STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
In the Matter of the Route Permit Application by
OAH Docket No. 7-2500-20283-2
MPUC Docket No. ET-2/TL-08-1474
FINDINGS OF FACT, CONCLUSIONS
AND RECOMMENDATION ON REMAND
TABLE OF CONTENTS
Page
Description of the
Cedar Mountain Substation – Helena Substation Section of the Brookings Project
Routes Proposed in
the Application
Federal and State
Agency Participation
Minnesota Department of Transportation
United States Fish and Wildlife Service and
Minnesota Department of Natural Resources
Application of
Statutory and Rule Criteria
Application of
Routing Factors to the 345 kV Transmission Line
Effects on Land
Based Economies
Effects on
Archaeological and Historic Resources.
Effects on Natural
Environment
Application of
Various Design Considerations
Use of Existing
Transportation, Pipeline, and Electrical Transmission System Right-of-Way
Costs of
Constructing, Operating, and Maintaining the Facility
Adverse Human and
Natural Environmental Effects Which Cannot be Avoided
Irreversible and
Irretrievable Commitments of Resources.
Consideration of
Issues Presented by State and Federal Agencies
Oral Testimony at the Public Hearings
Written Comments from the Public
|
OAH Docket No.
7-2500-20283-2 MPUC Docket No.
ET-2/TL-08-1474 |
|
|
STATE OF |
|
|
In the
Matter of the Route Permit Application by |
FINDINGS OF FACT, CONCLUSIONS, AND
RECOMMENDATION ON REMAND |
|
|
|
A Public Hearing
was held before Richard C. Luis, Administrative Law Judge (“ALJ”), commencing
on October 4, 2010, in Le Sueur, Minnesota and continuing at dates and places
more specifically set forth below. The Evidentiary
portion of the Hearing was held on October 6, 2010, in
Lisa M. Agrimonti
and Valerie Herring, Briggs and Morgan, appeared for Great River Energy, a
Karen Finstad
Hammel, Assistant Attorney General, appeared on behalf of the Department of
Commerce, Office of Energy Security (“OES”).
Carol Overland,
Overland Law Office, appeared on behalf of NoCapX2020 and United Citizens
Action Network (“U-CAN”).
Michael
Kaluzniak, Planning Director, Minnesota Public Utilities Commission
(“Commission,” “PUC,” or “MPUC” ), 121 Seventh Place East, Suite 350, St. Paul,
MN 55101 appeared on behalf of the Commission.
In consideration
of the criteria set forth in Minnesota Statute § 216E.03[1]
and Minnesota Rules Chapter 7850 as applied to facts developed in this remand
proceeding, is there any reason to modify the ALJ Findings of Fact, Conclusions
of Law, and Recommendations issued in ths proceeding for a Route Permit for the
Brookings to Hampton 345 kV transmission line project, including necessary
system connections, and, if so, what route complies best with applicable
statutes and rules?
Based on the
Findings of Fact and Conclusions that follow, the Administrative Law Judge
makes the following:
1.
That the Commission determine that all relevant statutory
and rule criteria necessary to obtain a Route Permit have been satisfied and
that there are no statutory or other requirements that preclude granting a Route
Permit based on the record.
2.
That the Commission grant a Route Permit to Applicants on
behalf of themselves and the participating CapX2020 utilities for the
facilities described below:
A.
For the segment between Cedar Mountain Substation and Helena
Substation of the 345 kV transmission line between Brookings, South Dakota, and
Hampton, Minnesota, and associated Facilities:
(1)
The
(1a) If the Modified Preferred Route is not granted a Permit, the ALJ
recommends granting a Route Permit for the Alternate Route utilizing the Gibbon
Crossover Route, with an aerial crossing of the Minnesota River at Belle Plaine;
and
(2)
A route width of 600 feet except for those locations
identified by Applicants where Applicants are requesting a route width of 1,000
feet or up to 1.25 miles;[2]
3.
That Applicants be required to take those actions necessary
to implement the Commission’s Orders in this proceeding.
Based on the Hearing
record, including the proceedings conducted on remand from the Commission, the
ALJ makes the following Findings of Fact and Conclusions:
1.
The Applicants in this proceeding are Great River Energy and
Xcel Energy.
2.
Applicants jointly applied for a Route Permit to construct a
345 kV transmission line project from the South Dakota/Minnesota border to
B.
Procedural Summary[6]
3.
On December 29, 2008, Applicants submitted an Application
for Route Permit (“Application”) for the Minnesota portion of a 345 kV
transmission line between Brookings County, South Dakota, and Hampton,
Minnesota and associated facilities, and for a new 115 kV transmission line
between Cedar Mountain Substation and the Minnesota Valley – Franklin 115 kV
transmission line (collectively “the Brookings Project” or the “Project”).[7]
4.
On January 29, 2009, the Commission accepted the Application
as complete and authorized the OES Energy Facility Permitting staff to process
the Application under the full permitting process in Minnesota Rules 7850.1700
to 7850.2800.[8] The Commission also authorized the OES Energy
Facility Permitting staff to name a public advisor and to establish an advisory
task force or task forces and develop a structure and charge for them.[9]
5.
On February 5, 2009, the Commission assigned this matter to
ALJ Richard C. Luis of the Office of Administrative Hearings (“OAH”).[10]
6.
After significant notices and other proceedings, OES issued
the Draft Environmental Impact Statement (“DEIS”) on October 21, 2009,.[11]
7.
From November 30 to December 28, 2009, 17 public hearings
were held in 8 different
8.
From December 15 to December 18, 2009, the Evidentiary
Hearing was held in the Commission’s large hearing room in
9.
On January 26, 2010, OES issued the Final Environmental
Impact Statement (“FEIS”), published in the EQB Monitor on February 8, 2010.[14]
10.
Public comments on the proposed Project were accepted by the
ALJ until February 8, 2010.
11.
The Hearing record closed for all purposes on March 22, 2010.
On April 22, 2010, ALJ issued Findings
of Fact, Conclusions of Law and Recommendation for the Route Permit Application
for the Project. The ALJ recommended that the Commission approve the
12.
On June 10, 2010, the U.S. Fish and Wildlife Service (USFWS)
issued a letter to Applicants (“June 10 USFWS Letter”) stating its preference
for the Belle Plaine crossing and stating it was unlikely a Bald and Golden
Eagle Protection Act (“BGEPA”) permit could be issued for a Le Sueur crossing.[16]
13.
In response to the June 10 USFWS Letter, on July 27, 2010, the
Commission issued an Order remanding this proceeding to the ALJ. The Commission described the scope of the
remand proceeding as follows:
Since the USFWS's letter
bears directly on the river crossing issue, since the ALJ and the parties had
no opportunity to address the letter in the contested case process, and since
there appears to be adequate time to examine the letter by the ALJ in a
tightly-focused contested case proceeding, the Commission will remand the ALJ's
recommendation regarding whether the crossing at Le Sueur or Belle Plaine is
preferable.
Further, in anticipation of the Commission's possible ultimate selection
of the river crossing at Belle Plaine, the Commission will also request that
the ALJ consider which of the crossover routes to the river crossing at Belle
Plaine is preferable, and to alter his April 22, 2010 findings of fact,
conclusions of law and recommendation, if necessary, accordingly. The
Commission clarifies that the objective of this request is simply to have
complete the set of ALJ recommendations regarding the options before the
Commission and in no way indicates a prejudgment that the river crossing at
Belle Plaine is preferable.
On remand, the ALJ is requested to schedule a hearing on the USFWS's
letter and give the parties adequate opportunity to develop the record with
respect to that letter. The ALJ will then consider and report to the Commission
whether and to what extent, in light of the USFWS's letter and the record
developed with respect to it, he wishes to modify or augment his findings of
fact, conclusions of law, and recommendations with respect to both the river
crossings and the crossover routes to the river crossing at Belle Plaine.[17]
14.
On August 18, 2010, the ALJ issued the First Prehearing
Order on Remand for the Project. The Order set forth that all parties to the
remand proceeding remain as those who were admitted during the matter in chief
and established a schedule for proceedings on remand.
15.
On September 14, 2010, the Commission issued its Order
Granting Route Permit for the Project from the South Dakota/Minnesota state
line to Cedar Mountain Substation and from the Helena Substation North site to
the Hampton Substation.[18]
16.
On October 4 and 5, 2010, the Public Hearings on Remand were
conducted in Le Sueur,
17.
Public Comment was received on the Remand Proceeding until
November 1, 2010. The record on the
Remand Proceeding closed on November 24, 2010.
C.
Description of the
18.
This Project consists of 345 kV and 115 kV transmission line
facilities.[19] The portion of the Project that is the
subject of the Remand Proceeding is the 345 kV transmission line facilities and
substation connections between the Cedar Mountain Substation and Helena
Substation, to be constructed with double-circuit 345 kV facilities.[20] Applicants indicated that the crossing of the
Minnesota River could be accomplished using either double-circuit 345 kV
facilities on a single H-frame structure or side-by-side structures using
single circuit 345 kV facilities.[21]
19.
The Commission issued a Certificate of Need for the 345 kV
facilities, including the segment being considered in the Remand Proceeding, on
May 22, 2009.[22]
D.
Routes Proposed for Segment 4
20.
In the Application, Applicants identified a
21.
Applicants also proposed an
22.
Applicants selected these two routes at the end of a
15-month route development process that was driven by extensive public
participation and agency coordination.[29] During this process, Applicants gathered
environmental data, held open houses and work group meetings, collected public
comments, and analyzed the statutory and rule factors set forth in the Power
Plant Siting Act (“PPSA”), Minnesota Statutes Chapter 216E and Minnesota Rules
Chapter 7850 to develop the Preferred Route and the Alternate Route for the
Project.[30]
23.
The ALJ Recommendation identified the Preferred Route, with
modifications at the crossing point of the Minnesota River, as the better route
for the 345 kV HVTL. The ALJ also noted
that the Belle Plaine crossing was suitable.[31] After the ALJ Recommendation was issued,
Applicants developed another alternative to cross from the Preferred Route to
the Alternate Route, in consultation with OES, running from near Gibbon (known
as the “the Gibbon Crossover Route” or “Alternate Crossover Route”).[32] The
24.
In the Remand Proceeding, Applicants identifed three
differences between the Le Sueur crossing and the Belle Plaine crossing as: 1) alignment flexibility and associated
engineering constraints; 2) agency input; and 3) use of existing
corridors. Applicants expressed their
preference for crossing the
During the initial
contested case proceeding Applicants supported either the
25.
Following a thorough review and analysis of the various
route and segment alternatives proposed in the EIS Scoping Decision, Applicants
reevaluated the
26.
The first of these two modifications alters the alignment of
the
27.
The second of these two modifications changed the
28.
The ALJ Recommendation specifically addressed the Applicants’
request for flexibilty in the width of the routes to assist in working around
problem sites.[41] Applicants initially requested a route width
of 1,000 feet along most of the proposed routes for the 345 kV transmission
line and, where necessary, up to 1.25 miles.[42] The route widths designated by the Commission
for Segments 1-3, 5, and 6 reflect Applicants’ later agreement to reduce the
requested route width to 600 feet in most areas with some flexibility. With one
exception for the area of the
29.
Applicants subsequently modified their requested route width
for the Modified Preferred Route to a route width of 600 feet in those areas
depicted on the 17 tile maps attached to Applicants’ February 8, 2010 Letter to
the ALJ.[44]
30.
