OAH 8-2500-19094-2
MPUC Docket No. PL9/CN-07-464 (Certificate of Need)
MPUC Docket No.
PL9/PPL-07-360 (Route)
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of
the Application of Enbridge Pipelines (Southern Lights) LLC for a Certificate
of Need for the and In the Matter of
the Application of Enbridge Pipelines (Southern Lights) LLC for a Route
Permit for the |
SummarY of testimony AT THE PUBLIC HEARINGS, findings of fact, conclusions and recommendations |
Proceedings in the evidentiary and public
hearings for the consolidated Certificate of Need and Route Permit dockets came
before Administrative Law Judge Eric L. Lipman.
Joint public hearings for both the Certificate of Need Docket and the
Route Permit Docket were held in Clearwater, Kittson, Marshall, Red Lake,
Pennington and Polk counties on November 27 and 28, 2007 and on January 17,
2008. An evidentiary hearing on the
Certificate of Need Docket was held on January 22, 2008.
STATEMENT OF THE ISSUES
1.
Has Enbridge
Pipelines (Southern Lights) LLC (“Enbridge” or “Applicant”) met the
criteria set forth in Minnesota Statutes § 216B.243 and Minnesota Rules
Chapter 7853 for a Certificate of Need for a crude oil pipeline?
The Administrative Law Judge concludes that the Applicant’s has demonstrated the need for the proposed facilities.
2.
Whether the Applicant has met the criteria for issuance
of a oil pipeline routing permit (Routing Permit) set forth in Minn. Stat.
§ 216G.02, subd. 3, and Minn. R. 7852.1900, subp. 3?
The Administrative Law Judge concludes that the Applicant’s
application meets those criteria, and recommends that the Routing Permit be
issued, subject to the conditions specified below.
3.
Whether any of the proposed route alternatives
minimize the human and environmental impacts associated with the proposed
pipeline to a greater extent than the Applicant’s
The Administrative Law Judge concludes that the Applicant’s
Overview of the Proposed LSr Project
The proposed LSr Project includes the installation of a
313 mile pipeline between
The LSr project is designed to transport “light” and “medium
sour” crude oil from western
If approved and constructed, the LSr Project will have an annualized capacity to transport 186,000 barrels of crude oil each day. With the addition of additional pumping infrastructure, which is not planned at this time, the capacity of a completed line could be increased to an average of 300,000 barrels of crude oil each day.
Enbridge asserts that demand for crude oil transportation on the Lakehead System has already increased steadily – from 1.35 million barrels-per-day in 2003 to 1.63 million barrels-per-day at the end of 2006.[1] Moreover, it argues that these increases in demand are part of larger upswing in national demand – demand that will peak at one-third more overall consumption of oil by 2030.[2]
Enbridge argues that the existing Lakehead System will be unable to meet this demand without expansion of its light-crude transportation capacity, generally,[3] and in particular, the proposed LSr project.
The Lakehead System is only pipeline system that now connects
Western Canadian oil production with the states of the
While acknowledging that the physical impacts of its proposed routing
fall particularly upon those who live and work along the existing pipeline corridor,
the Applicant maintains that the benefits to the energy system, and the wider
region as a whole, makes the proposed upgrades to the existing route the best
among the possible alternatives. The Applicant asserts that the LSr
Project is needed to relieve “bottleneck” pressures that occur in the current
pipeline system and to improve the “long-haul capacity of crude oil into the
The Commission will issue Orders on the Application for Certification of Need and the Routing Permit submitted by the Applicant after examination of this Report, the hearing transcripts, the filings submitted by the public, and all of the filings and arguments submitted by the Applicant, the Minnesota Department of Commerce, the Minnesota Center on Environmental Advocacy and other persons and entities interested in this matter.
Based on the evidence in the hearing record, the Administrative Law Judge makes the following:
SUMMARY
OF TESTIMONY AT THE PUBLIC HEARINGS
Pursuant to Minn. R. 7852.1700 and 7853.0200,
the Administrative Law Judge conducted public hearings to elicit public comment
regarding the need for, and routing of a crude oil pipeline from a state border
crossing at a point in Kittson, County 2 miles northeast from
Over the course of six public hearings 20 members of the public offered testimony.[5] Additionally, 12 sets of written comments were submitted before the close of the post-hearing comment period on February 8, 2008.
At the outset of the public hearings the Administrative Law Judge made introductory remarks, followed by short presentations from Bret Eknes of the Commission’s staff, Karen Finstad Hammel, as counsel to the Minnesota Department of Commerce’s Office of Energy Security, and a presentation from the Applicant. Following these presentations, members of the public asked questions of the panel members and shared their reactions to the material presented.
A summary of the testimony rendered at these evening hearings follows below:
Kittson
Remarks by Mr. Robert Patton, Land Use and Environmental Review Coordinator with the Minnesota Department of Agriculture: Mr. Patton testified as to the features of the Agricultural Mitigation Plan, the trench digging practices that will best help to preserve topsoil on farms in the Red River Valley and the role that Agricultural Monitors will play in ensuring compliance with the Agricultural Mitigation Plan.[6]
Remarks by Mr.
Thomas Dowdle, Town Clerk of
Remarks by Mr. Kelly Bengtson, of the Kittson County Highway Department: Mr. Bengston echoed the earlier concerns of Mr. Dowdle, emphasizing that having local roads in good working condition was important to agricultural areas at harvest time. Additionally, Mr. Bengston inquired of the panel as to the process for obtaining pipeline water crossing permits and the panel’s prediction of the likely impact of the proposed pipeline on gasoline prices.[9]
Marshall County Hearing – Argyle,
Remarks by Mr. Lon Aune, the Marshall County Engineer: Mr. Aune was complimentary of Enbridge’s efforts to contact local officials and to engage in early planning with those officials on matters relating to the pipeline project. His testimony was principally to highlight matters which he believed Enbridge staff already understood – principally, the importance of maintaining road access to adjacent farms for agricultural workers, the benefits of early notice to county officials of area construction work and the benefit of beginning any boring under paved roads from a point outside of the road right-of-way.[10]
Remarks by Mr. Clifford McGregor, a landowner in
Remarks by Mr. David Clark, a Marshall County Resident: Mr. Clark inquired into whether the accommodations his family had urged at Milepost 823 had been incorporated into the Applicant’s proposed route. Assured that these features were a part of the Applicant’s plan, he testified that he would “approve that route that they have proposed.”[13]
Remarks by Ms. Iona
By way of reply Enbridge staff indicated due to the proximity of a railway line near this site, an existing shelter bed of trees and the Berry home, the Applicant proposes to “neck down” the separation between various pipelines to approximately 15 feet between pipes, in this location.[15] Similarly, Enbridge also indicated that its construction space would be reduced from approximately 140 feet to approximately 80 feet at this location.[16] Enbridge also noted its intention to install exclusion fencing so as to cabin any construction activity to the portions of the property that are covered by the easement agreement.[17]
Remarks by Mr. Cortland Kleven, the Red Lake County Engineer: Mr. Kleven was complimentary of Enbridge’s efforts to contact local officials and to engage in early planning with those officials on matters relating to the pipeline project. His testimony focused upon the importance of transporting heavy loads by way of the higher-capacity trunk highways, the County’s close adherence to MnDOT “spring load restrictions” on overload permits, and the benefits of early notice to county officials of area construction work.[18]
Remarks by Mr.
Leroy Carriere, a landowner in
Remarks by Mr. Brent Strand, Red Lake County Commissioner: Commissioner Strand urged that any final release forms sent by Enbridge to landowners clearly state the contractual terms and be marked in such a way that these materials can be easily identified when they arrive by way of first class mail.[20]
Pennington
Remarks by Mr.
