|
|
OAH 4-2500-20645-2 PUC E-015/PA-09-526 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
FINDINGS
OF FACT, CONCLUSIONS
AND RECOMMENDATION |
TABLE OF CONTENTS
Page
I. SUMMARY
OF ISSUES, FINDINGS, AND CONCLUSIONS
B. Description
of Parties and Other Participants
C. Description
of the Transmission Line Purchase and Related Agreements
B. Development
of Necessary Transmission Infrastructure
D. The Capacity of the DC Line Not Used for
Transmission of
Renewable Energy Will Be Insignificant
E. Summary of Public Interest Analysis
F. Summary
of Resource Planning Analysis
A. Potential Capacity and Energy Payments to
Minnkota
B. Limiting the Cost of Curing Future Easement
Defects
C. Requiring an RFP Process for Future North
Dakota Wind
Generation Projects
D. Risk of Minnkota’s Failure to Complete Its
Proposed 345kV Line
E. Termination of the Company’s Involvement on
the Young 2
Operating Committee
Administrative Law Judge Bruce H. Johnson (the
ALJ) held an evidentiary hearing in this matter before on September 17, 2009, at
the Public Utilities Commission,
The parties to this proceeding are: ALLETE Corporation d/b/a Minnesota Power
Company (“Minnesota Power,” “MP,” or the “Company”); the Minnesota Department
of Commerce/Office of Energy Security (the “OES”); the Large Power Intervenors
(“LPI”); and NextEra Energy Resources, LLC (“NextEra”).
Christopher Anderson, Associate
General Counsel, ALLETE, Inc.,
Linda Jensen Assistant Attorney
General, 445 Minnesota Street, 1400 Bremer Tower, St. Paul, Minnesota 55101 appeared
on behalf of the OES.
Robert S. Lee and Andrew P.
Moratzka, Attorneys at Law, Mackall, Crounse & Moore, PLC, 1400
Christine Brusven and Todd
Guerrero, Fredrikson & Byron,
Commission staff members Clark Kaml and
Chris Fittipaldi, Financial Analysts appeared on behalf of the MPUC Staff.
The Commission will make the
final determination of the matter after the expiration of the period for filing
exceptions as set forth above, or after oral argument, if such is requested and
had in the matter.
(1)
Is the
volume of renewable energy supplies potentially movable over the direct-current
line proportional to the need for renewable resources?
(2)
Are the
transactions the Company proposes - the purchase of the direct current line,
the winding-down of the contract with the Milton R. Young Unit 2, and the
addition of both purchased and Company-owned wind power - the least-cost method
of meeting its obligations under the Renewable Energy Standard?
(3)
Will
the capacity of the direct-current line significantly exceed the capacity required
to meet the Renewable Energy Standard and, if so, how should the line's
"excess capacity" be treated?
(4)
Are the
transactions proposed by the Company reasonable and prudent?
(5)
Does
the proposed purchase of the direct-current line meet the public interest standard
set forth in Minn. Stat. § 216B.50?
The Commission also directed the
ALJ and the parties to analyze the proposed transactions under the factors set
forth in Minn. R. 7843.0400, subp. 4, and Minn. R. 7843.0500, subp. 3. As set forth below, the ALJ has also analyzed
the proposed transactions under factors set forth in Minn. Stat. § 216B.16, subd. 7c (a), that appear
pertinent to the proposed transactions.
The record in this matter shows that the
volume of renewable energy potentially movable over the DC Line is proportional
to Minnesota Power’s need. The proposed Transactions[1]
are the least-cost method for Minnesota Power to meet its renewable energy
standard obligations. With some
adjustment, the proposed Transactions are reasonable and prudent and in the
public interest. With the modifications
recommended in this Report, the ALJ recommends that the Commission approve the
Transactions because they are consistent with the public interest.
1.
Square
Butte Cooperative (“Square Butte”) currently owns the Milton R. Young
Unit 2 lignite coal electric generating station (“Young 2”) and a +/- 250kV direct current transmission line
(“DC Line”) that runs between the Square Butte Substation in Center,
North Dakota, and Minnesota Power’s Arrowhead Substation near Duluth. Minnkota
Power Cooperative (“Minnkota”) operates Young 2. Both Minnesota Power and Minnkota currently
have power purchase and sales agreements (PPAs) with Square Butte, which transmits
the purchased power to Minnesota Power along the DC Line. Minnesota Power, in turn, retransmits the
power purchased by Minnkota back to Minnkota on existing alternating current
transmission lines.
2.
Minnesota
Power, Minnkota, and Square Butte have entered into the series of agreements,
executed and delivered as of August 11, 2008,[2]
and subsequently amended in a Master Generation Planning Agreement on May 1,
2009.[3] Under those agreements Minnesota Power is
seeking to purchase the DC Line from Square Butte; to restructure its
PPA with Square Butte to facilitate the gradual reduction of Minnesota Power’s share
of the electricity taken from Young 2;[4]
and also potentially to replace the Company’s PPA with Square Butte with a PPA
with Minnkota in the event Minnkota exercises an option to purchase Young 2
from Square Butte.
3.
Commission
approval of the Transactions is required under Minn. Stat. § 216B.50 and
the Commission’s general regulatory authority.
4.
By
Petition filed on May 14, 2009,
Minnesota Power requested the Commission to approve the Transactions.[5]
5.
On July
1, 2009, the Commission issued a Notice and Order for Hearing referring the
matter to the Office of Administrative Hearings to conduct a contested case
proceeding. At that time, the parties to
the proceeding were Minnesota Power and the OES. Minnesota Power notified the Commission that the
parties desired to close the Transactions prior the end of the calendar year. The Notice and Order for Hearing expressed
willingness to meet that schedule, consistent with developing a proper record
and careful decision-making.
6.
The ALJ
conducted a prehearing conference on July 8, 2009, during which there was
agreement on an expedited schedule for prefiling the testimony and for
scheduling the hearing, subject to revision as necessary to assure a complete
record. The hearing was set to begin on September
17, 2009. On July 17, 2009 the ALJ
issued the First Prehearing Order, which memorialized the schedule and
addressed other preliminary matters.
7.
On
August 24, 2009, the Administrative Law Judge issued a Protective Order in this
matter.
8.
Petitions
to intervene were filed by the LPI and NextEra Energy Resources, LLC
(NextEra). The ALJ granted those
petitions at the hearing. On September
15, 2009, the Izaak Walton League of America, Midwest Office; Wind on the
Wires; and the Minnesota Center for Environmental Advocacy (MCEA) submitted a
letter of support of Minnesota Power’s application. At the hearing, the ALJ received that letter
into the hearing record.
9.
The hearing
was held on September 17, 2009, as scheduled.
10.
Minnesota
Power filed its Initial Brief and Proposed Findings of Fact on September 25,
2009. The OES filed its Reply Brief on
October 2, 2009. Due to a technical
failure, the LPI filed their Reply Brief on October 5, 2009; however, the LPI
Reply Brief is accepted as timely. NextEra
resources did not submit a post-hearing brief.
The hearing record closed on October 5, 2009.
11.
Minnesota
Power is an operating division of ALLETE, Inc., and is a public utility
primarily engaged in the generation, transmission, distribution and sale of
electric energy to customers in
12.
The Office
of Energy Security (OES) represents the interests of
13.
The LPI
are a number of Minnesota Power’s large industrial customers.[6]
14.
NextEra
is a wholly owned subsidiary of the FPL Group and a wholesale developer, owner,
and operator of energy generation systems using resources such as wind, solar,
hydroelectric, natural gas, and nuclear.
Many of NextEra’s wind facilities are situated in
15.
Minnkota
is an electrical generation and transmission cooperative, comprised of a number
of member cooperatives, based in
16.
Square
17.
The
Izaak Walton League, Fresh Energy, Wind on the Wires, and the
18.
The
subject of the purchase agreement is the +/- 250kV direct current transmission
line (“DC Line”), owned by Square Butte, that runs 465 miles between the Square
Butte Substation in Center, North Dakota and Minnesota Power’s Arrowhead
Substation near Duluth. The DC Line is
one of only five long distance DC transmission lines in the
19.
