OAH Docket Nos. 7-2500-19143-2
7-2500-19096-2
MPUC Docket Nos. ET-2/GS-07-715
ET-2/CN-07-678
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Application of In the Matter of the Application of |
SUMMARY OF TESTIMONY AT PUBLIC HEARINGS |
This matter was initiated with the Minnesota Public Utilities Commission
(“MPUC” or the Commission) by Great River Energy (GRE) on May 18, 2007. On that date, GRE filed an Application for a
Certificate of Need (CON) for a 175 megawatt (MW) simple cycle combustion
turbine (“CT”)(collectively “the Project”).[1]
On June 14, 2007, GRE applied for a site
permit to allow the Project to be built at GRE’s existing Elk River Station,
located in the City of
On August 1, 2007, the Commission ordered that the CON be considered under the alternative review process. The only portion of the CON process referred to the Office of Administrative Hearings (OAH) was for the convening of a public hearing and collection of public comment. The Commission ordered that the remaining CON process be conducted using the Commission’s notice and comment process.[4]
Administrative Law Judge (ALJ) Richard C. Luis conducted public hearings
in Rosemount and
Description of the Project
GRE proposes to install a simple-cycle combustion turbine plant fueled by
natural gas with ultra-low sulfur distillate fuel oil as a back up fuel.[5]
The Project is to be built at the site of GRE’s existing Elk River Station,
located in the City of
Using the Elk River site will require upgrading approximately 5.41 miles
of 69-kV transmission line in Sherburne and
Additional equipment at the Project site includes a generator step-up transformer; less than 500 feet of transmission line from the transformers to the existing substation at the Elk River site, and in the alternative, less than 1,000 feet of transmission line from a new switchyard to the existing transmission line at the Rosemount site; a new lateral natural gas pipeline, town-border-station and meter; an evaporative cooler; and an exhaust stack with silencer.[8]
The Project site is located on the GRE campus in
Hearing Notice
The Notice of Public Meeting was published in the Star Tribune on November 29, 2007.[11] The Notice was published in the EQB Monitor on December 3, 2007.[12] The Notice was published in the Elk River Star News on December 5, 2007 and the
Approximately 8 members of the public appeared at the public hearings. Several of the attendees offered testimony concerning the Project and related issues. The Administrative Law Judge established a deadline of February 8, 2008 for receipt of written comments from any interested person.
The Commission will issue an Order on GRE’s applications for a Certification of Need and a Site Permit after examination of this Summary, the hearing transcripts, all written filings submitted by the public and all filings and arguments submitted by the Applicant, the Minnesota Department of Commerce and other persons and entities interested in this matter.
Summary of Testimony in
Bill Storm, Project Manager with the Department of Commerce's Energy Facilities Permitting Group made a presentation regarding the Department's environmental review for the Project. He also noted the comments that other Department staff had made regarding CN issues.[15]
The environmental review conducted by the Department is summarized in a document entitled Environmental Report: Elk River Peaking Station (Environmental Report).[16] The Environmental Report is a general document discussing the potential human and environmental impacts of the Project as well as any alternatives to the Project as proposed.
As part of the Environmental Report development process, public meetings were held on July 31, 2007 and August 1, 2007 to solicit input into the issues to be addressed in the study. Written comments were also solicited.
The Environmental Report detailed the work needed to be performed for the Project, potential impacts, and mitigation measures, No significant impacts requiring extraordinary mitigation measures were identified in the Environmental Report. Mitigation measures were detailed for the very limited impacts and potential impacts resulting from the installation and operation of the Project.[17]
As of the time of the public hearings, the Department had not recommended whether the Commission should approve the Project.[18] Attendees at the public hearing were invited to comment on the Project and on the Department's inquiry.
Glen Skarbakka, Resource Planning Manager for GRE, discussed the anticipated need for electricity among the member cooperatives and customers of those cooperatives through 2022. GRE primarily purchases electricity from coal-fired generation plants and adds electricity obtained from hydro, natural gas, refuse-derived fuel (RDF), and wind sources. With the increase in wind-generated electricity, the need for peaking power generation increases due to the variability of the wind-generated supply.[19]
Vince Herda, Project Manager for GRE, provided an overview of the planning, design, and potential impacts of the Project. Herda set out GRE’s reasons for the location, size, and timing of the Project.[20]
Mark Strohfus, Environmental Project Leader for GRE, provided more specific information on the potential impacts of the Project. Air emissions, noise generated by the Project, and required permitting were detailed in his portion of GRE’s presentation.[21]
David Jacobson, Regulatory Unit Manager for the Public Utilities Commission, described the permit process and the PUC’s role in the considering the applications of GRE.[22]
Ewald Petersen, Sherburne County Commissioner, expressed support for the
Project and described the positive relationship between GRE and the
County. Commissioner Petersen inquired
as to whether the air quality figures presented were different for the two
different fuels proposed for the Project’s CT.
Strohfus responded that the figures were assuming a “worst-case scenario”
where fuel oil was being used to fire the turbine. The emissions numbers are projected to be far
lower using natural gas to fire the CT.
Commissioner Petersen also identified a strong need for electricity in
operating pumps and irrigation systems in
Chad Westberg, a resident in the Project area, inquired
as to the tax impact of adding the Project in
Summary of Testimony in Rosemount
At the public hearing in Rosemount, GRE and Department made similar
presentations to those made in
Frank Knoll, a resident of the area, noted that moving large equipment
such as a CT could cause damage to local roads.
Knoll supported the Project, but maintained that
Greg Fox, a resident near GRE’s property, inquired about the potential for noise impact arising from the Project. GRE described the manner in which the anticipated noise was calculated and how that would impact area residents. GRE responded that the anticipated sound level of 50 dB(A) would be the equivalent of normal room sounds.[27]
The potential economic impact of the Project was questioned by Fox. GRE responded that a modest increase would be
seen in local employment and a significant increase in property tax revenue
would occur for the local units of government.
Eric Zweber, Senior Planner for the City of
Summary of Written Comments
No written comments were received regarding the Project.
Dated this _20th_ day of March, 2008.
|
/s/ Richard C. Luis |
|
RICHARD
C. LUIS Administrative
Law Judge |
Reported: Janet Shaddix Elling, R.P.R.
Shaddix & Associates
Two Volumes
[1] Application for a Certificate of Need (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4159333)
[2] Exhibit 1, Application for a Site Permit, (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4385377).
[3] Application for a Certificate of Need, Section 2.9 – Site Selection
[4] ITMO the Application of
[5] Ex. 1, Application for a Site Permit, sections 3.1.3.
[6] Ex. 1, Application for a Site Permit, Introduction and section 1.1.
[7] Ex. 1, Application for a Site Permit, section 3.1.2.
[8] Ex. 1, Application for a Site Permit, section 3.1.1, and Figure 3-1;
[9] Ex. 1, Vicinity Map 1-2, (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4385352 ).
[10]
[13] Ex. 15.
[14]
[15]
[16] Environmental Report (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4897688 .
[17] Environmental Report (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4897688 .
[19]
[20]
[21]
[22]
[23]
[24]
[25] Rosemount Public Hearing Tr., at 9-41.
[26] Rosemount Public Hearing Tr., at 68 (Knoll).
[27] Rosemount Public Hearing Tr., at 45-47.
[28] Rosemount Public Hearing Tr., at 63-67.