|
|
OAH Docket No. 15-2500-20665-2 PUC No. ET2/TL-09-246 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Application for a Route Permit for
the |
TABLE OF CONTENTS |
Page No.
Description of the Proposed HVTL
Preferred Route and Route Alternates
Minnesota Department of Agriculture
Minnesota Department of Transportation –
Right-of Way
Minnesota Department of Transportation –
Fuller Lake Rest Area
Minnesota Department of Transportation –
Other Concerns
Minnesota Department of Natural Resources
(DNR)
Preferred Route – Fish Lake and Fish Creek Basin
Application Of Statutory And Rule Criteria
A. Effects
on Human Settlement
B. Effects
on Public Health and Safety
C. Effects
on Land-Based Economies
D. Effects
on Archaeological and Historical Resources
E. Effects
on Natural Environment
F. Effects
on Rare and Unique Natural Resources
G. Application
of Various Design Considerations
I. Use
of Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
J. Electrical
System Reliability
K. Costs
of Constructing, Operating and Maintaining the Facility
L. Adverse
Human and Natural Environmental Effects That Cannot be Avoided
M. Irreversible
and Irretrievable Commitments of Resources
N. Consideration
of Issues Presented by State and Federal Agencies
O. Evaluation
of Additional Alternatives
Alternative
Quarry Substation Site 3
|
|
OAH Docket No. 15-2500-20665-2 PUC No. ET2/TL-09-246 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Application for a Route Permit for
the |
FINDINGS OF FACT, CONCLUSIONS AND RECOMMENDATION |
This matter was assigned to
Administrative Law Judge (ALJ) Beverly Jones Heydinger to conduct a contested
case hearing on the application by Xcel Energy and Great River Energy for a
route permit for the
A combined public and evidentiary hearing
was held on
Post-hearing submissions were filed. The record closed upon receipt of OES post-hearing comments on April 16, 2010.
Appearances: Lisa M. Agrimonti and Matthew A. Slaven, Briggs and Morgan, P.A., appeared on behalf of Applicants, Northern States Power Company (Xcel Energy) and Great River Energy. Karen Finstad Hammel, Assistant Attorney General, appeared on behalf of the Department of Commerce – Office of Energy Security, Energy Facility Permitting (OES). Bret Eknes appeared on behalf of the Commission staff.
Should the Commission issue a route permit to Applicants Xcel Energy and Great River Energy (Applicants) and if so, for which of the routes under consideration and under what conditions?
Based on information in the Route Permit Application to the Commission, the testimony at the public hearing, written comments and exhibits received in this proceeding, the ALJ makes the following:
1.
Xcel Energy is a
2.
On April 8, 2009, Applicants submitted a Route
Permit Application (RPA or Application) for a 345 kV transmission line project
between
· Construction of one 345 kV HVTL approximately 28 miles long from the existing Monticello Substation to a new Quarry Substation, west of St. Cloud, on single poles that are double-circuit compatible;
· Construction of the new Quarry Substation at Substation Site 1, 2 or 4, as identified in Exhibit 7C;
· Modifications and additions to the existing Monticello Substation to accommodate the new transmission line facilities;
· A 115 kV transmission line connector between the existing St. Cloud to Sauk River 115 kV line and the new Quarry Substation.
3.
Because the
4. The Applicants have proposed three possible routes for the transmission line – a preferred route and two alternate routes.
5. On May 13, 2009, the Commission issued an order that accepted the Application as complete and authorized OES staff to process the Application under the full review process in Minn. R. 7850.1700 to 7850.2700. The Commission also authorized OES staff to name a public advisor and to establish an advisory task force (ATF).[2]
6.
On
7.
OES staff held two public information and
scoping meetings for the Proposed Project in
8.
On September 25, 2009, the ALJ held a prehearing
conference at the Commission offices in
9.
On
10.
On
11.
On
12.
The Prehearing Order specified an intervention
deadline of
13.
On
14.
On
15.
On
16. Notices were issued for the Proposed HVTL as follows:
·
The OES published notice of the contested case
hearing in two legal newspapers of general circulation in central
· The OES sent notice of the contested case hearing to local government officials.[11]
·
The OES sent notice of the contested case to
persons on the project contact list maintained by the Commission on
17.
Description of the Proposed HVTL
18.
The Proposed Project consists of approximately
28 miles of 345 kV transmission line and associated facilities between the
existing Monticello Substation and a new substation, Quarry Substation, to be
located west of
19. The Monticello Substation will be modified to include 345 kV equipment including switches, control panels, and circuit breakers.[14]
20.
The Project includes a connection to the
existing
21.
The new Quarry Substation will require a graded,
fenced area of approximately six acres to accommodate the
22. In the Certificate of Need Order, the Commission approved Applicants’ Upsized Alternative for this Project, which includes double circuit capable structures so that a second 345 kV circuit may be added when the Commission determines that a second circuit is needed.[17]
Preferred
Route and Route Alternates
23.
In the Application, Applicants identified three
proposed routes for the 345 kV transmission line – the
24.
The
25.
Route A is approximately 32 miles long, exiting
southwest from the existing Monticello Substation until intersecting with
I-94. Route A then generally extends
northwest, paralleling I-94 for brief distances only and mainly following
CSAHs, State Highways, and city or township roads west of I-94 until it
terminates at Applicants’ proposed Quarry Substation. There are several places where
26. Route B is approximately 35 miles long, exiting southwest from the existing Monticello Substation until intersecting with an abandoned railroad corridor, which it parallels for a short distance. Route B extends generally northwest, following CSAHs, State Highways, and city or township roads west of I-94 until it terminates at Applicants’ proposed Quarry Substation. Route B parallels I-94 for less of its length than Route A. There are several places where Route B follows property lines.[21]
27.
For the
28. According to MnDOT, the permitting of the five-foot alignment would constitute an “exception” under its rules and policies and would therefore require separate approval from the Federal Highway Administration (FHWA) because the davit arms and conductors on the highway-side of each pole would result in the permanent, physical overhang of the I-94 right-of-way. The transmission structures, including the poles and davit arms, would have to be placed approximately 20 to 25 feet outside of the right-of-way to comply with MnDOT policies.[23]
29. The 25-foot alignment would not result in a permanent, physical encroachment of the I-94 right-of-way, but may still result in intermittent encroachment because of conductor “blowout” (the occupancy of right-of-way under certain weather conditions that cause the conductors to swing). MnDOT confirmed that it can issue a Utility Permit for an alignment that does not create a permanent, physical encroachment of the I-94 right-of-way under its current rules and policies and that such approval would not require FHWA to approve an exception.[24]
30. The 75-foot alignment would generally place the utility facilities far enough from the I-94 right-of-way that Applicants would not need to obtain MnDOT permits.[25]
31. Applicants propose to use single pole, galvanized or self-weathering steel, double-circuit-capable, structures for the majority of the 345 kV transmission line Project. The poles will be manufactured to support two circuits, and davit arms for both circuits, a total of six, will be built during initial construction. For the Proposed Project, however, generally only one circuit (three conductors) will be installed on three davit arms.[26]
32. At I-94 crossings and interchanges, Applicants propose to install six conductors to facilitate the addition of a second circuit when conditions warrant. Installation of six conductors initially would prevent construction-related conflicts and disruptions to highway facilities when the second circuit is added. MnDOT agrees that six conductors should be installed at interchanges to minimize future highway disruptions.[27]
33. Specialty structures, including H-frame structures and dead-end structures, may be required in certain limited circumstances, such as near environmentally sensitive areas when longer spans are required.[28]
34. Spans of 750 to 1,100 feet between structures are expected for the majority of the 345 kV line. For the 115 kV transmission line, spans of 600 to 800 feet are anticipated.[29]
35. Applicants requested a route width of up to 1,000 feet for the majority of the length of each of the proposed routes.[30]
36.
Applicants request a route of up to 1.25 miles
in width in five areas along the proposed routes to accommodate site-specific
concerns.[31] There are three areas on the
37. At a fourth location on the Preferred Route, Applicants request a route width up to 1.25 miles to work with the existing Great River Energy 115 kV transmission line and MnDOT for structure placement along or adjacent to the existing 115 kV transmission line, or along an existing road and CSAH 75.[33]
38. Applicants also request a route up to 1.25 miles in width at Quarry Substation Sites 1, 2 and 4 to allow for flexibility in substation interconnection.[34]
39. The OES submitted post-hearing comments on April 16, 2010, in which it noted its concerns regarding the requested width of the Proposed and Alternate Routes. Applicants and OES have agreed to evaluate whether the proposed route width can be narrowed and appropriate permit language drafted that would allow landowners greater certainty and predictability regarding the final alignment.[35]
40. A 150-foot wide right-of-way will be needed for the majority of the 345 kV transmission line. In some limited instances a larger 180-foot wide right-of-way may be required.[36]
41.
For the transmission line extension of the
existing
42. If the Route Permit is approved for the Preferred Route or Routes A or B, Applicants expect to begin construction of the Project in the fourth quarter of 2010 and estimate that the Project will be completed by the second quarter of 2012.[38]
43. The total cost of the Project, including the survey, engineering, materials, construction, right-of-way, and project management associated with the transmission line and substations, is estimated to be between $76.2 million and $93.5 million in 2008 dollars depending on the route selected.[39]
44.
This Project includes the modification of the
Monticello Substation and the construction of a new Quarry Substation west of
45. No additional land or access roads will be required to accommodate the modifications to the existing Monticello Substation. Equipment to be installed at the existing Monticello Substation includes switches, control panels and circuit breakers.[41]
46.
Applicants have proposed three possible
substation sites for the new Quarry Substation.
Quarry Substation Site 1 is located along the east side of Minnesota
State Highway 23 approximately one-half mile northeast of the I-94 and Highway
23 interchange. Quarry Substation 2 is
located along the north side of State Highway 23 approximately one mile
northwest of the I-94 and Highway 23 interchange. Quarry Substation 4, which Applicants
identified after submitting the Application, is located north of the
intersection of State Highway 23 and
47.
The owners of the proposed Quarry Substation
Site 2 and Site 4 properties have notified the Applicants that they are willing
to sell the sites. Applicants confirmed
that Quarry Substation Site 2 and Site 4 would provide good access to the
existing 115 kV line intersect, and good access for connection to the proposed
48. The Applicants have provided no information regarding the ownership of Quarry Substation Site 1.
49.
The Quarry Substation will be connected to the
existing 115 kV transmission line running between the
50. Equipment being installed at the new Quarry Substation during the initial phase includes a 345 kV ring bus with three circuit breakers, two 345 kV line positions, 448 MVA 345/115 kV transformer, 115 kV ring bus with three circuit breakers and two 115 kV line positions. Other equipment to be installed includes associated switches, bus work, foundations, steel structures and control equipment.[45]
51.
The substation will be configured to accommodate
the possible addition of the second circuit of the
Minnesota Department of Agriculture
52. Applicants developed an Agricultural Impact Mitigation Plan (AIMP) to address mitigation action, restoration of damaged tiles, removal of construction debris, and restoration of soil to existing preconstruction conditions. The Minnesota Department of Agriculture (MnDOA) approved the AIMP in September 2009.[47]
Minnesota Department of Transportation –
53.
A utility must obtain a MnDOT Utility Permit to
occupy highway right-of-way, including interstate right-of-way, for crossings
and longitudinal installations.
Applicants’ proposed routes require Utility Permits because they cross
or parallel highway right-of-way. The
54.