The DC
Line currently has a capacity of 500MW. All of Young 2’s generation is
transferred by the DC Line to the Arrowhead Substation, with Minnkota’s share
routed back to Minnkota’s service territory via the AC transmission system.[11]
20.
Minnesota
Power entered into an agreement with Square Butte for an additional 50MW of DC
Line transmission capability that will be made available by 2013 through an
equipment upgrade.[12] The volume of energy potentially movable over
the DC Line will therefore increase to 550 MW by 2013.[13]
21.
Under
the Revised Minnesota Power PPA, which was executed in 1998, Minnesota Power purchased
entitlement to approximately 71 percent of the Young 2 capacity and energy through
January 1, 2027.[14]
22.
Beginning
in 2006, upon a two-year advance notice to Square Butte and Minnesota Power,
Minnkota held options to reduce Minnesota Power’s entitlement by approximately
five percent annually, down to a 50 percent share.[15]. As of January 1, 2009, Minnkota exercised all
available options; consequently, both Minnkota and Minnesota Power are now limited
to 50 percent of Young 2 generation, or approximately 227.5MW each.[16]
23.
Since
Minnesota Power has no direct ownership interest in Young 2,[17] the
Transactions do not include of any Company ownership interest in Young 2. Rather, Minnesota Power will be selling the
Company’s right to take a share of the energy and capacity provided by the
Young 2 unit under the existing Revised Minnesota Power PPA.[18] Accordingly, Commission regulation of that
aspect of the transaction is more properly exercised through the Commission’s
general authority rather than through Minn. Stat. § 216B.50.
D. Terms of the Transactions
24.
The
Asset Purchase Agreement provides for Minnesota Power to purchase Square
Butte’s transmission facilities associated with the DC Line for approximately
$72 million, subject to post-closing adjustments that will include inventory
and Construction Work In Progress (“CWIP”).[19] The Asset Purchase Agreement includes the base
agreement executed on August 11, 2008, together with multiple schedules and attachments.[20] Those schedules and attachments list and
describe the purchased assets in detail; they also describe the easements that
allow Minnesota Power to operate, maintain and replace the Square Butte AC
Substation-East facilities and provide the Company with access and the right to
operate and maintain the pumps, electrical distribution and other support
facilities for the DC Line on the Square Butte Substation.[21]
25.
Minnesota
Power estimates the cost of purchasing the DC Line at approximately $72
million.[22]
The Company initially estimated the net
expected benefit of the proposed Transactions for its ratepayers to be $146
million present value (PV).[23] Later direct testimony revised that estimate to
a net expected ratepayer benefit of $203 million PV.[24]
26.
The
Master Generation Planning Agreement is a three-party agreement between
Minnesota Power, Minnkota, and Square Butte that was executed on May 1, 2009;
it also contains multiple schedules and exhibits.[25]
27.
As
previously discussed, Minnesota Power and Minnkota each purchase half of the
power from Square Butte’s Young 2 station.[26] Minnesota Power also is requesting the
Commission’s permission to restructure its existing Revised Minnesota Power PPA
with Square Butte to facilitate the gradual reduction of Minnesota Power’s purchase
of energy from the Young 2 facility.
28.
Under
the Master Generation Planning Agreement, Minnesota Power would continue to
purchase current levels of Young 2 capacity and energy from Square Butte until
the in-service date of Minnkota’s new 345kV AC transmission line.[27] The parties to the agreement are planning for
this to occur in 2013.[28] After the in-service date of the Minnkota’s
new 345kV transmission line, a new PPA between Minnesota Power and Minnkota
(“Minnkota PSA”) would take effect.[29]
29.
Until
the 345kV line is constructed, Minnesota Power will continue to purchase energy
and capacity from Square Butte under its 1998 PPA. Over time, Minnesota Power will sell an
increasing amount of that energy and capacity to Minnkota. The specified levels
of energy and capacity to be sold under the Minnkota PSA are:
|
Percentage Entitlement of Net Capability and any Capacity available from Unit #2 above the URGE rating |
Megawatts based on 455MW Net Capability |
Time Period |
|
17.0329% |
77.5 MW |
In-Service Date through December 31, 2013 |
|
22.5275% |
102.5 MW |
January 1, 2014 through December 31, 2014 |
|
28.0220% |
127.5 MW |
January 1, 2015 through December 31, 2021 |
|
32.4176% |
147.5 MW |
January 1, 2022 through December 31, 2022 |
|
36.8132% |
167.5 MW |
January 1, 2023 through December 31, 2023 |
|
41.2088% |
187.5 MW |
January 1, 2024 through December 31, 2024 |
|
45.6044% |
207.5 MW |
January 1, 2025 through December 31, 2025 |
|
50.0000% |
227.5 MW |
January 1, 2026 through December 31, 2026 |
30.
However,
if Minnkota experiences a delay of the in-service date for its new 345 kV
transmission line, Minnesota Power’s sales to Minnkota will correspondingly be
delayed.[30]
31.
Under
the Minnkota PSA, Minnkota will pay Minnesota Power an amount equal to
Minnesota Power’s payment to Square Butte of the actual Monthly Charge for
Capacity and Energy plus the Annual Capacity Premium.[31] The Annual Capacity Premium will be applied
directly to reduce Minnesota Power’s fuel adjustment clause.[32]
32.
Also, under
the Minnkota PSA, beginning in 2018, Minnkota has the option, with notice (the
“Exchange Option”),[33]
to require Minnesota Power to convey its existing PPA with Square Butte to
Minnkota and to terminate the Minnkota PSA in exchange for a new power purchase
and sale agreement (New Minnesota Power PPA).[34]
33.
Under
the Master Generation Planning Agreement, Square Butte is required to use the
proceeds from the sale of the DC Line to redeem taxable Square Butte bonds and
pay its make-whole payment, thereby reducing Square Butte’s debt and fixed
payments on its assets and the fixed costs of Young 2 generation.[35] Square
34.
Pending
all state and federal regulatory approvals, Minnesota Power represents that the
proposed closing for the transactions will be December 31, 2009.[38]
35.
As
Young 2 energy deliveries phase out, Minnesota Power plans to add significant
wind-based energy supplies in central
36.
In
addition to using the DC Line to transmit its current Young 2 energy supply, Minnesota
Power is also using that line to transmit wind energy from
37.
Review
of the DC Line purchase is governed by Minn. Stat. § 216B.50, subd. 1, which
provides, in part, that:
No public utility shall sell, acquire, lease, or rent any plant as an operating unit or system in this state for a total consideration in excess of $100,000 … without first being authorized so to do by the commission. … If the commission finds that the proposed action is consistent with the public interest, it shall give its consent and approval by order in writing. In reaching its determination, the commission shall take into consideration the reasonable value of the property, plant, or securities to be acquired or disposed of, or merged and consolidated.
In
determining whether a transaction is in the public interest, no single factor
is determinative; the overall benefits of the sale should exceed the overall
detriments. The public utility seeking
approval of the transaction bears the burden of proof.[44]
38.
Since
the proposed Transactions will affect Minnesota Power’s resource needs,
particularly its needs for renewable energy and the way in which the Company
will meet those needs, it is necessary to analyze the proposed Transactions
under Minn. R. 7843.0400, and Minn. R. 7843.0500. Minn. R. 7843.0400, subp. 4, provides:
A utility shall include in its resource plan filing a nontechnical summary, not exceeding 25 pages in length and describing the utility's resource needs, the resource plan created by the utility to meet those needs, the process and analytical techniques used to create the plan, activities required over the next five years to implement the plan, and the likely effect of plan implementation on electric rates and bills.
39.
More
specifically, the proposed Transactions will create “changed circumstances”
within the meaning of Minn. R. 7843.0500, subp. 5, which provides:
The utility shall inform the Commission and
other parties to the last resource plan proceeding of changed circumstances
that may significantly influence the selection of resource plans. Upon
receiving notice of changed circumstances, the Commission shall consider whether
additional administrative proceedings are necessary before the utility’s next
regularly scheduled resource plan proceeding.
40.
Minn.
