct and indirect
environmental effects that cannot be avoided should the proposed site and route
be accepted;
(7) evaluation of alternatives to the applicant’s
proposed site or route proposed
pursuant to subdivision 1 and 2;
(8) evaluation of potential routes that would
use or parallel existing railroad and highway rights-of-way;
(9) evaluation of governmental survey lines
and other natural division lines of agricultural land so as to minimize interference with agricultural
operations;
(10) evaluation of future needs for additional
high-voltage transmission lines in the same general area as any proposed route,
and the advisability of ordering the construction of structures capable of expansion in transmission capacity through
multiple circuiting or design modifications;
(11) evaluation of irreversible and irretrievable
commitments of resources should the proposed site or route be approved; and
(12) when appropriate, consideration of problems raised by other state and federal
agencies and local entities.[82]
108.
Additionally,
by rule, the Commission has established a set of evaluation factors that mirror
the criteria established by Minn. Stat. § 216E.03, subd. 7 (b).
The Commission is to consider the:
A. effects on human settlement, including,
but not limited to, displacement, noise, aesthetics, cultural values,
recreation, and public services;
B. effects on public health and safety;
C. effects on land-based economies, including,
but not limited to, agriculture, forestry, tourism, and mining;
D. effects on archaeological and historic
resources;
E. effects on the natural environment,
including effects on air and water
quality resources and flora and fauna;
F. effects on rare and unique natural
resources;
G. application of design options that
maximize energy efficiencies, mitigate adverse environmental effects, and could
accommodate expansion of transmission
or generating capacity;
H. use or paralleling of existing rights-of-way,
survey lines, natural division lines, and agricultural field boundaries;
J. use of existing transportation, pipeline, and electrical transmission systems or rights-of-way;
K. electrical system reliability;
L. costs of constructing, operating, and
maintaining the facility which are dependent on design and route;
M. adverse human and natural environmental
effects which cannot be avoided; and
N. irreversible and irretrievable commitments
of resources.[83]
J.
Analysis of Applicants’ Route Under
Commission Routing Factors
(
1. Effects
upon Human Settlement
109.
The
Commission’s consideration of the effects on human settlement includes
displacement of homes by the Project, noise from the construction and
operation of the Project, and the Project’s impacts on aesthetics, cultural
values, recreation, and public services.
(i)
Displacement
110.
The
following summarizes the route alternatives’ potential to displace
residents:
Comparison of Route Alternatives’ Potential to Displace Residences
|
|
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Residences
within 125 feet of the right-of-way |
3 |
15 |
25 |
0 |
|
Residences
within the 1,000 foot route |
109 |
281 |
459[84] |
106 |
111.
Route 4
avoids the greatest number of homes.
112.
Additionally,
the Applicants pledge to further mitigate potential displacement by altering
the alignment of the Project so as to avoid those homes that lie in the
right-of-way.[85]
(ii) Noise
113.
The
noise levels of the 230 kV line will be below the most restrictive state
standards for noise. Area noise levels
as a result of the modifications at the
(iii) Aesthetics
114.
The
principal aesthetic impact of building the Project in any of the routes is the
loss of trees and the devaluation of high-value scenic resources because
of the addition of transmission lines to the landscape.[87] The
table below details the total loss of forested land that is associated with
each route:[88]
Comparison of
Route Alternatives’ Impact on
|
Forested Land |
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Total |
579 |
439 |
823 |
581 |
|
Within CNF |
294 |
202 |
324 |
249 |
115.
Locating
the Project in Route 2 results in the least tree loss.
116.
The
total loss of trees associated with Route 4 is comparable to Route 1 and results
in significantly less tree loss within the CNF when compared to Route 1.
117.
The
greatest visual impact of the Project would be in Routes 1 and 2, which cross a
central portion of the CNF and bisect the LLR.
Between these two alternatives, Route 1 is the most visually
isolated from highways and residential areas, but crosses important traditional gathering areas within the LLR – such as
the Ten Section area.[89]
Route 2, by contrast, parallels U.S. 2 most of its length, in a corridor
that is already disturbed with railroad, pipeline, and power line
rights-of-way along with a major highway.
While this line would be
partially buffered from U.S. 2 by forested areas, it would be noticeable along
much of the route.[90]
118.
In the
view of both the CNF and the LLBO, the negative impacts associated with the Route
1 crossings of sensitive areas outweigh the negative impacts of Route 2.[91]
(iv) Cultural
Values
119.
Route 4
minimizes the impacts upon natural resource appreciation and use. The
120.
Adverse
impacts on natural resource use, such as wild rice harvesting or berry picking,
are likewise not expected. The
opportunities for berry picking would likely increase due to conversion
of forest lands to grasslands and shrub lands within the transmission line
right-of-way, and the Project would span rivers and deep-water wetlands so as to avoid existing wild rice resources.[93]
121.
Game
animal populations are also not expected to be affected by locating the
Project along Routes 1, 2, 3 or 4;
thereby avoiding negative impacts upon hunting opportunities in the area.[94]
122.
Additionally,
due to the limited space available for construction in the area of
(v) Recreation
and Tourism
123.
The
Project would span recreation trails. It
would have minimal, if any, impacts upon fishing, water recreation and
developed recreation sites – such as golf courses.