On
55. MnDOT can permit blow out within the interstate right-of-way under its existing rules and policies without seeking FHWA approval. In contrast, a permanent physical occupation of the right-of-way, including arm or conductor overhang, would require FHWA approval.[50]
56. MnDOT has stated that the requirements of the National Environmental Policy Act (NEPA) could potentially apply if FHWA approval of the Proposed Project is required.[51]
57. Each of the three proposed alignments (5-feet, 25-feet and 75-feet from the I-94 right-of-way) creates a different set of impacts. Generally, the farther away the poles are from the road right-of-way, the larger the easement that must be acquired from a landowner. Placement of poles farther from the road right-of-way generally increases the impact on agricultural and commercial operations because the poles are placed farther into adjacent landowners’ properties.[52]
Minnesota Department of Transportation –
Fuller
58.
MnDOT noted particular concern with the Fuller
Lake Rest Area, which is part of the I-94 right-of-way. MnDOT would have to grant an exception for
the transmission line to pass through the right-of-way longitudinally, and
MnDOT has indicated that it is unlikely to grant such an exception. Applicants have therefore proposed a diagonal
interstate crossing that would avoid the
59.
If Applicants are unable to follow an alignment
on the north/east side of I-94 through the Fuller Lake Rest Area or,
alternatively, an alignment on the south/west side of I-94 that would avoid the
Fuller Lake Rest Area but cross I-94 diagonally to the north/east side of I-94
to avoid Warner Lake County Park, the Preferred Route would have to proceed
around the Fuller Lake Rest Area to the north along roads that would have
greater impacts on human settlement because of the proximity of ten homes in
the area. Applicants could not follow an
alignment entirely on the south/west side of I-94 in this area without crossing
through
60. MnDOT’s policies generally discourage diagonal crossings of highways by utility facilities, but the agency could permit a diagonal crossing subject to review and approval of the specific pole and crossing locations.[55]
Minnesota Department of Transportation –
Other Concerns
61.
MnDOT intends to expand I-94 from two lanes to
three lanes of travel in each direction between
62.
MnDOT noted some concerns regarding its proposed
interregional connection between I-94 and U.S. Highway 10, which would create a
new interchange on I-94 approximately one and one-half miles east of the intersection
of I-94 and Highway 24. MnDOT’s
preferred location for the transmission line at this new interchange location
would be on the south and west side of I-94 and routed entirely outside the
“flyover ramp” in that area. As
proposed, the
63. MnDOT has not identified any specific impediments to permitting along Alternate Routes A, B, C or D.[58]
64. Each of the proposed Quarry Substation sites is far enough from highway right-of-way that it would not require a MnDOT permit.[59]
Minnesota Department of Natural Resources
(DNR)
65.
The DNR provided written comments in response to
the DEIS on February 26, 2010. It
provided supplemental comments on March 19, 2010, in response to items
discussed at the March 8, 2010, public hearing.
The DNR expressed concerns with potential environmental impacts of the
proposed Project, particularly with respect to the two
66.
In its comments to the DEIS, the DNR noted that
it does not favor Route D because it requires two line crossings of the
67.
The DNR further noted that the Route D
Mississippi River crossings may visually impact the Mississippi River, which is
designated as a Scenic River District between
68.
The DNR noted that if the segment of
transmission line from
69.
The DNR also noted that much public concern has
been generated by the proposed crossing of the
70.
The DNR commented that any route would likely
impact the trumpeter swans and Blanding’s turtles found near the
71.
72. The scoping process is the first step in developing an environmental impact statement. OES “shall provide the public with an opportunity to participate in the development of the scope of the environmental impact statement by holding a public meeting and by soliciting public comments.” During the scoping process, alternative routes may be suggested for evaluation in the EIS.[67]
73. The scoping process “must be used to reduce the scope and bulk of an environmental impact statement by identifying the potentially significant issues and alternatives requiring analysis and establishing the detail into which the issues will be analyzed.”[68]
74. At the conclusion of the scoping process, OES must issue a scoping decision which shall address at least the following: 1) the issues to be addressed in the environmental impact statement; 2) the alternative sites and routes to be addressed in the environmental impact statement; and 3) the schedule for completion of the environmental impact statement.[69]
75. For this Project, OES staff collected and reviewed comments on the scope of the EIS by holding two Scoping Meetings and convening an ATF. The OES also accepted written comments through July 24, 2009, and a total of 64 comments were received by the close of the comment period.[70]
76. The ATF recommended four additional route alternatives and two alternate substation locations.[71]
77. On October 12, 2009, OES issued its Scoping Decision for the EIS. The Scoping Decision identified the topics to be covered in the Project EIS: regulatory framework; Project engineering and design; Project construction; and human and environmental resources impacted by the Project and each proposed route alternative. The Scoping Decision also determined that the EIS would address two of the ATF proposed route alternatives and one of the ATF alternate substation locations.[72]
78. On January 11, 2010, OES published the DEIS which included a discussion of all of the alternatives and topics required by the Scoping Decision.[73]
79. On February 9, 2010, OES held two informational meetings for the public to comment on the DEIS. The OES also accepted written comments through February 26, 2010.[74]
80.
81. A total of 47 respondents commented on the DEIS during the comment period. OES extracted 179 separate, substantive comments that are addressed at Section 2.0 of the FEIS.[76]
82. On March 26, 2010, OES published the FEIS.
83. A number of interested parties submitted comments in this proceeding. The ALJ received more than 50 written comments and 44 persons submitted oral comments and 45 written exhibits at the public hearing on March 8, 2010. The comments fall into general areas, summarized below.
84.
Many people voiced support for the
85.
The City of
86. Although the City did not mention the Alternative Routes, it appears from the maps that Routes A, B, and C would each affect the Annexation Area along Highway 24, as much, if not more than, the Preferred Route.
Preferred
Route –
87.
The ALJ received numerous comments that
expressing concern that the
88.
Ronald Schabel also voiced concern regarding the
89.
Karen Durant commented regarding the
environmental sensitivities of
90.
John Pazik noted that the
91.
The ALJ received many comments regarding Route
D. A few commenters supported Route
D. The Mississippi River Parkway
Commission and Wright County Soil and Water District support the use of Route
D.[85] The Mississippi River Parkway Commission
stated that the
92.
The Wright County Office of Planning and Zoning
supports the use of Route D or the
93.
Some commenters supported Route D because it
would reduce or eliminate any negative impact to the
94.
Many people opposed Alternative Route D. The ALJ received numerous comments in
opposition to Route D because the route would require two
95.
Lynn Waytashek of the Sherburne County Zoning
Office opposed Route D because it passes through the Wild and Scenic River
District. She stated that
96.
Some people opposed Route D because it would
pass through or near several parks.
Roger Neils commented that Route D would parallel
97.
Some people commented that Route D would not
promote electrical system reliability.
Jeff Schlingmann commented that the concentration of transmission lines
serving the
98.
A number of people who live along Route D
opposed the use of Route D because it would be unfair if another transmission
line ran over or near their properties.
They stated that they should not have to bear the burden of hosting all
the transmission lines serving the
99.
The City of
100. Many
people commented that proposed Route D would severely limit farming activity.[101] According to
101. Alan
Peterson, President of the Irrigator’s Association of Minnesota, stated that
irrigated land allows farmers to produce specialty crops, which often require
aerial spraying, but that it is difficult to maneuver aerial spray helicopters
or fixed wing aircraft around transmission lines and structures. He stated that irrigation is necessary to
sustain agriculture in the
102. Bud Stimmler opposed Alternative Route D because it would interfere with the pioneer burial site that is located near the existing 115 kV line.[106]
103. Michael D. Aune, Director of Facilities at Ziegler, opposed Route D because it would traverse Ziegler’s place of business. Ziegler sells, rents and services large, high-reaching construction equipment such as aerial lift booms capable of reaching a height of 135 feet. Power lines over or near the Ziegler property would jeopardize employees’ safety.[107]
104. The
ALJ received numerous comments expressing concerns with the potential aesthetic
impact to the
105. Richard
Phipps noted that the national scenic byway was developed in 1938. It is overseen by the Mississippi River
Parkway Commission. The State of
106. The Mississippi River Parkway Commission of Minnesota requested that decision makers utilize strategies to avoid, minimize and mitigate any impact to the Great River Road and Mississippi River corridors and exercise due diligence to assess potential impacts to the Great River Road.[110]
107. Some members of the public commented that they believed the EIS process was flawed. Carlos Lopez, on behalf of the Fish Lake Property Owners Association, stated that the DEIS public meeting was inadequate because there were no sign-in sheets, no maps, no displays, and only two copies of the DEIS for fifty people. He stated that the scoping phase was presented to the public and governmental agencies to gather input and ideas but that it seemed the scope was predetermined and that their comments were largely ignored.[111]
108. The
ALJ received comments from Sherburne County, the City of Becker, Becker
Township, Clear Lake Township and Haven Township expressing disappointment with
the Task Force process and lack of notice provided to local governmental units
on the east side of the Mississippi River.[112] State Senator Lisa Fobbe commented on behalf
of her constituents in
109.
110. The ALJ received numerous comments regarding the potential health effects of electric and magnetic fields.[115] Carol Overland and Richard Phipps commented that the electromagnetic fields were underestimated in the EIS.[116]
111. The
ALJ received some comments from those who objected to the
112. A number of people commented that the travelers who stop briefly at the Fuller Lake Rest Area should not be given the same consideration as the residents in the area. The travelers will view the transmission lines for only a short time, but the lines will be a permanent fixture for the residents.[118]
113. A number of people opposed Routes A and B because they did not want the transmission line near their homes or farms.[119]
114. One
party observed that Route A and Route B appear to cross or parallel
115. Eugene Smith opposed Route B but supported Route A. He stated that he has over 200 acres of irrigated land, but that production on that land has been disrupted twice in the last five years, once because of the construction of a power line that was constructed along County Road 104.[121]
116. The ALJ received comments that the transmission line should be placed underground at river crossings and other environmentally sensitive locations.[122]
117. The Power Plant Siting Act (PPSA) requires that route permit determinations “be guided by the state’s goals to conserve resources, minimize environmental impacts, minimize human settlement and other land use conflicts, and ensure the state’s electric energy security through efficient, cost-effective power supply and electric transmission infrastructure.”[123]
118. Under the PPSA, the Commission and ALJ must be guided by the following responsibilities, procedures and considerations:
(1) evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;
(2) environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;
(3) evaluation of the effects of new electric power generation and transmission technologies and systems related to power plants designed to minimize adverse environmental effects;
(4) evaluation of the potential for beneficial uses of waste energy from proposed large electric power generating plants;[124]
(5) analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;
(6) evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted;
(7) evaluation of alternatives to the Applicants’ proposed site or route proposed pursuant to Section 216E.03, subdivisions 1 and 2;
(8) evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way;
(9) evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;
(10) evaluation of future needs for additional high voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;
(11) evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and
(12) when appropriate, consideration of problems raised by other state and federal agencies and local entities.[125]
119. In addition to the PPSA, Minn. R. 7850.4000 provides that no route permit may be issued in violation of site selection criteria and standards found in Minnesota Statutes or Public Utilities Commission Rules. Power line permits must be consistent with state goals to minimize environmental impacts and conflicts with human settlement and other land use. The Commission and ALJ are governed by Minn. R. 7850.4100, which provides for the following factors to be considered when determining whether to issue a route permit for a high voltage transmission line:
A. effects on human settlement, including, but not limited to, displacement, noise, aesthetics, cultural values, recreation, and public services;
B. effects on public health and safety;
C. effects on land-based economies, including, but not limited to, agriculture, forestry, tourism, and mining;
D. effects on archaeological and historic resources;
E. effects on the natural environment, including effects on air and water quality resources and flora and fauna;
F. effects on rare and unique natural resources;
G. application of design options that maximize energy efficiencies, mitigate adverse environmental effects, and could accommodate expansion of transmission or generating capacity;
H. use or paralleling of existing rights-of-way, survey lines, natural division
lines, and agricultural field boundaries;
J. use of existing transportation, pipeline, and electrical transmission systems or rights-of-way;
K. electrical system reliability;
L. costs of constructing, operating, and maintaining the facility which are dependent on design and route;
M. adverse human and natural environmental effects which cannot be avoided; and
N. irreversible and irretrievable commitments of resources.[127]
120. There is sufficient evidence in the record for the ALJ to assess the proposed routes and alternatives using the criteria set out above.