R. 7843.0500, subp. 3, governs the scope of Commission review of utility
resource plans and provides:
In issuing its findings of fact and conclusions, the commission shall consider the characteristics of the available resource options and of the proposed plan as a whole. Resource options and resource plans must be evaluated on their ability to:
A. maintain or improve the adequacy and
reliability of utility service;
B. keep the customers' bills and the
utility's rates as low as practicable, given regulatory and other constraints;
C. minimize adverse socioeconomic effects
and adverse effects upon the environment;
D. enhance the utility's ability to
respond to changes in the financial, social, and technological factors
affecting its operations; and
E. limit the risk of adverse effects on
the utility and its customers from financial, social, and technological factors
that the utility cannot control.
41.
When
transactions similar to the proposed Transactions involve a transfer to a
utility under Federal Energy Regulatory Commission (FERC) jurisdiction, the
evaluation of the public interest of the transactions is guided by five specific
criteria in Minn. Stat. § 216B.16,
subd. 7c (a). Although the proposed Transactions do not
transfer assets covered by that statute, some of the public interest criteria
set out in that statute also represent reasonable criteria for assessing the
public interest in the Transactions. Minn.
Stat. § 216B.16,
subd. 7c (a) provides, in pertinent part:
In assessing the public interest, the commission shall evaluate, among other things, whether the transfer:
(1) facilitates the development of transmission infrastructure necessary to ensure reliability, encourages the development of renewable resources, and accommodates energy transfers within and between states;
* * *
(4) impacts
* * *
42.
In its
May 4, 2009 Petition, Minnesota Power lists four main benefits to the
transactions: (1) avoiding the cost and environmental effects of building a new
line, since the DC Line already exists; (2) securing access to high quality
renewable resources; (3) providing strategic energy benefits through reducing
Minnesota Power’s carbon intensity, expanding Minnesota Power’s renewable
resources, and diversifying Minnesota Power’s energy supply; and (4) maintaining
an adequate and competitive power supply.[45]
43.
The MCEA
recognized these benefits when it supported approval of the Transactions as
being in the public interest, stating:
In
addition, the 2007 legislature enacted greenhouse gas reduction goals. Minnesota Power’s proposal in this docket
assists the utility in doing its part to reduce its reliance on greenhouse gas-emitting
generation resources.
Finally,
federal legislative or regulatory action to mandate greenhouse gas reductions
is extremely likely in the near term. For
such mandates to be effective in reducing the nation’s greenhouse emissions at the
levels scientific consensus says is necessary, federal action will have to significantly
alter the economics for emitting greenhouse gases, and create incentives for
cleaner alternatives. It is therefore
prudent for Minnesota Power to take action now to reduce the financial risk its
customers will face in a regulatory environment that puts a price penalty on
greenhouse gas emissions.[46]
B. Development of Necessary Transmission
Infrastructure
44.
The
Commission specifically requested the ALJ and the parties to address whether
the volume of renewable energy supplies potentially movable over the
direct-current line would be proportional to the need for renewable energy.[47] That question is closely related to the
inquiries in Minn. R. 7843.0500, subps. 3A, C, and D relating to the adequacy
and reliability of the Company’s service, minimizing adverse effects upon the
environment, and the Company’s ability to respond to changes affecting its
operations, such as statutory renewable energy requirement. The Commission’s question is also closely
related to the first public interest factor set forth in Minn. Stat. § 216B.16,
subd. 7c(a)(1), that requires an inquiry into whether the Transactions
facilitate the development of transmission infrastructure necessary for
reliability and the development of renewable resources.
45.
In
2007, the Minnesota Legislature passed the renewable energy standard (“RES”),
Minn. Stat. § 216B.1691, which requires electric utilities to meet renewable
energy requirements of increasing percentages from 2012 through 2025.[48] In 2025, twenty-five percent of Minnesota
Power’s energy supply must be derived from renewable energy.[49]
46.
The
Transactions create a path for wind resources to be developed in
47.
Minnesota
Power’s current estimates for the use of the DC Line are as follows: First,
Minnesota Power indicates that the Oliver 1 (50.6 21 MW), Oliver 2 (48 MW), and
Bison 1 (75 MW) projects are scheduled to use the DC Line by 2012. Second, Minnesota Power plans to add an
additional 300 MW of wind capacity over the planning horizon. Thus, Minnesota Power’s current plans include
473.6 MW of wind capacity.[50] Although
Minnesota Power will use the DC Line to take its declining share of Young 2’s
output by 2026 the Company expects to have construction of its entire portfolio
of wind completed. Thereafter, the
Company will no longer be taking any output from Young 2.[51] Minnesota Power indicates that approximately
77 MW (550 MW minus 473 MW) of transmission capability will be “surplus” by
2026. [52]
48.
To meet
its RES requirements for the year 2025, Minnesota Power estimates its overall
renewable energy requirement to be in the range of 2.4 million to 3.6 million
MWh on an annual basis.[53] The OES estimates that by 2025 Minnesota
Power will require 1.0 million MWh to 2.2 million MWh in addition to the energy
from existing renewable sources and projects currently being implemented.[54] Existing renewable sources and projects
currently being implemented include the Oliver 1 (50.6 MW), Oliver 2 (48 MW),
and Bison 1 (75 MW) projects (Total of 173.6 MW).[55] Assuming a 45 percent capacity factor for
49.
The OES
evaluated the amount of renewable energy potentially movable over the DC Line
compared to the need for renewable resources.
The volume of additional renewable energy supplies potentially movable
over the DC Line covers the low end of the Company’s renewable energy
requirement estimate, and the volume is significantly less than the high end of
the renewable energy requirement estimate.[57] The OES therefore concluded that capabilities
of the DC Line reasonably match Minnesota Power’s need for renewable resources.[58]
50.
In view
of the above findings, the ALJ concludes that the volume or renewable energy
supplies potentially movable over the DC Line is proportional to Minnesota
Power’s need for renewable resources.
51.
The ALJ
also concludes that because the Transactions will combine to create a path for
wind resources to be developed by the Company in North Dakota, the transactions
will maintain or improve the adequacy and reliability of Minnesota Power’s
service, minimize adverse effect upon the environment, and enhance the
Company’s ability to respond to changes affecting operations, specifically
meeting Minnesota Power’s current and future needs for renewable resources. The Transactions will therefore satisfy the
criteria set forth in Minn. R. 7843.0500, subps. 3A, C, and D.
52.
The ALJ
further concludes that the Transactions will facilitate the development of
transmission infrastructure necessary for reliability and the development of
renewable resources and will therefore satisfy the public interest criterion set
forth in Minn. Stat. § 216B.16,
subd. 7c(a)(1), to the extent that that criterion helps define the public
interest in this proceeding.
C. The Transactions Represent the Least-Cost Method for
53.
The
Commission also specifically requested the ALJ and the parties to address
whether the proposed Transactions are the least-cost method for the Company of
meeting its renewable energy obligations.[59] That question is closely related to the
inquiries in Minn. R. 7843.0500, subps. 3B, C and D relating to keeping
customers’ bills and the Company’s rates as low as practicable, minimizing
adverse effects upon the environment, and enabling the Company’s to respond to
changes affecting its operations, such as statutory renewable energy
requirements. The Commission’s question
is also closely related to the first public interest factor set forth in Minn.
Stat. § 216B.16, subd. 7c(a)(4), that requires an inquiry into how the
Transactions are likely to impact
54.
Minnesota
Power analyzed three impacts that the Transactions would have on the Company’s
obligations under the RES. The Company
first analyzed the benefit or other impacts the Transactions would have on the
cost to the Company of meeting the
55.
Having identified the three areas of analysis,
the Company developed three different scenarios — a Base (or Expected), High
and Low scenario — to capture the uncertainty surrounding future replacement
power and renewable energy costs, along with potential carbon futures, as well
as the potential range of impact that this project would bring to the Minnesota
Power customers. The Base scenario was
based on assumptions associated with an ‘expected’ future for future power
costs, carbon futures and renewable mandate implications (expected
savings/benefits). The High scenario was
based on an optimistic outlook (high savings/benefits) for these key variables
affecting the decision, and the Low scenario was a pessimistic outlook (low
savings/benefits). It was the Company’s
belief that development of those three scenarios would provide a reasonable
basis for strategic decision making.[61]
56.