124.
The
Project would likewise have
only temporary impacts on hunting, due to the displacement of wildlife during
the pre-construction clearing of vegetation.[96]
125.
Among
the route alternatives, because Route 4 is primarily located along existing
transmission lines, pipeline rights-of-way and U.S. 2, it would have the least
impacts upon recreation and tourism.[97]
(vi) Public
Services
126.
The
record demonstrates that there are no anticipated adverse consequences to
public services as a result of the construction and operation of the Project
along any of the proposed Routes.[98]
2. Effects
on Public Health and Safety
127.
Applicants
have committed to build and operate Project facilities in compliance with the requirements
of the National Electrical Safety Code (NESC), Occupational Safety and Health Act (OSHA), and other applicable federal,
state and local regulations. The
Applicants have made a detailed description of the procedures they will follow
in building, operating, and maintaining the transmission line a part of this hearing record.[99]
128.
The
Applicants have established that transmission lines can be safely located in
rights-of-way that are adjacent to rights-of-way that host underground natural
gas and crude oil pipelines. The
Applicants have pledged to implement modern engineering practices so as to
safely collocate transmission lines adjacent to pipeline rights-of-way.[100]
129.
The Applicants
have also committed to meeting all applicable safety requirements with respect
to routing the Project along pipeline rights-of-way.[101]
130.
The
Applicants have satisfied the applicable standards for protecting the
public’s health and safety with respect to electro-magnetic fields (EMF). The Project will have a peak magnitude of
electric field density of approximately 2.6 kV/m at the point directly underneath the conductors at one meter above ground
level. It will also have a peak magnitude of magnetic field density of approximately
260 mG at the point directly underneath the conductors. Both of these levels are below the applicable
state and federal standards for electro-magnetic fields.[102] Further,
it is not anticipated that the Project will create stray voltage events.[103]
131.
Routes
1, 3 and 4 avoid the St. Regis Superfund Site in
3. Effects on Land-Based Economies
132.
The
Project’s impacts to agriculture, forestry and mining are considered by the Commission as part of its assessment
of the effects on land-based economies.
(i)
Agriculture
133.
The
following table shows the impacts of the route alternatives on agriculture:[105]
Comparison of
Route Alternatives on
|
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
210 |
117 |
503 |
191 |
134.
Among
the four alternatives, Route 4 has the second least impact upon agricultural land.
135.
Route 3
has a very high impact upon agricultural land.
136.
The Applicants
agree to further reduce the impact of its proposed route through the
implementation of an Agricultural Mitigation Plan.[106]
(ii) Forestry
137.
The
record shows the following impacts on forested land:[107]
Comparison of
Route Alternative Impacts on
|
|
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Total |
579 |
439 |
823 |
581 |
|
Within CNF |
294 |
202 |
324 |
249 |
138.
Route 2
traverses the Ten Section area of the CNF; an area that is of cultural and biological
importance to the LLBO.[108]
139.
Route 4
does not traverse the southern (and most highly-valued) portion of the Ten
Section area of the CNF.[109]
140.
Among
the four alternatives, Route 3 has the greatest impact upon forested land.
141.
Route 4
traverses two more acres of forested land than Route 1, but 45 fewer acres within
the CNF.
(iii) Mining
142.
There
are mining resources located within all of the route alternatives, but none of
the right-of-way alignments cross on, or over, active aggregate or mining
areas. Even if a re-alignment of the
Project’s right-of-way is required, the proposed route width is large enough to avoid impacting existing
aggregate operations and resources.[110]
4. Effects
on Archaeological and Historic Resources
143.
As part
of its assessment of the impacts upon cultural resources, the Commission
considers the adverse effects
routing may have on properties that are eligible for listing on the National Register
of Historic Properties (NRHP).[111]
144.
Potential
impacts to historic properties are evaluated in terms of the significance of
the resource and the potential for the Project to detract from that
significance.[112]
145.
The
number of known archaeological, historic and architectural sites of
significance within each route alternative is summarized below:[113]
Route Alternatives’ Potential Impacts on Known Cultural Resources
|
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
36 |
25 |
58 |
37 |
146.
After a
route is selected for the Project, the RUS will complete the identification and
evaluation of cultural resources that are eligible for the National Register.[114]
147.
RUS will
undertake these functions under Programmatic
Agreement between the other interested federal agencies, the LLBO Tribal
Historic Properties Office, other interested tribes and the Applicants. The terms of the agreement will guide the
identification and evaluation of historic properties, the assessment of
adverse effects to them, and the development of appropriate mitigation plans.[115]
148.
The
record suggests that while the Programmatic Agreement is not yet finalized, any
adverse impacts identified by the RUS will be adequately mitigated.[116]
5. Effects
on Natural Environment
149.
As part
of its assessment of the impacts upon natural environment, the Commission
considers the potential adverse effects on air and water quality, and on flora
and fauna.[117]
(i)
Air Quality
150.
The
construction of the Project will
result in the emission of air pollutants from construction equipment and the
release of fugitive dust from disturbing soil.
This impact is temporary.
Concentrations of ozone from the operation of the Project would be de minimus and have a negligible
impact on air quality.[118]
(ii)
Water
Quality
151.