Application Of Statutory And Rule Criteria
A. Effects on Human
Settlement
121.
122. The Applicants have provided information on alignments at varying distances outside the MnDOT right-of-way. Thus, a “5-foot alignment” is 5 feet outside the MnDOT right-of-way.
123. For purposes of this proceeding, displacement of a residence or business was defined to occur when a structure is within 75 feet of a proposed alignment.[129]
124. The
construction of the 345 kV line along the
125. The
Applicants will use a 150-foot right-of-way; 75 feet on either side of the
alignment. For the
126. For
the
127. For
the
128. For
the
129. For Route A’s 5-foot alignment, there are 0 homes within 75 feet from the alignment; 21 homes are within 75-150 feet from the alignment; 38 homes are within 150-300 feet of the alignment; and 26 homes are within 300-500 feet from the alignment. In total, 85 homes are within 500 feet of the alignment.[135]
130. For Route A’s 25-foot alignment, there are 0 homes within 75 feet from the alignment; 21 homes are within 75-150 feet from the alignment; 39 homes are within 150-300 feet of the alignment; and 26 homes are within 300-500 feet from the alignment. In total, 86 homes are within 500 feet of the alignment.[136]
131. For Route A’s 75-foot alignment, there are 0 homes within 75 feet from the alignment; 22 homes are within 75-150 feet from the alignment; 43 homes are within 150-300 feet of the alignment; and 30 homes are within 300-500 feet from the alignment. In total, 95 homes are within 0-500 feet of the alignment.[137]
132. For Route A’s 5-foot alignment, there are 15 non-residential structures within the right-of-way. For Route A’s 25-foot alignment, there are 5 non-residential structures within the right-of-way. For Route A’s 75-foot alignment, there are 8 nonresidential structures within the right-of-way.[138]
133. For Route B, there are 0 homes within 75 feet from the alignment; 30 homes are 75-150 feet from the alignment; 51 homes are 150-300 feet from the alignment; and 39 homes are 300-500 feet from the alignment. In total, 120 homes are within 500 feet from the alignment.[139]
134.
For Route B,
there are 4 non-residential structures within the right-of-way.[140]
Summary of Residential and Non-Residential Structures
|
Route/ Alignment |
Homes Within 0 to 75’ of Alignment |
Homes Within 75 to 150’ of
Alignment |
Homes Within 150 to 300’ of Alignment |
Homes Within 300 to 500’ of Alignment |
Homes Within 0 to 500’ of Alignment |
Number of
Non-Residential Structures Within Right-of-Way |
Preferred Route
|
5-Foot
Alignment |
0 |
3 |
22 |
37 |
62 |
22 |
|
25-Foot
Alignment |
0 |
5 |
22 |
36 |
63 |
12 |
|
75-Foot
Alignment |
0 |
5 |
30 |
31 |
66 |
12 |
Route A
|
5-Foot
Alignment |
0 |
21 |
38 |
26 |
85 |
15 |
|
25-Foot
Alignment |
0 |
21 |
39 |
26 |
86 |
5 |
|
75-Foot
Alignment |
0 |
22 |
43 |
30 |
95 |
8 |
Route B
|
|
0 |
30 |
51 |
39 |
120 |
4 |
135. The
136. Alternate
Routes A, B or C could affect the City of
137. The MPCA has established standards for the regulation of noise levels. For residential, commercial and industrial land, the MPCA noise limits are 60-65 A-weighted decibel (dBA) during the day and 50-55 dBA during the night.[142]
138. The audible noise levels for the proposed transmission line are not predicted to exceed the MPCA Noise Limits outside the right-of-way.[143]
139. Construction
of the facilities along the
140. The
aesthetic impacts differ among the
141. The
142. The
Applicants evaluated route and alignment alternatives to avoid the
143. Where
feasible, the proposed alignment along the north/east side of I-94 locates the
transmission line on the south/west side of CSAH 75 between I-94 and the
144. The
145. Opponents of the Preferred Route and Route A stated concerns about the potential for the Great River Road’s loss of designation as a National Scenic Byway but no scenic byway has ever been involuntarily delisted.[150]
146. The
147. Mitigation
measures may be employed to minimize the visual impacts of utility facilities
near the
148. MnDOT
does not have jurisdiction over the
149. The
150. The communities in the vicinity of the Project value their pioneer roots, the history of their settlement, and their predominately agricultural economy. Manufacturing, retail, and service industries are also a commercial strength in the region.[154]
151. The proposed transmission lines are intended to serve the region with a stable power supply without compromising the area’s cultural values. The proposed Project should not impact the cultural values of the nearby communities, regardless of the route selected.
152. Recreational
resources near the
153. There
are two Scientific and Natural Areas (SNAs) within one mile of the
154. There are two SNAs and one WMA but no WPAs within one mile of Route A. There are two SNAs and one WMA but no WPAs within one mile of Route B.[157]
155. The
156. Construction or operation of the Project along any route is not expected to impact the operation of any existing public services in the vicinity of the Project area.[158]
157. The Proposed HVTL will not impact public services, regardless of which route is chosen.
B. Effects on Public Health
and Safety
158. The Commission must consider effects of the Proposed HVTL on public health and safety.[159]
159. The maximum electric field associated with Applicants’ proposal, measured at one meter above the ground, is calculated to be 3.76 kV/m.[160] The Commission has imposed a maximum electric field limit of 8 kV/m measured at one meter above the ground.[161]
160. The highest projected magnetic field level during peak operation at the edge of the right-of-way is 23.79 mG. These levels are considerably less than one percent of the recommended exposure guidelines.[162]
161. There is no indication that any significant impact on human health and safety from EMFs will arise from the Proposed HVTL, regardless of which route is chosen.
162. Applicants will ensure that all safety requirements are met during the construction and operation of the proposed transmission line and associated facilities. The Project will be designed and constructed according to local, State and National Electric Safety Code (NESC) standards regarding ground clearance, crossing utilities clearance, building clearance, strength of materials, and right-of-way widths.[163]
163. The proposed transmission lines will be equipped with protective devices breakers and relays to safeguard the public in the event of an accident or if the structure or conductor falls to the ground.[164]
164. Applicants’ Proposed HVTL design and construction will comply with all applicable standards to minimize the possibility of human safety hazards.
C. Effects on Land-Based
Economies
165. The Commission must consider the effect of the Project on land-based economies, including agriculture, forestry, tourism and mining.[165]
166. The Project will have permanent and temporary impacts on farmland. Structure placement along the route centerline will have a permanent impact, affecting 1,000 square feet per pole.[166]
167. There will be a temporary impact, such as soil compaction and crop damage, during construction. Applicants estimate that the temporary impact in agricultural fields will be one acre per pole. MNDOA and Applicants developed an AIMP to address the temporary impact to farmland caused during construction.[167]
168. The
169. Route A’s 5-foot alignment will permanently impact 235,000 square feet (5.40 acres) and temporarily impact 235 acres of farmland. Route A’s 25-foot alignment will permanently impact 238,000 square feet (5.47 acres) and temporarily impact 238 acres of farmland. Route A’s 75-foot alignment would permanently impact 237,000 (5.44 acres) square feet and temporarily impact 237 acres of farmland.[169]
170. Route B would permanently impact 254,000 square feet (5.84 acres) and temporarily impact 254 acres of farmland.[170]
171. The Project is not expected to impact any economically important forestry resources.[171]
172. The
Project is not expected to impact tourism.
Potential impact to the
173. Mining
resources have been identified along the
174. There
are two aggregate mines located within .25 miles of the
175. There
are four aggregate mines located within .25 miles of Route A. Two of the mines are the same ones located
within .25 miles of the
176. There are three aggregate mines located within .25 miles of Route B. One of these is an inactive pit and the other two are prospected pits.[175]
D. Effects on Archaeological
and Historical Resources
177. The Commission must consider the proposed route’s effect on archaeological and historic resources.[176]
178. Based
on the
179. Based on Route A’s 5-foot alignment, there are three known archaeological sites and four known historic sites within 500 feet of the alignment. Based on Route A’s 25-foot alignment, there are three known archaeological sites and four known historic sites within 500 feet of the alignment. Based on Route A’s 75-foot alignment, there are two known archaeological sites and four known historic sites within 500 feet of the alignment.[178]
180. For Route B, there is one known archaeological site and two known historic sites within 500 feet of the alignment.[179]
181. There
are a greater number of known archaeological sites associated with the
182. The Proposed HVTL is not expected to have a significant impact on archaeological and historic resources. In the event an impact occurs, Applicants will determine, in consultation with the State Historic Preservation Officer (SHPO), whether the resource is eligible for listing in the National Register of Historic Places.[181]
183. Route B has the potential to affect the fewest number of known historic sites.[182]
E. Effects on Natural
Environment
184. The Commission is required to consider the proposed route’s effect on the natural environment, including effects on air and water quality resources and flora and fauna.[183]
185. During construction, construction vehicle emissions and dust created by right-of-way clearing will have a temporary impact on air quality. The operation of the Project will not cause any long-term impact to air quality.[184]
186. Numerous surface water resources including lakes, rivers, streams, wetlands and floodplains will be crossed by or located in the right-of-way of the proposed routes.[185]
187. Sedimentation could reach these surface waters during construction because of ground disturbance caused by excavation, grading, construction traffic, and dewatering of holes drilled for transmission structures. Water quality could be temporarily degraded because of turbidity. Applicants will avoid and minimize these impacts using appropriate sediment control practices and construction practices.[186]
188. Using
the 5-foot alignment, there are 59 acres of wetlands within the
189. The
Applicants estimate that the
190. The
DNR noted that much public concern has been generated by the proposed crossing
of the
191.