Applicants’ amended request is for a 600 foot route width
and, where necessary, the flexibility to increase the route width up to 1,900
feet, centered on the proposed alignment for the majority of the Gibbon
Crossover route. The route widths for the
31.
Applicants indicate that while a narrowed route may be
workable in some areas, wide route widths will also be necessary in specific
locations. In particular, if the
32.
Applicants’ request for a route width of 600 feet and where
necessary up to 1.25 miles for the
33.
A 150-foot wide right-of-way will be required for the
majority of 345 kV line. In some limited
instances, where specialty structures are required for long spans or in
environmentally sensitive areas, a larger right-of-way width may be required.[48]
34.
Applicants expected to begin construction of the Project in
the fourth quarter of 2010 and estimated that the Project would be completed by
the third quarter of 2013.[49] The Remand Proceeding has caused a modest
delay in the start of this process, but the delay is not an impediment to the
Project going forward.
I.
Route Segment 4 Project Costs
35.
Applicants identified the total cost of the Project, including
the survey, engineering, materials, construction, right-of-way, and project
management associated with the transmission line and substations as dependent,
in significant part, on the length of the transmission line.[50] The total cost is estimated to be between
$700 million and $755 million in 2007 dollars.[51]
36.
Applicants provided
specific estimates for the
37.
This Project includes the construction of four new
substations and modifications to four existing substations. Both of the substations serving Route Segment
4 are new substations (
38.
Applicants’ proposed site for the Cedar Mountain Substation
for the
39.
Applicants’ proposed site for the Helena Substation for the
40.
The Commission approved the
K.
Federal and State Agency Participation
41.
In this Remand Proceeding, Applicants have been in
consultation with the USFWS, MnDNR, and Minnesota Department of Transportation
(“Mn/DOT”). These agencies have
submitted comments or provided staff to testify at the hearings held pursuant
to the Commission’s Remand Order.
1.
Minnesota Department of
Transportation
42.
The Minnesota Department of Transportation (Mn/DOT) owns or
otherwise controls all state trunk highways, including freeways/interstate
highways.[61] Mn/DOT shares oversight over a right-of-way
with the Federal Highway Administration to the extent the right-of-way has been
acquired by Mn/DOT with federal funding.[62]
43.
Mn/DOT’s rules governing use of trunk highway rights-of-way
are included in Minnesota Rules 8810.3100-.3600.[63]
44.
Minnesota Rule 8810.3300, subp. 1 requires Applicants to
obtain a permit from Mn/DOT to occupy state highway right-of-way, including
interstate roads (also called freeways), and for crossings and longitudinal
installations (“Utility Permit”). [64]
45.
Mn/DOT follows the standards published in the Mn/DOT Procedures for Accommodation of
Utilities on Highway Right-of-Way, Mn/DOT Position Statement – Highways No. 6.4,
July 27, 1990, revised November 8, 2005 (“Accommodation Policy”) when issuing
Utility Permits.[65] The Accommodation Policy notes that it is in
the public interest for utility facilities to be accommodated on any highway
right-of-way when such use or occupancy does not conflict with provisions of
federal, state, or local laws or regulations.[66]
46.
In Route Segment 4, the
47.
On November 30, 2009, Mn/DOT filed a comment letter on the
DEIS.[68] In this letter, Mn/DOT advised that it would
be unable to issue a Utility Permit for the proposed alignment in a segment of
the Applicants’
48.
Based on Mn/DOT’s November 30, 2009 letter, Applicants
reevaluated the alignment of the
49.
The Myrick Alternative follows the north side of the U.S.
Highway 169 corridor across the
50.
Bimeda, Inc., a small pharmaceutical manufacturer located
near the
51.
Applicants will need a route width of approximately 4,700
feet for the
52.
On February 8, 2010, Mn/DOT sent a letter to the ALJ to
provide additional comments regarding the Project.[83] In its letter, Mn/DOT reiterated that the Utility
Accommodation Policy seeks to allow utilities to occupy portions of the highway
rights-of-way where such occupation does not put the safety of the traveling
public or highway workers at risk or unduly impair the public’s investment in
the transportation system.[84]
53.
During the hearings on remand Mn/DOT indicated that there
are no Mn/DOT scenic easements located along Route Segment 4 of the Project in
Belle Plaine or Le Sueur (using the Myrick Alternative).[85]
54.
Mn/DOT has not identified any impediments to permitting the
2.
United States Fish and
Wildlife Service and Minnesota Department of Natural Resources
55.
Beginning in December 2008, USFWS began providing comments
to Applicants regarding the Project.[87]
56.
USFWS submitted written comments to Applicants on December
3, 2008.[88]
57.
In its December 3, 2008 letter, USFWS provided some comments
regarding the impacts of aerial obstructions on migratory birds and USFWS’s
plans to develop future wildlife habitat resources. USFWS stated that aerial obstructions, such
as transmission lines, can adversely affect migratory birds, especially when
located in migration corridors, if the lines are not sited or designed to
minimize collisions (“bird strikes”) and electrocution.[89] USFWS informed Applicants of its plans to
acquire lands and develop habitat resources in the Project corridor.[90]
58.
In its December 3, 2008 letter, USFWS also expressed a
preference for the Project to cross the
59.
On March 5, 2009, USFWS provided comments to OES in which it
stated that additional research was being conducted on the environmental
impacts resulting from crossing the
60.
On April 30, 2009, USFWS submitted additional comments to
the Commission. USFWS identified a large
year-round bald eagle population, high concentrations of waterfowl during
migratory periods and a heron rookery within the proposed Le Sueur crossing
corridor.[96] Due to the presence of these species, USFWS
supported the Le Sueur crossing only if a non-aerial construction method were
used.[97] If a non-aerial crossing were not feasible,
USFWS recommended the
61.
On November 30, 2009, USFWS provided written comments to OES
regarding items in the DEIS that required further clarification.[101] In particular, USFWS sought additional
information regarding non-aerial river crossings at Le Sueur and Belle Plaine.[102]
62.
In response to USFWS, Applicants also evaluated several
non-aerial construction methods: connecting the new transmission line to the
U.S. Highway 169 bridge, attaching the new transmission line to a stand alone
pier that would be constructed next to the U.S. Highway 169 bridge, and
undergrounding the new 345 kV transmission line.[103]
63.
MnDNR also provided written comments to OES on November 30,
2009.[104]
In its November 30, 2009 letter, MnDNR opined that a Belle Plaine crossing by
way of the USFWS/MnDNR Alternative “appears to be the most protective of the
64.
On February 8, 2010, USFWS sent a letter to Applicants
regarding the
65.
In its letter, USFWS urged Applicants to further analyze
both the economic and technological feasibility of a non-aerial line at any
66.
On February 8, 2010, the MnDNR filed comments regarding the
FEIS.[112] In these comments MnDNR encouraged the
Applicants to coordinate directly with MnDNR “through a pre-application
meeting(s) concerning impacts to DNR administered lands, public waters, public
water wetlands, and state-listed species prior to application for water permits
and utility licenses to cross public lands and public waters. The applicant is
encouraged to further develop mitigation plans for impacts related to these
resources and review these with the DNR prior to applying for any DNR permits.”[113]
67.
OES expressed concern that the Applicants have not been
sufficiently specific regarding technical aspects of the proposed HVTL,
particularly regarding the
68.
In the Remand Proceeding, the MnDNR indicated that its
concerns regarding adequacy of information (similar to those identified by OES)
had been addressed by the Applicants, including information needed regarding
potential crossing points of the
As explained in testimony on October 5, 2010, the DNR previously
expressed concern regarding the location of the route alignment at
The DNR also will require additional information as part of the DNR
permitting process for the License to Cross Public Lands and Waters for this
project, as described in testimony October 5, 2010. Additional coordination is also needed
regarding possible impacts to habitats such as native prairie to determine if
surveys for endangered or threatened species are needed and whether a Takings
Permit is needed. Previous DNR comment
letters discussed mitigation for potential impacts to Species of Special
Concern and rare native plant communities. The DNR encourages the applicant to
coordinate regarding possible adjustments in route alignment to address these
potential impacts to natural resources.[116]
69.
On October 29, 2010, USFWS sent Applicants a letter for
inclusion in the record of the Remand Proceeding (USFWS Remand Comment). The USFWS Remand Comment addressed the Bald
and Golden Eagle Protection Act (BGEPA) permit issues which triggered this
proceeding and stated in pertinent part:
To summarize, new information available to my agency leads us to
conclude that we do not currently have sufficient biological evidence to
determine conclusively that more bald eagles would be affected by one crossing
alternative or the other. Based upon
this new information, our earlier recommendation of June 10, 2010 is suspended.
We propose that a study of eagle winter habitat use and availability in the
Since the transmission crossing location was remanded back to the
Administrative Law Judge, we have had the opportunity to talk with many
citizens and local birders of the
We would like to briefly comment on the next steps involved in route
selection and Eagle Act permitting for this project. You will likely need an
eagle take permit no matter which crossing site is selected, since the data now
available suggests significant eagle use near both sites. Until such time as
the Public Utilities Commission (PUC) makes a final route selection, an eagle take permit would be available only
for the least impacting site; the winter survey discussed below would inform
this determination, and might be particularly valuable if completed before the
PUC's final route decision. However, we
understand that the PUC route permitting process must continue. Unlike the
scenario facing us in June, where both crossing sites were still available, PUC
may soon be required to select a specific route based upon the many public
policy concerns under its jurisdiction. When
PUC selects a route for permitting, we will work with you to develop and
process a permit application for whichever route is selected. In the
meantime, however, we will work with you to gather biological information to
give us as [sic] stronger
understanding of eagle use along the
As the
Service, Great River Energy (GRE), Xcel Energy, and the Office of Energy
Security (OES) discussed during our phone conservation of October 14, the
Service would like for GRE to perform a study to determine the potential
impacts of the route crossing locations on bald eagles. This study should
include field surveys in the
70.
L.
Summary of Party Testimony
1.
71.
The pre-filed testimony of Daniel Lesher and Kevin Lennon
provided information regarding Applicants’ preferred
72.
With regard to the Le Sueur crossing, Kevin Lennon testified
that the severe slope and ravines along the Myrick Alternative limit possible
locations where structures can be placed.[123] He stated that this constraint may result in
longer spans, wider easements, more tree clearing, and taller poles which may
create greater aesthetic impacts.[124] If spans were shortened to accommodate a
level workspace, more poles would be required.[125]
Lennon testified that a crossing at Belle Plaine does not present similar
alignment or pole placement limitations.[126]
73.
Lennon also testified that the topography at the Belle
Plaine crossing area presents fewer engineering and design challenges than a Le
Sueur crossing.[127] The primary engineering challenges at Le
Sueur relate to the steep terrain and the retention ponds at the Le Sueur
crossing.[128] Access for repairs and maintenance is also a
consideration.[129] Because of the steeper terrain near Le Sueur,
an access road to each structure location may have to be built to accommodate
construction and maintenance equipment.[130]
74.
Lennon testified that while retention ponds are an issue at
both the Le Sueur and Belle Plaine crossings, the constraints are more
significant at Le Sueur.[131] The Myrick Alignment Alternative requires
that the line be moved away from the retention ponds to the east side of US
169.[132] This area is more flood prone and has
unstable soils.[133] At the Belle Plaine crossing, the elevation
is higher, less flood prone and has relatively firmer soils.[134]
75.