The company assessed the carbon impact of the
57.
For the replacement power impact of this
project, Minnesota Power evaluated the costs associated with reducing Young 2
energy and capacity from its resource mix gradually from 2013 through
2026. To determine the replacement
energy cost component, Minnesota Power ran a production cost generation
dispatch scenario for its system with and without Young 2 generation for the
planning period to determine what resources would be needed to replace the
reduced energy from the Young 2 resource. The difference between the two cases includes
a component of wholesale market purchases and a ramping up of the existing
Minnesota Power generation fleet resources to meet the loss of Young 2
energy. To quantify the cost component
of the replacement energy, the production dispatch model for the Expected
scenario included natural gas prices starting at $8.00/MMBtu, associated
wholesale market prices, and the existing fleet dispatch costs. The two components (market energy costs and
existing fleet energy dispatch costs) were aggregated together based on the
amount of each included in the replacement dispatch to identify an annual
replacement energy price to associate with the energy lost from the Young 2
resource. For the High and Low scenarios
a natural gas price of $6.00/MMBtu and $10.00/MMBtu were used respectively (as
replacement power is a cost, the higher priced energy was associated with the
low savings scenario). For all three scenarios, the capacity that phased out
with the Young 2 generation from 2013 – 2026 was replaced with peaking
capacity. The replacement energy costs
and capacity savings were netted together on an annual basis to determine an
overall replacement power cost for the North Dakota Wind Project.[63]
58.
Based on its analyses, Minnesota Power concluded
that completing the North Dakota Wind Project could be expected to bring a
range of potential benefits to Minnesota Power ratepayers of $13 Million to
$275 Million reflecting the potential Low and High scenarios for the project
and an Expected net benefit of $146 Million of net benefit over the study
period.[64]
59.
OES
Witness Rakow and LPI Witness Hayet reviewed and tested the Company’s analyses.
Both witnesses used somewhat different methodologies,
calculations, and assumptions, but both reached essentially the same
conclusion.[65]
Minnesota Power agreed with the overall
conclusion of both witnesses.[66]
60.
OES
Witness Rakow summarized his conclusions as follows:
The
result of my calculations, assuming the low end of the range for carbon
savings, renewable energy savings, and externality costs, is that the proposed
Transactions represent a benefit of about $63.2 million PV. The result,
assuming the high end, is a benefit of $293.9 million PV. Therefore, I conclude
that the proposed Transactions are the least cost method for the Company to
fulfill its obligations under the renewable energy standard.[67]
61.
LPI
Witness Hayet summarized his conclusions as follows:
Based
on a review of the Company’s Base Case and sensitivity analyses, I believe the
Company’s results are reasonable, and that the Company should be authorized to
proceed with the proposed transactions. Although I do have some minor concerns
about the Company’s analyses, I don’t believe that those concerns are of
sufficient magnitude that addressing them would alter the outcome of the
Company’s analysis.[68]
62.
In view
of the above findings, the ALJ concludes that the Transactions that Minnesota
Power proposed are the least-cost method for the Company to meet its
obligations under the RES.
63.
The ALJ
also concludes that the Transactions will combine to keep customers’ bills and
the Company’s rates as low as practicable, minimize adverse effects upon the
environment, and enhance the Company’s ability to respond to changes affecting
operation, specifically meeting Minnesota Power’s current and future needs for
renewable resources. The Transactions
will therefore satisfy the criteria set forth in Minn. R. 7843.0500, subps. 3B,
C and D.
64.
The ALJ
further concludes that the Transactions will reduce the impacts that the
RES will have on Minnesota Power’s retail rates and will therefore satisfy the public interest criterion set forth in Minn.
Stat. § 216B.16, subd. 7c(a)(4), to
the extent that that criterion helps define the public interest in this
proceeding.
D. The Capacity of the DC Line Not Used for Transmission of
Renewable Energy Will Be Insignificant
65. The Commission directed the parties and the
ALJ to evaluate whether the capacity of the DC Line will significantly exceed
the capacity required to meet the RES and, if so, how the line's "excess
capacity" should be treated,[69] Based on information provided by the Company, OES
Witness Rakow determined the capacity of the DC Line will be 550 MW and that
Minnesota Power’s current plans include 473.6 MW of wind capacity.[70] In addition, the DC Line will be used to
transmit Minnesota Power’s declining share of the output from Young 2 until
2026.[71] The excess of transmission capacity over
Minnesota Power’s planned use is 77 MW.[72] However, as noted by OES Witness Rakow,
Minnesota Power may need additional renewable resources. Minnesota Power agreed
with this conclusion.[73]
66.
In view
of the above, the ALJ concludes that the capacity of the DC Line will not
significantly exceed the capacity required by Minnesota Power to meet its RES
requirements. Any available excess
capacity not used by Minnesota Power will be subject to the FERC open access
requirements,[74]
and the FERC process will address how any excess capacity would be used. [75]
E. Summary
of Public Interest Analysis
67. The
proposed Transactions satisfy the pertinent public interest criteria in Minn.
Stat. § 216B.16, subd. 7c (a)(4) and
Minn. R. 7843.0050, subp. 3, to the extent that those criteria assist in
determining whether the proposed Transactions are consistent with the
public interest within the meaning of
Minn. Stat. § 216B.50, subd. 1.
68. The proposed Transactions will also result
in a volume of renewable energy supplies potentially movable the DC Line
proportional to Minnesota Power’s need for renewable resources and are the
least-cost method for the Company to meet its obligations under the RES. Moreover, the excess capacity of the DC Line
will not significantly exceed the capacity required to meet the RES.
69. The
economic analyses that the parties conducted compared implementing the proposed
Transactions to continuing with Minnesota Power’s prior RES compliance plan and
concluded that this project’s potential benefits significantly exceeded its
potential costs.[76] Translated into rate impact, implementing the
proposed Transactions will cause rates to be lower than they would otherwise
have been under Minnesota Power’s prior RES compliance plan.[77]
70. Since Minnesota Power’s petition is not
proposing a new facility, the analysis in this Docket is analogous to Certificate
of Need and siting proceedings. Detailed
information regarding rate impacts is not available. That information will not
be available until Minnesota Power's next rate case. The information that is
available is the annual cost impact of the proposed project.[78]
71.
The
Transactions proposed by Minnesota Power are the least-cost method of meeting
its obligations under the Renewable Energy Standard. As such, the Transactions meet public
interest criteria relating to rates. The
impact on
72. In determining whether the proposed
Transactions are reasonable and prudent, it was the understanding of OES
Witness Rakow that:
This
criterion refers to the net effect of the proposed Transactions. Considering the results of the cost analysis,
as long as Dr. Amit’s concerns are addressed, I conclude that the proposed
Transactions are reasonable and prudent.[79]
73.
It is
the position of the OES that its analysis supports a finding that the
Transactions are in the public interest, subject to certain conditions that OES
has proposed.[80]
74.
As part
of its public interest analysis, the OES analyzed the Transactions under the
framework of resource planning as set out in Minn. Rule 7843.0500. Under that framework, the OES concluded that:
The
proposed Transactions have either no impact or a positive impact on the
resource planning criteria. There may be a positive impact to the extent that
the Transactions increase MP’s renewable resources without adding significant
new infrastructure.[81]
75.
The proposed Transactions satisfy the evaluative
criteria set forth in Minn. R.
7843.0050, subp. 3.
A. Potential
Capacity and Energy Payments to Minnkota
76.
It is
the opinion of OES witness Dr. Amit that provisions of the New Minnesota Power
PPA, taken together, are contrary to the public interest because they would
result in Minnesota Power being obligated to pay Minnkota for contracted, but
undelivered, capacity and energy for up to twelve consecutive months.[82]
77.