192. Of
the routes under consideration, only the
193. One
option to minimize impacts to
194. Applicants will try to avoid disturbance of individual wetlands and drainage systems during construction by spanning wetlands and drainage systems where possible. There will be a permanent impact on wetlands where structures must be located within wetland boundaries. Permanent structure placement will result in approximately 55 square feet of wetland loss per standard single-pole structure. The temporary impact to wetlands will be about 20 feet in width per span across a wetland. The Applicants will attempt to use appropriate sediment control and construction practices to minimize temporarily degrading water quality during construction. Once the Project is completed, there will be no significant impact on surface water quality because wetland impact will be minimized and mitigated, disturbed soil will be restored to previous conditions or better, and the amount of land area converted to an impervious surface will be small.[193]
195. The
196. The
197. The
198. 201. Route A’s 5-foot alignment will permanently impact approximately 1,045 square feet of wetlands, temporarily impact 5.8 acres of wetlands, impact three acres of forested wetlands, cross 14 streams, and have no permanent structure impact on FEMA-designated floodplains.[197]
199. Route A’s 25-foot alignment will permanently impact approximately 1,100 square feet of wetlands, temporarily impact 5.9 acres of wetlands, impact three acres of forested wetlands, cross 14 streams, and have no permanent structure impact on FEMA-designated floodplains.[198]
200. Route A’s 75-foot alignment will permanently impact approximately 990 square feet of wetlands, temporarily impact 5.7 acres of wetlands, impact three acres of forested wetlands, cross 14 streams, and have no permanent structure impact on FEMA-designated floodplains.[199]
201. Route B will permanently impact approximately 1,320 square feet of wetlands, temporarily impact 7.3 acres of wetlands, impact approximately three acres of forested wetlands, cross 15 streams, and have no permanent structure impact on FEMA-designated floodplains.[200]
202. Several
commenting parties raised concerns regarding the
203. Within the Preferred Route, the Applicants intend to place the poles as close to CSAH 75 as possible in areas that are already disturbed, thereby mitigating to the greatest extent possible impact on any wetlands in this area. In addition, Applicants confirmed that the potential impact is limited to the placement of the 55-square-foot concrete base for each utility pole. Operation of the aerial transmission lines will not affect the wetlands or water quality.[202]
204. The
Applicants’ alignment would also place the transmission line behind a natural
tree line that has grown up along an abandoned elevated rail bed, which would
provide a natural visual buffer from the oxbow of the
205. Design and construction techniques can be employed to minimize silting and runoff during construction and to minimize wetland impact through efforts to span the wetlands and place pole foundations in previously disturbed areas to the extent possible.[204]
206. OES
confirmed during the evidentiary hearing that it had not identified any
environmental impediments that would prevent an alignment from being placed
within the Applicants’
207. MnDOT
also confirmed that it does not foresee any impediment to permitting an
alignment within the Applicants’
208. The
209. Flora throughout most of the Project area is typical of that found in an agricultural setting. The Project is not anticipated to substantially disrupt vegetative community quality or function. Transmission lines will span areas containing native communities wherever possible. Applicants will work with DNR and USFWS to avoid and minimize the direct impact to habitat and conservation areas.[207]
210. There will be a temporary impact on flora at the structure locations where borings will take place and spoils will be stored. The temporary impact is estimated at one acre per span. The permanent impact is estimated at 55 square feet per pole.[208]
211. Staging areas and stringing areas will temporarily impact flora across the route. Grading could occur at the staging areas if they are not located in previously disturbed sites. In forested areas, these will be cleared for access roads and staging areas only as necessary to permit the passage of equipment. Temporary access roads will be removed and the area restored to its original condition following construction.[209]
212. There will be permanent vegetative changes in woodland areas within the right-of-way. Trees and shrubs that may interfere with maintenance and the safe operation of the transmission line will not be allowed to establish within the right-of-way. Following existing corridors through wooded areas will reduce the impact on trees and habitats they support. Vegetation is controlled mechanically or with herbicides on a regular maintenance schedule. Vegetation that does not interfere with the safe operation of the transmission line is allowed to reestablish within the right-of-way after construction.[210]
213. Applicants will work with the DNR and USFWS to avoid or minimize impact on sensitive flora along the route and will avoid and minimize impact on any areas known to contain native vegetation. DNR commented that the tubercled rein-orchid, a state-listed endangered plant, has been documented in the vicinity of the proposed Project. Once the final route is selected, Applicants can coordinate with DNR to identify the presence of tubercled rein-orchid and minimize impact to its habitat.[211]
214. Areas disturbed due to construction activities are to be restored to pre-construction contours and will be reseeded with a seed mix that is certified to be free of noxious weeds, as recommended by local DNR management.[212]
215. There
are no sections of the Preferred Route or Route A that cross WPAs, United
States Fish and Wildlife Service (USFWS) easements, NWRs or WMA lands. Regardless of the selected alignment, the
216. Route
B does not cross any WPAs, USFWS easements, or NWRs, but Route B does cross a small
section of Hoglund WMA in
217. The
218. Wildlife throughout the Project area consists of birds, mammals, fish, reptiles, amphibians, mussels, and insects, both resident and migratory, which use the area for forage, shelter, breeding, or stopover during migration.[215]
219. Throughout the Project area, there are several areas where high-quality wildlife habitat occurs naturally or is being managed.[216]
220. There is potential for the temporary displacement of wildlife and loss of habitat during construction of the Project. It is likely that affected species would only be displaced a short distance since there is similar habitat close by.[217]
221. Permanent impact to wildlife could take place at new Quarry Substation locations.[218]
222. To mitigate possible impact to wildlife, Applicants intend to span designated habitat or conservation areas wherever feasible. In areas where complete spanning is not possible, Applicants will minimize the number of structures placed in high quality wildlife habitat and will work with the DNR and USFWS to determine appropriate mitigation.[219]
223. The Project will be constructed in a manner to minimize potential risk to avian species. Applicants will avoid areas known as major flyways or migratory resting spots. Raptors, waterfowl and other birds may be affected by the construction and placement of the transmission line. Avian collisions are a possibility but typically because of the large size of conductors associated with the transmission lines compared to distribution lines, transmission line conductors are more visible. The Applicants will address avian issues at waterbody crossings and other areas of concern by working with the DNR and USFWS to identify any areas that may require marking transmission line shield wires with bird flight diverters or using alternate structures to reduce the likelihood of collision and electrocution.[220]
224. In 2002, Xcel Energy entered into a Memorandum of Understanding with the USFWS to address avian issues.[221]
225. The
Preferred Route, Route A and Route B will have a similar impact to fauna, but
the Preferred Route, which is the shortest route, will likely have the least
impact. By avoiding a
F. Effects on Rare and
Unique Natural Resources
226. The Commission must consider the proposed routes’ effect on rare and unique natural resources.[222]
227. Many
of the threatened and endangered species identified in the Project area are
associated with wetlands and other habitats associated with water
resources. River species of mussels are
encountered in major rivers within the one-mile buffer, particularly the
228. Applicants will span rivers, streams and wetlands where it is possible. Wherever it is not feasible to span, Applicants will conduct a survey to determine the presence of special status species or suitability of habitat for such species and coordinate with the appropriate agencies to avoid and minimize any impact.[224]
229. A
total of 10 different threatened and endangered species were recorded within
one mile of the
230. A total of 11 threatened and endangered species were recorded within one mile of Route A.[226]
231. A total of 11 threatened and endangered species were recorded within one mile of Route B.[227]
232. The
G. Application of Various Design
Considerations
233. The Commission must consider the Project’s applied design options that maximize energy efficiency, mitigate adverse environmental effects, and accommodate expansion of transmission or generating capacity.[228]
234. The entire length of the 345 kV transmission line will be constructed with double circuit capable poles so a second circuit can be strung if expansion is approved by the Commission. This will allow for maximizing the use of existing right-of-way and minimizing the construction time for a new circuit when circumstances merit expansion.[229]
235. The Applicants also propose to install six conductors at interstate crossings and interchanges to facilitate the addition of a second circuit. The six conductors will be tied together in pairs and will act as a single circuit until addition of a second circuit is approved. Installation of six conductors during initial construction will avoid construction-related conflicts and disruptions to highway facilities at the time the second circuit is added.[230]
236. The Applicants plan to acquire at least 40 acres for the new Quarry Substation to create a buffer around the substation and to provide for future expansion.[231]
237. The
new Quarry Substation will be configured to accommodate a second circuit, the
future addition of the
238. The
Project along the
H. Use
or Paralleling of Existing Right-of-Way, Survey Lines, Natural Division Lines
and Agricultural Field Boundaries
239. The Commission is required to consider the proposed routes’ use or paralleling of existing rights-of-way, survey lines, natural division lines, and agricultural field boundaries.[233]
240. Approximately
97 percent of the Preferred Route, at the 5-foot or 25-foot alignments and 96
percent at the 75-foot alignment, uses or parallels existing right-of-way,
survey lines, natural division lines, or agricultural field lines. Approximately 320 acres of new right-of-way
would be required for the
241. Approximately
94 percent of Route A, regardless of which alignment, uses or parallels
existing right-of-way, survey lines, natural division lines, or agricultural
field lines. Approximately 406 acres of
new right-of-way would be required for
242. Approximately 94 percent of Route B uses or parallels existing right-of-way, survey lines, natural division lines, or agricultural field lines. Approximately 458 acres of new right-of-way would be required for Route B.[236]
243. The
I. Use
of Existing Transportation, Pipeline, and Electrical Transmission System
Right-of-Way
244. The Commission must consider the proposed routes’ use of existing transportation, pipeline and electrical transmission system right-of-way.[237]
245. Approximately
83 percent of the
246. Approximately 70 percent of Route A’s 5-foot alignment follows existing transportation, pipeline and electrical transmission system ROWs. Approximately 70 percent of Route A’s 25-foot alignment follows existing transportation, pipeline and electrical transmission system ROWs. Approximately 50 percent of Route A’s 75-foot alignment follows existing transportation, pipeline and electrical transmission system ROWs.[239]
247. Approximately 60 percent of Route B follows existing transportation, pipeline and electrical transmission system ROWs.[240]
248. The
J. Electrical System
Reliability
249. The Commission is required to consider the Project’s impact on electrical system reliability.[241]
250. The
Project is proposed to be constructed with double-circuit-capable
structures. The
K. Costs of Constructing,
Operating and Maintaining the Facility
251. The Commission is required to consider each proposed route’s cost of construction, operation and maintenance.[242]
252. Construction
of the Project along the approximately 28-mile
253. Construction of the Project along Route A, which is approximately 32 miles in length, is estimated to cost $87.4 million to construct and $300 to $500 per mile to operate and maintain.[244]
254. Construction of the Project along Route B, which is approximately 35 miles in length, is estimated to cost $93.5 million to construct and $300 to $500 per mile to operate and maintain.[245]
255. The
L. Adverse
Human and Natural Environmental Effects That Cannot be Avoided
256. The Commission is required to consider the adverse human and natural environmental effects that cannot be avoided, for each proposed route.[246]
257. Unavoidable adverse impacts include the physical impact on the land, primarily agricultural land, due to the construction of the Project.[247]
258. For
the
259. For Route A, approximately 235,000 square feet of permanent agricultural land impact is anticipated for the 5-foot alignment; approximately 238,000 square feet of permanent agricultural land impact is anticipated for the 25-foot alignment; and approximately 237,000 square feet of permanent agricultural land impact is anticipated for the 75-foot alignment.[249]
260. Approximately 254,000 square feet of permanent agricultural land impact is anticipated for Route B.[250] There will also be a temporary impact, such as soil compaction and crop damage, during construction. The damage is estimated to effect one acre per pole.[251]
261. The
M. Irreversible and
Irretrievable Commitments of Resources
262. The Commission must consider the irreversible and irretrievable commitments of resources that are necessary for each proposed route.[252]
263. There are few commitments of resources associated with this Project that are irreversible and irretrievable, but those few resources primarily relate to construction of the Project. Only construction resources, such as concrete, steel and hydrocarbon fuels, will be irreversibly and irretrievably committed to this Project. The irretrievable resources for the Project are the same, regardless of which route or substation site is chosen.[253]
264. The
N. Consideration of Issues
Presented by State and Federal Agencies
265. The Commission must consider issues raised by state and federal agencies when appropriate.[254]
266. MnDOT has stated a number of concerns with the proposed routes. Applicants must obtain a MnDOT permit for each location where the proposed transmission lines cross or occupy trunk highway right-of-way. Longitudinal installations that parallel I-94 right-of-way also require separate FHWA approval in those locations where there is permanent physical encroachment. MnDOT confirmed that FHWA concurrence is not required where there will be only the potential for intermittent encroachment from conductor blow-out. Applicants’ proposed 25-foot alignment is intended to avoid permanent physical occupation of the I-94 right-of-way.[255]
267. Some members of the public questioned the relative impact of the transmission line to travelers briefly stopping at the Rest Area as compared to the aesthetic effect on those who live or work near them. Their view was that less consideration should be given to the travelers’ sensibilities. [256]
268. It is not clear whether the transmission line could cross the rest area in a safe location where the only concern with placement is aesthetic.