Short-term
and long-term impacts to surface water resources are unlikely to occur to the
water basins (e.g., lakes and ponds)
and watercourses (e.g., rivers and
streams) located in the route alternatives.
For the most part, each route
alternative avoids direct impact to surface water. In those instances where an impact occurs, the
Applicant pledges to align the line, and to place supporting structures, so as
to span affected water bodies.[119]
152.
No
adverse impacts to groundwater have
been identified along any of the route alternatives.[120]
153.
Routes
1, 2 and 4 all propose a crossing of the Mississippi River on the south side of
U.S. 2, west of Ball Club,
154.
The
Applicants pledge to locate structures outside the floodplain to the extent practicable and to
restore any disruption to the floodplain contours that occurs during
construction to its pre-construction state.[122]
155.
The
wetland impacts of the route alternatives are summarized in the table
below:[123]
Comparison of Route Alternatives’ Impact on Wetlands (acres)
|
|
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Total Wetland
within right-of-way |
292 |
225 |
420 |
317 |
|
Forested
Wetland conversion |
209 |
166 |
110 |
97 |
156.
Direct
impacts to wetlands due to pole placements would be similar for all the route
alternatives – impacting less than one acre of land.[124]
157.
Among
the four alternatives, Route 3 has the greatest impact upon wetlands.
158.
Route 4
traverses 92 more acres of wetlands than Route 2, but 69 fewer acres of
forested wetlands. Among the four
alternatives, Route 4 has the fewest impacts upon forested wetlands.
159.
The location of structures by and in any
wetland along the proposed routes is subject to review and permitting by
Army Corps of Engineers, Minnesota Department of Natural Resources, Minnesota
Pollution Control Agency, and Minnesota Board of Water and Soil Resources.[125]
160.
Applicants
have identified specific best management practices that they will use to
minimize any impacts to wetlands.[126]
(iii)
Flora
161.
Among
the four route alternatives, Route 3 results in the greatest disturbance to
vegetation cover.[127]
162.
Between
Routes 1 and 2, the impacts on vegetation are comparable. Route 1 would have more impact on upland
deciduous communities than Route 2, but less impact on upland shrub areas.[128]
163.
One
significant difference between Routes 1 and 2 is the potential impact on the
Ten Section Area and Guthrie Till Plain.
Route 1 crosses these areas, potentially impacting old growth forest. Route 2 passes along the northern
border of the Ten Section Area and has a limited 3-mile impact on the Guthrie
Till Plain, east of the Ten Section.[129]
164.
The
eastern sections of the Ten Section Area and Guthrie Till Plain crossed by
Route 2 are now developed, with existing right-of-way, and are not as heavily used by members of
the LLBO for hunting, gathering or spiritual activities as the portions of the
Ten Section Area and Guthrie Till Plain crossed by Route 1.[130]
165.
Route 4
incorporates the portion of Route 2 that avoids the impacts of Route 1 on the Ten Section and Guthrie
Till Plain.[131]
(iv)
Fauna
166.
Because
the Project primarily follows pre-existing rights-of-way, rather than establishing
new rights-of-way, the Project will not result in substantial forest fragmentation
or isolation of habitat patches.[132]
167.
The
Project will convert some forested habitat to shrub land within its
right-of-way, but that is not anticipated to adversely impact the wildlife
population generally.[133]
168.
The
impact of the Project on wildlife species and habitat is similar between and among the various
route alternatives.[134]
169.
With
the possible exception of some mortality for less mobile species, and the
disturbance of some nest habitats, wildlife populations in the vicinity of the
existing rights-of-way would not be adversely affected by the expansion of those rights-of-way.
170.
It is
not expected that there will be impacts to aquatic species from the Project because
the lines will either span or site around water bodies.[135]
171.
Applicants
pledge to design the Project with adequate spacing between conductors to
reduce the risk of avian
electrocution.[136]
172.
Applicants
pledge to complete an Avian Protection Plan and to use flight diverters on
those portions of the Project that are located within primary flyways between breeding and foraging areas.[137]
6. Effects
upon Rare and Unique Natural Resources
173.
Species
of special concern are those plants, birds, mammals, reptiles, and
invertebrates that are identified as endangered, threatened, sensitive, or of
special concern by federal, state or tribal authorities.[138]
174.
The
habitat for 17 species of special concern has been identified along Route 1; a
comparable number in Route 2 but with fewer overall occurrences, and 23 species
of special concern in Route 3.[139]
175.
Route 4
has a comparable number of species of special concern as Routes 1 and 2.[140]
176.
None of
the routes traverse the federally-designated critical habitats for the
177.
The
Applicants maintain that among the advantages of approving a wider route,
at or near 1,000 feet wide, is the flexibility that such an authorization would
provide to avoid plant species of concern within the later-selected Project
right-of-way.[142]
178.
The
long-term impact on birds due to the conversion of forested land to shrub
land within the Project right-of-way
can be minimized by avoiding known breeding and nesting sites.[143]
179.
The Minnesota
Department of Natural Resources, the
180.
Applicants
have agreed to complete pre-construction surveys of each portion of the
selected route to identify species of special concern so that they can be
avoided in the alignment of the Project’s right-of-way and siting of the
Project’s structures. If the impacts to such species cannot be
reasonably avoided, Applicants have agreed to take prescribed steps to mitigate
the impacts of the Project.[145]
7. Application
of Various Design Options
181.
