|
OAH Docket No.
7-2500-20283-2 MPUC Docket No.
ET-2/TL-08-1474 |
|
|
STATE OF |
|
|
In the
Matter of the Route Permit Application by |
AMENDMENTS TO FINDINGS OF FACT, CONCLUSIONS,
AND RECOMMENDATION ON REMAND |
|
|
|
Administrative
Law Judge Richard C. Luis issued Findings of Fact, Conclusions, and
Recommendation on Remand in this proceeding on December 22, 2010. Subseqently, several clerical errors were
identified in the report issued on that date.
Pursuant to
[Page 1]
Michael Kaluzniak, Planning Director, Minnesota Public Utilities
Commission (“Commission,” “PUC,” or “MPUC” ), 121 Seventh Place East, Suite
350, St. Paul, MN 55101 appeared on behalf of the Commission Staff.
[FINDINGS OF FACT, page 4, Finding 11]
11. The Hearing record closed for all purposes
on March 22, 2010. On April 22, 2010,
ALJ issued Findings of Fact, Conclusions of Law and Recommendation for the
Route Permit Application for the Project (ALJ Recommendation). The ALJ
recommended that the Commission approve the
[FINDINGS OF FACT, page 6, Finding 21]
21. Applicants also proposed an The
[footnote deleted] In order to
connect the (Modifed)
[FINDINGS OF FACT, page 6, Finding 22]
22. Applicants selected these two the
Preferred and Alternate routes at the end of a 15-month route development
process that was driven by extensive public participation and agency
coordination.[footnote retained] During
this process, Applicants gathered environmental data, held open houses and work
group meetings, collected public comments, and analyzed the statutory and rule
factors set forth in the Power Plant Siting Act (“PPSA”), Minnesota Statutes
Chapter 216E and Minnesota Rules Chapter 7850 to develop the Preferred Route
and the Alternate Route for the Project.[footnote retained]
[FINDINGS OF FACT, page 7, Finding 24,
Footnote 35]
Remand Ex. 163,
at 12 (Lesher Remand Direct); see
Findings 71-76, infra. The Findings finally proposed by the OES included
the Applicants’ concerns about a Le Sueur Crossing utilitzing the Myrick
Alternative described at Finding 49, infra.
[FINDINGS OF FACT, page 15, Finding 63,
Footnote 105]
Ex. 140 at
Schedule 49 at p. 3 8 (Poorker Supplemental).
[FINDINGS OF FACT, page 15, Finding 63,
Footnote 106]
Ex. 140 at
Schedule 49 at p. 2 (Poorker Supplemental)
[FINDINGS OF FACT, page 15, Finding 63,
Footnote 107]
Ex. 140 at
Schedule 49 at p. 3 (Poorker Supplemental)
[FINDINGS OF FACT, page 16, Finding 67,
Footnote 114]
Applicants’ Reply
Brief, March 16, 2010, at 11-13.
[FINDINGS OF FACT, page 34, Finding 163]
163. U-CAN and NoCapX favor an underground
crossing of the Minnesota River, and asserted that “the relative weight of
the economic and environmental costs of an aerial crossing have increased due
to acknowledged potential for eagle takes at either crossing, evidence of
consistent and essentially similar impacts the length of the Valley, and the
prohibitive DOT scenic easements near LeSueur”
[CONCLUSIONS, page 37, number 7]
7. The record demonstrates
that the Modified Preferred Route for Segment 4, and its Associated Facilities,
with an aerial crossing of the Minnesota River at Le Sueur, satisfies
the route permit criteria set forth in Minnesota Statute § 216E.03, subd. 7 and
[CONCLUSIONS, page 37, number 8]
8. The record establishes
that both the Gibbon Crossover Route and the Arlington Crossover Route, each
connecting the Modified Preferred Route and Alternate Route in Sibley County, and
with an aerial crossing of the Minnesota River west of Belle
Plaine, and its Associated Facilities, satisfy the route permit criteria set
forth in Minnesota Statute § 216E.03, subd. 7 and
Dated: December 23,
2010
_/s/
Richard C. Luis_______________
RICHARD
C. LUIS
Administrative
Law Judge