The
concerns identified by Dr. Amit relate to the terms in the restructured
PPAs. On May 29, 1998, Minnesota Power
entered into a power purchase agreement to purchase power from Square Butte
(Minnesota Power PSA). On April 30,
2009, Minnesota Power, Minnkota, and Square Butte executed an Amended and
Restated Master Generation Planning Agreement (Master Agreement). Among other things, the Master Agreement
contained two proposed new Purchased Power Agreements. The first covered power purchased by Minnkota
from MP (New Minnkota PPA), and the second covered power purchased by MP from
Minnkota (New Minnesota Power PPA). Neither
new PPA is to become effective until the closing date of the transactions being
submitted for Commission approval.[83]
78.
Section
3.6 of the New Minnkota PPA contained the following provision for an Exchange
Option:
Exchange
Option. Minnesota Power grants Minnkota the exclusive
option (the “Exchange Option”) to be effective as of the Exchange Option
Exercise Date, to surrender and terminate the New Minnkota PSA and exchange the
Minnesota Power PSA for the Revised Minnesota Power PPA (the “Exchange”). If Minnkota exercises the Exchange Option,
Minnkota will surrender the New Minnkota PSA in exchange for the Revised
Minnesota Power PPA. Minnkota shall
request Square Butte to consent to such Exchange in order to exercise the
Exchange Option.[84]
79.
In
other words, in the event that Minnkota does exercise its Exchange Option, the
proposed New Minnesota Power PPA replaces the existing PPA that Minnesota Power
has with Square Butte. Under the
replacement PPA, Minnesota Power becomes entitled to certain receive scheduled
net capability and capacity entitlements.[85]
80.
Those
scheduled net capability and capacity entitlements are covered in Article III,
Section 3.2, of the New Minnesota Power PPA , which states in pertinent part:
[U]nder
this Agreement beginning on the Exchange Option Exercise Date and during the
time period indicated below, Minnesota Power shall purchase from Minnkota and
be entitled to the percentage entitlement of Net Capability, and to the Energy
associated with such entitlement to Net Capability as measured at the Delivery
Point for Energy for the remaining time period in which the Exchange Option
Exercise Date occurs, and for the corresponding percentage entitlements of Net
Capability and associated Energy for the subsequent time periods as follows.[86]
A table in that Section establishes a
schedule of percentage entitlements of Net Capacity that begins at 50% on the
Closing Date and progressively decline to 0% on January 1, 2026.
81.
Section
4.1 of the Proposed PPA provides, in part:
Monthly
Charges. Minnesota Power shall pay to
Minnkota for each Month of each Contract Year a monthly charge (hereinafter
called the “Monthly Charge for Capacity and Energy”), regardless of the
percentage entitlement of Net Capability or Alternate Capacity actually made
available to Minnesota Power or the amount of Energy or Alternate Energy
actually delivered to Minnesota Power, except as provided in Section 4.4.[87]
82.
Sections 4.1.1 et seq., describe how the
Monthly Charges for Capacity and Energy are to be calculated.
83.
Section
4.5.1 of the Proposed PPA provides:
Obligation
to Make Payment. Except as provided in Section 4.5.2,
Minnesota Power shall make all payments that are required pursuant to the terms
of this Agreement at such time or times herein provided for such payments,
notwithstanding (1) the non-performance of Minnkota of any of its obligations
herein or in the Joint Operating Agreement, whether due to Uncontrollable
Forces or otherwise; (ii) the failure, inoperativeness or suspension,
interruption or interference of the operation of Unit #2; (iii) the failure to
make available to Minnesota Power its percentage entitlement of Net Capacity or
Alternate Capacity or to deliver to Minnesota Power the Energy or Alternative Energy
(except provided in Section 4.5.2; (iv) the invalidity or unenforceability or
lack of due authorization of this Agreement; or (v) any other matter or event
whatsoever, including without limitation the bankruptcy or insolvency of
Minnkota or the disaffirmance of any agreement by any trustee or receiver,
which might otherwise relieve Minnesota Power from the obligation to pay such
amounts at such times, notwithstanding any present or future law to the
contrary.[88]
84.
Section
4.5.2 of the Proposed PPA provides:
Suspension
of Payment Obligation. Minnesota Power’s obligation to pay charges
under Section 4.1 shall be suspended only in the event that Minnkota does not
receive from Square Butte and Minnkota fails to deliver any Energy or Alternate
Energy whatsoever to any Delivery Point for a period of twelve (12) consecutive
Months. Such suspension, if any, shall
begin at 12:01 a.m. CPT of the first (1st) day of the Month following such
twelve (12) Month period, and shall continue until such time as Minnkota shall resume
the delivery to Minnesota Power of any Energy or any Alternate Energy at any
Delivery Point; provided, however, that such suspension shall not relieve
Minnesota Power of its obligation to make payment of the Monthly Charges for
Capacity and Energy incurred prior to the commencement of such suspension.[89]
85.
Based
on the testimony of its witness Dr. Amit, the OES maintains that Sections 4.1,
4.5.1, and 4.5.2 of the New Minnesota Power PPA, taken together, are contrary
to the public interest because they would result in Minnesota Power being
obligated to pay Minnkota for contracted, but undelivered, capacity and energy
for up to twelve consecutive months.
This, OES argues, would inappropriately shift the financial risk of
nonperformance and failure to provide the contracted capacity and energy for
events other than force majeure
events to MP’s ratepayers, rather than that risk being borne by Minnkota or by
MP’s shareholders.[90]
86.
The OES suggests two alternative approaches to
correcting what it considers to be an inappropriate allocation of financial
risk. One alternative is to amend the
New Minnesota Power PPA to require the Company to pay Minnkota only for
capacity and energy actually delivered.
The second alternative is to approve the New Minnesota Power PPA without
changes but allow the Company to recover from ratepayers only the costs of
capacity and energy actually delivered by Minnkota to Minnesota Power.[91] In effect, the second alternative shifts the
risk of Minnkota’s failure to provide the contracted capacity and energy to
Minnesota Power’s shareholders.
87.
The OES
favors the second alternative and recommends that the Commission approve MP’s
Petition subject to the following conditions:
(1) MP may only recover the cost of capacity
payments for capacity actually credited to MP; and
(2) MP
may recover the cost of alternate energy only up to the level of the cost of
the energy that would have been provided by Young 2.[92]
88.
Minnesota
Power disagrees with the OES position that the proposed contractual obligation
to pay Minnkota for contracted, but undelivered, capacity and energy is
contrary to the public interest.
Minnesota Power addressed the OES’s objections and recommendation by
citing five reasons why the terms of the New Minnesota Power PPA should not be
altered or conditions imposed on Commission approval of its Petition.[93]
89.
First, Minnesota Power argues that the current
Minnesota Power PSA between the Company and Square Butte, which was executed on
May 29, 1998, contains identical provisions, and that those provisions have
never been invoked or resulted in a cost to ratepayers during the last eleven
years.[94] In response, the OES argues that neither past
practice nor the absence of past triggering events makes inappropriate
provisions appropriate.[95]
90.
Second, the Company argues New Minnesota Power
PPA, which contains the contract provisions in question, will only become
effective if and when Minnkota actually exercises the Exchange Option. Moreover, that is likely to happen only if
Square Butte has a significant financing need.
If such a need is met, for example, by issuing bonds, then payments for
undelivered capacity and energy will be needed to pay bond obligations if a
major outage were to occur. Minnesota
Power further argues that the existence of these undelivered capacity and
energy obligations will reduce investment risk and therefore the financing cost
for Square Butte. Lower financing costs
will, in turn, reduce the cost of the power that MP ratepayers pay for power
purchased from Square Butte.[96] In response, the OES argues that it is not
clear that the existence of undelivered capacity and energy obligations will
necessarily result in least-cost financing for Square Butte. Moreover, those payment obligations constitute
imputed long term debt which results in higher debt and equity costs for
Minnesota Power. On balance, the
existence of those obligations may therefore result in a net increase, rather
than net decrease, in the cost of power that the Company purchases from Square
Butte.[97]
91.
Third, Minnesota Power does not have an
ownership interest in Young 2, and it is therefore not a rate-based asset. Nevertheless, the Company argues that Young 2
is analogous to a rate-based asset because, unlike an independent power producer,
Square Butte does not build a risk premium or a rate of return component into
the purchase price that Minnesota Power pays.