As part
of its assessment of design alternatives, the Commission considers options that could maximize energy
efficiency, mitigate adverse environmental effects and accommodate the
expansion of transmission or generating capacity in the future.[146]
182.
Although
the primary purpose of the Project is to improve long-term reliability of the
local transmission system in the
183.
As
detailed above, Applicants have also identified the specific mitigation
procedures that will be taken to address the various adverse environmental
impacts that could result from the Project.[148]
184.
A
line’s ability to transport increasing amounts of electric power – referred to
as the “line’s loading limit” – is generally constrained by the “line’s thermal
limit.” When a line exceeds a certain
length, however, its loading limit is less than the thermal limit because of
the increased impedance that is associated with longer transmission lines. The high impedance causes a drop in voltage
at modest to high power transfer levels, thus making it difficult to maintain a
steady voltage along the line.[149]
185.
Because
of its length, Route 3 reduces the Project’s loadability to approximately 75 percent of the capacity of the
shorter routes. In comparison to the
other, much shorter routes, Route 3 is far less effective in addressing the
current reliability concerns in
the
186.
The
longer length of Route 3 also adversely impacts the Project’s energy
efficiency and ability to curb system
losses. Some amount of energy
transmitted across the transmission system is lost during transport. As the length of a transmission line increases,
so does the amount of system losses over that line.[151]
Annual and 40-Year Cumulative Present Value of Loss Reductions
|
Route |
Annual Savings ($ Thousands) |
Cumulative Present Value |
||
|
Demand Savings |
Energy Savings |
Total Savings |
||
|
Route 3 |
$413 |
$3,490 |
$3,903 |
$25.7 |
|
Route 4 |
$499 |
$4,344 |
$4,843 |
$31.9 |
187.
In
comparison with Route 3, Routes 1, 2 and 4 present much greater
opportunities to realize demand and energy savings.[152]
8. Use
of Existing Transportation, Pipeline and Transmission Systems or Rights-of-Way
188.
The various
route alternatives compare favorably in the amount of existing road, pipeline or transmission
rights-of-way paralleled by the Project.
As each route alternative parallels existing rights-of-way for 90
percent or more of the length of each route, there is not a significant
difference between alternatives in this respect.[153]
189.
While
most of Route 4 runs adjacent to existing road, rail and pipeline
rights-of-way, it is not anticipated that it will share any of those
rights-of-way due to construction, operation and maintenance issues.[154]
190.
Applicants
disfavor requirements that they undertake
double circuiting of the Project line, for the following reasons:
·
Within
the Mid-Continent Area Power Pool (MAPP) region during the period 1991 – 2000,
weather-related events were the cause of more than 70 percent of the
outages of 230 kV lines; outdistancing every other cause of line disruption.
·
During this
period, weather-related outages occurred, on average, once per year for
every 100 miles of transmission lines. These
outages, on average, lasted more than one day each.
·
Failure of the common structure, for whatever
reason, results in an outage of two transmission elements.
·
Buildups
of sleet and ice on double-circuited structures placed these structures
at greater risk of failure. The increased weight and stress placed on
the conductors and the structures contributes to the failure of both circuited
lines.
·
Double circuiting involves higher construction
costs and greater impacts to ratepayers.
Double circuit construction, on average, is 1.5 times more costly than
single circuit construction.
·
Double-circuiting permits fewer, and
less-attractive, planned outage options in comparison with single circuit
designs. Adjacent transmission elements
on double circuited segments must be de-energized at the same time in order to
allow a safe approach by utility workers.
·
Double
circuited segments trigger higher maintenance costs, because specialized
equipment and training is required when working near energized
conductors.
·
The reduced
reliability of double-circuited systems places at risk residential customers
who rely upon electricity to cool and heat their homes.
·
Double-circuiting
the 230 kV and 69 kV lines that would run between Bena and Ball Club,
9. The
Costs Associated with Electrical System Reliability
191.
Because
Route 3 does not include a connection to a substation in the vicinity of
192.
The
estimated cost of constructing the Project in Route 4, Route 1, or Route 2 –
each of which is approximately 68 to 70 miles long – is between $65.4 and $66.2
million.[155]
Cost Comparison of Locating Project in Route Alternatives ($ millions)
|
Project
Component |
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
230 kV Line (including adders for
woodland/ wetland construction) |
$54.5 |
$52.8 |
$91.6 |
$55.8 |
|
Boswell Substation Expansion |
$1.0 |
$1.0 |
$1.0 |
$1.0 |
|
|
$1.5 |
$1.5 |
$1.5 |
$1.5 |
|
|
N/A |
$5.2 |
N/A |
$5.2 |
|
New |
$5.7 |
N/A |
N/A |
N/A |
|
Nary Breaker Station |
$2.7 |
$2.7 |
$2.7 |
$2.7 |
|
Total for 230 kV Line and Associated
Facilities |
$65.4 |
$65.7 |
$96.8 |
$66.2 |
193.
Each of
the shorter alternatives links the 230 kV line to a new or expanded
substation. The substations can provide
the needed voltage support to the
194.