269. MnDOT
has confirmed that the
O. Evaluation of Additional
Alternatives
270. The Commission must consider alternatives to the proposed route.[258]
271. In the draft EIS, the OES studied and one segment alternative to Applicants’ proposed route Alternate B, one route alternative and one Quarry Substation site alternative. These alternatives are referred to as Route C, Route D, and Quarry Substation Site 3, respectively.[259]
272. Route
C is the same as Applicants’ proposed Route B with one segment
modification. Route C, which is
approximately 30 miles long, commences at the Applicants’ Route B in
273. Applicants estimate Project costs for construction along Route C at approximately $65.5 million.[261]
274. Construction
along Route C would have greater impacts to residences than the
275. Route C would permanently and temporarily impact agricultural lands but no measurable impact would occur on prime farmlands. The proposed 150-foot right-of-way would impact six center-pivot irrigation systems.[263]
276. Under
the Route C option, no impact to forested areas or economically important
forestry would occur.
277. Aesthetic
resources and potential impacts associated with Route C are the same as Route B
except at the eastern end of the route in
278. Route
C’s impact on recreation is similar to that of Route B. One WMA would be impacted by the
right-of-way. Route C also encompasses a
parcel of land owned by the DNR on the south side of
279. Route C impacts no facilities open to public use.[267]
280. No archaeological or historic facility resources have been found within 500 feet of the centerline of Route C.[268]
281. A total of 12 state-protected species have been identified within one mile of Route C – one state-listed endangered species, three state-listed threatened species, and eight different species of special concern. No critical habitat occurs within one mile of the route.[269]
282. Route
C requires two more crossings of Public Waters Inventory (“PWI”) streams (both
crossings of Johnson Creek) than the
283. Route
C crosses fewer wetland acres than the
284. Route C’s impact on flora would be the same as the impact for Route B. A total of six MCBS sites of biodiversity significance would be crossed by the route.[272]
285. Route
C’s impact on air and water quality would be the same as the impact for the
286. There was no public support for Route C.
287. Route
D is a route alternative from the Monticello Substation to the new Quarry Substation
site and is also approximately 30 miles long.
It exits the Monticello Substation adjacent to an existing 115 kV line
and crosses the
288. The
289. Route D continues to parallel the existing 115 kV transmission line and road right-of-way for approximately 15 miles where it turns southwesterly and crosses the Mississippi River for a second time in an area designated as a Scenic River District and then generally follows the Preferred Route to any one of the proposed Quarry Substation Sites (1, 2, 3, or 4).[277]
290. Applicants estimate Project costs for Route D at approximately $53.6 million. However, Route D’s actual costs may be higher because it is unclear whether this alignment can be constructed on the Monticello Nuclear Generating Plant property or if multiple transmission line crossings of the existing transmission lines can be avoided. If the line had to be located off plant property or in another location on the property, it would be longer and overall costs would increase. Similarly, the crossing or reconfiguration of existing transmission lines in the corridor could cause additional costs. The estimate does not account for any requirements that may be imposed by the DNR, U.S. Army Corps of Engineers (USACE), or the USFWS because of the river crossings. The cost estimate also does not consider any special construction techniques for the river crossings.[278]
291. Route
D has a greater impact on various resources than Applicants’
292. Approximately
5.67 acres of vegetation would need to be permanently removed at the
Mississippi River crossing in
293. The
Route D proposed
294. The
additional regulatory review required for the two Route D crossings of the
295. Although the river crossings would require special design considerations, it appears that the change in design and construction needed to span the river does not pose a major impediment to the selection of Route D.[283]
296. Applicants
would likely be able to span the
297. There
are several impediments to construction of Route D. Route D would traverse the Monticello Nuclear
Generating Plant property to reach the
298. After
crossing the
299. After crossing the existing double-circuit 345 kV line and 69 kV line, Route D would proceed to the northwest through an area that is currently pivot irrigated farmland, but which is planned to be an industrial reserve for future development, and where a large landfill is currently located. Public comments raised concerns about the impact to development in this area, as well as the potential loss of landfill disposal capacity if Route D is chosen.[287]
300. The existing 115 kV line right-of-way is only 80-feet wide, and Applicants anticipate that they would need to acquire an entirely new 150-foot wide right-of-way to parallel the existing 115 kV line. Efforts to parallel the existing 115 kV along Route D would require the span lengths of the new 345 kV line to be shortened to match the existing spans. As a result, Applicants would be unable to maximize span lengths on Route D.[288]
301. Route
D would have a greater impact on agriculture than the other alternatives. Construction along Route D would impact 36
center pivot irrigation fields compared to three on the
302. Route
D also would impact more acres of wooded and forested land than the
303. Route
D would have a greater impact on recreation than the
304. Natural
Heritage Information System records identify 15 species listed as special
concern, threatened or endangered within on mile of Route D, which is higher
than any of the proposed routes.[292] The additional crossings of the
305.
No facilities
open to public use are expected to be impacted by Route D.[294]
306. Many
people opposed the use of Route D. Fewer
people supported the use of Route D, usually because it paralleled an existing
115 kv line. The DNR specifically
objected to Route D because the increase in lines crossing the Mississippi
River would pose hazards for migrating birds that use the
307. Route
D’s impact on air and water quality would be the same as the impact for the
308. In
contrast to Route D, construction along the
309. Some members or the public suggested the transmission lines should be installed underground at sensitive locations.[299]
310. Applicants prepared a report in connection with the CAPX 2020 projects to estimate the cost of undergrounding. The study concluded that undergrounding a 345 kV double circuit capable transmission facility would cost approximately $40 million per mile.[300]
311. Applicants estimate the cost of the entire 28-mile transmission line to cost $53 million to $71 million. The cost to place the facilities underground would thus exceed by several times the cost of Applicants’ proposed aerial installation.[301]
312. The additional cost and difficulty associated with undergrounding does not warrant placing the transmission line underground.
313. The
Applicants did not provide any estimate of the cost to underground the
transmission lines for specific areas, such as the river crossings or the
314. The
associated facilities for the Project include modifications at the existing Monticello
Substation, construction of the proposed Quarry Substation, and the
interconnection of the existing
315. No additional land is required for modifications to be made at the Monticello Substation.[303]
316. Applicants
seek to acquire up to 40 acres for the proposed Quarry Substation to ensure
adequate space for planned facilities, future transmission line
interconnections and an area surrounding the proposed facility to minimize immediate
encroachment with other existing or new land uses. The existing
317. With regard to human settlement, there are existing residences located within or near the proposed Quarry Substation Sites. Approximately 99% of Substation Site 1 is zoned agricultural, and there is one existing residence and two nonresidential buildings located within the siting area. The substation would ultimately be sited to avoid the displacement of these structures.[305]
318. Approximately 80% of Substation Site 2 is zoned agricultural and 20% is zoned residential. There is one existing residence and 10 non-residential buildings located within the siting area. The substation could ultimately be located within the approved siting area to avoid the displacement of these structures.[306]
319. The evidence on the record demonstrates that there will be no impact associated with noise, cultural values and public services from any of the Substation Sites.[307]
320. Neither Substation Site 1 or 2 would significantly impact the viewshed. Site 1 is located approximately 1,000 feet west of an existing residential use area, but there is a stand of trees between the siting area and the residential area.[308]
321. Applicants have committed to implement appropriate safeguards during construction and operation to avoid any impact to human health and safety.[309]
322. With regard to land-based economies, the Quarry Substation will have a permanent impact on agricultural land because a minimum of six acres will be permanently removed from existing land uses, including agricultural use. There is no anticipated impact to any forest resources or tourism. Aggregate mining continues to occur within the area encompassed by the proposed Quarry Substation Site 2 and Quarry Substation Site 4, which could pose some constructability considerations. Based upon their review of soil borings provided by the property owner, however, Applicants do not anticipate problems with soil conditions at Quarry Substation Site 4. There is no anticipated impact to any active mining in Quarry Substation Site 1.[310]
323. With regard to impacts to archaeological and historical resources, there are no archaeological sites, architectural sites or historical landscapes within the proposed Quarry Substation Siting Areas.[311]
324. With regard to the natural environment, the construction of the proposed Quarry Substation will have the potential for impact air quality during construction. The Proposed Quarry Substation Siting Areas have NWI wetlands present within the boundaries, and Quarry Substation Site 2 also has two bodies of water flowing through the boundaries, one of which is included in the Minnesota PWI. Applicants will avoid all identified wetland and water features to the extent feasible and will install erosion control devices (e.g., silt fence, straw bales) to ensure that sediment does not enter the water feature. The Applicants will obtain all necessary permits from the MPCA and DNR. The Project will likely result in minimal impacts on wildlife at proposed substation locations because of the abundance of similar adjacent habitat. Permanent impacts on wildlife could take place at substation locations where 40 acres of land will be changed from existing land uses, most likely agricultural, to the developed substation area.[312]
325. No impact to rare and unique resources is anticipated at any of the proposed substation sites.[313]
326.
There are no
significant differences between Quarry Substation Site 1 or 2.
Alternative Quarry Substation Site 4
327. On
February 1, 2010, the Applicants asked to add evaluation of a new Quarry
Substation site to the EIS. The request
was made as a result of further review and discussion with affected landowners
near proposed Quarry Substation Sites 1 and 2.
Quarry Substation Site 4 is proposed to be located north of the
intersection of State Highway 23 and
328. Approximately 60 percent of Substation Site 4 is zoned for agricultural uses and approximately 40 percent is zoned for industrial/municipal uses. There are no residential or non-residential structures in the area. Since industrial and commercial properties currently exist in this area, a substation would be consistent with existing and planned land use.[315]
329. Quarry Substation 4 has no prime farmland, center pivots or wooded acres within the substation site boundary. [316]
330. Quarry Substation 4 is a better site than Substation Sites 1 or 2 because there no residential or non-residential structures in the area and because Substation Site 4 is zoned for industrial use.