Joel Kezar, a
By way of reply Enbridge staff indicated at the
hearing that its plans – similar to that on the
Remarks by Mr.
Mike Flaagan, Pennington
Remarks by Mr.
Mark Thune, a
Polk
Remarks by Mr. Cory Carlson, owner of Carlson Flying Service, an aerial application company: Mr. Carlson expressed concern that the proposed alignment of the pipeline, at Mile Post 896, along the northern portion of his property, would oblige burdensome relocation of existing buildings and significant restrictions on his company’s ability to expand operations.[26]
By way of reply Enbridge staff indicated that at this point of Mile Post 896, there are a number of other developments that the Applicant hoped to avoid – including a nearby railroad crossing – such that it preferred to again “neck down” the distance between proposed pipelines and to reduce workspace immediately adjacent to the Carlson home and hangar facilities.[27]
Remarks by Mr. John
Gunvalson, a landowner in
By way of reply Enbridge staff indicated that relocating this culvert could be accomplished, if the necessary permits could be obtained from the authorities who have jurisdiction over the ditch.[31]
Remarks by Mr.
Wayne Brekke, a landowner in Gully,
Remarks by Mr.
Charles Aakre, a landowner in
Remarks by Mr.
Hiram Gustafson, a resident of
By way of
reply, Enbridge representatives restated their company’s commitment to
landowner satisfaction and to the payment of market value for the property
rights that are obtained by way of the pipeline easements.[36] Further, Enbridge witness Mark Sitek noted that
Enbridge currently pays approximately $10 million each year in property taxes
in
Remarks by Mr.
James V. Thompson, a resident of
Remarks by Mr.
Curt Amundson, a landowner in
Remarks by Mr.
Dan Sauve, the
SUMMARY
OF THE WRITTEN COMMENTS
Five sets of written comments were received by the Administrative Law Judge before the close of the post-hearing comment period. A summary of the written comments follows below:
Mr.
George Berbee of
Mr.
Donald Berry of
Mr. Donovan Dyrdal of
Mr. Glenn Johnson of
Mr. Jeff Nelson of
Ms.
Alice Peterson of Argyle,
Written
Comments from the
Written Comments from the Minnesota Department of Agriculture: In written comments, Robert Patton, Land Use and Environmental Review Coordinator of the Department’s Agricultural Development and Financial Assistance Division, noted that while Department officials and Enbridge staff “were able to agree on nearly all of the changes to the [Agriculture Mitigation Plan],” there was “one provision about which we were unable to come agreement.” Mr. Patton explained that Section 25 of the AMP provides that later “global changes to the AMP that are requested by Enbridge, the Landowners, the Tenants or the Agriculture Monitors must be reviewed and approved by [the Minnesota Department of Agriculture] ….” While acknowledging the desirability of having flexibility in the AMP to account for later occurring circumstances, the MDA asserts that the rightful authority to approve such modifications lies with the Commission, and not with it.
Written Comments from the Minnesota Department of Natural Resources: In written comments, Matthew Langan, Environmental Planner of the Department’s Environmental Review Unit, outlined a number of concerns with respect to the proposed pipeline routing plan. He urged the Commission to impose a rigorous and continuing set of controls over the project so as to mitigate foreseeable impacts to humans and the environment. Specifically, Mr. Langan suggested measures for the “entirety of the pipeline project” relating to seven distinct topics – namely, clear regulatory controls regarding combating anthrax, obtaining adjustments in the pipeline center line, crossing of sensitive areas, crossing forested river corridors, undertaking winter construction, proper Horizontal Directional Drill practice and avoiding spills of Bentonite into nearby streams.
Based upon the evidence in the hearing record, the Administrative Law Judge makes the following:
FINDINGS OF FACT
I. INTRODUCTION
A. The Parties and Participants
1.
The Applicant is Enbridge Pipelines (Southern
Lights) L.L.C. (hereinafter referred to as “Applicant” or “Enbridge”), a
limited liability company organized under the laws of the state of
2.
The parent company to Enbridge Pipelines
(Southern Lights) L.L.C is Enbridge Energy Company, Inc. Enbridge Energy Company, Inc. is a
3.
Enbridge has international operations and is
involved in the natural gas transmission business. Enbridge’s primary
4. Enbridge is a common-carrier of crude petroleum. As such, its rates, tariffs and accounting practices are subject to the authority of the Federal Energy Regulatory Commission (“FERC”).[47]
5.
Together, the affiliates of Enbridge own and
operate the largest natural gas distribution network in
B. Procedural History
6. Enbridge filed an Application for a Pipeline Routing Permit for a Crude Oil Pipeline on April 20, 2007 for the LSr Project (the “LSr PRP Application”) with the Minnesota Public Utilities Commission (“PUC” or “Commission”). The LSr PRP Application was assigned PUC Docket No. PL9/PPL-07-360.
7. On April 24, 2007 Enbridge filed an Application for a Certificate of Need for a Crude Oil Pipeline for the LSr Project (the “LSr CON Application”) with the PUC. The LSr CON Application was assigned PUC Docket No. PL9/CN-07-464.
8. On April 30, 2007 the Commission sought comments on the completeness of the LSr CON Application.
9. Following the receipt of comments on the application, on July 12, 2007, the Commission accepted the LSr CON and PRP Applications.[49]
10. On July 27, 2007 the PUC issued an Order Accepting Application, Initiating Full Review, Referring to Office of Administrative Hearings and Order and Notice of Hearing for the LSr PRP Application under Docket No. PL9/PPL-07-360.[50] Among other items, the Commission referred the LSr PRP Application to the Office of Administrative Hearings (“OAH”);[51] directed that a contested case hearing under Minn. Stat. Ch. 14 and Minn. R. Ch. 1405 be held on the LSr PRP Application;[52] and noted the nine-month time frame for consideration of the Application set out in Minn. R. 4415.0045.[53]
11. Also on July 27, 2007 the PUC issued an Order Accepting Application as Substantially Complete, Referring Matter to Office of Administrative Hearings and Issuing Notice and Order for Hearing for the LSr CON Application under Docket No. PL9/CN-07-464.[54] Among other items, the Commission’s July 27, 2007 Order, noted that Minn. Stat. § 216B.243, subd. 5 places a 12-month restriction on the time for the PUC to act on the LSr CON Application;[55] directed Enbridge to work with PUC staff to develop notice materials to individuals and entities listed in Minn. R. 7829.2550, subparts 3 and 4;[56] directed any party that wished to make an appearance at the hearing to file a notice of appearance within 20 days of the Order;[57] and directed the DOC to study the issues and indicate its position on the reasonableness of granting a Certificate of Need to Enbridge.[58]
12. On July 27, 2007 the DOC issued a document titled “Notice of Pipeline Routing Permit Application Acceptance and Public Information Meetings on the Enbridge Pipeline Projects.” This nine-page notice document provided an overview of the LSr Project, described some of the Commission’s procedures for reviewing the application and listed the dates, times, and locations of twelve public information meetings.[59]
13. The official notice and cover letter were sent by certified mail on July 30, 2007 to all landowners along the proposed route that Enbridge was able to identify as being reasonably likely to be affected by the Projects. A map of the proposed route, a cover letter from Enbridge, and Notices of Intent from the United States Department of State (“USDOS”) accompanied the mailing to landowners.[60] The same notice documents and copies of the LSr CON and PRP Applications were also mailed to 23 public libraries in communities along the proposed route.[61]
14. On July 30, 2007, similar notice packets were sent to tribal governments, and to the governments of towns, statutory cities, home rule charter cities and counties reasonably likely to be affected by the proposed Projects. The packets were sent in accordance with the Commission’s July 27, 2007 Order and the requirements of Minn. R. 7829.2550 (3) (C).[62]
15. Also on July 30, 2007, the Minnesota Environmental Quality Monitor published a seven-page document titled “Notice of Pipeline Routing Permit Application Acceptance and Public Information Meetings on the Enbridge Pipeline Projects.” This document provided information regarding the nature of the LSr and Alberta Clipper CON and PRP Applications and the opportunities for public involvement in the review process.[63]
16. The official notice and a map depicting the proposed route for the Projects were published in 34 papers of general circulation between August 1 and August 10, 2007.[64]
17. On August 1, a similar packet of information – including the July 27 notice document, a cover letter, a map of the proposed route, the USDOS Notices of Intent, and a CD-ROM of application materials – was sent by certified mail to 126 public officials. The mailings were made pursuant to Minn. R. 4415.0106.[65]
18. The first in a series of prehearing conferences was held on August 7, 2007 at the Commission offices; with the LSr, Alberta Clipper, and Southern Lights Diluent Projects all being presented under OAH Docket No. 8-2500-19094-2.[66]
19.
