OAH DOCKET NO. 16-2500-19766-2
PUC DOCKET NO. IP-6670/CN-08-334
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITES COMMISSION
|
In
the Matter of Application of |
SUMMARY
OF PUBLIC
TESTIMONY |
A public hearing was held before
Administrative Law Judge Manuel J. Cervantes on August 14, 2008, at 6:00 p.m.
at the Elkton Community Center Building,
Eighteen members of the public
attended the public hearing and nine signed the hearing roaster. Two of those who registered on the hearing
roster offered testimony during the hearing.
After the hearing, the record remained open for four days to allow all
interested persons to submit written comments.
One member of the public filed a written comment. The record closed on August 18, 2008.
NOTICE
The Public Utility Commission (PUC)
has the option of holding a hearing itself or request that an Administrative
Law Judge conduct the hearing and compile a record for consideration by the PUC
in making its final decision. Under
This
report contains a summary of the public testimony. It is not a final decision. Pursuant to Minn. R. 7849.5720, subp. 3, the PUC shall not make a final decision on a permit for a
project that requires a Certificate of Need from the PUC until the applicant
has obtained the necessary approval from the PUC.
BACKGROUND
ON THE APPLICATION
The electrical collector system will
consist of underground 34.5 kV collection lines and facilities providing
step-up transformation. Wapsipinicon is
also proposing to build a 161/34.5 kV project substation which will consist
generally of 2 161/34.5 transformers, and associate switching and protection
equipment as well as metering equipment, and a small control house.
Power from the turbines will be
collected at this substation and transmitted to the Pleasant Valley Substation
located in section 19 of
Other project-associated facilities
will include pad mounted step-up transformers and access roads.
The project will be located in central
Several of issues were raised at the
hearing by landowners in the proposed project areas, including the location of wind
turbines and the directions they face; the ability of Community–Based Energy
Development (C-BED) projects to connect to the transmission line proposed by
Wapsipinicon; and safety concerns raised by the timing of Wapsipinicon’s
proposed construction schedule during the peak of the agricultural harvest
period.
The Commission will make the final
decision whether to issue the Certificate of Need following a review of this
Summary of Public Testimony, as well as all of the hearing transcripts, written
comments submitted by the public, filings and arguments submitted by
SUMMARY
OF PUBLIC TESTIMONY
Eighteen members of the public were in
attendance at the hearing and nine signed the hearing roster. Two of those who registered on the hearing
roster offered testimony during the hearing.
One member of the public timely submitted his comments in writing.
Administrative Law Judge Manuel J.
Cervantes began the hearing by explaining that the purpose of the public
hearing was to solicit public comments regarding the environmental report which
was prepared and made available to the public on August 11, 2008 by the
Office of Energy Security (OES). David Birkholz,
Project Manager, Energy Facility Permitting Division of OES at the Minnesota
Department of Commerce (DOC), briefly explained the process which was
undertaken as a result of
Remarks
by Mr. Ray Dietrich: Mr. Dietrich stated
that he has three windmills on his farm and noted that the alignment of the
windmills was offset by 120 feet. He
indicated a preference of a straight alignment from east to west, without
offset.
Remarks
by Mr. James Hartson: Mr. Hartson noted that he had appeared and
commented at the Public Information and Scoping Meeting held on July 22,
2008. He inquired whether those remarks
and submissions were made part of the record in these proceedings.[3] Mr. Hartson raised several issues. He stated that the Governor and other state
officials, have indicated that Community-Based Energy Development (C-BED) projects
are a priority in this state. Mr.
Hartson questioned whether
Recently, Mr. Hartson asked representatives of
Wapsipinicon if his project could tap into its transmission line and was told by
a
SUMMARY
OF WRITTEN COMMENTS
There was one written comment
submitted on August 15, 2008 to the Administrative Law Judge prior to the close
of the post-hearing comment period.
Comments
of Eric Lee: in his cover e-mail
correspondence[4],
Mr. Lee identified himself as a community banker, landowner, and resident of
the community where the project will be located. He stated that in his capacity as a banker he
is familiar with the contractual obligations of
In his attached letter, dated August
15, 2008,[5] Mr.
Lee highlighted a portion of Minn. R. 7849.0120, and asks the PUC to consider:
The appropriateness of the … type, and the timing of
the proposed facility compared to those of reasonable alternatives; … the
effects of the proposed facility upon the … socioeconomic environments compared
to the effects of reasonable alternatives; and … by a preponderance of the
evidence on the record, the proposed facility, or a suitable modification of
the facility, will provide benefits to society in a manner compatible with
protecting … socioeconomic environments….
Mr. Lee raised the concern that the
parent company of
Lastly, Mr. Lee is also concerned about the timing of
Dated: August 20, 2008
s/Manuel
J. Cervantes
|
MANUEL J. CERVANTES Administrative Law Judge |
[1] Ex. 9.
[2] Exs. 1-4 and 6-8.
[3] Ex. 5 submitted at this hearing by Mr. Birkholz,
contains copies of the material submitted by Mr. Hartson at the meeting of July
22 and is incorporated in this hearing by reference.
[4] Ex. 11.
[5] Ex. 12.
[6] GAO-04-756 Report to the Ranking Democratic Member,
Committee on Agriculture , Nutrition, and Forestry, U.S. Senate: Renewable
Energy-Wind Power’s Contribution to Electric Power Generation and Impact on
Farms and Rural Communities, September 2004.