Lesher noted that the Belle Plaine crossing also uses an
existing 69 kV transmission corridor across the
76.
The testimony filed by Mr. Lennon and Mr. Lesher regarding
engineering challenges in the Le Sueur/Myrick Alternative Route Area is
summary/conclusory in nature and lacks references to detailed support such as
cost studies or engineering data. For
example, Mr. Lennon’s contention, at Finding 74 above, that the line along the
Myrick Route needs to be moved to the east side of Highway 169 to stay away
from the retention ponds stands alone, without an illustrative map or any reference
to or factual showing of flood history or soil studies. It is noted also that any of the challenges
to construction at Le Sueur relied upon by the Applicants to result in a
“slight preference”for a Belle Plaine Crossing existed at the close of the
record in the original CAPX 2020 case, when the Applicants preferred the Le
Sueur Crossing.
77.
Public comment was received orally at the public hearings in
the Remand Proceeding and in writing. The
Findings in this report make reference to a very few comments that are
particularly appropriate to the issue being discussed. More detailed summaries of the oral and
written comment received are attached to this Report.[136]
78.
The PPSA requires that route permit determinations “be
guided by the state’s goals to conserve resources, minimize environmental
impacts, minimize human settlement and other land use conflicts, and ensure the
state’s electric energy security through efficient, cost-effective power supply
and electric transmission infrastructure.”[137]
79.
In the ALJ Recommendation issued on April 22, 2010, all of
the responsibilities, procedures and considerations that the Commission must
follow under the PPSA were identified and analyzed. There are no issues related to those
standards that were raised regarding the overall route analysis. Consistent with the Commission’s direction to
conduct a “tightly focused proceeding” on remand, the only portions of the PPSA
that will be addressed are those newly raised and specific to Route Segment
4. In all other respects the Findings of
the ALJ Recommendation remain unchanged.
80.
The following criteria were addressed by specific testimony
and comments to require further analysis:
(1) evaluation
of research and investigations relating to the effects on land, water and air
resources of large electric power generating plants and high voltage
transmission lines and the effects of water and air discharges and electric and
magnetic fields resulting from such facilities on public health and welfare,
vegetation, animals, materials and aesthetic values, including baseline
studies, predictive modeling, and evaluation of new or improved methods for
minimizing adverse impacts of water and air discharges and other matters
pertaining to the effects of power plants on the water and air environment;
(2) environmental
evaluation of sites and routes proposed for future development and expansion
and their relationship to the land, water, air and human resources of the
state;
* * *
(5) analysis
of the direct and indirect economic impact of proposed sites and routes
including, but not limited to, productive agricultural land lost or impaired;
(6) evaluation
of adverse direct and indirect environmental effects that cannot be avoided
should the proposed site and route be accepted;
* * *
(8) evaluation
of potential routes that would use or parallel existing railroad and highway
rights-of-way;
* * *
(11) evaluation
of irreversible and irretrievable commitments of resources should the proposed
site or route be approved; and
(12) when
appropriate, consideration of problems raised by other state and federal
agencies and local entities.[138]
81.
In addition to the PPSA, Minn. R. 7850.4000 provides that no
route permit may be issued in violation of site selection criteria and
standards found in Minnesota Statutes or Public Utilities Commission
Rules. Power line permits must be
consistent with state goals to minimize environmental impacts and conflicts
with human settlement and other land use.
A. effects
on human settlement, including, but not limited to, displacement, noise,
aesthetics, cultural values, recreation, and public services;
* * *
C. effects
on land-based economies, including, but not limited to, agriculture, forestry,
tourism, and mining;
D. effects on archaeological and historic
resources;
E. effects
on the natural environment, including effects on air and water quality resources
and flora and fauna;
* * *
J. use
of existing transportation, pipeline, and electrical transmission systems or
rights-of-way;
* * *
L. costs
of constructing, operating, and maintaining the facility which are dependent on
design and route;
M. adverse human and natural environmental
effects which cannot be avoided; and
N. irreversible and irretrievable
commitments of resources.
82.
There is sufficient evidence in the record for the Commission
to assess the proposed routes and alternatives of Route Segment 4 using the
criteria set out above.
Application of Statutory
and Rule Criteria
I. Application of Routing Factors to the 345 kV
Transmission Line
A.
Effects on Human Settlement
83.
Minnesota statutory and rule routing criteria for high
voltage transmission lines require consideration of the proposed transmission
line route’s effect on human settlement, including displacement of residences
and businesses; noise created during construction and by operation of the
Project; and impacts to aesthetics, cultural values, recreation and public
services.[139]
84.
For purposes of this proceeding, displacement of a residence
or business was defined to occur when a structure is located within the 150
foot right-of-way or 75 feet on either side of the proposed transmission
centerline.[140]
85.
Applicants do not anticipate that construction of the 345 kV
line in Route Segment 4 along the
86.
Construction of the facilities along the
87.
Applicants recognize the transmission lines will be a
contrast to the surrounding land.
Applicants pledged to continue working with landowners and public
agencies to identify concerns related to the transmission line and aesthetics. Several potential mitigative measures have
been identified.[146] Examples of the mititgative measures were set
out in the ALJ Recommendation.
88.
The aesthetic impacts differ among the
89.
In light of the factors noted in the preceding Finding, the
record, including the proceedings on Remand, confirms that the
90.
Public services and facilities are generally defined as
services provided by government entities, including hospitals, fire and police
departments, schools, public parks, and water supply or wastewater disposal
systems.[150]
91.
Applicants did not anticipate that construction of the
Project along the
92.
Superintendent Kelly Smith of the Belle Plaine Schools
(Independent School Distict No. 716) noted that there is a new elementary
school located in the far southwest corner of Belle Plaine. ISD 716 owns additional land in that area for
a future new high school. These school
sites are approximately .4 miles from the
93.
Superintendent Smith also noted that the ISD 716 property
was surrounded by a residential development area. Some of the land set aside for residences is
located less than .4 miles to the the
94.
During construction, Applicants will make efforts to
minimize any disruption to public services or public utilities.[155] To the extent disruptions to public services
occur, these would be temporary and the Applicants will work to restore service
promptly.[156] Where any impacts to utilities have the
potential to occur, Applicants will work with both landowners and local
agencies to determine the most appropriate pole placement.[157]
95.
In light of the factors noted in the preceding Findings, the
record, including the proceedings on Remand, indicates that the
B.
Effects on Land Based Economies
96.
97.
The Project will result in permanent and temporary impacts
to farmland.[159] Permanent impacts will occur as a result of
structure placement along the route centerline.
Applicants estimated that the permanent impacts in agricultural fields
will be 1,000 square feet per pole.[160] Temporary impacts, such as soil compaction
and crop damage, are likely to occur during construction.[161] Applicants estimated temporary impacts in
agricultural fields to be one acre per pole for construction.[162]
98.
The
99.
There is no evidence that any expansion of residential areas
in Le Sueur is anticipated in the area of the proposed Myrick Alternative to
the
100.
The record demonstrates that the
C.
Effects on Archaeological and Historic Resources
101.
102.
Archaeological and historic resources are those places that
represent the visible or otherwise tangible record of human occupation.[166] When identifying the archaeological and
historic resources along the proposed routes, Applicants included “[i]dentified
locations that have special meaning for specific communities along the
Project.”[167]
103.
For Route Segment 4, 15 archaeological sites lie within one
mile of the
104.
The
105.
The
106.
Applicants proposed to mitigate impacts to these resources and
those methods are set out in the ALJ Recommendation. The record demonstrates that there are fewer
archaeological and historic sites within the
D.
Effects on Natural Environment
107.
1.
Water Quality and Resources
108.
The Project crosses two major hydrologic units (“HUs”)
within the Upper Mississippi Drainage Region.[172]
109.
Several rivers, including the
110.
Applicants will not place any structures within these
features and do not anticipate any direct impacts to these features.[174] Indirect impacts are expected and will be
avoided and minimized using the appropriate construction practices.[175]
111.
Because wetland impacts will be minimized and mitigated,
disturbed soil will be restored to previous conditions or better, and the
amount of land area converted to an impervious surface will be small, there
will be no significant impact on surface water quality once the Project is
completed.[176]
112.
Wetlands and floodplains will be crossed by the Project or
will be situated within the right-of-way of the Project.[177]
113.
Applicants will avoid major disturbance of individual
wetlands and drainage systems during construction.[178] This will be done by spanning wetlands and
drainage systems, where possible.[179] When it is not possible to span such areas,
Applicants have proposed other options that will minimize impacts.[180]
114.
Permanent impacts to wetlands would take place where
structures must be located within wetland boundaries.[181]
115.
The
116.
The
117.
The
118.
The record demonstrates that there are fewer water resources
within the
119.
The ALJ Recommendation sets out detailed findings regarding
fauna potentially affected by the Project.
The only fauna to be addressed on remand is the potential impact on
eagles. In all other respects, the ALJ
Recommendation Findings regarding fauna are not modified.
120.
In response to the USFWS position regarding the potential
impact on eagles in the Minnesota River Valley, Applicants conducted pedestrian
and aerial surveys of avian species in that area. [188] These surveys sought to locate eagle nests,
concentration sites, foraging areas, and winter roost nest areas that may be
subject to disturbance and/or displacement effects from proposed facility
expansion at
121.
The Applicants’ survey identified two locations near each of
the proposed
122.
Five eagle nests were identified in the
123.
An active feeding area was identified where approximately
twenty eagles have been observed. That
site is near the Belle Plaine crossing location of the
124.
No eagle nests have been observed within a mile of the
proposed corridors, but eagle nest locations can change from year to year. Eagle nests are typically spaced 2-3 miles
apart based on their home range and territory, and a pair of nesting eagles
will not tolerate another pair in “their” territory..[193] The entire area of the
125.
Both locations and any location along the
126.
The evidence in the record of the Remand Proceeding does not
show a marked difference between the impact on eagles to be expected from
following either the
E.
Application of Various Design Considerations
127.
128.
The design options of the facilities in Segment 4 along the
F.
Use or Paralleling of Existing Right-of-Way, Survey Lines,
Natural Division Lines and Agricultural Field Boundaries
129.
Minnesota high voltage transmission line routing criteria
require consideration of the proposed route’s use or paralleling of existing
rights-of-way, survey lines, natural division lines, and agricultural field
boundaries.[198]
130.
Regarding Segment 4, approximately 92.9% of the
131.
Approximately 93.2% of the
132.
Approximately 91.2% of the
133.
The record demonstrates that, in Segment 4, the Modified
Preferred Route, Arlington Crossover Route, and Gibbon Crossover Route nearly equally
use or parallel existing rights-of-way, survey lines, natural division lines,
and agricultural field boundaries.
G.
Use of Existing Transportation, Pipeline, and Electrical
Transmission System Right-of-Way
134.
135.
Applicants analyzed possibilities for co-locating the
Project at the
136.
The Modified Preferred route follows an existing road/bridge
corridor across the
137.
The ALJ Recommendation issued on April 22, 2010, analyzed
the proposed structures and Applicants’ need for flexibility in making the
final decision on what structures are approporiate. Applicants continue to need flexibility in
the permit terms to work with USFWS and MnDNR to arrive at the final structure
type to be used for the HVTL when crossing
the
138.
Approximately 72% of the
139.
Approximately 70% of the
140.
Approximately 68% of the
141.
The record demonstrates that the
H.
Costs of Constructing, Operating, and Maintaining the
Facility
142.
143.
For Route Segment 4, the
144.