At an estimated
cost of $114 million, the cost to construct the Project along Route 3 is 75
percent more than the cost of locating the Project along the shorter routes.[157]
10. Unavoidable
Adverse Human and Natural Environmental Effects
195.
Construction
and operation of the Project will result in long-term impacts to some soils,
forested land, wetlands, shrub land, cropland, grassland, agricultural land, and
farmland.[158]
Estimated Impacts to Resources Within 125-Foot Right-of-Way (acres)
|
Resource |
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Forested Land |
579 |
439 |
813 |
575 |
|
Soils |
3 |
3 |
5 |
3 |
|
Wetland type
Conversion |
209 |
166 |
269 |
226 |
|
Wetlands |
<1 |
<1 |
<1 |
<1 |
|
|
<1 |
<1 |
up to 1.4 |
<1 |
|
Cropland/Grassland |
<1 |
<1 |
up to 2.4 |
<1 |
|
Agricultural
Land Use |
<1 |
<1 |
2.03 |
<1 |
|
Prime
Farmland |
1.3 |
<1 |
3.6 |
<1 |
196.
These
resources would not return to separate productive uses until the transmission
line and associated facilities are removed.[159]
197.
Because
it is a combination of portions of Routes 1 and 2, Route 4 will have
long-term impacts on resources comparable to those for Routes 1 and 2.[160]
198.
It is
not expected that there will be long-term impacts to other resources identified
in the EIS beyond the Project’s 50-year lifetime.[161]
199.
The
principal impact of the Project is the low-to-moderate visual impact of a high-voltage
transmission line.[162] This
impact would be experienced by the people who live and work in the areas adjacent to the line, as well as those
who come to these communities for recreation and tourism.
11. Irreversible and
Irretrievable Commitments of Resources
200.
Construction
and operation of the Project may result in the “irreversible or irretrievable
commitment of certain resources.” As
commonly understood in this field, an irreversible resource commitment occurs
when the commitment limits the future options for a resource and an
irretrievable commitment occurs
when a resource is consumed that is neither renewable nor recoverable.[163]
201.
The
Applicants pledge to pursue preservation of archaeological and historical sites
by avoiding these sites and recovering others as part of the Programmatic
Agreement for these resources.[164]
202.
Construction
of the proposed Project would require the irretrievable commitment of some
non-recyclable building materials and fuel for construction equipment. Many components of the Proposed Project would
be recycled after their life, particularly metal components.[165]
203.
Portions
of Route 1 that are not included in Route 4 would require the irreversible or
irretrievable commitment of old growth forest, including the Ten Section area
and
K.
Evaluation of Route Alternatives:
204.
Routes
1, 2 and 4 are comparable in terms of the costs of construction and later
performance of the transmission line.
205.
Each of
the proposed alternatives will result in efficiencies and a greater reduction
in energy losses than the current system.
206.
However,
because of their much shorter lengths, Routes 1, 2 and 4 all reduce energy
losses far more than Route 3.[167]
207.
Moreover, because of their shorter length, Routes
1, 2 and 4 have fewer environmental impacts than Route 3.
208.
Among
the route alternatives, Routes 1, 2 and 4 had comparable impacts forested
wetlands, total wetlands within the right-of-way, the total acres of forested
lands that are converted and the number of public crossings.[168]
209.
Among the
four route alternatives, Route 4 is the superior choice. Route 4 best mitigates the impacts of routing
to land, adjacent residences and air quality.
210.
Importantly,
Route 4 avoids areas of
particular concern of the CNF – including the most sensitive portions of Pike
Bay Experimental Forest, the Goblin Fern study area, the canopy along the Great
Lakes pipeline, the Ten Section and Cuba Hill area of the LLBO.[169]
211.
The CNF
and LLBO have indicated a preference for Applicants’ Route because, to the
extent that the route does not avoid areas of concern altogether, the impacts
identified with the route will occur during the installation of the Enbridge
pipelines. In this respect, the impacts
that will occur in the area can be mitigated by combined restoration efforts of
the Applicants and Enbridge, as soon as their respective projects are
completed.[170]
212.
Route 4
obliges fewer and less severe impacts to residences than Routes 1, 2 and 3.[171]
Comparison of the Impacts Upon Residences
|
Environmental |
Route 1 |
Route 2 |
Route 3 |
Route 4 |
|
Residences within
ROW |
3 |
15 |
25 |
0 |
|
Residences within
62.5 to 200 feet of ROW |
23 |
54 |
102 |
15 |
|
Residences within
1000 feet of ROW[172] |
92 |
269 |
444 |
156 |
213.
The
average air emission rates per megawatt hour of energy generation, which have
been estimated by the Mid-Continent Area Power Pool (MAPP) and approved by the
Minnesota Pollution Control Agency, are shown in the table below:
MAPP Average Emission Rates
|
Emission Type |
Emission Rate |
|
SO2 |
5.537 pounds per
MWh |
|
NOx |
3.982 pounds per
MWh |
|
Particulate PM10 |
0.3257 pounds per
MWh |
|
CO2 |
0.834 metric
tonnes per MWh |
|
Mercury |
0.0000432 pounds
per MWh[173] |
214.
Routes
1, 2 and 4 have a higher total loss reduction than Route 3.