Public information meetings were held between
August 13 and 23, 2007 in Kittson,
20. On September 14, 2007, Enbridge submitted direct testimony of witnesses Mark Sitek, Denise Hamsher, Paul Meneghini, Tim Andersen, Jerrid Anderson, Paul Eberth, Mike Harris, and Paul Norgren in the LSr CON proceeding.[68]
21. On October 5, 2007, DOC Witnesses Adam J. Heinen and Brian J. Minder filed direct testimony and exhibits in the LSr Certificate of Need proceeding.[69]
22.
Enbridge filed its
23.
The
24. Also on October 10, 2007, Enbridge also filed nine route alternatives. Enbridge asserted that these modifications improved the constructability of the project, reduced its impact to the natural environment and addressed a number of concerns raised by landowners.[71]
25.
The Commission met on November 1, 2007, to
consider the
26.
On November 5, 2007, the Minnesota Environmental Quality Monitor published a seven-page
document titled “Notice of Public Meetings and Public Hearings Before the
Minnesota Public Utilities Commission Regarding:
27. On November 9, 2007, eight Enbridge witnesses filed direct testimony for the LSr PRP Application.[73]
28. On November 9, 2007, Enbridge filed its Comparative Environmental Analysis for the Route Alternatives filed on October 10, 2007.[74] The Comparative Environmental Analysis was approved for release by the DOC.[75] This document compared the Route Alternatives to the route originally described in the LSr PRP Application.[76]
29.
Public hearings were held on November 26 and 27,
2007, in Kittson, Marshall, Pennington and
30.
Meetings in Polk and
31.
On November 30, 2007, the PUC issued an Order
accepting the
32. On December 21, 2007, Enbridge witness Mark Sitek filed rebuttal testimony in the LSr CON proceedings. This testimony provided the Applicant’s response to the testimony of DOC witnesses and corrected information regarding tax benefits to counties that was contained in the LSr Applications.
33.
On January 2, 2008, notice of the rescheduled public
hearings in Polk and
34. On January 4, 2008, Adam J. Heinen and Brian J. Minder, witnesses for the Department of Commerce, completed the filing of all testimony in the LSr CON matter by filing written surrebuttal testimony. Mr. Heinen’s surrebuttal testimony included an updated review of the future economic demand for the type of crude oil that will be transported by the proposed projects.
35.
On January 9, 2008, the
36.
Public hearings were held on January 17, 2007 in
Polk and
37. The Contested Case Hearing for the LSr CON Application was held on January 22, 2008.
38.
Proceedings in the contested case followed oral
argument from counsel on the Petition for Intervention from the
39. A formal order denying MCEA party status in the LSr Project proceedings followed on February 11, 2008.[78]
40. Availing herself of rights extended to all members of the public,[79] counsel for MCEA questioned Department witnesses, Adam J. Heinen and Bryan J. Minder, at the contested case hearing on January 22, 2007.[80]
C. Operational Details of the LSr Project
41.
Enbridge and its corporate affiliates operate
the longest crude oil and liquids pipeline system in the world. This system originates in
42.
The portion of this system in the
43.
The proposed LSr Project is an approximately 313
mile long 20-inch outer-diameter crude oil pipeline between
44.
The LSr project is designed to transport crude
oil from Western Canada to the
45. The LSr Pipeline is designed to transport light and medium density crude oil,[87] although the facilities could be used to transport other types of oil.[88]
46.
Currently, Enbridge injects segregated batches
of light and medium density crude oil from
47. Under Enbridge’s LSr proposal, transportation of these (now segregated) batches of light and medium density crude oil will occur along their own dedicated pipeline.[93] Further, from the vantage point of other expansion projects that it envisions over the course of the next decade,[94] Enbridge asserts that the LSr Project will help to relieve “bottlenecks” in capacity that it projects for this expanded system.[95]
48. The LSr Project will have an Annual Capacity, defined as the average sustainable rate over a year, of 186,000 barrels-per-day (“bpd”). The maximum capacity of the LSr Project is 300,000 bpd – but the Applicant asserts that such a transport capacity would first require the addition of new pumping stations along the pipeline route. The pumping stations that would be needed to meet this maximum capacity are not planned at this time.[96]
49.
The LSr Project will utilize the facilities of
two existing pumping stations. The first
station is located near
50.
The total construction cost of the portion of
the LSr Project that is located within
51. If the project is approved, Enbridge anticipates beginning construction in the spring of 2008, with an expected operational date of December 31, 2008.[99]
II. CERTIFICATE OF NEED
A.
Projections
of Future Energy Demand
52. The United States Department of Energy’s Energy Information Agency (EIA) projects that worldwide demand for oil will increase over the next 25 years from 83 million barrels-per-day to between 105 and 134 million barrels-per-day by 2030. Global demand will increase petroleum prices as competition for a finite resource increases.[100]
53.
According to the Energy Information
Administration’s 2007 Annual Energy Outlook, oil consumption in the
54.
Petroleum demand in the West North Central
Region, a group of seven states that includes
55.
The
56.
Refineries in
57.
The Enbridge Lakehead System currently supplies
approximately 70 to 80 percent of the petroleum refined in
58.
While domestic demand for crude oil is projected
to rise, in
59.
The DOC concluded that consumption of petroleum
in
B.
Projections
of the Impact of Conservation Measures on Demand
60. Enbridge does not produce, refine or market oil.[113] Instead, Enbridge is a common carrier of petroleum products.[114] As a common carrier, Enbridge accepts nominations from shippers, subject to the terms of an earlier FERC-approved tariff, to transport crude oil.[115]
61. Enbridge’s conservation programs are limited to internal corporate efforts to reduce the amount of resources that its operations consume. As a transportation company, it does not have a conservation program that impacts or influences the broader demand for petroleum products.[116]
62. A “preliminary version” of the climate change action plan required by Minn. Stat. § 216H.02 was submitted to the Legislature on February 1, 2008.[117] In general, the preliminary plan recommends pursuing the hoped-for reductions in greenhouse gas emissions through government encouragement of “clean” and renewable energy technologies.[118]
63. Likewise significant, Rates Analyst Adam J. Heinen expressed the view that even in the event of an increase in Corporate Average Fuel Economy (“CAFE”) standards for automobiles, any reductions in consumption that follow from increased fuel efficiency will be outpaced by an increase in overall miles traveled by Minnesotans.[119] Mr. Heinen opined that raising CAFE standards will not reduce demand for the petroleum products transported by the LSr Project.[120]
64. Similarly Rates Analyst Bryan J. Minder expressed the view that potential, future recommendations from the Minnesota Climate Change Advisory Group, the Midwest Governor’s Climate Change Group or the Intergovernmental Panel on Climate Change were simply too indefinite to be analyzed under the Department’s long-range demand forecasts.[121]
65. The DOC reviewed the impact of alternative fuel sources and technologies as part of its analysis of demand for refined petroleum products.[122] The DOC noted that, at best, adoption of new alternative energy technology would slow the growth in demand for refined petroleum products, but not reduce demand below current levels.[123]
C.