The
145.
The
146.
The record demonstrates that it will cost marginally less to
construct the
I.
Adverse Human and Natural Environmental Effects Which Cannot
be Avoided
147.
148.
Unavoidable adverse impacts include the physical impacts to
the land, primarily agricultural land, due to the construction of the Project.[211]
149.
Applicants have identified mitigation measures and Applicants
will work with the public and public agencies to minimize the unavoidable
adverse environmental effects that may arise during construction of the
Project.[212]
J.
Irreversible and Irretrievable Commitments of Resources
150.
151.
Irreversible and irretrievable resource commitments are
related to the use of nonrenewable resources and the effects that the use of
those resources have on future generations.[214] Irreversible effects result primarily from
the use or destruction of a specific resource that cannot be replaced within a
reasonable time frame.[215] Irretrievable resource commitments involve
the loss in value of an affected resource that cannot be restored through later
actions.[216]
152.
There are few commitments of resources associated with this
Project that are irreversible and irretrievable, but those few resources
primarily relate to construction of the Project.[217]
153.
Only construction resources, such as concrete, steel and
hydrocarbon fuels, will be irreversibly and irretrievably committed to this
Project.[218]
154.
The commitment of these resources is similar for the
Modified Preferred Routes,
155.
The overall length of the
K.
Consideration of Issues Presented by State and Federal
Agencies
156.
157.
Mn/DOT, USFWS, and MnDNR expressed concern with various
aspects of the
158.
The ALJ Recommendation set out the USFWS and MnDNR concerns
regarding waterfowl, particularly during migration periods, and a heron rookery
which lies within the proposed Le Sueur/US 169 project corridor of the
159.
The USFWS concerns were all related to the Applicants’
obligations under the BGEPA. Those
concerns were discussed in the foregoing Findings.
160.
On remand, MnDNR did not identify any new issues with the Le
Sueur and Belle Plaine crossings.
161.
The
162.
For both Le Sueur and Belle Plaine, Applicants analyzed
undergrounding alternatives. A full
analysis of undergrounding was conducted in the contested case held prior to
the Remand Proceeding.[224]
163.
U-CAN and NoCapX asserted that “the relative weight of the
economic and environmental costs of an aerial crossing have increased due to
acknowledged potential for eagle takes at either crossing, evidence of
consistent and essentially similar impacts the length of the Valley, and the
prohibitive DOT scenic easements near LeSueur”.[225]
164.
U-CAN and NoCapX cite the federal regulations regarding
eagle take permits as supporting their position. An eagle take permit is required where “the
take cannot practicably be avoided.”[226] As defined in federal rules:
Practicable means capable of being done after taking into
consideration, relative to the magnitude of the impacts to eagles, the
following three things: the cost of remedy compared to proponent resources;
existing technology; and logistics in light of overall project purposes. [227]
165.
Applying the three criteria in the federal regulation, the
cost ($400 million in 2007 dollars) of the remedy (undergrounding) is very high
in relation to the cost of the rest of the Project ($700 - $800
million in 2007 dollars), existing technology will address the problem, and
logistically, implementing the undergounding alternative would be
difficult. Under the rule criteria,
undergrounding is not a practicable option for crossing the
166.
As discussed elsewhere in this Recommendation, the USFWS has
not identified any impact to the eagle population that precludes issuance of a
permit for aerial routing of the HVTL.
Mn/DOT has affirmatively stated that neither proposed crossing will
affect any scenic easement held by Mn/DOT.
No undergrounding alternative has been identified that would
significantly reduce the cost of that option.
167.
Due to the significant environmental impacts, construction
challenges and costs, undergrounding at Le Sueur or Belle Plaine is not a
superior alternative to an aerial crossing.
168.
The record does not support an underground design at either
of the
169.
The PPSA directs the Commission to locate transmission lines
in a manner that “minimize[s] adverse human and environmental impact while
ensuring continuing electric power system reliability and integrity and
ensuring that electric energy needs are met and fulfilled in an orderly and
timely fashion.”[228]
170.
The PPSA further authorizes the Commission to meet its
routing responsibility by designating a “route” with a “variable width of up to
1.25 miles.”[229]
171.
Applicants requested originally a route width of 1,000 feet
for the 345 kV transmission line, and where necessary, flexibility to increase
the width up to 1.25 miles, centered on the proposed alignment for the majority
of the
172.
Applicants subsequently agreed to narrow the route width to
600 feet except for certain locations in Segment 4, where they requested a
width of 1,000 feet to 1.25 miles.[231]
173.
The ALJ Recommendation analyzed the issue of route width
flexibility and noted that the proposed route width is consistent with prior
Route Permits issued by the Commission.[232]
174.
Applicants’ Amended Request for a 600 foot-wide route width,
except for those areas where they continue to request a width of 1,000 feet to
1.25 miles, for the
175.
176.
The notice that Applicants provided to the public and local
governments prior to the Remand Proceeding was detailed in the ALJ
Recommendation and found to satisfy of
177.
On September 17, 2010, Applicants mailed a notice to
landowners whose property was within or adjacent to the proposed or alternate
routes in Segment 4 in accordance with Minn. Stat. § 216E.03, subd. 6.[236] That mailed notice was limited to those
landowners whose property falls within 1000 feet of the proposed routes.
178.
Between September 22, 2010, and September 23, 2010, OES published
notice of the public hearings to be held in the Remand Proceeding, along with
information about the Project and the methods for submitting public comment, in
three newspapers located in
179.
The Commission is required to determine the adequacy of the
FEIS.[238] An FEIS is adequate if it: (A) addresses the
issues and alternatives raised in scoping to a reasonable extent considering
the availability of information and the time limitations for considering the
permit application; (B) provides responses to the timely substantive comments received
during the DEIS review process; and (C) was prepared in compliance with the
procedures in Minnesota Rules 7850.1000 to 7850.5600.[239]
180.
The Commission’s Remand of this proceeding did not change
the locations to be examined for routing of the segment under
consideration. All of those areas were
included in the FEIS completed by the OES.
The record demonstrates that the FEIS is adequate for this routing
decision because the FEIS addresses the issues and alternatives raised in the
Scoping Decision, provides responses to the substantive comments received
during the DEIS review process, and was prepared in compliance with Minnesota
Rules 7850.1000 to 7850.5600.
1.
The Public Utilities Commission and Administrative Law Judge
have jurisdiction to consider Applicants’ Application for a Route Permit. [240]
2.
The Commission determined that the Application was
substantially complete and accepted the Application on January 29, 2009.
3.
OES has conducted an appropriate environmental analysis of
the Project for purposes of this route permit proceeding and the FEIS satisfies
Minn. R. 7850.2500. Specifically, the
FEIS addresses the issues and alternatives raised through the scoping process in
light of the availability of information and the time limitations for
considering the permit application, provides responses to the timely
substantive comments received during the DEIS review process, and was prepared
in compliance with the procedures in Minn. R. 7850.1000-7850.5600.
4.
Applicants gave notice as required by Minn. Stat. § 216E.03,
subd. 3a; Minn. Stat. § 216E.03, subd. 4; Minn. R. 7850.2100, subp. 2; and Minn.
R. 7850.2100, subp. 4.
5.
OES gave notice as required by Minn. Stat. § 216E.03, subd.
6; Minn. R. 7850.2300, subp. 2; Minn. R. 7850.2500, subp. 2; Minn. R.
7850.2500, subp. 7; Minn. R. 7850.2500, subp. 8; and Minn. R. 7850.2500, subp.
9.
6.
Public hearings were conducted in communities located along
the proposed high voltage transmission line routes for Segment 4. Applicants and OES gave proper notice of the
public hearings, and the public was given the opportunity to speak at the
hearings and to submit written comments.
All procedural requirements for the Route Permit were satisfied.
7.
The record demonstrates that the Modified Preferred Route
for Segment 4, and its Associated Facilities, satisfies the route permit
criteria set forth in Minnesota Statute § 216E.03, subd. 7 and
8.
The record establishes that both the Gibbon Crossover Route
and the Arlington Crossover Route, each connecting the Modified Preferred Route
and Alternate Route in Sibley County, and crossing the Minnesota River west of
Belle Plaine, and its Associated Facilities, satisfy the route permit criteria
set forth in Minnesota Statute § 216E.03, subd. 7 and
9.
The record demonstrates that the
10.
The record demonstrates that it is appropriate to grant a
Route Permit for the 345 kV transmission line and Associated Facilities along
the
11.
The record demonstrates that it is appropriate for the Route
Permit to provide the requested route width of 600 feet, except for those
locations where Applicants are requesting a route width of 1,000 feet or up to
1.25 miles, as shown on Attachment 2 to Applicants’ Proposed Findings of Fact,
Conclusions and Recommendation.[241]
12.
It is appropriate for the Route Permit to require Applicants
to obtain all required local, state, and federal permits and licenses, to
comply with the terms of those permits or licenses, and to comply with all
applicable rules and regulations.
13.
Any Findings more properly designated Conclusions are
adopted as such.
THIS REPORT IS
NOT AN ORDER AND NO AUTHORITY IS GRANTED HEREIN. THE
Based on the
Findings of Fact, Conclusions, and the record, the Administrative Law Judge
makes the Recommendations set forth above in this Report.
Dated: December _22nd_,
2010
_/s/
Richard C. Luis __
RICHARD
C. LUIS
Administrative
Law Judge
Reported: Janet Shaddix and Associates
Transcripts
Prepared
Under the PUC’s Rules of Practice and
Procedure, Minn. R. 7829.0100 to 7829.3200, exceptions to this Report, if any,
by any party adversely affected must be filed within 15 days of the mailing
date hereof with the Executive Secretary of the PUC, 350 Metro Square Building,
121 Seventh Place East, St. Paul, Minnesota 55101-2147. Exceptions must be specific, relevant to the
matters at issue in this proceeding, and stated and numbered separately. Proposed Findings of Fact, Conclusions, and
Order should be included, and copies thereof served upon all parties.
The PUC shall make its determination on the
applications for the Certificate of Need and Route Permit after expiration of
the period to file Exceptions as set forth above, or after oral argument, if
such is requested and had in this matter. In accordance with Minn. R.
4400.1900, the PUC shall make a final decision on the Route Permit within 60
days after receipt of this Report.
Notice is hereby given that the PUC may
accept, modify, condition, or reject this Report of the Administrative Law
Judges and that this Report has no legal effect unless expressly adopted by the
PUC.
Oral
Testimony at the Public Hearings
1.
More
than 250 people attended the four public hearings on remand held in three
different locations. Public hearings
were held on October 4 and 5, 2010. The
hearings were held in Le Sueur at 2:00 p.m. on October 4, 2010;
2.
At the Le Sueur hearing, 10 people spoke in addition to the
parties.[242]
3.
Delores Hagen testified on behalf of herself and Henderson
Feathers. Ms. Hagen submitted several
documents into the record including a copy of the BGEPA and a sample of
information gathered by Henderson Feathers over 20 years. Henderson Feathers is a birding organization
that monitors and reports sightings of various birds in the Le Sueur and
Henderson areas (Ms. Hagen referred to this area as the “Henderson/Le Sueur
recovery zone”). Ms. Hagen also provided
a booklet that Henderson Feathers prepared which includes maps of nests within
the area monitored by Henderson Feathers.[243]
4.
Art Straub testified and submitted a written copy of his
testimony at the Le Sueur public hearing.[244] Mr. Straub testified that he participated in
some of the recordkeeping referred to by Ms. Hagen in her submission of
information from Henderson Feathers. Mr.