Reduction in Air Emissions
|
Route |
Line Loss Reduction (MWh/Yr.) |
SO2 Reduction (Lbs./Yr) |
NOx Reduction (Lbs./Yr.) |
PM 10 Reduction (Lbs./Yr.) |
CO2 Reduction (Metric
Tonnes/Yr.) |
Mercury Reduction (Grams/Yr.) |
|
Routes 1, 2 and 4 |
86,886 |
481,088 |
345,980 |
28,299 |
72,463 |
1,704 |
|
Route 3 |
69,800 |
386,483 |
277,944 |
22,734 |
58,213 |
1,369 |
215.
Accordingly,
the emissions reductions of SO2, NOx, PM10, CO2,
and Mercury for Routes 1, 2 and 4 are likewise greater than Route 3. The emission reductions arising from the
Project being located along Route 4 are greater than it would be if located
along Route 3.[174]
L.
Route Width:
216.
The Applicants requested a route width of 1,000
feet.[175]
217.
At the
request of the OES, following the public hearings, Applicants undertook a
series of “on-foot field inspections of the route alternatives with engineering
and construction firms.” These inspections were part of an effort to narrow the
width of the Applicants’ preferred route.[176]
Conclusions
1.
The Public Utilities Commission and Administrative
Law Judge have jurisdiction to consider the Applicants’ Application for a Route
Permit.[177]
2.
The
Commission determined that the Application was substantially complete and
accepted the Application on July 14, 2008.
3.
OES has
conducted an appropriate environmental analysis of the Project for purposes of
this route permit proceeding and the FEIS satisfies Minn. R. 7850.2500.
4.
The
FEIS addresses the issues and alternatives raised in scoping to a reasonable
extent considering the availability of information and the time limitations for
considering the permit application.
Moreover, the FEIS provides responses to the substantive comments
received during the DEIS review process and was prepared in compliance with the
procedures in Minn. R. 7850.1000 through 7850.5600.
5.
Applicants gave notice as required by Minn. Stat. § 216E.03, subd. 3a;
Minn. Stat. § 216E.03, subd. 4; Minn. R. 7850.2100, subp. 2, and Minn. R.
7850.2100, subp. 4.
6.
OES gave notice as required in Minn. Stat. § 216E.03, subd. 6; Minn. R.
7850.2300, subp. 2; Minn. R. 7850.2500, subp. 2; Minn. R. 7850.2500, subp. 7;
Minn. R. 7850.2500, subp. 8; and Minn. R. 7850.2500, subp. 9.
7.
Public
hearings were conducted in communities located along the proposed high voltage
transmission line routes. Applicants and
OES gave proper notice of the public hearings, and the public was given the
opportunity to speak at the hearings and to submit written comments. All procedural requirements for the Route
Permit have been satisfied.
8.
The evidence on the record demonstrates that Route
4 for the Project and Associated Facilities satisfies the route permit criteria
set forth in Minn. Stat. § 216E.03, subd. 7, and
9.
The
record evidence shows that Route 4 combines the best design features of Routes
1 and 2 into a single route.
10.
The evidence demonstrates that Route 4 is the best alternative on the
record for the 230 kV transmission line between Wilton Substation and Boswell
Substation.
11.
Route 4 does not present a potential for
significant adverse environmental effects pursuant to the Minnesota
Environmental Rights Act (MERA) and Minnesota Environmental Policy Act (MEPA).
12.
Double-circuiting of the Project
route is not recommended. The increased operational
risks associated with double-circuiting runs counter to the key purpose of this
Project – namely, to boost the overall reliability of the electricity system in
this service area.[178]
13.
Notwithstanding this recommendation, the Applicants assert that four
segments adjacent to Route 4 could be double circuited without significantly
impacting system reliability. Those
segments are:
·
Minnkota Power’s and Otter Tail Power’s 115 kV line
between
·
Minnkota Power’s and Otter Tail Power’s 69 kV lines
in the Bemidji/Cass Lake area;
·
Great River Energy’s 69 kV line between Bena and
Ball Club; and
·
Minnesota Power’s 115 kV line between
14.
The Commission should a grant a route permit for
the 230 kV
transmission line and associated facilities along Route 4.
15.
The Commission's final permit decision should include
a route that is, in the locations identified in the Applicants’ May 17, 2010
filing, narrower than 1,000 feet.[180]
16.
The Commission's final permit decision should include
provisions to ensure that the Applicants employ such construction and
management practices so as to avoid the displacement of homes and mitigate
impacts to the natural environment.[181]
Dated:
September 20, 2010
/s/ Eric L. Lipman
_______________________
ERIC L. LIPMAN
Administrative Law Judge
Reported:
Shaddix & Associated, transcribed (five volumes)
Under the PUC’s Rules of Practice and Procedure, Minn. R. 7829.0100 to 7829.3200, exceptions to this Report, if any, by any party adversely affected must be filed within 15 days of the mailing date hereof with the Executive Secretary of the PUC, 350 Metro Square Building, 121 Seventh Place East, St. Paul, Minnesota 55101-2147. Exceptions must be specific, relevant to the matters at issue in this proceeding, and stated and numbered separately. Proposed Findings of Fact, Conclusions, and Order should be included, and copies thereof served upon all parties.