Demand
Impact of Enbridge’s Promotional Activities
66.
Enbridge has not undertaken any promotional
activities that would increase demand for crude oil supplies to
D.
Projections
of Current and Planned Facilities to Meet Demand
67.
The Lakehead System is the only pipeline system
that now connects Western Canadian oil production with the states of the
68. Enbridge’s “Mainline System” is operating at or near its oil transportation capacity.[126]
E.
Energy
Conservation Measures Employed By Enbridge
69. Electrical power for pumping on the Lakehead System constitutes approximately 35 percent of Enbridge’s total operating budget for this system.[127]
70. Responding to the operational significance of reducing the amount of power consumed by the line, Enbridge’s Energy Management Department allocates power to pumps on the Enbridge Mainline System,[128] and employs a variety of measures to reduce the amount of energy that its own facilities consume.[129]
F.
Comparing
the LSr Project to Alternative Methods of Meeting Demand
1. The truck transport alternative
71. Responding to the operational significance of reducing the amount of power consumed by the line, Enbridge’s Energy Management Department allocates power to pumps on the Enbridge Mainline System,[130] and employs a variety of measures to reduce the amount of energy that its own facilities consume.[131]
72. The United States Department of Transportation, Pipeline and Hazardous Material Safety Administration determined that, in general, truck transportation of oil is significantly more hazardous than pipeline transportation.[132] For example, the agency projects that transporting crude oil by truck presents a far greater risk – 87.3 times greater – of death than operations which move crude oil by pipelines. Similarly, transporting crude oil by truck is nearly 35 times more likely to result in a fire or an explosion than if this same oil is transported by way of a pipeline.[133]
73.
Transporting 186,000 barrels-per-day of crude
oil between
74. There is genuine doubt that there are sufficient vehicles or drivers available to accomplish such a massive daily caravan.[135]
75. Even if transportation of similar quantities of crude oil were possible by truck, the capital and operating costs of such an enterprise compare poorly with the capital and operating costs associated with transporting crude oil by way of the proposed pipeline. The annual operating cost of the trucking alternative would be approximately $875 million – a figure exceeds the capital costs of the proposed LSr Project.[136]
76. The DOC concurred that truck transportation was a poor alternative to the proposed pipeline due to the higher costs, environmental impacts and increased safety risks associated with transporting this quantity of crude oil by truck.[137]
2.
The rail
transport alternative
77. Responding to the operational significance of reducing the amount of power consumed by the line, Enbridge’s Energy Management Department allocates power to pumps on the Enbridge Mainline System,[138] and employs a variety of measures to reduce the amount of energy that its own facilities consume.[139]
78.
Transporting 186,000 barrels-per-day of crude
oil between
79.
Even if the underlying facilities were
available, transporting 186,000 barrels of oil each day by railway, would
require a total of 26 trains, of approximately 110 cars each, to move between
80. As with a truck transport alternative, it is likely that the annual operating costs of transporting a similar quantity of crude oil by rail, exceeds the overall capital cost of the proposed LSr Project.[143]
3. Pipeline system alternatives
81. Responding to the operational significance of reducing the amount of power consumed by the line, Enbridge’s Energy Management Department allocates power to pumps on the Enbridge Mainline System,[144] and employs a variety of measures to reduce the amount of energy that its own facilities consume.[145]
82. Transporting crude oil by way of alternative pipeline systems – namely, the Enbridge North Dakota System and the proposed Keystone Pipeline system – were also analyzed.
83. Because of the costs and available service dates associated with these alternatives, the DOC concluded that there were not reasonable alternative pipeline systems to the proposed LSr Project.[146]
4. Pipeline route alternatives
84. Enbridge examined alternative routes, but determined that following the route of the existing pipelines in the Lakehead System was the best option.[147]
85. By following along the pipeline existing route, the LSr project pipeline can access and use existing pumping station equipment and consume the least amount of new right-of-way of any construction option.[148]
5. Pipeline design alternatives
86. Enbridge examined the use of various pipe sizes to deliver the proposed capacity of 186,000 barrels-per-day of oil. Among the alternatives considered by Enbridge was deployment of 16, 20 or 24-inch diameter pipe on the LSr Project.[149]
87. In light of the effect that pipeline diameter size had upon such factors as pipeline routing, pump station design, pump station location, system hydraulics and project costs,[150] Enbridge concluded that a 20-inch diameter pipe was the best choice for the LSr Project.[151]
88. A 24-inch pipeline design was less favored, because this option added a considerable amount (approximately $37 million) to the overall project costs, would require construction of larger pump stations and was not well matched to the forecasts of the amount of crude oil that would be transported along the pipeline.[152]
89. Likewise, Enbridge’s analysts did not favor a 16-inch pipeline design, because of the comparatively higher operating costs, need for additional pumping power and lack of expandability associated that would be associated with such a design.[153]
90. The DOC concurs in Enbridge’s assessment that a 20-inch pipeline design is more suitable than either a 24-inch or 16-inch design alternative.[154]
G.
Comparing
the LSr Project to a No-Build Alternative
1.
Operational
impacts of the LSr project compared to a no-build alternative
91.
The key impact of not building the LSr project
is that oil transportation “bottlenecks” in the current system, between
92. As noted above, the LSr Project will eliminate the need to halt the Enbridge Mainline System so as to inject light and medium crude oil into the pipeline.[156] Without this stopping and starting, Enbridge asserts that the Enbridge Mainline System will operate at its full annual capacity[157] and recapture the long-haul capacity that is otherwise lost during the batch injection process.[158]
93. Enbridge projects that the net increase in system capacity achieved (over both systems) by completing the LSr project would be 219,000 barrels-per-day.[159]
2.
Socio-economic
impact of the LSr project compared to a no-build alternative
94. The total cost of the LSr Project is estimated at $125.5 million.[160] Enbridge estimates that nearly 1,000 workers will be required for construction-related tasks along the LSr Project route during the six-month pipeline construction period.[161] Because both local workers will be hired and new workers will relocate to the communities along the pipeline route,[162] Enbridge argues that both local communities and area suppliers will enjoy new revenues from an approved project.[163]
95. The LSr project is expected to result an estimated incremental initial tax value of approximately $3.4 million dollars.[164] Based upon the number of pipeline miles, and the presence of any associated infrastructure, within a particular county, distribution of the incremental increase in taxes will vary among the counties along the LSr Project route.[165]
3.
Environmental
impacts of the LSr project compared to a no-build alternative
a.
Addressing
specific environmental impacts and risks
96. Throughout its application materials Enbridge concedes that installation of the proposed pipeline will necessitate some disruption of the natural environment, however Enbridge argues that these impacts will be mitigated by pre-construction planning and close oversight during and after the construction phase.