Alternative Quarry Substation Site 3
331. This
alternative encompasses approximately 15 acres in the southeast corner of
Section 36, T124N, R29W and the northeast corner of Section 1, T124N, R29W in
332. Quarry Substation Site 3 has the minimum amount of space required for the Project but would not allow for any future expansion. Also, the narrow shape of the Quarry Substation Site 3 does not lend itself to efficient substation layout or design. In addition to having no significant buffer between the Quarry Substation and neighboring properties, the approach areas for the transmission lines are limited by the roads that border the property.[318]
333. In contrast to Quarry Substation Site 3, Quarry Substation Sites 1, 2 and 4 allow for sufficient space for the Project, as well as future expansion, and still have enough space remaining to maintain a buffer area between the substation and surrounding properties.[319]
334. In addition, because the small Quarry Substation Site 3 is so small (15 acres), should additional transmission facilities be needed in the area, a new substation site would likely be required.[320]
335. Quarry
Substation Site 3 is also far from the
336. The DNR noted that Alternative Site 3 has the least impact from a natural resource perspective but that because the area between Site 3 and the Fargo-Moorhead segment is environmentally sensitive, Site 3 is not the best site.[322]
337. There was no public support for the selection of Quarry Substation Site 3.
338. OES similarly confirmed that it had identified no advantage in selecting Quarry Substation Site 3 over Applicants’ proposed Quarry Substation Sites 1, 2 or 4.[323]
339. The Commission must locate transmission lines in a manner that minimizes adverse human and environmental impact while ensuring electric power system reliability and integrity. The PPSA further authorizes the Commission to designate a route with a variable width of up to 1.25 miles.[324]
340. Applicants have requested a route width of up to 1,000 feet for the 345 kV transmission line, and a route width of up to 1.25 miles in five areas along the proposed routes, particularly along the I-94 corridor, and at the Proposed Quarry Substation Siting Areas.[325]
341. Applicants
note that in those locations where the Proposed Routes parallel a roadway, a
large portion of the 1,000 foot route width is occupied by the road
right-of-way, particularly within the control-of-access fence lines of I-94
along the
342. OES submitted comments on April 16, 2010, stating concerns about the route widths proposed by the Applicants, and expressing its view that the proposed route widths should be narrowed for most of the route.[327] Applicants and OES have agreed to evaluate whether the proposed route width can be narrowed further and appropriate permit language crafted that would ensure Applicants’ need for flexibility and provide landowners and other stakeholders greater certainty and predictability regarding the potential location of a final alignment. These discussions may result in Applicants submitting proposed permit language to the Commission for consideration.[328]
343.
344. In August 2008, Applicants mailed a letter to officials of local governments within the Project area in accordance with Minn. Stat. § 216E.03, subd. 3a.[330]
345. On
April 8, 2009, Applicants mailed a notice to landowners whose property was
within or adjacent to proposed or alternate routes and substation sites, the
original list of citizens on the Certificate of Need mailing lists and to the
list of persons requesting notice of submitted High Voltage Transmission Line
Applications for Route Permits maintained by the Commission in accordance with
Minn. Stat. § 216E.03, subd. 4, and
346. In
April 2009, Applicants also mailed a copy of the Application by certified mail
to any regional development commission, county, incorporated municipality, and
town in which any part of the site or route is proposed, in accordance with
Minn. Stat. § 216E.03, subd. 4, and
347. Between
April 9, 2009 and April 17, 2009, Applicants published notice of the submission
of the Route Permit Application in nine newspapers throughout the Project area
in accordance with Minn. Stat. § 216E.03, subd. 4, and
348.
349. On
June 15, 2009, the OES mailed the Notice of Public Information/Scoping Meetings
in accordance with Minn. R. 7850.2300, subp. 2 and
350. Between June 18, 2009, and June 20, 2009, the OES published Notice of Public Information/Scoping Meetings in newspapers of general circulation in each county where the proposed project may be located in accordance with Minn. R. 7850.2300, subp. 2.[336]
351. On October 15, 2009, the OES mailed the Notice of Environmental Impact Statement Scoping Decision in accordance with Minn. R. 7850.2500, subp. 2.[337]
352. In addition to notice requirements imposed by Minnesota Statutes and Rules, on October 27, 2009, the OES mailed a notice to landowners affected by one or more of the route alternatives proposed for evaluation in the EIS.[338]
353. On January 11, 2010, the OES mailed Notice of DEIS Availability and Public Information Meetings in accordance with Minn. R. 7850.2500, subps. 7 and 8.[339]
354. On January 11, 2010, the OES published Notice of DEIS Availability and Public Information Meetings in the EQB Monitor in accordance with Minn. R. 7850.2500, subp. 7.[340]
355. By January 15, 2010, the OES had mailed paper copies of the DEIS to public libraries in each county where the proposed project may be located in accordance with Minn. R. 7850.2500, subp. 7.[341]
356. On February 11, 2010, the OES mailed Notice of public hearings in accordance with Minn. Stat. § 216E.03, subd. 6.[342]
357. Between February 24, 2010 and February 25, 2010, the OES published Notice of public hearings in newspapers of general circulation in each county where the proposed project may be located in accordance with Minn. Stat. § 216E.03, subd. 6.
358. On March 26, 2010, OES published the FEIS.
359. On March 29, 2010, OES issued a press release that the FEIS had been released.[343]
360. The Commission is required to determine the adequacy of the FEIS. To be adequate, the FEIS must, among other things, address the issues and alternatives identified in the Scoping Decision “to a reasonable extent considering the availability of information and the time limitations for considering the permit application.”
361. The evidence on the record demonstrates that the FEIS is adequate because it addresses the issues and alternatives raised in the Scoping Decision, provides responses to the substantive comments received during the DEIS review process, and was prepared in compliance with Minnesota Rules 7850.1000 to 7850.5600.
Based on these Findings of Fact, the Administrative Law Judge makes the following:
1. The Public Utilities Commission and Administrative Law Judge have jurisdiction to consider Applicants’ Application for a Route Permit.[344]
2. The Commission determined that the Application was substantially complete and accepted the Application on May 13, 2009.
3. OES has conducted an appropriate environmental analysis of the Project for purposes of this route permit proceeding and the FEIS satisfies Minn. R. 7850.2500.
4. Applicants gave notice as required by Minn. Stat. § 216E.03, subd. 3a; Minn. Stat. § 216E.03, subd. 4; Minn. R. 7850.2100, subp. 2, and Minn. R. 7850.2100, subp. 4.
5.
OES gave notice as required in Minn. Stat. §
216E.03, subd. 6;
6. Public hearings were conducted in communities located along the proposed transmission line routes. Applicants and OES gave proper notice of the public hearings, and the public was given the opportunity to speak at the hearings and to submit written comments. All procedural requirements for the Route Permit were satisfied.
7.
The
8.
The
9.
The
10. The Route Permit should provide Applicants with a route width of up to 1,000 feet except for those locations identified on the record where Applicants have requested a route width up to 1.25 miles (as illustrated in Exhibits 7A, 7B and 7C).
11. The Route Permit should permit the Applicants to install six conductors at highway crossings and interchange locations to facilitate the addition of a second circuit at a later date, upon approval of the Commission.
12. Any of the Quarry Substation Sites proposed by Applicants (Quarry Substation Sites 1, 2 and 4) is suitable. However, based on the record, Substation Site 4 would have the least impact on residential and non-residential structures and agricultural land, and more consistent with current zoning.
13. It is appropriate for the Route Permit to require Applicants to obtain all required local, state, and federal permits and licenses, to comply with the terms of those permits and licenses, and to comply with all applicable rules and regulations.
14. Any findings more properly designated Conclusions are adopted as such.
Based upon these Conclusions, and for the reasons explained in the accompanying Memorandum, the Administrative Law Judge makes the following:
The Commission issue to Applicants the
following permit for the
1. A route
permit for a high voltage transmission line corridor up to 1,000 feet wide,
except for those locations identified on the record where Applicants have
requested a route width up to 1.25 miles, along Applicants’ Preferred Route,
which is depicted in Figure 5-2 and Appendices B and C of the Route Permit
Application. The
2.
The route permit shall include the Applicants’ requested
modifications to the Monticello Substation, a new Quarry Substation, and
connection to the existing
3. The route permit shall require the Applicants to seek approval from the Commissioner to place a portion of the transmission line underground if necessary to comply with restrictions imposed by the DNR or USFWS.
4. The route permit shall allow the Applicants to install six conductors at highway crossings and interchange locations.
Dated: May 18, 2010
s/Beverly Jones Heydinger
|
BEVERLY JONES HEYDINGER Administrative Law Judge |
Reported: Shaddix & Associates
Under the PUC’s Rules of Practice and Procedure, Minn. R. 7829.0100 to 7829.3200, exceptions to this Report, if any, by any party adversely affected must be filed within 15 days of the mailing date hereof with the Executive Secretary of the PUC, 350 Metro Square Building, 121 Seventh Place East, St. Paul, Minnesota 55101-2147. Exceptions must be specific, relevant to the matters at issue in this proceeding, and stated and numbered separately. Proposed Findings of Fact, Conclusions, and Order should be included, and copies thereof served upon all parties.
The PUC shall make its determination on the applications for the Certificate of Need and Route Permits after expiration of the period to file Exceptions as set forth above, or after oral argument, if such is requested and had in this matter. In accordance with Minn. R. 4400.1900, the PUC shall make a final decision on the Route Permits within 60 days after receipt of this Report.
Notice is hereby given that the PUC may accept, modify, condition, or reject this
Report of the Administrative Law Judges and that this Report has no legal effect unless
expressly adopted by the PUC.

Mailing
Address: Voice: (651) 361-7900
P.O. Box 64620 TTY: (651) 361-7878
May 18, 2010
|
To All Parties Listed on the OAH E-Docket System Service List |
|
Re: In the Matter of the Application for a Route Permit for the
OAH
15-2500-20665-2; PUC No. E-002/TL-09-246
Dear Parties:
The document listed below has been filed with the E-Docket system and served as specified on the OAH E-Docket service list.
Findings of Fact,
Conclusions and Recommendation
The official record will be sent to the Commissioner under
separate cover.
Sincerely,
s/Beverly
Jones Heydinger
BEVERLY
JONES HEYDINGER
Administrative
Law Judge
Telephone:
(651) 361-7838
BJH:nh
Encl.
[1] MPUC Docket No. ET-2, E-002, et
al./CN-06-1115.
[2]
Order, MPUC Docket No. ET2/TL-09-246, filed
[3] Ex. 9, Notice of Public Scoping Meeting.
[4] Ex. 12, EIS Scoping Decision.
[5] Ex. 12, EIS Scoping Decision.
[6] Ex. 14, DEIS; Ex. 15, Notice of Availability of DEIS.
[7] Ex. 2, Lahr Prefiled Direct Testimony; Ex. 4, Chezik Prefiled Direct Testimony; Ex. 6 Kline Prefiled Direct Testimony.
[8] FEIS.
[9] FEIS.
[10] Ex. 19, Notice of Public Hearing as published.
[11] Ex. 18, Certified Letters to Local Governments.
[12] Ex. 17, Notice of Public Hearing with Certificate of Service.
[13] Ex. 2, at 6.
[14] Ex. 2, at 6.
[15] Ex. 4, at 3.
[16] Ex. 2, at 7.
[17]
MPUC Docket No. ET-2, E-002, et al./CN-06-1115, Order,
[18] Ex. 1A (RPA), at 5-1; Ex. 2, at 8-9 and Schedule 4; Exs. 7A, 7B and 7C (Hearing Maps).
[19] Ex. 1A, at § 5.1; Ex. 2, at 8.
[20] Ex. 1A, at § 5.2; Ex. 2, at 9.
[21] Ex. 1A, at § 5.3; Ex. 2, at 9.
[22] Ex. 1A at 4-5 and Figure 2-2.
[23] Ex. 1A at Figure ES-1; Ex. 2 at Schedule 9; Trans. Vol. 1 at 77 (Lahr); Ex. 14 (DEIS) at 5-78.