The PUC shall make its determination on the applications for the Certificate of Need and Route Permits after expiration of the period to file Exceptions as set forth above, or after oral argument, if such is requested and had in this matter. In accordance with Minn. R. 4400.1900, the PUC shall make a final decision on the Route Permits within 60 days after receipt of this Report.
Notice is hereby given that the PUC may accept, modify, condition, or reject this
Report of the Administrative Law Judges and that this Report has no legal effect unless
expressly adopted by the PUC.
[1] Ex. 24 (Route Application) at 1-1.
[2] Ex. 29 (Lindholm Direct) at 7; see also Ex. 24 (Route Application) at 6-2
to 6-8.
[3] Ex. 29 (Lindholm Direct) at 7; see also Ex. 24 (Route Application) at 6-2
to 6-8.
[4] Ex. 29 (Lindholm Direct) at 8; see also Ex. 24 (Route Application) at 6-2
to 6-8.
[5] Ex. 23; see
also Ex. 29 (Lindholm Direct) at 9-10.
[6] Ex. 29 (Lindholm Direct) at 9.
[7] Hearing Transcript (Tr.), (Volume I), at 39-42.
[8]
[9]
[10]
[11]
[12]
[13] Tr. (Vol. I), at 66-82, 94-99.
[14]
[15]
[16]
[17] Tr. (Vol. II), at 28-31.
[18]
[19]
[20]
[21] Tr. (Vol. III), at 29-38.
[22]
[23]
[24]
[25]
[26] Tr. (Vol. III), at 57-63.
[27]
[28]
[29] Tr. (Vol. IV), at 31-35.
[30]
[31]
[32]
[33]
[34] Tr. (Vol. V), at 25-26.
[35]
[36] In the Matter of the Application
of Otter Tail Power Company,
[37]
[38] CON
Docket, Finding that Minnesota Power, Minnkota Power Cooperative, and Otter
Tail Power Company have met statutory and rule criteria for a certificate of
need and granting a certificate of need to for the 230 kV transmission line
between the Wilton and Boswell Substations (July 14, 2009).
[39] Ex. 24.
[40] Ex. 4.
[41] Ex. 6 at 1.
[42] Exs. 5, 7, and 8.
[43] Ex. 6.
[44] Ex. 10.
[45] Ex. 13.
[46] Ex. 15.
[47] Ex. 16.
[48] See, In the Matter of the Application for a
Route Permit for the Bemidji – Grand Rapids 230kV Transmission Project, Third Prehearing Orders, OAH Docket No. 8-2500-20825-2 (March 16, 2010).
[49] See, Ex.
35A (E- Docket No. 20109-54088-01) (The undersigned denominated the FEIS as
late-filed exhibits 35A through 35D).
[50] Ex. 24 (Route Application) at 6-16 to 6-17;
Ex. 29 (Lindholm Direct) at 4-5.
[51] Applicants’ Post-Hearing Response Brief
(Applicants’ Response Brief) at 4.
[52] Ex. 24 (Route Application) at 6-16; Ex. 29
(Lindholm Direct) at 5.
[53] Ex. 24 (Route Application) at 6-17; Ex. 29
(Lindholm Direct) at 5-6. A kcmil is one
thousand circular mils. A circular mil is the area of a wire one mil in
diameter.
[54] Ex. 24 (Route Application) at 6-17; Ex. 29
(Lindholm Direct) at 6; see also,
Rural Utility Service Bulletin 1724E-200 at 5-7 (the right-of-way width for a
particular line “requires the consideration of a variety of judgmental,
technical, and economic factors” in place at the time of the line’s final
design).
[55] Applicants’
Response Brief, at 11.
[56] Ex. 24 (Route Application) at 6-21; Ex. 30
(Weiers Direct) at 3.
[57] Ex. 24 (Route Application) at 6-21; Ex. 30
(Weiers Direct) at 3.
[58] Ex. 24 (Route Application) at 6-21; Ex. 30
(Weiers Direct) at 3-4.
[59] Ex. 30 (Weiers Direct) at 3-4.
[60] Ex. 24 (Route Application) at 6-21; Ex. 30 (Weiers
Direct) at 3-4.
[61] Ex. 24 (Route Application) at 6-21 to 6-22; Ex.
30 (Weiers Direct) at 4.
[62] Ex. 24 (Route Application) at 6-21 to 6-22; Ex. 30
(Weiers Direct) at 4-5.
[63] Ex. 24 (Route Application) at 6-22; Ex. 30
(Weiers Direct) at 5-8.
[64] Ex. 30 (Weiers Direct) at 6-7.
[65]
[66]
[67]
[68] Ex. 30 (Weiers Direct) at 5.
[69]
[70] Ex. 34 at 3 (Applicants’ Responses to
Information Requests from April 21-23 Evidentiary Hearings).
[71] Ex. 29 (Lindholm Direct)
at 6 and Schedule 2.
[72]
[73]
[74] Ex. 24 (Route Application) at 5-1 to 5-3.
[75] Ex. 29 (Lindholm Direct) at 9-10.
[76]
[77]
[78]
[79] Ex. 31 (Lindholm Rebuttal) at 1-2.