97. For example, the Environmental Mitigation Plan proposed by the Applicant includes a series of testing and inspection regimes – including Hydrostatic testing of discharge water for the presence of contaminants,[166] and filtering techniques so as to limit discharge of solids into local streams, rivers and lakes.[167]
98. These features of the Enbridge Environmental Mitigation Plan are bolstered by the requirements of the accompanying Water Appropriation Permit from the Minnesota DNR and the NPDES Construction Stormwater General Permit, the NPDES Hydrostatic Test Water Discharge Individual Permit and the Construction Dewatering Discharge Permit issued by the Minnesota Pollution Control Agency.[168]
99. Daily operation of the completed LSr Project will generate no noise along the pipeline path in the approved right-of-way.[169] There is some noise that is generated by operating the pipeline pump stations. Enbridge pledges to keep this noise level below 40 decibels (when measured at a distance of fifty feet from the pumping station structure) or to any other minimum set by state law.[170]
100. Because the pipeline pumps are powered by electricity, and operate as closed systems, under normal operating conditions the LSr Project will not contribute to local emissions into the air.[171]
101. While petroleum spills are possible during the construction phase – primarily as a result of mishandling petroleum during the refueling of construction vehicles or equipment – Enbridge has a Spill Prevention, Containment and Control Plan to mitigate this risk. For example, among the practices outlined in this plan is that construction equipment will be refueled at least 100 feet from streams or other bodies of water.[172]
102. In order to assure compliance with Enbridge’s various environmental plans and conditions imposed by state agencies, Enbridge has retained a team of inspectors to review the progress of pipeline construction and the overall system following the completion of the construction phase.[173] These inspectors will work alongside, and share information with, inspectors who are gauging compliance with the Agriculture Mitigation Plan (“AMP”).[174]
b.
Addressing
specific impacts and risks to agricultural land
103. The route of the Proposed LSr Project crosses 97.1 miles of agricultural land.[175]
104. While Enbridge argues that most of the existing right-of-way will not be impacted by the addition of the proposed LSr project pipeline,[176] and that any agricultural land disturbed during construction is likely to return to productive use soon after construction,[177] installation of a new pipeline in agricultural areas will necessarily result in disruption to soils and crops.
105. Enbridge will reimburse landowners for construction-related crop damage based upon market rate price of the item that is destroyed.[178]
106. The Enbridge AMP addresses methods of preserving agricultural land during construction – including proper methods of topsoil stripping and segregation, weed control and prevention of erosion.[179] Further, Enbridge pledges in the Agriculture Mitigation Plan to have these practices separately inspected by independent Agricultural Monitors.[180] While the salaries of these monitors will be paid by Enbridge, the Monitors will report their findings to the Minnesota Department of Agriculture.[181]
c.
Addressing
the risks of a petroleum spill
107. While acknowledging if the LSr pipeline is installed, there is a risk that the pipeline might leak petroleum at some time in the future, Enbridge argues that this risk is minimal due to the improvement in pipeline safety records, across the industry,[182] and the measures it undertakes to prevent spills, specifically.
108. The design, construction and any later operation of the LSr Project is subject to oversight by the United States Department of Transportation, Pipeline and Hazardous Material Safety Administration.[183]
109. Under federal regulations, all materials that are used in pipeline construction are inspected for integrity before leaving the factory. Additionally, these items are transported according to special specifications, protected from corrosion during transit and re-tested following installation.[184]
110. Enbridge pledges to design and construct the LSr Project according to industry standards for pipe, pipe coating, valves and other materials.[185] Moreover, Enbridge declares that it will subject all field-welded joints to x-ray inspection – an inspection practice that exceeds the requirements of the current regulations.[186]
111. The completed system will be hydrostatically tested prior to being placed in service.[187] Additionally, Enbridge has a series of systems to inspect, test and verify the integrity of the pipeline following installation.[188]
112. In compliance with federal regulations,[189] Enbridge undertakes periodic preventive maintenance activities. Moreover, the procedures that the Applicant used during the inspection process have been reviewed by the Federal and State regulators.[190] The Minnesota Office of Pipeline Safety frequently monitors maintenance work during onsite inspections.[191]
113. Enbridge patrols the pipeline route by air, at two week intervals, for a total of 26 times per year.[192]
114.
Enbridge operates and manages the Lakehead
System from a central control center in
115.
All Enbridge operations personnel are trained in
emergency response, and response crews are stationed in both
116. Federal regulators have approved Enbridge’s emergency response plans; plans that will be amended to include provisions and mapping for the proposed LSr pipeline if it is approved.[196]
117. Transporting petroleum through a pipeline, presents fewer safety risks for long-distance shipping than transporting petroleum by truck, rail, barge or tank ship.[197]
118. Enbridge considered, but rejected a No- Build Alternative – concluding that no action on the LSr pipeline would spur price spikes for refined petroleum products, negatively impact regional employment opportunities and increase the nation’s reliance on less-secure sources for crude oil.[198]
119. The DOC concluded that the socioeconomic benefits of constructing the LSr Project outweigh the potential effects on the natural environment.[199] Moreover, DOC concluded that Enbridge plans for, and responds well, to pipeline emergencies that occur.[200]
120. The DOC concluded that Enbridge’s examination of alternatives and conclusions that there was no reasonable alternative to the LSr Project satisfies the rule and was reasonable.[201]
H.
The Impact
Of The LSr Project On Future Development
121.
The LSr Project will contribute to future
development in
122.
Enbridge asserts that the proposed LSr pipeline
will provide the resources that are needed in order for
I.
Conclusions
of the Parties and Participants as to Enbridge’s CON Application
123. The DOC concluded that Enbridge should be granted a Certificate of Need for the LSr Project.[205]
124. MCEA argued that the hearing record does not establish that the proposed pipeline project is a superior alternative to receipt of petroleum products from potentially less expensive sources or that the overall consequences to society of granting the certificate of need are more favorable than the consequences of denying the certificate.[206]
III. PIPELINE ROUTING PERMIT
A.
Consultation
with Stakeholders, Agencies and the Public
125. Environmental analysis, land surveys and consultations with landowners on the project began in late 2006 and have continued to be refined through the present day.[207]
126. Drawing
upon the information it developed from consultations with landowners, and the
results of the DOC-led public information meetings, Enbridge filed its
127. As
part of its application materials, Enbridge identified site-specific
construction methods and attendant workspace needs along the project route
north and west of
128. While some commentators expressed concern about the breadth of the route requested in Enbridge’s application,[212] the Applicant argues that a 500 foot route width will permit it to harmonize and balance a number of different construction-related objectives.
129. Pointing to the results of the land surveys and various informational meetings, Enbridge contends that a broad route width will provide it the flexibility to accommodate site-specific routing requests from landowners, address unforeseen construction conditions,[213] reduce the impacts to environmentally sensitive areas and areas of human settlement,[214] and implement federally-required pipeline design features.[215]
130. Likewise,
a broad permit route will enable the Applicant to harmonize the requirements of
three levels of related government permits – those from the U.S. Army Corps of
Engineers, the Minnesota Department of Natural Resources and Pollution Control
Agency, and County governments.[216]
B.
Enbridge’s
Proposed Route Alternatives
131. In most locations along the proposed pipeline route the LSr Project will require 50 feet of additional permanent easement space and 50 feet of temporary workspace immediately adjacent to the new permanent easement space.[217]
132. The 50 feet of new permanent easement space is required to provide a 25-foot safety buffer on both sides of the LSR Project pipeline.[218] The LSr Project will be located 25 feet from the nearest existing pipeline within Enbridge’s current pipeline easement space and 25 feet from the edge of the new permanent easement space.[219]
133. The 50 feet of additional temporary workspace is needed for construction-related activities such as stringing and bending pipe, storing excavated material, moving equipment.[220]
134. Further,
in limited areas, additional temporary workspaces will also be required. At points that are near water crossings or
road crossings, or in any location that requires a bore or directional drill in
order to install the pipeline, additional temporary workspace has been
requested.[221] A list of these areas is set forth in the
C.