Thus, the Company contends, its ratepayers pay decreased costs for power
supplied by Young 2. The Company further
argues that those decreased costs are possible because Minnesota Power and
Minnkota provide the only credit support for Square Butte’s debt financing
through the obligations they have contracted for in their respective PPAs. MP contends that those obligations, including
the obligation to pay for contracted but undelivered capacity and energy, are
therefore what make the reduced power costs to ratepayers possible.[98] In response, the OES argues that if Minnkota
exercises the exchange option and the Revised Minnesota Power PPA and the
obligations at issue become effective, then Minnesota Power ratepayers will be
holding Minnkota financially harmless from the risk of its nonperformance due
to a major Square Butte outage. The OES
contends that this is then more properly a risk that Minnkota ratepayers or shareholders
should bear, as opposed to the ratepayers or shareholders of Minnesota Power,
regardless of how both companies decide to finance Square Butte.[99]
92.
Fourth, the Company contends that if Young 2
were to experience an extended forced outage of less than 12 months, Minnesota
Power could still count the capacity under MISO accreditation rules as long as
Young 2 were placed back in service within that time frame.[100] The OES agreed that in that event, Minnesota
Power should continue making its capacity payments. However, in essence the OES argues that
Minnesota Power should not also be obliged to pay fixed costs for energy that
is not delivered when the Company would be required to purchase energy from
other sources to meet its peak load capacity.[101]
93.
Fifth, the Company points out that under Article
III, Section 3.2, of the New Minnesota Power PPA, the Company’s percentage
entitlements of Net Capacity will begin at 50% on the Closing Date and
progressively decline to 0% on January 1, 2026. The company therefore argues
that any ratepayer financial risk associated with paying Minnkota for capacity
and energy not actually delivered will correspondingly decline and will no
longer represent any risk on January 1, 2026.[102] The OES responded that although the risk to
the Company’s shareholders would decline over time and eventually disappear in
2026, it still would be a risk more properly borne by the Company’s
shareholders than its ratepayers.[103]
94.
In the final analysis, the ALJ concludes that
approval of the transmission line purchase and associated agreement will be in
the best interests of Minnesota Power’s ratepayers, shareholders, and the
public at large. Since requiring the
Company to amend the New Minnesota Power PPA to require the Company to pay
Minnkota only for capacity and energy actually delivered might jeopardize
consummation of the pending transaction, the ALJ concludes that such a
condition of approval would not be in the public interest.
95.
Furthermore, since it appears to be commercially
reasonable for Minnesota Power to recover from its ratepayers the cost of
capacity and the cost of producing energy that is actually delivered to the
Company by Minnkota, the ALJ recommends that the Commission place no conditions
on approval that would prevent that from occurring in the event that Minnkota
exercises the Exchange Option.
96.
However, the ALJ concludes that it would not be
commercially reasonable and in the public interest for MP to recover from its
ratepayers the cost of energy not actually delivered to the Company by Minnkota
in the event that it exercises the Exchange Option. First, Minnesota Power’s arguments that the
risk of nondelivery for up to twelve consecutive months is essentially de minimis because of past practice and
experience, relative unlikelihood that the Exchange Option will be exercised,
and the declining nature of the risk over an eight-year period apply with equal
force to risk that is borne by ratepayers or by shareholders. Second, allowing the Company to recover from
ratepayers both capacity costs and the costs of producing energy that is
actually delivered further diminishes the potential financial risk to
shareholders.
97.
There appears to be no compelling commercial
reason for Minnesota Power ratepayers to bear the financial risk of having to
pay for the costs of undelivered energy under the New Minnesota Power PPA, and
there is no apparent commercial reason or public policy consideration for
relieving MP shareholders of that risk.
For these reasons, the ALJ concludes that it would be in the public
interest for the Commission to condition approval of the Transactions on the
terms set out in Finding 87, above.
B. Limiting
the Cost of Curing Future Easement Defects
98.
In
Article VII of the Asset Purchase Agreement, Minnesota Power assumes
responsibility to cure easement defects discovered prior to closing.[104] The LPI expressed concern that ratepayers could
be responsible for litigation and other costs associated with curing easement
defects discovered after the Transactions closed. Specifically, the LPI contemplate such problems
as tax forfeitures, railroad and highway crossings, recording problems that
might not be discoverable before closing.
The LPI propose that Minnesota Power avoid having any responsibility for
easement defects through a title insurance policy. They also recommend that the Commission cap
recovery for any expenses related to curing easements that Minnesota Power subsequently
incurs at $25,000.[105]
99.
Minnesota
Power acknowledged the possibility of undiscovered easement defects but argued
that the cost of curing future easement problems cannot be quantified. Moreover, the Company further characterized
the possibility of significant financial impact from undiscovered easements as
“a remote possibility that can be addressed at the time, if necessary.”[106]
100. Minnesota Power has had considerable experience
with the kinds of property transactions involved in the transfer of DC Line
assets. Moreover, the kinds of easement
problems to which the LPI refer are no different than the kinds of easement
problems that periodically arise with any electrical utility’s existing
transmission lines. There is no evidence
that such problems have previously resulted in significant costs to the
Company’s ratepayers. The ALJ therefore
concludes that the terms of the Transactions regarding responsibility for easements
are reasonable and prudent and concludes that Commission approval of the
Transactions should not be conditioned on requiring Minnesota Power to obtain a
title insurance policy or on capping recovery for any easement-curing related
expense assumed by Minnesota Power at $25,000.
C. Requiring an RFP Process for Future
101. LPI
Witness Hayet’s expressed skepticism that future
[T]he Commission should not explicitly or
implicitly agree that the Company itself should construct the additional wind
resources in
102. The LPI assert that Minnesota Power has not
followed the Certificate of Need process, nor has it yet filed an amended IRP
to demonstrate that the costs of constructing its own future wind generating
project will be prudent. Based on that and
Mr. Hayet’s testimony, the LPI contend that the Commission should require
Minnesota Power to conduct an RFP process for any future North Dakota wind
generation project to ensure that Minnesota Power pursues the most
cost-effective alternative for obtaining future North Dakota wind energy that
will be transmitted along the DC Line.
The LPI argue that requiring such an RFP process is necessary to adequately
protect Minnesota Power’s ratepayers.[108]
103. In response, Minnesota Power asserts that it
will necessarily have the burden of proof to establish that any of its own future
104. In view of the above findings, the ALJ
concludes that the LPI have failed to establish that an RFP process is necessary
to supplement the Commission’s existing processes for assessing new generation
sources to assure that the Company will obtain the lowest cost
D. Risk
of Minnkota’s Failure to Complete Its Proposed 345kV Line
105. The LPI also ague that the possibility that
Minnkota’s anticipated 345 kV line might not be completed poses an unreasonable
risk to ratepayers because that would alter Minnesota Power’s scheduled use of
the DC line, would require the Company to obtain more expensive alternative
sources of renewable energy, and would diminish the projected monetary benefits
that the Transactions would provide to ratepayers. The LPI propose that Minnesota Power
recalculate the costs derived through its production cost planning model using
actual data and compare the results with the forecast in this Petition. LPI further proposes that any difference
between actual and projected costs would then be refunded to ratepayers.[111]
106. Alternatively, the LPI recommend modifying
the terms of the Transactions to remove the provision that triggers the conclusion
of 227.5 MW of firm point-to-point transmission service when the Minnkota 345
kV line comes into service. In its
place, the LPI propose that Minnesota Power’s reassignment of 227.5 MW of firm
point-to-point transmission service rights should run from the closing date
until January 1, 2013. The LPI contend
that that modification would ensure that “Minnesota Power can proceed as
planned to meet the State renewable mandates and Minnkota is properly
incentivized to timely conclude construction of the AC Line.”[112]
107. In response, Minnesota Power maintains that Minnkota
has every financial incentive to permit and construct the 345 kV transmission
line and is on course to do so by 2013.[113] Minnesota Power also contends that the
failure to build the 345 kV line would leave ratepayers in the same position as
if the Transactions had never occurred except for Minnesota Power now owning a
significant transmission asset.[114]
108. Minnesota Power also objected to the LPI
proposal as being unworkable from a contracting or implementation standpoint
given the difficultly in assessing the potential direct rate impacts.[115] Minnesota Power stated that it was committed
to keeping the Commission informed on the progress of the permitting and
construction schedule of the new 345kV line through this Docket and through future
Commission proceedings to assess Minnesota Power’s renewable resource plans
under Minn. Stat. § 216B.1691, subd. 3, and Minnesota Power’s resource
plans under Minn. Stat. § 216B.2422.[116]
109. In addition to the Company’s responses, the
ALJ concludes that a fallacy underlies the LPI’s recommendation for the
requested conditions. If the 345 kV line
were not constructed, the result would not be an additional cost that the
Company’s ratepayers would have to pay.