[80]
[81] Minn. Stat. § 216E.03, subd. 7.
[82] Minn. Stat. § 216E.03, subd. 7 (b).
[83]
[84] Ex. 35A (FEIS), Table 3.11-10 at 335;
Ex. 29 (Lindholm Direct) at Schedules 5, 6, and 7.
[85] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7, note A.
[86] Ex. 24 (Route Application) at 8.3-2 to 8.3-3.
[87] Ex. 35A (FEIS) at 66.
[88] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7; see also Ex. 35A (FEIS), Table
5-3 at 506.
[89] Ex. 35A (FEIS) at 68-72.
[90]
[91] Letter of Robert Harper,
[92] Ex. 24 (Route Application) at 8.7-2.
[93]
[94] Ex. 35A at 282.
[95] Ex. 24 (Route Application) at 8.7-2 to 8.7-3.
[96] Ex. 35A at 361-62.
[97] Ex. 24 at 8.22-3; see also Ex. 35-A
391-93.
[98]
[99] Ex. 24 (Route Application) at 6-27, 8.2-3,
and 8.24-4 to 8.24-6; Ex. 35A (FEIS) at 448-49.
[100] Tr. (Vol. III) at 30-33.
[101] Ex. 24 (Route Application) at 8.24-4 to
8.24-6; Tr. (Vol. III) at 30-31, 138-43; Tr. (Vol. IV) at 41-43.
[102] Ex. 24 (Route Application) at 8.10-2 to
8.10-3.
[103]
[104] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7.
[105]
[106] Ex. 35A (FEIS) at 417-18.
[107] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7.
[108]
[109] Ex. 35A (FEIS) 183.
[110] Ex. 24 (Route Application) at 8.26-1; Ex. 35A
(FEIS) at 438-39.
[111] Ex. 35A (FEIS) at 282 and 286.
[112]
[113] Data from Ex. 35A (FEIS),
Table 3.9-3 at 281; Ex. 29 (Lindholm Direct) at Schedules 5, 6, and 7.
[114] Ex. 35A (FEIS) at 286.
[115]
[116]
[117]
[118] Ex. 35A (FEIS) at 103-05.
[119]
[120]
[121] Ex. 29 (Lindholm Direct) at 11; Ex. 35A
(FEIS) at 122-23.
[122] Ex. 24 (Route Application) at 8.16-5 to
18.6-6.
[123] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7.
[124] Ex. 35A (FEIS), Table
3.6-4 at 161.
[125] Ex. 24 (Route Application), at 4-5 to 4-8.
[126]
[127] Ex. 35A (FEIS) at 198.
[128]
[129]
[130]
[131]
[132]
[133]
[134]
[135]
[136]
[137] Ex. 29 (Lindholm Direct) at 11.
[138] Ex. 35A (FEIS) at 220-21.
[139]
[140]
[141]
[142]
[143]
[144]
[145]
[146]
[147] Ex. 24 (Route Application) at 1-1.
[148]
[149] Ex. 30 (Weiers Direct) at 12-13, and Schedule
1.
[150]
[151]
[152]
[153] Ex. 35A (FEIS), Table ES-1 at ES-9; Ex. 29
(Lindholm Direct), Schedules 5-7.
[154] Ex. 24 (Route Application) at 8.24-1 to
8.24-6.
[155] Ex. 29 (Lindholm Direct) at Schedule 2.
[156] Ex. 30 (Weiers Direct) at 13-14.
[157]
[158] Ex. 35A (FEIS), Table 5-3 at 593.
[159]
[160] Ex. 29 (Lindholm Direct) at Schedules 5, 6,
and 7.
[161] Ex. 35A (FEIS) at 593.
[162] Ex. 24 (Route Application) at 10-1, 10-2.
[163]
[164]
[165]
[166] Ex. 35A (FEIS) at 592.
[167]
[168] Ex. 35-A at 124, 305 and 332.
[169] See, Ex. 35A at 261-62, 323 and
359-74.
[170] Ex. 29 (Lindholm Direct) Schedule 6, note D; Tr.
(Vol. III) at 121-23.
[171] See, Ex. 29 (Lindholm Direct) at 15
and Schedule 6; Ex. 35-A at 333 and 335.
[172] Ex. 35A at 335.
[173] Ex. 29 (Lindholm Direct) at 14.
[174] Ex. 35A at 104-05.
[175] Ex. 29
at 1-1.
[176] "Potential Narrowing of Applicants’
Route," In the Matter of the Application for a Route Permit for the
Bemidji-Grand Rapids 230 kV Transmission Project, (May 17, 2010) (E-Docket
No. 20105-50526-01).
[177] See, Minn.
Stat. §§ 14.57 - 14.62 and 216E.02, subd. 2.
[178] Compare,
Findings 88, 90, 182 and 185.
[179] Ex. 30 (Weiers Direct) at 8-9.
[180] "Potential Narrowing of Applicants’
Route," In the Matter of the Application for a Route Permit for the
Bemidji-Grand Rapids 230 kV Transmission Project, (May 17, 2010) (E-Docket
No. 20105-50526-01).
[181] See, Ex. 29 (Lindholm Direct) at 8.17-5
to 8.17-6 and Schedules 5, 6, and 7.