Straub and his wife have been teachers for 50 years. Currently they both volunteer full-time for
several organizations. He testified that
in 2009 MnDNR asked if he would obtain the longitude and latitude of each eagle
nest between “upper Le Sueur and Jessenland.”[245] Mr. Straub testified that the Applicants’
aerial survey in the spring was conducted while eagles were on nests with eggs
and eaglets. Additionally, he testified
that the
5.
Linda Rist noted that the viewing of eagles is better in the
Le Sueur vicinity than it is in the vicinity of Belle Plaine. Because U.S. Highway 169 slopes downhill as
it moves from north to south in vicinity of Le Sueur, Ms. Rist is concerned
also that helicopters would not be able to land on the highway for emergencies,
especially if the power line is in the way.
6.
Dr. Deb McKay noted that to cross the Minnesota River at
Belle Plaine, the proposed 345 kV line would not have to deal with as great a
change in elevation as it would at Le Sueur, and stated also that the Myrick
alternative route in Le Sueur, as opposed to the “Stoppelmann” route at Belle
Plaine, is much prettier. Dr. McKay
called the decision between building a 345 kV powerline crossing at Belle
Plaine or at Le Sueur to be a “no brainer” – it is obvious to McKay that
Belle Plaine should be chosen.
7.
Allan Muller of Red Wing argued that the Applicants should
build the 345 kV line underground at whatever
8.
James Meehan’s testimony related to the farm he owns in
9.
Fran and David Hennen testified regarding the Myrick
Alignment Alternative. The Hennens
testified that because “there are no issues in Belle Plaine” the Le Sueur
crossing should not be selected.[248]
10.
Applicants’ witness Mr. Lesher responded to the Hennens’
comments by clarifying that the Myrick Alignment Alternative was selected
because of the Mn/DOT easements identified along U.S. Highway 169 in the fall
of 2009. Additionally, Mr. Lesher
testified that although there are some challenges associated with following the
Myrick Alignment Alternative, the
11.
Four of the 10 speakers at the Le Sueur public hearing
testified that they believed a Belle Plaine crossing of the
12.
Nine members of the public spoke at the
13.
Kelly Baggenstoss testified that he was concerned that the
transmission line, if placed near his home in
14.
Vicky Wolter testified at the
15.
Ms. Wolter is concerned that many of the houses lying within
or less than 500 feet from the proposed centerline for the 345 kV line in Faxon
Township of Sibley County were not accounted for in the Applicants’ estimates.
16.
Several members of the public present at the
17.
Mark Kuske presented data bearing on the potential impact on
eagles if a Belle Plaine crossing is chosen.
Mr. Kuske concentrated on the wildlife/“eagles” situation on the
18.
Kevin Fahey, a long time employee of CenterPoint Energy,
raised questions regarding electromagnetic force (EMF) levels and stray
voltage, which the Administrative Law Judge already addressed in his initial
Report in this matter. The
Administrative Law Judge explained to Mr. Fahey that it was his opinion
evidence regarding EMF and stray voltage was immaterial to the issues on
remand.
19.
In response to concerns regarding stray voltage and EMF, Mr.
Lesher noted that such effects are often radiated from distribution lines,
rather than transmission lines of the type under consideration in this matter
and that distribution lines that cause difficulty to adjacent farm yards can be
buried.
20.
Darik Schultz questioned whether companies that own
utilities that may either be crossed or paralleled by the Project had been
notified of the project.[256] Mr. Lesher responded that utilities are aware
of the Project and Applicants will work closely with those affected utilities
after a route is selected and a Route Permit is issued by the Commission.[257]
21.
At the Belle Plaine afternoon hearing, eight members of the
public testified in addition to parties and two representatives of MnDNR.[258]
22.
Dr. Shayne Marker, D.V.M., represented the Wayne Koepp
family during the afternoon hearing at Belle Plaine, and noted that stray
voltage can “stress” farm animals, specifically dairy cattle. Mr. Lesher, on behalf of the Applicants,
noted that if the Belle Plaine crossing is chosen and the 345 kV line is built
in the vicinity of Wayne Koepp’s animals (or anyone else’s) the company will
check for stray voltage before the line is built, and after.
23.
Glen Schultz testified that he was concerned about impacts
on his personal use grass runway located near
24.
Kevin O’Brien questioned how close the Project would be to
the Belle Plaine elementary school if the Belle Plaine crossing of the
25.
At the afternoon public hearing in Belle Plaine, State
Representative David Bly testified. Rep.
Bly represents District 25B, which includes the area between
26.
Gary Steinhagen serves on the Belle Plaine School
Board. Steinhagen predicts that the
27.
Esther Stoppelmann, after whose family Stoppelmann Boulevard
(which runs from the Minnesota River to Highway 169, on a line parallel to the
proposed 345 kV line) noted that the City of Belle Plaine was considering
annexation of the territory between the current west edge of the City’s
residential area to the east side of Stoppelmann Boulevard.
28.
Judy Theis lives with her husband, Jesse Theis, on farmland
situated on top of a bluff west and 70 feet above
29.
Sarah Leonard, an adult daughter of Wayne Koepp, noted that
the Koepp dairy farm houses 375 dairy cattle, and is a place where eagles perch
on the trees frequently. They are found
on the tree line that separates the farms of Wayne and Mark Koepp, who has a
large hog-raising operation.
30.
The afternoon hearing in Belle Plaine featured appearances
by Jamie Schrenzel and Lisa Gelvin-Innvaer, from the staff of the Minnesota
Department of Natural Resources (DNR).
Ms. Schrenzel pointed out that the DNR has authority to issue crossing
permits for the placement of transmission lines on public lands and
waters. She noted that Belle Plaine and
Le Sueur have “roughly similar” environmental characteristics, noting further
that, when choosing between Belle Plaine and Le Sueur as river crossing sites,
the presence of eagles is the “tie breaker”.
Ms. Schrenzel then noted that the United States Fish and Wildlife
Service (USFWS) is the authority to decide which crossing point would impact
eagles greater. Ms. Schrenzel testified
that the DNR formerly favored Belle Plaine as the crossing point because it was
perceived as an area where there would be less impact on the environment in
general, but since Applicants now propose to construct the line across the
Minnesota River at a location south of Buck’s Lake (if Le Sueur is chosen as
the crossing point), the considerations “are even”.[264] As between the Gibbon and Arlington Crossover
Routes, the DNR has no preference regarding choosing of a way to get to the
Belle Plaine River Crossing, emphasizing again that it favored Belle Plaine
initially because of concerns about Buck’s
31.
Ms. Gelvin-Innvaer noted that eagles generally do not nest
on power poles. She then presented to
the parties confidential data from the Natural Heritage Database Information
System, noting where the Department has confirmed that eagles are nesting.[266].
32.
Twenty-one people testified at the evening public hearing in
Belle Plaine in addition to the parties and Mn/DOT.[267]
33.
Dallas Giles testified at the evening public hearing in
Belle Plaine that it appeared, based on the information provided through a
website created by USFWS, that the information USFWS relied on to support its
conclusion that Le Sueur crossing would be more impactful to eagles was
information provided by a local Le Sueur birder who made observations and
submitted those observations to USFWS.[268]
34.
Kevin Fahey testified he was concerned about the safety of
the Project and an existing pipeline existing in the same area.[269]
35.
Nancy Giles, who lives on
36.
Mayor Tim Lies testified and represented both the City of
37.
Mayor Lies also stressed that the City has an Orderly
Annexation Agreement in place with Blakeley Township of Scott County, within
whose boundaries lies the area where the Applicants hope to build the 345 kV
line if a Belle Plaine crossing is chosen.
38.
Mike Kreger testified he was asked to attend and speak at
the hearing after Letter to the Editor he wrote two weeks prior to the hearing
was published in the Belle Plaine Herald.[272] Mr. Kreger started the Minnesota Waterfowl
Association (“MWA”) in
39.
Mr. Kreger is a former DNR employee. He lives within 200 to 300 yards of
40.
Joel Bahr noted that last year (the winter of 2009-2010)
open water remained on the
41.
Vicki Wolter presented a Petition (Exhibit 416), signed by
several hundred people living in Faxon Township, Sibley County, urging the
commission to choose the Le Sueur crossing.
42.
Ms. Wolter also related that Mr. Sullins had told her the
USFWS relied on reports from birders from the
43.
David Seykora from the Minnesota Department of
Transportation noted that a scenic easement exists in the Belle Plaine area,
but that easement will not impede the crossing of a 345 kV line at Belle Plaine
along the line preferred by the Applicants.
The easement is 1500 feet east of the intersection of Highway 169 and
44.
Maria Tracy, who lives 300 feet away from the proposed
center line of the 345 kV line in the Belle Plaine vicinity, noted that she did
not receive specific individual notice of the public Hearings on Remand. Ms. Tracy urged that the remand proceeding
focus itself away from eagles and concentrate on looking at the human impacts
of any route alternative the Commission may choose.
45.
Sheri Prokosch grew up on a farm near the area proposed for
construction of the 345 kV line near Belle Plaine. She remembers that open water existed for
eagles during the winter in the area of the Minnesota River near her family’s
farm, and that she was told not to skate on the river when she was a little
girl, because of the dangers of thin ice.
46.
Jim Koonst is a manager for Stier Bus Company at Belle
Plaine. The company has a cell phone
tower lying 2000-3000 feet west of the centerline of the proposed 345 kV line
on the
47.
Lyle Wiste of
48.
Belle Plaine Public Schools Superintendent Kelly Smith testified
that he had submitted comments in a letter addressed to ALJ Luis on August 26,
2010.[279] The letter stated that the Belle Plaine
schools are located approximately 0.4 miles from the
49.
Superintendent Smith noted also that a certain number of
houses lie between the present school building on the School District’s site
west of the built-up portion of Belle Plaine, which site is planned to
accommodate Belle Plaine’s Senior High School in the future. It is anticipated that Belle Plaine will grow
to over 10,000 population (from its present population of 6,000) in the next 20
years, and that households will have to build around the powerline if the Belle
Plaine crossing is chosen.
50.
Jesse Theis testified that he is a scientist by profession,
and that an average science student in the fifth grade would “laugh” at the
“science” behind the USFWS letter issued June 10, 2010.
51.
Theresa Ruhland, a resident of
52.
At both the afternoon and evening public hearings in Belle
Plaine, there were members of the public who testified to water bodies that
were open year-round near the Belle Plaine crossing area.[284]
53.
Members of the public testified at the Belle Plaine public
hearings about locations of either eagle sightings or nests in and around Belle
Plaine.[285]
54.
Also, several members of the public who spoke at the
55.
At all of the hearings there were members of the public who
expressed concern that there were so many comments and concerns about
protecting eagles, but that the impacts on humans must also be considered.[287]
Written
Comments from the Public
1.
A large
number of written comments were received from concerned members of the public,
State and Federal agencies, and businesses.
These comments addressed a variety of issues. Some of the public comments have been
addressed in the body of the Report, where the issue raised is addressed. The summary provided here does not reference
all of the comments received. The
following Findings summarize the issues presented by the commentators.
2.
A
number of comments raised the question of a potential for adverse health
effects from EMF/ELF, and to a lesser extent, stray voltage, which was fully discussed
in the ALJ Recommendation. Additionally,
that issue is outside of the scope of this Remand Proceeding.
3.
4.