[24] Ex. 1A at 2-9; Ex. 2 at Schedule 10; Trans. Vol. 3 at 46-47 (Seykora).
[25] Ex. 1A at 2-9; Ex. 2 at Schedule 10.
[26] Ex. 1A at § 3.1; Ex. 4 at 3-4; Ex. 2 at 7.
[27] Trans. Vol. 2 at 43-53 (Chizek); Trans. Vol. 3 at 59-60 (Seykora).
[28] Ex. 4 at 4.
[29] Ex. 4 at 5.
[30] Ex. 4 at 2-4; Ex. 2 at 10.
[31] Ex. 1A at 2-4 and § 2.3, Figures 2-3 to 2-8.
[32] Ex. 1A at §2.3, Figures 2-4 to 2-6.
[33] Ex. 1A at 2-15.
[34] Ex. 1A at 2-17 and Figure 2-7.
[35] Trans. Vol. 2 at 7-9 (Lahr).
[36] Ex. 1A a 3-3; Ex. 4 at 5.
[37] Ex. 4 at 5.
[38] Ex. 4 at 5-6.
[39] Ex. 4 at 7.
[40] Ex. 1A at 3-5; Ex. 2 at 6.
[41] Ex. 1A at § 3.1.
[42] Ex. 2 at 7-8; Ex. 1A at § 2.4.
[43] Trans. Vol. 1 at 40-43 (Lahr).
[44] Ex. 1A at § 3.1.2; Ex. 2 at 6.
[45] Ex. 1A at 3-5; Ex. 2 at 6.
[46] Ex. 1A at 3-5.
[47] Ex. 2 at 26-27.
[48]
[49] Ex. 2 at 22 and Schedule 9; Trans. Vol. 3 at 8 (Seykora).
[50] Trans. Vol. 3 at 46-47 (Seykora) (overriding earlier MnDOT concerns that intermittent encroachment would require advance FHWA approval, as noted in Ex. 2 at 22 and Schedule 9).
[51] Ex. 2 at Schedule 9 and 24; 23 C.F.R. 771.117(c)(2)(2009).
[52] Ex. 2 at 25-26; Ex 1B at Appendix E; Ex. 22; FEIS at 3-10 and 3-11.
[53] Trans. Vol. 1 at 30-31(Lahr); Trans. Vol. 3 at 39-43, 61 (Seykora).
[54] Trans. Vol. 1 at 27-30 (Lahr); Ex. 7B; Ex. 3 at Schedule 14.
[55] Trans. Vol. 3 at 39-43, 61 (Seykora).
[56] Trans. Vol. 3 at 21-23, 30-32, 58-59 (Seykora).
[57] Trans. Vol. 3 at 17-21, 48-49 (Seykora); Ex. 29 (Map); Trans. Vol. 1 at 24-25 (Lahr).
[58] Trans. Vol. 3 at 51-52.
[59] Trans. Vol. 3 at 52.
[60] DNR Comments, E-Docket Doc. No. 20103-48255-02.
[61] DNR Comment, Feb. 26, 2010.
[62] DNR Comment, Feb. 26, 2010.
[63] DNR Comment, Mar. 19, 2010, citing DEIS Appendix H, p. 1.
[64] DNR Comment, Jamie Schrenzel, Mar. 19, 2010.
[65] DNR Comment, Feb. 26, 2010.
[66]
[67]
[68]
[69] Minn. R. 7850.2500, subp. 4.
[70] Ex. 12 at 2-3 (Scoping Decision).
[71] Ex. 12 at 4-8 (Scoping Decision).
[72] Ex. 12 at 4-6, 4-8 (Scoping Decision).
[73] Ex. 14 (DEIS).
[74] Ex. 15 at 2; Ex. 16.
[75]
[76] FEIS at 1-4; FEIS at § 2.0.
[77] See e.g., Jerry Zabinski, Trans. Mar. 8, afternoon, at 59; Paul Schwinghammer, Trans. Mar. 8, afternoon, at 78; Mark Conroy, Trans. Mar. 8, afternoon, at 79; Phil Bautch, Trans. Mar. 8, afternoon, at 102; Ex. 124 (City of St. Augusta); Ex. 125 (William and Karen Rademacher); Ex. 126 (Town of Lynden, Resolution No. 2010-1); Comment, Jim and Dawn Froelich, Mar. 18, 2010; Comment, Robert and Shirley Laudenbach, Mar. 9, 2010; Comment, Jerry and Judi Tollefson, Mar. 15, 2010; Comment, Gary and Karen Smith, Mar. 14, 2010; Comment, Gene and Judy Post, Mar. 12, 2010; Comment, Mark Sytsma, Mar. 19, 2010.
[78] Comment, Mar. 5, 2010.
[79]
City of
[80] Carlos Lopez, Trans. Mar. 8, afternoon, at 61-63; Ex. 106; Ex. 107.
[81] Ronald Schabel, Trans. Mar. 8, afternoon, at 84; Ex. 112.
[82] Comment, Mar. 15, 2010.
[83] Karen Durant, Trans. Mar. 8, afternoon, at 97-99; Ex. 115-119.
[84] Comment, Mar. 12, 2010, with Attachment, citing proposed Route A hybrid suggested by Ron Schabel.
[85]
[86]
[87]
Comment,
[88] See e.g., Comment, Stephen Nohava, Mar. 11, 2010; Comment, Rick Phipps, Mar. 16, 2010.
[89] See e.g., Ex. 113 (Elaine Paumen);
[90] See e.g., Roger Neils, Trans. Mar. 8, afternoon, at 45-49.
[91]
Jeff Schlingmann, Trans. Mar. 8, afternoon, at 71; see also Comment,
[92]
Trans. Mar. 8, afternoon, at 108, Ex. 122 (Sherburne County Board of
Commissioners, citing DEIS Table 5-9); see
also Ex. 123 (City of
[93] Roger Neils, Trans. Mar. 8, afternoon, at 51-53.
[94] Schmiesing, Trans. Mar. 8, afternoon, at 70; Schlingmann Comment, Mar. 2, 2010.
[95] Ex. 123.
[96]
Ex. 108; see also Ex. 123 (City of
[97]
Ex. 109 (
[98] See e.g., Comment, Michael and Barb Fitch, Mar. 19, 2010; Comment, Barbara Gulbrandson, Mar. 17, 2010; Comment, Joe and Mary Jansky, Mar. 16, 2010.
[99] Ex. 123.
[100]
Trans. Mar. 8, afternoon, at 108-109; see
also Ex. 121 (
[101]
See e.g., Comment,
[102] Ex. 122.
[103] Roger Neils, Trans. Mar. 8, afternoon, at 49.
[104] Trans. Mar. 8, afternoon, at 36-38; see also Larry Seeley, Trans. Mar. 8, afternoon, at 38-40.
[105] Ex. 114; see also, Mike Hayes, Trans. Mar. 8, afternoon, at 110-113.
[106] Trans. Mar. 8, afternoon, at 40-41; Ex. 100; Ex. 101.
[107] Comment, Feb. 25, 2010.
[108] See e.g., Comment, Heidi and Donald Cox, Mar. 18, 2010; Comment, Carol Overland, Mar. 19, 2010; Comment, John Pazik, Mar. 12, 2010.
[109] Ex. 127; Ex. 128; Ex. 129; Ex.
130.
[110] Ex. 130.
[111] Carlos Lopez, Trans. Mar. 8, afternoon, at 61-63; Ex. 106; Ex. 107.
[112] Roger Neils, Trans. Mar. 8, afternoon, at 48; Jeff Schlingmann, Trans. Mar. 8, afternoon, at 67-68; Ex. 110 (Paul Gray); Felix Schmiesing, Trans. Mar. 8, afternoon, at 106-107, and Comment, received Mar. 19, 2010; Gary Hammer, Trans. Mar. 8, afternoon, at 114-116; Ex. 120 (City of Becker); Ex. 121 (Becker Township); Ex. 122 (Sherburne County Board of Commissioners); Ex. 123 (City of Becker).
[113] Comment, Mar. 25, 2010; see also Comment, William Gulbrandson, Mar. 19, 2010.
[114] Comment, Roger Neils, Mar. 18, 2010.
[115] See e.g., Joe Kenning, Trans. Mar. 8, evening, at 43-51, and Ex. 139, and Comment, received Mar. 22, 2010; Brad Zadow, Trans. Mar. 8, evening, at 59-60, and Ex. 143; Comment, Kenneth and Mary Wolters, Mar. 15, 2010; Gary and Karen Smith, Comment, Mar. 14, 2010.
[116] Ex. 128.
[117] See e.g., Comment, Julie and Brent Neisch, Mar. 16, 2010.
[118] See e.g., Jerry Finch, Mar. 8, afternoon, at 124.
[119] See e.g., Comment, Meridith Kjelberg, Mar. 17, 2010; Comment, Julie Blomberg and Brett Admixtures, Mar. 10, 2010; Comment, Kent Kjellberg, Mar. 19, 2010; Comment, Gene and Judy Post, Mar. 12, 2010.
[120] Paul Schwinghammer, Mar. 8, afternoon, at 76.
[121] Comment, Mar. 11, 2010.
[122] Mark Conroy, Tran. Mar. 8, afternoon, at 80-81; Rose Thelen, Trans. Mar. 8, evening, at 41, and Ex. 138; Comment, Charles Guill, Mar. 18, 2010.
[123]
[124] This subfactor is inapplicable because Applicants have not applied for a route permit for a large electric generating plant.
[125]
[126] This criterion is inapplicable because Applicants have not applied for a permit for a large electric generating plant.
[127]
[128]
[129] Ex. 1A at § 7.2.2.3.
[130] Ex. 1A at 6-2, 7-22, 7-60, 7-72.
[131] Ex. 1A at 7-22; Ex. 1B at Appendix E.
[132] Ex. 1A at 7-22; Ex. 1B at Appendix E.
[133] Ex. 1B at Appendix E.
[134] Ex. 22 at p. 1; Ex. 1B at Appendix E, p. 6.
[135] Ex. 1A at 7-60; Ex. 1B at Appendix E.
[136] Ex. 1B at Appendix E.
[137] Ex. 1B at Appendix E.
[138] Ex. 22 at 1.
[139] Ex. 1A at 7-73; Ex. 1B at Appendix E.
[140] Ex. 22 at 1.
[141] Walters, Trans. Mar. 8 (afternoon) at 120.
[142]
[143] Ex. 1A at 7-25; Ex. 14 at 5-140 (DEIS).
[144] Ex. 1A at 6-2.
[145] Ex. 1A at 6-6, 6-2; Ex. 1B at Appendix E.
[146] Exs. 7A, 7B and 7C (Maps).
[147] Ex. 3 at 2-3; Trans. Vol. 1 at 18, 70-71 (Lahr).
[148] Ex. 14 at 5-43 (DEIS); FEIS at 2-4.
[149] Trans. Vol. 2 at 60-61 (Kline); Ex. 14 at 5-32; FEIS at Appendix C.
[150] Trans. Vol. 2 at 17 (Lahr).
[151] Trans. Vol. 2 at 67-68 (Birkholz).
[152] Trans. Vol. 2 at 17 (Lahr).
[153] Trans. Vol. 3 at 38-39 (Seykora).
[154] Ex. 1A at 7-33.
[155] Ex. 1A at 6-2.
[156] Ex. 1A at 6-2.
[157] Ex. 1A at 6-2.
[158] Ex. 1A at 7-37, 7-64, 7-76.