Enbridge’s
Proposed Route Alternatives
135. Enbridge filed nine route alternatives in order to address environmental and constructability issues that were raised as to the originally-proposed LSr Project alignment.[223] Those nine Route Alternatives are:
Route Alternative 1: Coulee Crossing Alternative, Mile Post 805-4.[224]
136. The coulee crossing alternative shifts the point at which the pipeline would cross a small, frequently dry, streambed approximately 50 feet southwest from the location originally identified in the LSR PRP Application.[225] The alternative minimizes the environmental impact to the unnamed coulee and improves constructability of the project.[226]
Route Alternative 2: Donaldson Station Alternative, Mile Post 814.0.[227]
137. This alternative deviates from the existing right-of-way southwest of Donaldson Station and crosses under Minnesota Highway 11. The alternative route passes between an existing electrical substation and an abandoned residence, then turns east, crossing under a county road to re-enter the existing right-of-way along existing pipelines.[228] This alternative reduces congestion with existing utilities and pipelines in this area of the Donaldson Station. Further, as initially proposed, there would be insufficient space between the Donaldson Station property, and Minnesota Highway 11, to safely install the pipeline.[229]
Route Alternative 3: Farmstead Alternative, Mile Post 822.9.[230]
138. This alternative turns south of the existing right-of-way at point that is west of a group of farm buildings and the associated shelter belt.[231] The alternative was developed at the request of the landowner, so as to minimize the impact on the landowner’s structures and shelter belt.[232]
Route Alternative 4: Farmstead Alternative, Mile Post 831.3.[233]
139. This alternative crosses under the existing pipeline at a point northwest of farmstead buildings and tree shelter belts located at Mile Post 831.3.[234] The LSr pipeline would then run along the north side of the existing right-of-way and then cross under the right-of-way at a point southeast of the Farmstead buildings and shelter belt.[235] Because there is insufficient space between the south side of the existing right-of-way, and the farmstead that is located at Mile Post 831.3, this alternative was developed to reduce impact to the farmstead property.[236]
Route Alternative 5: Revised
140. This
alternative will employ a horizontal directional drill to cross under a private
driveway, the
Route Alternative 6:
141. At Mile Post 843.1, the proposed LSr Project pipeline will parallel the southern-most existing pipeline in Enbridge’s right-of-way at a distance of approximately 25 feet.[241] This alternative minimizes the amount of tree clearing required in this location, because the proposed pathway runs into a clear, workspace area that was established during the installation of a pipeline in 1984.[242] Further, this alternative also reduces the length of the proposed pipeline by approximately 300 feet.
Route Alternative 7: Fen Avoidance Alternative, Mile Post 853.5.[243]
142. For this alternative, the proposed LSr Project pipeline will cross under existing pipelines within the Enbridge right-of-way at a point near 60th Street N.W. in Viking, Minnesota, and run parallel to the northern-most existing pipeline at a distance of approximately 25 feet. Approximately 2,700 feet southeast of the initial crossing point, the pipeline would cross back under the existing pipelines, and continue to the southwest, parallel to the existing right-of-way.[244] Environmental survey work conducted by Enbridge revealed a sensitive wetland with the characteristics of a calcareous fen. Constructing the pipeline as initially proposed would adversely impact the fen and relocating the pipeline as proposed in this alternative will minimize that impact.[245]
Route
Alternative 8:
143. For
this alternative, the proposed LSr Project pipeline will cross under existing
pipelines within the Enbridge right-of-way at Mile Post 864.2. This alternative has the effect of altering the
location of the Horizontal Directional Drill (HDD) crossing of the
Route Alternative 9: Railroad Crossing Alternative, Mile Post 896.0.[249]
144. This alternative alters the point at which the project crosses from the north side of the existing right-of-way to the south side of the existing right-of-way. This alternative improves the constructability of the proposed pipeline by avoid existing utility poles and providing a larger area for temporary workspace to affect the railroad crossing at Mile Post 896.[250]
145. As memorialized in an Order dated November 30, 2007, the PUC accepted all nine route alternatives.[251]
D.
Enbridge’s
1.
Impact
upon human settlement, existence and density of populated areas, existing and
planned future land use, and management plans
146. The LSr PRP Application includes an Environment Assessment Supplement which details areas of human settlement, and the population density of those areas, along the proposed route. Municipalities located within one mile of the route are identified in Table 3.1-2.[252]
147. In Table 4.3.5-1 of the Application, Enbridge has identified 198 structures (residences and commercial buildings) located within 500 feet of the construction work area.[253] Possible construction impacts are noted in the application materials and Enbridge has outlined a series of steps to control dust near residences.[254] Further, Enbridge declares that construction activity will generally be limited to daylight hours so as to limit the noise level impacts that are associated with construction.[255]
148. The points at which the proposed route intersects a public road – something that occurs 134 times along the proposed route – are identified by jurisdiction[256] and by milepost[257] in the application materials. Similarly, the application materials detail the number and location of rail crossings.[258]
149. Current land use along the proposed route is identified and classified as open land, forest lands, agricultural lands, developed lands or wetlands-open water.[259] Tellingly, the amount of “developed land” that is affected by pipeline construction is .7 percent of the total land affected by the project. [260]
150. Data from the Minnesota Geological Survey and the Minnesota Department of Health’s water well information database, reveals only one domestic well within 200 feet of the pipeline route.[261]
151. Enbridge continues to search for the location of additional, non-registered wells, if any, within 200 feet of the pipeline route.[262]
152. During public hearings, an Enbridge representative confirmed that if cased wells are later discovered within the 150 foot setback area along the pipeline route, Enbridge will, at its expense, either adjust the location of the pipeline or relocate the well to a different part of the property outside of the setback area.[263]
153. Enbridge’s survey and easement processes include providing landowners with a pre-printed checklist of important features and characteristics of the landowner’s property – including the location of wells. Enbridge uses such individualized checklists when conferring with landowners and making alignment and work space decisions along the pipeline route.[264]
2.
Impact
upon the natural environment, public and designated lands; including, natural
areas, wildlife habitat, water and recreational lands[265]
154. Enbridge has assembled a thorough catalogue of the typography, soils, habitats, ecological systems and water resources traversed by the LSr pipeline route. [266]
155. The proposed pipeline route crosses two state-designated canoe and boating routes[267] and comes within ½ of a mile of a state wildlife management area.[268] Any impacts upon water crossings can be mitigated by implementation of the EMP.[269]
156. Vegetation cover will be removed from the right-of-way and temporary workspace areas during construction, but restored following the completion of construction.[270]
157. Similarly, Enbridge representatives testified that they recognize the aesthetic value and sheltering benefits ornamental trees; and pledged that the Applicant will hire consultants, if necessary, to accurately appraise the value of any trees taken during the construction process.[271]
158. Installation of the pipeline will occur below ground, generally, at a depth of 10 feet. For most of the pipeline route, this depth is above the water table.[272]
159. Enbridge has detailed the measures it will use to prevent groundwater contamination and disruption to water resources in the accompanying Spill Prevention, Contaminant and Control Plan and the Environmental Mitigation Plan.[273]
3.
Impact
upon lands of historical, archeological or cultural significance[274]
160. Enbridge’s review of files from the Minnesota State Historic Preservation Office has revealed one site of archeological significance within the proposed construction corridor.[275] Any routing permit issued by the Commission should condition installation on measures to avoid, minimize or mitigate adverse impacts to this site.[276]
4.
Impact
upon economies within the route including agricultural, commercial or industrial,
forestry, recreational and mining operations[277]
161. Approximately 1,177 acres of agricultural land, 44 acres of timber and 9.8 acres of developed land (including both residential and commercial properties), will be disturbed during construction and installation of the LSr pipeline.[278]
162. Under the accompany mitigation plans, Enbridge has pledged to compensate (or provide other value) to landowners for damage caused by construction activity, installation-related crop loses, damage to drainage systems, clearing of otherwise merchantable timber or impacts to gravel deposits.[279]
163. The impact of pipeline construction upon roads and transportation resources is likely to be minimal. Construction disturbances at open-cut road crossings will typically be limited to one day. Further, Enbridge pledges that, with the exception of brief periods during the process of laying the new pipeline, it will maintain at least one traffic lane, or establish a detour, on the roads where construction activities occur.[280]
164. Additionally,
during the public hearing hearing in
5.