Jeanette
Seeman of
5.
William
and Sandra Boecker of
6.
Mary
Albrecht, who lives on the
7.
C. Jay
and Scott Gavin of
8.
Kevin
Kamps of
9.
Loren
and Shirley Stier of Belle Plaine noted that they have seen several bald eagles
from their home which borders the proposed route in Belle Plaine. The Stiers
request that a complete scientific study of avian life in the
10.
John
Lambrecht of Belle Plaine expressed concern about the impact that the Belle
Plaine crossing will have on wildlife, the economic growth of Belle Plaine, and
the enrollment in the Belle Plaine public schools. Mr. Lambrecht also noted
that the Belle Plaine crossing costs more than the Le Sueur crossing.[295]
11.
Shelia
Lambrecht, a resident of Belle Plaine who lives on
12.
Kathryn
Hodapp of Belle Plaine opposes the Belle Plaine crossing. She notes that the
Belle Plaine crossing route goes near her property, which has many breeds of
birds, including eagles. Ms. Hodapp is
concerned about the impact that the proposed transmission lines will have on
her home value and on nearby schools. Ms. Hodapp supports burying the proposed
transmission line.[297]
13.
Mark
Hodapp of Belle Plaine opposes the Belle Plaine crossing. Mr. Hodapp states
that the Belle Plaine crossing will impact a greater number of people, that
there are eagle populations at Belle Plaine, and that the Belle Plaine crossing
will cost more. Mr. Hodapp is also concerned about the effect of the proposed
transmission lines on property values in the area.[298]
14.
Irene
Sickmann of
15.
Larry and
Sharon Sickmann of
16.
Laura
Fahey of Belle Plaine states that the proposed transmission lines will stunt
the growth of Belle Plaine and requests that the
17.
Jenna
Fahey opposes the Belle Plaine crossing and is concerned about the impact that
the proposed transmission lines will have on trees, plants, and animals that
are living near her home which is along the proposed Belle Plaine Crossing
route.[302]
18.
Merry
Kay Bandelin of
19.
Victor
and Trisha Zaiher oppose the
20.
Harlan
Harms of Arlington wrote in opposition to the
21.
Gordon
and Sherry Bates of Green Isle comment that impacts to people should be given
greater weight than impacts to animals and that the route selected should be
the one that impacts the fewest number of people. The Bateses noted that the
southerly
22.
Catherine
Creech of
23.
Beth
Hansen of Belle Plaine states that the Belle Plaine crossing will impact the migration
of a number of avian species. Ms. Hansen maintained that adding the proposed
345 kV line along the same route as the existing 69 kV line will result in a
number of bird deaths. Ms. Hansen requested that instead of choosing either the
Belle Plaine or Le Sueur crossing, that a route along
24.
Steve
Gerken of Belle Plaine writes that he believes the eagle population in Belle Plaine
either matches or exceeds the eagle population that is present at Le Sueur. Mr.
Gerken requests that USFWS perform a more complete study of the eagle
populations at both locations before it makes a final recommendation.[309]
25.
Ross
Arneson, the City Attorney for
26.
Curtiss
and Norma Mueller of Belle Plaine write that they are discouraged by the lack
of communication they have received regarding this process. The Muellers
expressed concern about the impacts that the proposed transmission line will
have on eagle populations in the area and on farming properties that they own.[311]
27.
Louis
and Vera Lieske requested that the ALJ order that the USFWS do a complete
scientific study on avian life in the
28.
Mark
and Bruce Koepp operate a hog farm in Belle Plaine. The Koepps are concerned
about the impact that the proposed transmission lines will have on their pigs
because studies have shown that 2 to 4 mG of EMF cause health issues. The
Koepps note that eagles feed on pig carcasses on their farm.[313]
29.
Attorney
Daniel Steinhagen writes on behalf of his brother, Gary Steinhagen who owns and
operates a dairy farm in Belle Plaine. Mr. Steinhagen opposes the Belle Plaine
crossing in favor of the Le Sueur crossing. Mr. Steinhagen is concerned that
the proposed transmission lines will limit the amount of his brother’s pasture
land and will result in less food for the cows.[314]
30.
Mark
and Michelle Kuske of Belle Plaine oppose the Belle Plaine crossing because it
will impact 14 more homes than the Le Sueur crossing. The Kuskes contend that the proposed power
lines will impact the value of these homes. The Kuskes also noted that the
Belle Plaine crossing will result in a transmission line being located over the
top of an underground petroleum pipeline in multiple places.[315]
31.
Theresa
Ruhland wrote that the Unites States Fish and Wildlife Service recommended the
power line cross the Minnesota River in Belle Plaine for the safety of bald and
golden eagles. She urged the ALJ to
recommend the CapX2020 power line cross the Minnesota River in Belle Plaine to
avoid the addition of another aerial crossing of the
32.
Steve
Ruhland suggested that calling one route “preferred” and the other “alternate”
had led many to a false sense of complacency.
He added that the power line running by the new elementary school in
Belle Plaine would be more than a half mile away. He further said that while no one would want
their children to go to a school under a transmission line, a half mile is far
cry from directly under the line.[317]
33.
Robert
Fimon lives in Belle Plaine. His son
attends
34.
Mark
and Shirley Katzenmeyer from Le Sueur suggested that the
35.
Louis
Longhenry is a retired postmaster from Carver,
36.
Gary
Schrupp wrote that he did not want to have the power line go through Belle
Plaine because too many homes and wild life habitats will be affected. He urged selection of the
37.
Kevin
Fahey favors a Le Sueur crossing because there are more eagles in Belle Plaine
by Silver Lake, which is really close to the power line; the current school and
future school would be close to the proposed power line; Faxon Township has an
airport with low flying planes; and that Faxon Township (across the Minnesota
River from Belle Plaine) is the fastest growing township in Sibley County. The power line would be running along
Highway 25, which is prime land for future building.[321]
38.
Peggy
Kreger and her husband have been in
39.
Karl
and Rosemary Dieball live near
40.
David
Ruehling owns a farm in
41.
Michelle
Burns lives in Le Sueur in the
42.
David
and Mary Hennies expressed concern about the power line passing north of
43.
Mark
Melsha requested that the “original”
44.
Maynard
Rucks was a member of the site task force at
45.
Joel
and Tami Wentzlaff live on
46.
Dolores
Hagen of Henderson Feathers wrote that much of what had been submitted by the
USFWS and Henderson Feathers about the transmission line crossing through the

Mailing
Address: Voice: (651) 361-7900
P.O. Box 64620 TTY: (651) 361-7878
December 22, 2010
|
To: All Participants on the Service List |
|
Re: In the
Matter of the Application of the Route Permit Application by
from
MPUC
Docket No. ET-2/TL-08-1474
OAH
Docket No. 7-2500-20283-2
Dear Parties:
The document listed below has been
filed with the E-Docket system and served as specified on the attached service
list.
Findings of Fact, Conclusions, and Recommendation on Remand
Very
truly yours,
/s/
Richard C. Luis
RICHARD
C. LUIS
Administrative
Law Judge
Telephone:
(651) 361-7843
RCL:mo
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
ADMINISTRATIVE LAW SECTION
P. O.
CERTIFICATE OF SERVICE
|
Case Title: In
the Matter of the Application of the Route Permit Application by Great River
Energy and Xcel Energy for a 345 KV Transmission Line from Brookings County,
South Dakota to Hampton, Minnesota |
OAH Docket No. 7-2500-20283-2 MPUC Docket No. ET-2/TL-08-1474 |
Mary Osborn certifies that on the 22nd day of December, 2010, she served a true and correct copy of the Findings of Fact, Conclusions, and Recommendation on Remand; by electronic mail (or as indicated on the Service List) to the following individuals:
|
First Name |
Last Name |
Email |
Company Name |
Address |
Delivery Method |
View Trade
Secret |
|
Lisa
|
Agrimonti
|
lagrimonti@briggs.com
|
Briggs
And Morgan, P.A. |
2200
IDS Center80 |
Electronic
Service |
No |
|
Julia
|
|
|
Office
of the Attorney General-DOC |
1400
BRM Tower |
Paper
Service |
Yes |
|
Kenn
|
Barnaby
|
kenn.barnaby@wellsfargo.com
|
Cushman
and |
|
Electronic
Service |
No |
|
Robert
|
Bauer
|
BauerR@seversonsheldon.com
|
Severson,
Sheldon, Dougherty & Molenda, P.A. |
|
Electronic
Service |
No |
|
Bob
|
Cupit
|
bob.cupit@state.mn.us
|
Public
Utilities Commission |
|
Electronic
Service |
Yes |
|
Scott
|
Ek
|
scott.ek@state.mn.us
|
Department
of Commerce |
N/A
|
Electronic
Service |
No |
|
|
|
sharon.ferguson@state.mn.us
|
Department
of Commerce |
|
Electronic
Service |
Yes |
|
Burl
W. |
Haar
|
burl.haar@state.mn.us
|
Public
Utilities Commission |
|
Electronic
Service |
Yes |
|
Karen
Finstad |
Hammel
|
Karen.Hammel@state.mn.us
|
Office
of the Attorney General-DOC |
1400
BRM Tower |
Paper
Service |
Yes |
|
Valerie
|
Herring
|
vherring@briggs.com
|
Briggs
and Morgan, P.A. |
2200
IDS Center |
Paper
Service |
No |
|
Michael
|
Kaluzniak
|
mike.kaluzniak@state.mn.us
|
Public
Utilities Commission |
|
Paper
Service |
No |
|
Michael
|
Klemm
|
KlemmM@seversonsheldon.com
|
Severson,
Sheldon, Dougherty & Molenda, P.A |
|
Electronic
Service |
No |
|
Phillip
R. |
Krass
|
|
Krass
Monroe, P.A. |
|
Paper
Service |
No |
|
Michael
|
Krikava
|
mkrikava@briggs.com
|
Briggs
And Morgan, P.A. |
2200
IDS Center80 |
Electronic
Service |
No |
|
John
|
Lindell
|
|
Office
of the Attorney General-RUD |
900
BRM Tower |
Paper
Service |
Yes |
|
Richard
C. |
Luis
|
|
Office
of Administrative Hearings |
|
Paper
Service |
Yes |
|
Paula
|
Maccabee
|
Pmaccabee@visi.com
|
Just
Change Law Offices |
|
Paper
Service |
No |
|
Russell
|
Martin
|
bens@integra.net
|
|
|
Electronic
Service |
No |
|
Joyce
H. |
Osborn
|
|
|
|
Paper
Service |
No |
|
Carol
|
Overland
|
overland@legalectric.org
|
Legalectric,
Inc. |
P.O.
Box 176 |
Electronic
Service |
No |
|
First Name |
Last Name |
Email |
Company Name |
Address |
Delivery Method |
View Trade
Secret |
|
Priti
R. |
Patel
|
|
Xcel
Energy |
5th
Floor |
Paper
Service |
No |
|
Deborah
|
Pile
|
|
Department
of Commerce |
|
Electronic
Service |
No |
|
Craig
|
Poorker
|
|
|
|
Paper
Service |
No |
|
Pamela
J. |
Rasmussen
|
pamela.jo.rasmussen@xcelenergy.com
|
Xcel
Energy |
|
Paper
Service |
No |
|
Laureen
|
Ross
McCalib |
|
CapX2020/Great
RIver Energy |
|
Electronic
Service |
No |
|
Carole
|
Schmidt
|
cschmidt@grenergy.com
|
|
|
Paper
Service |
No |
|
Janet
|
Shaddix
Elling |
jshaddix@janetshaddix.com
|
Shaddix
And Associates |
|
Electronic
Service |
Yes |
|
Donna
|
Stephenson
|
|
|
|
Paper
Service |
No |
|
Dan |
Lesher |
|
|
Electronic
Service |
|
[1] Unless
otherwise noted, the statutes and rules are cited to the 2009 edition.