Rather, that contingency would simply result in an unrealized benefit for
ratepayers because the Company’s least-cost method of obtaining renewable
energy would be some other proposal. In
view of the above, the ALJ recommends that the Commission not impose conditions
on approval of the Transactions requiring modifications to the Transactions or
requiring Minnesota Power to make a refund to ratepayers in the event that
Minnkota’s anticipated 345 kV line is not completed.
E. Termination of the Company’s Involvement on the Young 2
Operating Committee
110. The LPI also contends that terms in the
Transactions specifying that Minnesota Power’s term on the Young 2 operating committee
runs until Minnesota Power’s net entitlement to the output of Young 2 is 100 MW
or less poses another risk to ratepayers. That is expected to occur in 2015.[117] The LPI’s concern is that, under the existing
contractual terms, Minnesota Power will be ending its involvement in the
process for deciding what Minnkota’s costs will be before the Company stops
receiving energy from Young 2. The LPI
suggest the Minnkota would have complete discretion to determine what costs it
would be able from Minnesota Power under, for example, the Make Whole
Adjustment. The LPI also express concern
that any projects to address carbon emissions reduction for Young 2 will be
planned and budgeted well after 2015, when Minnesota Power would no longer be a
member of the operating committee. The LPI
therefore propose that the Commission require changes to the Transactions to ensure
that Minnesota Power will remain on the operating committee until the Company no
longer entitled to power from that facility.[118]
111. In response, Minnesota Power asserts that
its agreement to the provisions in the Transactions ending its involvement with
the Young 2 operating committee before the Company stops receiving any energy
from that facility was a matter of reasonable business judgment:
Certainly
it was a judgment call on our part on when the time and effort needed to – to meaningfully
participate in an operating committee was justified. And we participate now in
that operating committee because we have 227 megawatts of the power, or half of
the power out at the plant. We just made the judgment that when our take went
down to a small enough level – in this case, when it gets to 100 megawatts --
that we wouldn't directly participate in the operating committee. Certainly our
interests are very much aligned with Minnkota. Minnkota has every incentive in the world to
keep the costs down on that project. And through the years our interests have
been very much aligned. So, in our
opinion, we didn't jeopardize our customers' costs at all by choosing to not
directly participate.[119]
112. Minnesota Power has no ownership interest in
Young 2.[120] The Company’s current participation in the operating
committee arises from Minnesota Power’s entitlement to one-half of the
electricity generated by that facility. One
of the Transactions’ goals is ending Minnesota Power’s use of Young 2 as a
source of energy. As Minnesota Power’s
share of the output is reduced, the importance of Minnesota Power’s
participating on the operating Committee is commensurately reduced. The ALJ therefore concludes that Minnesota Power’s
agreement to terms in the Transactions that end the Company’s participation in
the Young 2 operating committee before the Company stops receiving any energy
from that facility was a matter of reasonable business judgment. The ALJ therefore concludes that the
Commission should not impose a condition on its approval of the Transaction
requiring modification of the Transactions to end Minnesota Power’s
participation in the Young 2 operating committee only when the Company stops receiving
energy from that facility.
113. Minnesota Power agreed to conditions
regarding capacity premiums, transaction costs, and the timing of the reduction
to Minnesota Power’s common equity ratio.[121] Those conditions are appropriate for adoption
by the Commission. To the extent
clarification is necessary regarding Minnesota Power’s “next” rate case,
conditions referring to the next rate case should apply with reference to the
first rate case filed by Minnesota Power subsequent to its rate increase in
Commission Docket No. E-015/GR-08-415.
114. The citations to exhibits in the Findings
are not intended to indicate that all evidentiary support in the record has
been cited.
Based on these Findings of Fact,
the Administrative Law Judge makes the following:
1.
The Minnesota
Public Utilities Commission and Administrative Law Judge have jurisdiction to
consider the Minnesota Power’s application for approval of the Transactions.[122]
2.
No
public utility shall sell any plant as an operating unit or system in
3.
Although
the Transactions do not involve a sale by Minnesota Power of ownership in a
generating facility, the Transactions have a similar effect by modifying PPAs
that vest Minnesota Power with the rights to the electricity generated. The Transactions are therefore subject to the
Commission’s approval.
4.
The
Commission shall give its consent and approval by order in writing if the
proposed sale is “consistent with the public interest.”[124] In assessing the public interest, the Commission
shall evaluate several statutory criteria.[125]
5.
The
public utility seeking approval of a transaction bears the burden of proof that
the statutory criteria are satisfied.[126]
6.
Minnesota
Power has demonstrated that
a. The Transactions facilitate the development
of transmission infrastructure necessary to ensure reliability, encourage the
development of renewable resources, and accommodate energy transfers within and
between the states.
b. The proposed
Transactions will maintain or improve the adequacy and
reliability of Minnesota Power’s service and will keep its customers' bills and
the Company’s rates as low as practicable, given regulatory and other
constraints.
c. The
proposed Transactions will minimize adverse socioeconomic effects
and adverse effects upon the environment and will enhance the utility's ability
to respond to changes in the financial, social, and technological factors
affecting its operations.
d. Subject
to the conditions described below, the
proposed Transactions will limit the risk of adverse effects on
the utility and its customers from financial, social, and technological factors
that the utility cannot control.
e. Satisfy
the evaluative criteria for reviewing resource plans contained in Minn. R. 7843.0050, subp. 3.
f. The Transactions will not have a negative
impact on
g. The proposed Transactions will also result
in a volume of renewable energy supplies potentially movable the DC Line
proportional to Minnesota Power’s need for renewable resources and are the
least-cost method for the Company to meet its obligations under the RES.
h. The capacity of the DC line will not
significantly exceed the capacity required to meet the Company’s RES. Minnesota Power’s offering of any "excess
capacity" pursuant to the FERC open tariff is reasonable.
i. The Transactions are reasonable and prudent,
and in the public interest.
7.
If the
Commission approves the Transactions, it is in the public interest to condition
approval upon Minnesota Power’s acceptance of certain limitations on costs that
can be recovered from ratepayers, specifically:
a.
MP may
only recover the cost of capacity payments for capacity actually credited to
MP; and
b.
MP may
recover the cost of alternate energy only up to the level of the cost of the
energy that would have been provided by Young 2.
8.
Any of
the Findings more properly designated Conclusions are hereby adopted as such.
Based
upon these Conclusions, the Administrative Law Judge makes the following:
Dated: October 27, 2009
s/Bruce H. Johnson
|
BRUCE
H. JOHNSON Administrative
Law Judge |
Reported: Shaddix
& Assoc., 1 volume
Notice is hereby given that, pursuant to
Minn. Stat. § 14.61, and the Rules of Practice of the Minnesota Public
Utilities Commission and the Office of Administrative Hearings, exceptions to
this Report, if any, by any party adversely affected must be filed by the date
set by the Commission with the Executive Secretary, Minnesota Public Utilities
Commission, 350 Metro Square, 121 - 7th Place East, St. Paul, Minnesota 55101,
or electronically filed.
The Minnesota Public Utilities Commission
will make the final determination of the matter after the expiration of the
period for filing exceptions, or after oral argument, if it is held.
The Commission may accept or reject the
Administrative Law Judge’s recommendation and this recommendation has no legal
effect unless expressly adopted by the Commission as its final order.
[1] The proposed sale and associated agreements are hereafter referred collectively to as the “Transactions.”