[159]
[160] Ex. 1A at 3-22.
[161] Ex. 14 at 5-142 (DEIS).
[162] Ex. 14 at 5-143 (DEIS); Ex. 2 at Schedule 2 (Lahr Direct).
[163] Ex. 1A at 6-2, 7-17.
[164] Ex. 1A at 7-17.
[165]
[166] Ex. 1A at 7-38.
[167] Ex. 1A at 7-38; Ex. 2 at 26-27.
[168] Ex. 22 at 7-8
[169] Ex. 22 at 7-8.
[170] Ex. 22 at 7-8.
[171] Ex. 1A at 6-3.
[172] Ex. 1A at 6-3, 7-39.
[173] Ex. 1A at 6-3, 7-40; Trans. Mar. 8, 2010, afternoon, at 24 (Lahr).
[174] Ex. 1A at 6-3, 7-65.
[175] Ex. 1A at 6-3, 7-77.
[176]
[177] Ex. 1A at 7-40; Ex. 22 at 4-5.
[178] Ex. 22 at 4-5.
[179] Ex. 22 at 4-5.
[180] Ex. 1A at 6-4.
[181] Ex. 1A at 7-43.
[182] Ex. 1A at 6-4.
[183]
[184] Ex. 1A at 6-4, 7-44.
[185] Ex. 1A at 7-45.
[186] Ex. 1A at 7-47.
[187] Ex. 1B, Appendix E, at 4.
[188] Ex. 1B, Appendix E, at 4.
[189] DNR Comment, Feb. 26, 2010; DNR Comment, Mar. 19, 2010.
[190] FEIS at 3-20.
[191] FEIS at 3-20.
[192] FEIS at 3-21.
[193] Ex. 1A at 7-47, 7-48; Ex. 1B at Appendix E, at 4.
[194] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[195] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[196] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[197] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[198] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[199] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[200] Ex. 1B, Appendix E, at 4; Ex. 22 at 2-3, 9.
[201] See e.g., FEIS at 3-20 and Appendix D.
[202] Trans. Vol. 1 at 22-23 (Lahr); Trans. Vol. 2 at 29 (Lahr).
[203] Trans. Vol. 1 at 20-22 (Lahr).
[204] Trans. Vol. 2 at 28-30 (Lahr).
[205] Trans. Vol. 2 at 64 (Birkholz)
[206] Trans. Vol. 3 at 53-54 (Seykora).
[207] Ex. 1A at 7-51.
[208] Ex. 1A at 7-52.
[209] Ex. 1A at 7-52.
[210] Ex. 1A at 7-52.
[211] Ex. 1A at 7-52; FEIS at 2-81.
[212] Ex. 1A at 7-52.
[213] Ex. 1A at 6-5, 7-50, 7-69; Ex. 22 at 10.
[214] Ex. 1A at 6-5, 7-81; Ex. 22 at 10.
[215] Ex. 1A at 7-52.
[216] Ex. 1A at 7-53.
[217] Ex. 1A at 6-5.
[218] Ex. 1A at 7-53.
[219] Ex. 1A at 7-54; Ex. 14 at 5-133 (DEIS); FEIS at 2-17.
[220] Ex. 14 at 7-54 (DEIS).
[221][221] Ex.1A at 7-55 (Application). Xcel also submitted a draft Avian Protection Plan in 2009.Ex. 14 at 5-133 (DEIS).
[222]
[223] Ex. 1A at 7-56.
[224] Ex. 1A at 7-57.
[225] Ex. 1A at 6-5, 7-56; Ex. 1B at Appendix E, p. 5.
[226] Ex. 1A at 6-5, 7-70; Ex. 1B at Appendix E, p. 5.
[227] Ex. 1A at 6-5, 7-82; Ex. 1B at Appendix E, p. 5.
[228]
[229] Ex. 1A at 3-6.
[230] Trans. Vol. 2 at 43-53; Exs. 24, 25, and 26 (Chezik Drawings).
[231] Ex. 2 at 7.
[232] Ex. 1A at 3-5.
[233]
[234] Ex. 1B at Appendix E, p. 2 and Appendix H; Ex. 1A at 6-6 and § 3.2.
[235] Ex. 1B at Appendix E, p. 2 and Appendix H; Ex. 1A at 6-6 and § 3.2.
[236] Ex. 1A at 6-6 and § 3.2; Ex. 1B at Appendix H.
[237]
[238] Ex. 1A at § 3.2, 6-6; Ex. 1B at Appendix H.
[239] Ex. 1A at § 3.2, 6-6; Ex. 1B at Appendix H.
[240] Ex. 1A at § 3.2, 6-6.
[241]
[242]
[243] Ex. 1A at § 2.6; Ex. 5 at 1-2.
[244] Ex. 1A at § 2.6; Ex. 5 at 1-2.
[245] Ex. 1A at § 2.6; Ex. 5 at 1-2.
[246]
[247] Ex. 1A at 6-6, 6-7.
[248] Ex. 22 at 7.
[249] Ex. 22 at 7.
[250] Ex. 22 at 7.
[251] Ex. 22 at 8; Ex. 1B Appendix E,
p. 1.
[252]
[253] Ex. 1A at 6-7.
[254]
[255] Ex. 2 at 22; Trans. Vol. 1 at 69 (Lahr); Trans. Vol. 3 at 46-47 (Seykora).
[256] See e.g., Jerry Finch, Mar. 8, afternoon, at 124.
[257] Ex. 3 at Schedule 15, p. 11-12; Trans. Vol. 3 at 48-51 (Seykora).
[258]
[259] Ex. 14 at 1-2.
[260] Ex. 2 at 12.
[261] Ex. 5 at 2.
[262] Ex. 2 at 12-13; Ex. 14 at 5-17, 5-111 (DEIS).
[263] Ex. 14 at 5-27 (DEIS).
[264] Ex. 14 at 5-27 (DEIS).
[265] Ex. 14 at 5-40 (DEIS).
[266] Ex. 14 at 5-55 (DEIS).
[267] Ex. 14 at 5-67 (DEIS).
[268] Ex. 14 at 5-91 (DEIS).
[269] Ex. 14 at 5-100 (DEIS).
[270] Ex. 14 at 5-111 (DEIS).
[271] Ex. 14 at 5-116 (DEIS).
[272] Ex. 14 at 5-126 (DEIS).
[273] See Ex. 14 at 5-134 (DEIS).
[274] See Ex. 14 at 5-141 (DEIS).
[275] Ex. 2 at 12; FEIS at Appendix C.
[276] Trans. Vol. 2 at 60-61; Ex. 14 at 5-32 (DEIS); Trans. Vol. 1 at 71; FEIS at Appendix C; Comment, Waytashek, Mar. 8, 2010 (afternoon), at 108.
[277] Ex. 14 at 1-14 (DEIS); Ex. 2 at 12.
[278] Ex. 5 at 2; Trans. Vol. 2 at 22.
[279] Ex. 14 at 5-59, 5-60 (DEIS); Ex. 2 at 13-14.
[280] FEIS at 2-76.
[281] Ex. 2 at 13-14; Ex. 6 at 5; Ex. 14 at S-4 (DEIS).
[282] Ex. 2 at 13-14; Ex. 4 at 6.
[283] See e.g., Ex. 14 at Appendix B-7 (DEIS).
[284] See Ex. 14 at 1-14 (DEIS).
[285] Ex. 2 at 13-14; Trans. Vol. 1 at 44, 46-48 (Lahr).
[286] Trans. Vol. 1 at 48-50, 59-60, 61-62 (Lahr); Trans. Vol. 1 at 51-56 (Kline); Ex. 6 at 4-5.
[287] Trans. Vol. 1 at 56-57; Exs. 120, 121, 122, 123; Waytashek, Mar. 8, 2010, afternoon, at 108-109.
[288] Trans. Vol. 1 at 44-46, 58 (Lahr).
[289] Ex. 14 at 5-24, 5-28 (DEIS); Trans. Vol. 1 at 45-46, 57, 59 (Lahr).
[290] Ex. 14 at 5-23 (DEIS); Ex. 2 at 14.
[291] FEIS at Appendix C; Ex. 14 at 5-51 (DEIS).
[292] Ex. 14 at 5-102 (DEIS).
[293] See DNR Comment, Feb. 26, 2010.
[294] Ex. 14 at 5-67 (DEIS).
[295] DNR Comment, Feb. 26, 2010.
[296] See Ex. 14 at 5-134 (DEIS).
[297] See Ex. 14 at 5-141 (DEIS).
[298] Ex. 2 at 14-15; Ex. 6 at 4-5; Ex. 14 at S-4 (DEIS).
[299] See, e.g., Conroy, March 8 (afternoon) at 80; Hammer, March 8 (afternoon) at 115; Phipps, March 8 (evening) at 26; Amhalt-Warner, March 8 at 33; Thelen, March 8 (evening) at 40-41.
[300] Trans. Vol. 1 at 9 (Lahr); Ex. 21 (DEIS Comment Letter and Underground Report).
[301] Trans. Vol. 2 at 20-21 (Lahr).
[302] Ex. 1A at 2-19.
[303] Ex. 1A at 2-19.
[304] Ex. 1A at 2-19; Ex. 2 at 6; Ex. 1A at 2-19.
[305] Ex. 1A at 7-22.
[306] Ex. 1A at 7-22; Ex. 14 at 5-117 (DEIS).
[307] Ex. 1A at 7-22, 7-25, 7-26, 7-33, 7-35, 7-37.
[308] Ex. 1A at 7-24; FEIS at 3-2.
[309] Ex. 1A at 7-1.
[310] Ex. 1A at 7-38; Trans. Vol. 1 at 41-42 (Lahr).
[311] Ex. 1A at 7-42.
[312] Ex. 1A at 7-42 to 7-53.
[313] Ex. 1A at 7-57.
[314] FEIS at 3-1.
[315] FEIS at 3-2.
[316] FEIS at 3-2.
[317] Ex. 14 at 1-8
[318] Ex. 2 at 16-17; Trans. Vol. 1 at 39, 72-73 (Lahr); Trans. Vol. 2 at 19-20 (Lahr).
[319] Ex. 1A at 2-19; Ex. 2 at 6-7.
[320] Ex. 6 at 6.
[321] Ex. 14 at 1-8, 1-14 (DEIS); Ex. 6 at 5-6; Ex. 2 at 17.
[322] DNR Comment, Mar. 19, 2010.
[323] Trans. Vol. 2 at 69 (Birkholz).
[324]
[325] Ex. 1A at § 2.3, Figures 2-3 and 2-8; Ex. 2 at 10 and Schedule 4.
[326] Trans. Vol. 1 at 83-84.
[327] OES Comment, Apr. 16, 2010.
[328] Trans Vol. 2 at 7-9 (Lahr).
[329]
[330] Ex. 1B at 2-2 and Appendix H.
[331] Ex. 30 (Affidavits of Mailing and Publication).
[332] Ex. 30 (Affidavits of Mailing and Publication).
[333] Ex. 30 (Affidavits of Mailing and Publication).
[334]
[335] Ex. 9.
[336] Ex. 10.
[337] Ex. 13.
[338] OES Notice to Landowners on Alternative Routes, E-Docket Doc. No. 200910-43298-01 (filed Oct. 28, 2009).
[339] Ex. 15.
[340] Ex. 16.
[341] Ex. 15.
[342] Ex. 17.
[343] E-Docket Doc. No.
20103-48564-01 (filed Mar. 30, 2010).
[344]