Pipeline
cost and accessibility[283]
165. In
2006 U.S. dollars, Enbridge has estimated the cost of the
166. Access to the pipeline right-of-way will be from either public roadways or approved access roads.[285]
6.
Use
of existing right-of-way and right-of-way sharing or paralleling[286]
167. With the exception of a few discreet instances, where the site-specific conditions made placement of the pipeline in the existing right-of-way inappropriate,[287] Enbridge has proposed to use the south-western edge of the right-of-way as the pathway for most of the LSr project.[288] Enbridge proposes to leverage “co-location” on the existing right-of-way throughout its suggested route.
7.
Impact
upon natural resources and features[289]
168. The topography of the proposed pipeline route is characterized by gently rolling till plains.[290]
169. The
elevation of the LSr pipeline route varies from a low point of 766 feet above
sea level in
8.
The
extent to which human or environmental effects are subject to mitigation by
regulatory control and by application of the permit conditions for pipeline
right-of-way preparation, construction, cleanup, and restoration practices[292]
170. If approved for a pipeline routing permit, the LSr Project will be subject to a pyramiding series of regulatory controls – beginning with the Commission’s requirements and continuing with further restrictions regulating road crossings, water crossings, water discharge, protection of endangered species and protection of sites of historical significance.[293]
171. Enbridge has also developed substantial environmental and impact mitigation plans as part of the Environmental Assessment Supplement to the LSr PRP Application.[294] Compliance with these mitigation plans[295] should be a condition of a routing permit issues for the LSr Project.
172. Likewise, imposition of the fourteen permit conditions set forth in Minn. R. 7853.3600, to the LSr Pipeline Routing Permit, will provide still further protection against adverse impacts to humans or the environment.[296]
9.
Consideration
of cumulative potential effects of related or anticipated future pipeline
construction[297]
173. The
174. The proposed routes of the LSr and Alberta Clipper Projects are adjacent and parallel.[299]
175. Enbridge
states that beyond the proposed LSr and Alberta Clipper Projects, it does not
currently have plans for pipeline construction in
10.
Consideration
of the relevant applicable policies, rules and regulations of other state and
federal agencies, and local government land use laws including ordinances
adopted under Minn. Stat. § 299J.05, relating to the location, design, construction
or operation of the proposed pipeline and associated facilities[300]
176. Construction of the LSr pipeline will require consultation with federal, state and local government agencies. Specifically, Enbridge has identified 31 permits, licenses or plans that must be obtained, approved and filed prior to undertaking project-related construction.[301]
177. The record does not support a finding that Enbridge cannot – or will not – abide by federal, state or local requirements relating to the construction of the proposed pipeline.[302]
CONCLUSIONS
I.
ANALYSIS
OF THE NEED FOR THE PROPOSED FACILITY
1.
The Public Utilities Commission and
Administrative Law Judge have jurisdiction to consider Enbridge’s application
for a Certificate of Need and a Routing Permit.
2. Minn. Stat. § 216B.243 governs certificates of need for large energy facilities, including crude oil pipelines.
3. Minnesota Rules Part 7853 governs the application process and Minn. R. 7853.0130 sets for the showing that must be made in order for issuance of a Certificate of Need to be proper.
4. Under Minn. R. 7853.0130, the Certificate of Need application, alongside accompanying comments and filings, is assessed according to a four-factor test. Those factors are:
(a)
the probable result of denial would adversely
affect the future adequacy, reliability, or efficiency of energy supply to the
applicant, to the applicant's customers, or to the people of
(b) a more reasonable and prudent alternative to the proposed facility has not been demonstrated by a preponderance of the evidence on the record by parties or persons other than the applicant;
(c) the consequences to society of granting the certificate of need are more favorable than the consequences of denying the certificate; and
(d) it has not been demonstrated on the record that the design, construction, or operation of the proposed facility will fail to comply with those relevant policies, rules, and regulations of other state and federal agencies and local governments.[303]
A.
The Future
Adequacy, Reliability, or Efficiency of Energy Supply to the Applicant, to the Applicant's
Customers, or to the People of
5.
Petroleum demand in the West North Central
Region, a group of seven states include
6.
While the Minnesota Legislature has established a
schedule of emission reductions as state goals,[306]
the methods by which
7.
The demand for crude oil supplies in
8. The Enbridge Mainline System is currently operating at or near capacity.[309]
9. No existing or planned facilities can meet the future demand without a Certificate of Need.
10.
The net result of the LSr Project will be an
increase in system capacity of 219,000 barrels-per-day. The 186,000 barrels-per-day
LSr Project will eliminate the need to halt the system between the upstream
portion of the Enbridge Mainline System in
11. The best conclusion from the record is that a denial of the LSr CON Application would “constrain petroleum supply to Minnesota and surrounding regional markets, leading to higher petroleum prices . . . [which would] adversely affect the future adequacy, reliability, and efficiency of energy supply to the applicant, the applicant’s customers, and to the people of Minnesota and neighboring states.”[312]
B.
A
More Reasonable and Prudent Alternative to the Proposed Facility-Pipeline has
Not Been Demonstrated By a Preponderance of the Evidence on the Record By Third
Parties or Other Persons or Entities
12. Minn. R. 7853.0540 requires an applicant for a certificate of need to provide information regarding alternatives to the proposed project that were considered. Enbridge examined six alternatives to the LSr Project.[313]
13. No pipeline alternatives were introduced or established by any other person or party.
14. The alternatives considered were no action, trucking, rail transportation, pipeline system alternatives, alternative routes and alternative pipeline designs.
15.
Because no action would tend to “constrain
petroleum supply to
16.
Enbridge reasonably concluded that the
17. Due to the associated costs, environmental disruption and reduced safety, transportation of 186,000 barrels of oil per day by truck is not a reasonable alternative to the LSr Project.
18. Due to the associated costs, environmental disruption and reduced safety, transportation of 186,000 barrels of oil per day by rail is not a reasonable alternative to the LSr Project.[315]
19.
The Keystone Pipeline is not a feasible
alternative to the proposed LSr project because it does not connect to refinery
markets in
20. Because following the route of the existing Lakehead System permits Enbridge to use existing pumping station equipment, and requires the least amount of additional new right-of-way, it is a reasonable option and the best alternative.[317]
C.
The
Consequences to Society of Granting the Certificate of Need are More Favorable than
the Consequences of Denying the Certificate
21.
The primary benefit of the LSr Project to
22.
The LSr Project will allow the upstream portion
of the Enbridge Mainline System to operate at its full annual capacity.[320]
This increased crude oil transportation capacity will result in a more stable
supply to refineries in
23. The LSr Project will provide numerous socioeconomic benefits – including increased crude oil supplies, increased tax revenue and significant investments that will spur employment and spending in local communities.
24. Approval of the LSr CON Application will result in significant socioeconomic benefits over both the short and long terms.
25. The negative environmental consequences, such as disruption to cropland, damage during construction and potential oil spills can be mitigated (and in many cases fully remediated), through observance of the various plans accompanying the Enbridge Application.
26. The socioeconomic benefits of constructing the LSr Project outweigh the effects of pipeline construction upon the natural environment.[321]
27.
Denial of the LSr CON Application will result in
a loss of the potential socioeconomic benefits and would “adversely affect the
future adequacy, reliability and efficiency of energy supply to Enbridge’s
customers, the people of
D.
The
Design, Construction, and Operation of the Proposed Facility Will Comply with the
Relevant Policies, Rules and Regulations of All Other Applicable Agencies and
Governments
28. There is no indication in the record that the design, construction or operation of the LSr Project will fail to comply with the relevant policies, rules, and regulations of other state and federal agencies and local governments.[323]
E.