[2]
Attachment 2 to Applicants’ Proposed Findings of Fact, Conclusions and
Recommendation shows the portions of the Modified Preferred Route where
Applicants are requesting a route width of up to 1.25 miles.
[3] Ex. 2 at
p. 1-1 (Application).
[4]
[5] Ex. 2 (Application).
[6] Additional motions concerning
discovery, intervention and other matters were filed and additional orders were
issued. All of these documents are
included in the record.
[7] Ex. 2
(Application).
[8] In the Matter of the Route Permit
Application for a 345 kV Transmission Line from Brookings County, South Dakota
to Hampton, Minnesota, Docket No.: ET-2/TL-08-1474, (Commission Order
issued Jan. 29, 2009).
[9]
[10] In the Matter of the Route Permit
Application for a 345 kV Transmission Line from Brookings County, South Dakota
to Hampton, Minnesota, Docket No.: ET-2/TL-08-1474, (Commission Order
issued Feb. 5, 2009).
[11] Ex. 23
(DEIS).
[12] Ex. 30
(OES November 6, 2009 Notice of Public Hearings); Ex. 160 (Applicants’ Notice
of Rescheduled New
[13] Ex. 30
(OES November 6, 2009 Notice of Public Hearings).
[14] EQB
Monitor Vol. 34 No. 3 (February 8, 2010) at p. 5.
[15] On April
30, 2010, ALJ Luis issued Amendments to the ALJ Findings for the Project
to correct
clerical errors pursuant to Minnesota Rule 1400.8300 (2009).
[16] USFWS
Letter, June 10, 2010 (eDocket No. 20106-51560-01).
[17]
Commission Order Remanding to Office of Administrative Hearings issued July 27,
2010 (eDocket No. 20107-52970-01).
[18]
Commission Order Granting Route Permit issued September 14, 2010 (eDocket No.
20109-54429-01).
[19] Ex. 2 at
§§ 2.2 and 2.4 (Application).
[20]
[21] Remand Ex. 164, at 3-4 (Lennon Remand Direct).
[22] In the Matter of the Application of Great
River Energy, Northern States Power Company (d/b/a Xcel Energy) and others for
Certificates of Need for the CapX 345-kV Transmission Project, Docket No.
ET-2, E-002, et al./CN-06-1115 (PUC Order Granting Certificates of Need with
Conditions, issued May 22, 2009 as modified August 9, 2009) (“Certificate of
Need Order”).
[23] Ex. 2 at
§ 5 (Application); Ex. 102 at p. 11 (Poorker Direct).
[24] Remand
Ex. 161; see also Ex. 2 at § 5.1
(Application); Ex. 102 at p. 12 (Poorker Direct).
[25] Remand Ex. 163, at 14 (Lesher Remand Direct).
[26] Remand Ex. 163, at 3 (Lesher Remand Direct).
[27] Remand
Ex. 161; see also Ex. 2 at § 5.2
(Application); Ex. 102 at p. 13 (Poorker Direct).
[28] Remand Ex. 163, at 15 (Lesher Remand Direct).
[29] Ex. 2 at
§ 4.0 (Application); Ex. 102 at p. 11 (Poorker Direct).
[30]
[31] ALJ Findings of Fact, Conclusions and Recommendation, at 99, issued
April 22, 2010 (eDocket No. 20104-49478-01).
[32] Remand Ex. 163, at 3-4 (Lesher Remand Direct).
[33] Remand Ex. 163, at 15 (Lesher Remand Direct).
[34] It is noted that the USFWS, after examination of the record developed on
remand, no longer favors either crossing.
See Finding 68, infra.
[35] Remand Ex. 163, at 12 (Lesher Remand Direct).
[36] Ex. 102
at p. 15 (Poorker Direct).
[37]
[38] Ex. 140
at Schedule 49 at p. 2 (Poorker Supplemental).
[39]
[40] Ex. 103
at pp. 16-19 (Poorker Rebuttal); Ex. 105 at pp. 1-3 (Lennon Rebuttal).
[41] ALJ
Recommendation, at 92-94.
[42]
[43]
Applicants February 8, 2010 Letter at Tile Maps, filed Feburary 8, 2010 (eDockets
No. 20102-46898-05).
[44] See Applicant’s February 8, 2010 Letter,
filed 02/08/10, Doc.
[45] Ex. 44 at
CH Segment Maps (OES EFP Comments and Recommendations).
[46] Ex. 2 at
Appendix B.5, Sheets CH10 and CH11 (Application).
[47] Minn.
Stat. § 216E.02, subd. 1.
[48] Ex. 2 at
§ 3.1.1.2 (Application).
[49] Ex. 104
at p. 7 (Lennon Direct).
[50] Ex. 104
at p. 8 (Lennon Direct).
[51] Ex. 104
at p. 8 (Lennon Direct); Ex. 141 at p. 8 (Lennon Supplemental).
[52] Remand Ex. 164, at 7 (Lennon Remand Direct).
[53]
[54] Ex. 104
at p. 8 (Lennon Direct).
[55] Ex. 2 at
§ 2.4 (Application); Ex. 102 at p. 20 (Poorker Direct).
[56]
[57]
[58]
[59] Ex. 102
at p. 22 (Poorker Direct).
[60]
Commission Order Granting Route Permit issued September 14, 2010.
[61] Ex. 102
at p. 29 (Poorker Direct).
[62]
[63] Ex. 102
at pp. 29-30 (Poorker Direct).
[64] Ex. 102
at p. 27 (Poorker Direct).
[65] Ex. 102
at p. 30 (Poorker Direct).
[66] Ex. 102
at p. 30 (Poorker Direct); Ex. 102 at Schedule 19 (Poorker Direct).
[67] Ex. 102
at p. 31 and Schedule 20 (Poorker Direct); Seykora Vol. 3 at pp. 183-184.
[68] Ex. 309
(Mn/DOT November 30, 2009 Comment Letter); Ex. 140 at Schedule 47 (Poorker
Supplemental).
[69] Ex. 309
at p. 12 (Mn/DOT November 30, 2009 Comment Letter); Seykora Vol. 3 at p. 175.
[70] Ex. 309
at p. 12 (Mn/DOT November 30, 2009 Comment Letter).
[71] Ex. 309
at p. 12 (Mn/DOT November 30, 2009 Comment Letter).
[72]
[73] Ex. 140
at p. 11 (Poorker Supplemental).
[74]
[75] Ex. 140
at p. 12 (Poorker Supplemental).
[76]
[77]
[78]
[79]
[80] Ex. 140
at p. 12 (Poorker Supplemental).
[81] Bimeda Exceptions to ALJ Report,
filed 5/7/10, Doc.
[82] Ex. 140
at p. 11 (Poorker Supplemental).
[83] Mn/DOT
February 8, 2010 Letter at p. 1, filed 02/08/10, Doc.
[84]
[85] Belle
Plaine Evening Remand Public Hearing, Tr. at 98; Remand Evidentiary Hearing,
Tr. at 35-38 (Seykora). Mn/DOT does hold
an easement along Highway 169, east of CSAH 53, but the easement is not
affected by the
[86] Remand
Evidentiary Hearing, Tr. at 39-40 (Seykora).
[87] Ex. 140
at Schedule 42 (Poorker Supplemental).
[88]
[89] Ex. 140
at Schedule 42 at p. 1 (Poorker Supplemental).
[90]
[91] Ex. 140
at Schedule 42 at p. 2 (Poorker Supplemental).
[92]
[93]
[94]
[95] Ex. 140
at Schedule 43 (Poorker Supplemental).
[96] Ex. 140 at
Schedule 44 at p. 1 (Poorker Supplemental).
[97]
[98] Ex. 140
at Schedule 44 at pp. 1-2 (Poorker Supplemental).
[99]
[100]
[101] Ex. 140
at Schedule 46 at pp. 1-3 (Poorker Supplemental).
[102] Ex. 140
at Schedule 46 at pp. 1-2 (Poorker Supplemental).
[103] Ex. 140 at
pp. 4-5 (Poorker Supplemental).
[104] Ex. 140
at Schedule 49 (Poorker Supplemental).
[105] Ex. 140
at Schedule 49 at p. 3 (Poorker Supplemental).
[106] Ex. 140
at Schedule 49 at p. 2 (Poorker Supplemental).
[107] Ex. 140
at Schedule 49 at p. 3 (Poorker Supplemental).
[108] USFWS
February 8, 2010 Letter at p. 1, filed 2/9/10, Doc.
[109] USFWS
February 8, 2010 Letter at p. 1, filed 2/9/10, Doc.
[110]
[111]
[112] MnDNR
February 8, 2010 Letter at p. 1, filed 2/10/10, Doc.
[113]
[114]
Applicants’ Reply Brief, at 11-13.
[115] October
5, 2010 Afternoon Tr., at 77 (Schrenzel).
[116] MnDNR
October 18, 2010 Comment (eDocket No. 201010-55731-01); see also October 5, 2010 Afternoon Tr., at 106-119
(Gelvin-Innaver).
[117] USFWS
Remand Comment, eDockets Document No. 201011-56096-01 (emphasis in original).
[118] Minn. R.
7850.2500, subp. 1.
[119] FEIS
(eFiled Jan. 26, 2010), eDocket Document No. 20101-46444-03.
[120] See FEIS
and DEIS at Appendix G (the
[121] Ex. 163 at p. 12 (Lesher Remand
Direct).
[122] Ex. 163 at pp. 12-15 (Lesher Remand
Direct).
[123] Ex. 164 at p. 5 (Lennon Remand
Direct).
[124] Ex. 164 at p. 5 (Lennon Remand
Direct).
[125] Ex. 164 at p. 5 (Lennon Remand
Direct)
[126] Ex. 164 at p. 6 (Lennon Remand
Direct).
[127] Ex. 164 at p. 6 (Lennon Remand
Direct).
[128] Ex. 164 at p. 5 (Lennon Remand
Direct).
[129] Ex. 164 at p. 5 (Lennon Remand
Direct).
[130] Ex. 164 at p. 6 (Lennon Remand
Direct).
[131] Ex. 164 at p. 6 (Lennon Remand
Direct).
[132] Ex. 164 at p. 6 (Lennon Remand
Direct).
[133] Ex. 164 at p. 6 (Lennon Remand
Direct).
[134] Ex. 164 at p. 6 (Lennon Remand
Direct).
[135] Ex. 163 at pp. 14-15 (Lesher Remand
Direct).
[136] See Attachment 1.
[137] Minn.
Stat. § 216E.03, subd. 7.
[138] Minn.
Stat. § 216E.03, subd. 7.
[139] Minn.
Stat. § 216E.03, subd. 7(b);
[140] Ex. 2 at
p. 6-11 (Application).
[141] Remand
Ex. 163, Schedule 10 (Lesher); see also
Ex. 2 at p. 4-10, p. 6-11 (Application); Ex. 102 at p. 17 (Poorker Direct).
[142] Remand
Ex. 163, Schedule 10 (Lesher).