[2] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 46; Paulseth Direct, Ex. 7 at 5.
[3]
[4] Hodnik Direct, Sched. I, Part 1, at 12; Minke Direct, Ex. 19 at 2.
[5] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 12; Rakow Direct, Ex. 16 at 2-3.
[6] The LPI are ArcelorMittal USA (Minorca Mine); Blandin Paper Company; Boise, Inc.; Enbridge Energy Limited Partnership; Hibbing Taconite Company; NewPage Corporation; Sappi Cloquet, LLC; United States Steel Corporation (Keewatin Taconite and Minntac Mine); and United Taconite, LLC.
[7] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 18-19.
[8]
[9] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 19.
[10] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 19; Tr. at 58.
[11]
[12] Hodnik Direct, Sched. I, Part 1, Ex. 3, n.13 at 19.
[13] Rakow Direct, Ex. 16 at 6.
[14] Ex. 3 at 19.
[15]
[16]
[17] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 18-19.
[18] Rakow Direct, Ex. 16 at 2-3.
[19] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 46-48.
[20]
[21] Donahue Direct, Ex. 9 at 2; Hodnik Direct, Sched. I, Part 1, Ex. 3 at 83-121.
[22] Hodnik Direct, Sched. I, Part 3, Ex. 5 at 611; Minke Direct, Ex. 19 at 2.
[23] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 58; Rakow Direct, Ex. 16 at 4.
[24] Pierce Direct, Ex. 8 at 10.
[25] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 49; Ex. 7 at 5.
[26]
[27] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 50, Hodnik Direct, Sched. I, Part 2, Ex. 4 at 436‑437; Paulseth Direct, Ex. 7 at 3.
[28]
[29] The Minnkota PSA would be executed at closing and is labeled Exhibit A-1 to the Master Generation Planning Agreement. Hodnik Direct, Sched. I, Part 1, Ex. 3 at 50-51; Paulseth Direct,Ex. 7 at 3; Hodnik Direct, Sched. I, Part 3, Ex. 5 at 492-533.
[30] Hodnik Direct, Sched. I, Part 2, Ex. 4 at 421; Tr. at 28.
[31] Hodnik Direct, Sched. I, Part 2, Ex. 4 at 433 (Table 3).
[32] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 40; Ex. 17 at 17-18; Tr. at 29.
[33] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 53; Ex. 5 at 510; Paulseth Direct, Ex. 7 at 7-8.
[34] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 53; Hodnik Direct, Sched. I, Part 3, Ex. 5 at 540‑572; Paulseth Direct, Ex. 7 at 8; Ex. 13. The New Minnesota Power PPA is labeled Exhibit A-2 to the Master Generation Planning Agreement.
[35] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 55; Paulseth Direct, Ex. 7 at 9; Hodnik Direct, Sched. I, Part 3, Ex. 5 at 440 (Public); Hodnik Direct, Sched. I, Ex. 2 at 440 (TS).
[36] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 55; Hodnik Direct, Sched. I, Part 3, Ex. 5 at 440.
[37] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 55; Paulseth Direct,Ex. 7 at 8-9; Hodnik Direct, Sched. I, Part 2, Ex. 4 at 429-430.
[38] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 24, 72.
[39]
[40] Hodnik Direct, Ex. 1 at 4-7; Paulseth Direct, Ex. 7 at 7-8; Rakow Direct, Ex. 16 at 8.
[41] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 20; Ex. 7 at 9-10; Rakow Direct, Ex. 16 at 6-7.
[42] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 20; Rakow Direct Ex. 16 at 6-7; Tr. at 31.
[43] Docket No. E015/M-09-285.
[44] See e.g. Minn. Stat. § 216B.16, subd. 4 (regarding
changes in rates); Minn. R. 1400.7300, subd. 5; In re
[45] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 23; Rakow Direct, Ex. 16 at 3-4.
[46] Ex. 14.
[47] Notice of Hearing at p. 2.
[48] Hodnik Direct, Ex. 1 at 5.
[49] Minn. Stat. § 216B.1691, subd. 2a(a).
[50] Those estimates were contained in Minnesota Power’s response to OES Information Request No. 10 and were relied upon by OES witness Rakow in his testimony. Rakow Direct, Ex. 16 at 6-7.
[51] Rakow Direct, Ex. 16 at 6, 8.
[52]
[53] Pierce Direct, Ex. 8 at 8.
[54] Rakow Direct, Ex. 16 at 8.
[55] See Finding No. 46.
[56] Rakow Direct, Ex. 16 at 6-8; see also, Pierce Direct, Ex. 8 at 7-8.
[57] Rakow Direct, Ex. 16 at 8.
[58] Rakow Direct, Ex. 16 at 8.
[59] Notice of Hearing at p. 2.
[60] Pierce Direct, Ex. 8 at 2.
[61]
[62] Pierce Direct, Ex. 8 at 2.
[63]
[64]
[65] Rakow Direct, Ex. 16 at 9-17; Hayet Rebuttal, Ex. 17 at 7-14.
[66] Tr. at 23, 26-27.
[67] Rakow Direct, Ex. 16 at 16.
[68] Hayet Rebuttal, Ex. 17 at 5.
[69] Notice of and Order for Hearing at 2.
[70] Rakow Direct, Ex. 16 at 8-9.
[71]
[72]
[73] Tr. at 24.
[74] Norberg Direct, Ex. 6 at 9.
[75] Rakow Direct, Ex. 16 at 9.
[76]
[77] Rakow Direct, Ex. 16 at 17-18.
[78]
[79] Rakow Direct, Ex. 16 at 16.
[80] OES Reply Brief at 1-6.
[81] Rakow Direct, Ex. 16 at, at 21.
[82] Amit Direct, Ex. 15 at 5-6.
[83] Hodnik Direct, Sched. 1, Pt. 3, Ex. 5, at 493.
[84]
[85] Section 4.4 of the Master Agreement (Hodnik Direct, Sched. 1, Pt. 2, Ex. 5, at 432.
[86] Hodnik Direct, Sched. 1, Pt. 3, Ex. 5, at 541.
[87]
[89]
[90] OES Reply Brief, pp. 3-6; Amit Direct, Ex. 15, at 3-6.
[91] OES Reply Brief, p. 6; Amit Direct, Ex. 15 at 6.
[92] OES Reply Brief, pp. 3-6.
[93] MP’s Post-Hearing Brief, pp. 6-8.
[94]
[96] MP’s Post-Hearing Brief, pp. 6-8.
[97] OES Reply Brief at p. 4; Ex. 15, Amit Direct, Ex. 15 at 8.
[98] MP’s Post-Hearing Brief, p. 7.
[99] OES Reply Brief at pp. 4-5; Amit Direct, Ex. 15 at 8-9.
[100] MP’s Post-Hearing Brief, p. 8.
[101] OES Reply Brief at p. 5; Amit Direct, Ex. 15 at p. 9.
[102] MP’s Post-Hearing Brief, pp. 8-9.
[103] OES Reply Brief at pp. 5-6; Amit Direct, Ex. 15 at. 9-10.
[104] Hodnick Direct, Sched. 1, Ex. 3 at 101, Section 7.3(c).
[105] LPI Brief, at 5.
[106]
[107] Hayet Rebuttal, Ex. 17 at 20.
[108] LPI Brief, at 4-5.
[109]
[110]
ITMO the Petition of
[111] LPI Brief, at 7.
[112] LPI Brief, at 7.
[113] Tr. at 28; Hodnik Direct, Sched. 1, Part 2, Ex. 4 at 436 (Section 6.1 “Minnkota shall use its best efforts to permit, design, finance, procure, construct, install and complete the New AC Line.”); Donahue Direct, Ex. 9 at 8 and Sched. 1.
[114]
[115]
[116]
[117] LPI Brief, at 8.
[118] LPI Brief, at 8.
[119] Tr. 32-33.
[120] Hodnik Direct, Sched. I, Part 1, Ex. 3 at 18-19.
[121]
LPI Reply Brief, at 1-2; Tr. at 29, 42.;
[122]
[123]
[124]
[125]
[126]
See