[143] Remand
Ex. 163, at 17 and Schedule 10 (Lesher).
[144] Ex. 2 at
§ 6.2.5 (Application).
[145] Ex. 2 at
pp. 6-16-17 (Application).
[146] Ex. 2 at
§ 6.2.5.2 (Application).
[147] Ex. 102
at p. 9 (Poorker Direct); Ex. 2 at 5-6 (Application); Ex. 140 at p. 7 (Poorker
Supplemental).
[148] Ex. 102
at p. 17-18 (Poorker Direct); Ex. 2 at 4-10 (Application); Applicants January
19, 2010 Letter to the ALJ at Route Impact Table, filed 01/19/10, Doc.
[149] Ex. 2 at
p. 4-10 (Application).
[150] Ex. 2 at
p. 6-28 (Application).
[151] Ex. 2 at
pp. 6-30, 8-16 (Application).
[152]
[153] Remand
Ex. 421.
[154]
[155] Ex. 2 at
pp. 6-30, 8-16 (Application).
[156]
[157]
[158] Minn.
Stat. § 216E.03, subd. 7(b)(5);
[159] Ex. 2 at
p. 6-44 (Application).
[160] Ex. 2 at
p. 6-44 (Application).
[161]
[162]
[163] Remand
Ex. 163, at 17 and Schedule 10 (Lesher).
[164] Belle
Plaine Evening Tr. at 162-163.
[165] Minn.
Stat. § 216E.03, subd. 7(b)(1);
[166] Ex. 2 at
p. 6-48 (Application).
[167]
[168] Remand
Ex. 163, Schedules 10 and 11 (Lesher).
[169] Remand
Ex. 163, Schedules 10 and 11 (Lesher).
[170] Remand
Ex. 163, Schedules 10 and 11 (Lesher).
[171] Minn.
Stat. §§ 216E.03, subd. 7(b)(1) and (2);
[172]
[173] Ex. 2 at
pp. 6-54-55 (Application).
[174] Ex. 2 at
pp. 6-54-55 (Application).
[175] Ex. 2 at
p. 6-59 (Application).
[176]
[177]
[178]
[179]
[180]
[181] Ex. 2 at
p. 6-60 (Application).
[182] Ex. 2 at
p. 6-60 and 8-30 (Application).
[183] Ex. 163
at Schedules 10 and 11 (Lesher Remand Direct).
[184] Ex. 163
at Schedules 10 and 11 (Lesher Remand Direct).
[185] Ex. 163
at Schedule 10 (Lesher Remand Direct).
[186] Ex. 163
at Schedules 10 and 11 (Lesher Remand Direct).
[187] Ex. 163
at Schedule 10 (Lesher Remand Direct).
[188] Ex. 163
at Schedule 3, at 8 and Attachment 14 (Lesher Remand Direct).
[189]
[190] Ex. 163
at Schedule 3, Attachment 14, at 6-9 (Lesher Remand Direct).
[191] Remand
Ex. 405, Le Sueur/Henderson Recovery Zone map.
[192] Remand
Exs. 420A-420C; Belle Plaine Evening Tr. at 146-155.
[193] Remand Ex.
516, at 6 (Albrecht Remand Direct).
[194]
[195] Remand
Ex. 516, at 12 (Albrecht Remand Direct).
[196] Minn.
Stat. §§ 216E.03, subd. 7(b)(3) and (10);
[197] Ex. 2 at
pp. 3-5, 3-6 (Application).
[198] Minn.
Stat. § 216E.03, subd. 7(b)(9);
[199] Remand Ex. 163, Schedule 10 (Lesher Remand Direct).
[200] Remand Ex. 163, Schedule 10 (Lesher Remand Direct).
[201] Remand Ex. 163, Schedule 10 (Lesher Remand Direct).
[202] Minn.
Stat. § 216E.03, subd. 7(b)(8);
[203] Remand Ex. 163, Schedule 10 (Lesher Remand Direct).
[204]
[205]
[206]
[207] Remand Ex. 164, at 7 (Lennon Remand Direct).
[208]
[209]
[210] Minn.
Stat. § 216E.03, subd. 7(b)(5) and (6);
[211] Ex. 2 at
p. 4-13 (Application).
[212] Ex. 2 at
§ 6-9 (Application).
[213] Minn.
Stat. § 216E.03, subd. 7(b)(11);
[214] Ex. 2 at
p. 4-14 (Application).
[215]
[216]
[217]
[218]
[219] Ex. 2 at
p. 4-14 (Application); Ex. 102 at pp. 16-19 (Poorker Direct); Ex. 104 at pp.
8-10 (Lennon Direct); Applicants January 19, 2010 Letter at Route Impact Table,
filed 01/19/10, Doc. Id. 20101-46155-01.
[220] Remand
Ex. 163, Schedules 10 and 11 (Lesher).
[221] Minn.
Stat. § 216E.03, subd. 7(b)(12).
[222] Ex. 102
at Schedule 20 at pp. 27-38 (Poorker Direct); Ex. 103 at pp. 14-16 (Poorker
Rebuttal); Ex. 140 at pp. 3-11 and Schedules 42- 47 (Poorker Supplemental).
[223] ALJ
Recommendation, at 23-26.
[224] ALJ
Recommendation, at 64-66..
[225] NoCapX
Remand Brief, at 11.
[226] 50 C.F.R.
§ 22.26.
[227] 50 C.F.R.
§ 22.3.
[228] Minn.
Stat. § 216E.02, subd. 1.
[229] Minn.
Stat. § 216E.02, subd. 1.
[230] Ex. 2 at
§ 2.3 (Application).
[231]
Applicants’ Reply Brief, at 8.
[232] See In the Matter of the Application for a
[233]
[234] Minn.
Stat. § 216E.03, subd. 3a; Minn. Stat. § 216E.03, subd. 4; Minn. R. 7850.2100,
subp. 2; Minn. R. 7850.2100, subp. 4.
[235] ALJ
Recommendation at 4-8, 94-99.
[236] Remand
Ex. 46 (eDockets No. 20109-55052-01).
[237] Remand
Ex. 45 (eDockets No. 20109-55018-01).
[238] Minn. R.
7850.2500, subp. 10.
[239]
[240] Minn. Stat. §§ 14.57-.62 and 216E.02, subd.
2.
[241]
Applicants’ Proposed Findings of Fact, Conclusions and Recommendation, filed
02/16/10, Doc.
[242] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at p. 3.
[243] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at pp. 34-39.
[244] Ex. 406.
[245] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at p. 43.
[246] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at pp. 39-47.
[247] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at pp. 47-53.
[248] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at pp. 54-73.
[249] Le Sueur, Public Hearing, Oct. 4,
2010, 2:00 p.m. at pp. 61-63.
[250] See
Le Sueur, Public Hearing, Oct. 4, 2010, 2:00 p.m. at pp. 59, 67, 86 and 88.
[251]
[252]
[253]
[254]
[255] See
Arlington, Public Hearing, Oct. 4, 2010, 6:30 p.m. at pp. 72, 78, 97, 99, 110
and 129; Ex. 409.
[256]
[257]
[258] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at p. 3.
[259] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at p. 38.
[260] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at p. 47.
[261] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at p. 49.
[262] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at pp. 97-105.
[263] Belle Plaine Public Hearing, Oct.
5, 2010, 2:00 p.m, at p. 61.
[264] Belle Plaine afternoon transcript,
at 90.
[265]
[266]
[267] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 3-4.
[268] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 34-35.
[269] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 43-45.
[270] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 47.
[271] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 52-55.
[272] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 59.
[273] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 61.
[274] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 61.
[275] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 62 and 64.
[276] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 65.
[277] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 67.
[278] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 117.
[279] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 161.
[280] Ex. 421 (Letter from Superintendent
Kelly Smith).
[281] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 167.
[282] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at p. 172.
[283] Belle Plaine, Public Hearing, Oct.
5, 2010, 6:30 p.m. at pp. 172-74.
[284] Belle Plaine, Public Hearing, Oct.
5, 2010, 2:00 p.m. at p. 121; Belle Plaine, Public Hearing, Oct. 5, 2010, 6:30
p.m. at pp. 75 through 77.
[285] See
Belle Plaine, Public Hearing, Oct. 5, 2010, 2:00 p.m. at pp. 37, 120-21, 135
and 162; Belle Plaine, Public Hearing, Oct. 5, 2010, 6:30 p.m. at pp. 33, 47,
63, 65, 76, 87, 125, 127-28, 135, 144, 146-47, 157 and 159-60.
[286] See
Arlington, Public Hearing, Oct. 4, 2010, 6:30 p.m. at pp. 57, 77, 81 and 129;
Belle Plaine, Public Hearing, Oct. 5, 2010, 2:00 p.m. at p. 136; Belle Plaine,
Public Hearing, Oct. 5, 2010, 6:30 p.m. at p. 86.
[287] See
Belle Plaine, Public Hearing, Oct. 5, 2010, 2:00 p.m. at pp. 30-31; Belle
Plaine, Public Hearing, Oct. 5, 2010, 6:30 p.m. at pp. 37-38, 105-06, 111, and
120.
[288] Nagel October 12, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[289] Seaman October 12, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[290] Boecker October 11, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[291] Albrecht October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[292] Gavin October 16, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[293] Kamps October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[294] Stier October 12, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[295] Lambrecht October 13, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[296] Lambrecht October 11, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[297] Hodapp October 8, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[298] Hodapp October 5, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[299] Sickmann October 7, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[300] Sickmann October 5, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[301] Fahey October 7, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[302] Fahey October 13, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[303] Bandelin October 14, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[304] Zeiher October 14, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[305] Harms October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[306] Bates October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[307] Creech October 16, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[308] Hansen October 9, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[309] Gerken October 10, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[310] Arneson October 13, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[311] Mueller October 12, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[312] Lieske October 12, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[313] Koepp October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[314] Steinhagen October 18, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[315] Kuske October 20, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 20101-55811-01.
[316] Ruhland October 29, 2010 Letter
(efiled Nov. 17, 2010), eDockets Document No. 201011-56630-01.
[317] Ruhland October 31, 2010 Letter
(efiled Nov. 4, 2010), eDockets Document No. 201011-56178-01.
[318] Katzenmeyer October 14, 2010 Letter
(efiled Oct. 29, 2010), eDockets Document No. 201010-55948-01.
[319] Longhenry October 13, 2010 Letter
(efiled Oct. 29, 2010), eDockets Document No. 201010-55948-01.
[320] Schrupp October 12, 2010 Letter
(efiled Oct. 26, 2010), eDockets Document No. 201010-55830-01.
[321] Fahey October 16, 2010 Letter
(efiled Oct. 26, 2010), eDockets Document No. 201010-55830-01.
[322] Kreger October 8, 2010 Letter
(efiled Oct. 26, 2010), eDockets Document No. 201010-55830-01.
[323] Dieball October 13, 2010 Letter
(efiled Oct. 26, 2010), eDockets Document No. 201010-55830-01.
[324] Ruhling October 16, 2010 Letter
(efiled Oct. 26, 2010), eDockets Document No. 201010-55830-01.
[325] Burns October 15, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 201010-55745-01.
[326] Hennies October 14, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 201010-55745-01.
[327] Melsha October 17, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 201010-55745-01.
[328] Rucks October 17, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 201010-55745-01.
[329] Wentzlaff October 17, 2010 Letter
(efiled Oct. 25, 2010), eDockets Document No. 201010-55745-01.
[330]