Conclusion
Regarding A Certificate Of Need For The LSr Project
29. The Public Utilities Commission should grant a certificate of need to Enbridge Pipelines (Southern Lights) L.L.C. and Enbridge Energy, Limited Partnership for the LSr Project.
II.
ANALYSIS
OF THE PROPOSED ROUTING
A. Regulatory Analysis
30. Minnesota Statutes Chapter 216G governs the routing of crude oil pipelines.
31.
A pipeline may not be constructed in
32. Environmental review is a part of the Pipeline Routing Permit process. Under the rules of the Environmental Quality Board (EQB), “any pipeline reviewed under Chapter 4415[325] automatically satisfies EAW and EIS requirements.”[326]
33. Under Minn. R. 7852.1900, the pipeline route application, alongside accompanying comments and filings, is assessed according to a ten-factor test. Those factors are:
(a) Human settlement, existence and density of populated areas, existing and planned future use, and management areas;[327]
(b) The natural environment, public and designated lands, including, but not limited to, natural areas, wildlife habitat, water and recreational lands;[328]
(c) Lands of historical, archeological, and culture significance;[329]
(d) Economies within the route, including agricultural, commercial or industrial, forestry, recreational and mining operations;[330]
(e) Pipeline cost and accessibility;[331]
(f) Use of existing rights-of-way and right-of-way sharing or paralleling;[332]
(g) Natural resources and features;[333]
(h) The extent to which human or environmental affects are subject to mitigation by regulatory control and by application of the permit conditions contained in Part 7852.3400 for pipeline right-of-way preparation, construction, clean up, and restoration practices;[334]
(i) Cumulative potential effects of related or anticipated future pipeline construction;[335] and,
(j) The relevant applicable policies, rules, and regulations of other state and federal agencies, and local government land use laws including ordinances adopted under Minn. Stat. § 299J.05, relating to the location, design, construction, or operation of the proposed pipeline and associated facilities.[336]
34. Enbridge has carefully planned its proposed pipeline so as to minimize the impacts to human settlements, densely-populated areas and both existing and planned future land uses.
35. Enbridge has carefully planned its proposed pipeline so as to minimize the impacts to the natural environment, public lands and designated lands – including natural areas, wildlife habitat, water, and recreational lands.
36. Enbridge has carefully planned its proposed pipeline so as to minimize the impacts to lands of historical, archeological and cultural significance.
37. Enbridge has carefully planned its proposed pipeline so as to minimize the impacts to agricultural, commercial, industrial, forestry, recreational or mining operations.
38. Enbridge has carefully planned its proposed pipeline so as to minimize costs, consistent with an accessible and safely-operated pipeline.
39. Enbridge has carefully planned its proposed pipeline so as to maximize the use of existing right-of-way and right-of-way sharing or paralleling.
40. Enbridge has carefully planned its proposed pipeline so as to minimize the impacts to natural resources and naturally-occurring features.
41. As the Applicant acknowledges in its submissions, the benefits of the proposed projects can be maximized, and its adverse impacts reduced, by application of certain regulatory controls – including the permit conditions contained in Minn. R. 7852.3600 relating to pipeline right-of-way preparation, construction, cleanup and restoration practice.[337]
42.
As noted above, Enbridge states that beyond the
proposed LSr and Alberta Clipper Projects, it does not have plans for pipeline
construction in
43. Enbridge has carefully planned its proposed pipeline so as to detail and meet the requirements of applicable policies, rules and regulations of local, state and federal agencies – including ordinances adopted under Minn. Stat. § 299J.05 that relate to the location, design, construction or operation of pipeline facilities.
44. The record of this proceeding demonstrates that Enbridge has satisfied the criteria set forth in Minn. Stat. § 216B.243 and Minn. R. 7853.0130.
45. No party or person has demonstrated by a preponderance of the evidence that there is a more reasonable and prudent alternative to the proposed pipeline.
46. The Applicant has conducted an appropriate environmental assessment consistent with Minn. R. 4415.0115 to 4415.0170 and met the requirements for alternative environmental review in Minn. R. 4410.3600
B.
Width
of the Stipulations of LSr Pipeline Routing Permit
47. Enbridge has addressed all the criteria set forth by Minn. R. 7852.1900.
48.
The Commission should grant a Pipeline Routing
Permit for the LSr Project. The permit
should authorize construction and operation of the LSr Project within the
49.
The 500 foot wide
50. Further a 500 foot wide route and alignment width is needed to permit safe and efficient operation of equipment if construction methods must be changed due to unforeseen developments.[339]
51. Any Pipeline Routing Permit issued to Enbridge should include the route alternatives listed above, as they are responsive to site-specific environmental concerns, landowner requests or pipeline constructability issues.
C.
Stipulations
of LSr Pipeline Routing Permit
52. While there is no evidence in the record to suggest that applicable regulatory requirements will not be met during the construction and operation of the LSr Project, compliance with such policies, rules and regulations should be made an explicit permit condition for the LSr Project.[340]
53. The Routing Permit should require Enbridge to attain all required local, state and federal permits and licenses, to comply with the terms of those permits or license, and to comply with all applicable rules and regulations.
54. Specifically, the Routing Permit should require Enbridge to comply with the:
(a) permit conditions listed in Minn. R. 7852.3600;
(b) permits listed in Ex. 200, § 7853.0230, as issued by the relevant regulatory agency or local authority;
(c)
mitigation measures developed for the
(d) Enbridge Environmental Mitigation Plan;[341]
(e) Enbridge Spill Prevention, Containment and Control Plan;[342]
(f) Enbridge Agriculture Mitigation Plan, as approved by the Minnesota Department of Agriculture;[343]
(g) Enbridge Petroleum-Contaminated Soil Management Plan;[344]
(h) Enbridge Drilling Mud Containment, Response, and Notification Plan.[345]
55. The Routing Permit should require Enbridge to confer with the Minnesota Historical Society prior to commencing construction at “Site 21MA39” to determine what mitigation measures can be made to preserve this archeological site. Moreover, the Commission should specify that Enbridge may not excavate at this site until so authorized by the Historical Society.[346]
56. With regard to depth of cover, Enbridge should be permitted to seek the waivers allowed by Minnesota Law in subdivisions 2 and 3 of Minn. Stat. § 216G.07.
57. The Routing Permit should require Enbridge to assume any additional costs of development that may be the result of installing roads, driveways and utilities that must cross the right-of-way.
58. The Routing Permit should require Enbridge to cooperate with all entities that have existing easements or infrastructure within the route to ensure minimal disturbance to existing or planned developments.
59. Any Finding of Fact that is more properly characterized as a Conclusion is incorporated here by reference.
Based upon these Findings of Fact and Conclusions, and for the reasons stated in the accompanying Memorandum, the Administrative Law Judge makes the following:
1. Enbridge’s Application for a Certificate of Need for a Crude Oil Pipeline known as the LSr Project should be GRANTED.
2.
Subject to the conditions set forth in the
Conclusions, Enbridge’s Application for a Routing Permit for a crude oil
pipeline known as the LSr Project, including the
Dated: March 24, 2008
|
/s/
Eric L. Lipman __ |
ERIC
L. LIPMAN
Administrative
Law Judge
Reported: Shaddix and Associates
Transcript prepared, 10 volumes
Notice is hereby given that, pursuant to Minn. Stat. § 14.61, and the Rules of Practice of the
Minnesota Public Utilities Commission (“Commission”) and the Office of
Administrative Hearings, exceptions to this Report, if any, by any party
adversely affected must be filed according to the schedule which the Commission
will announce. Exceptions must be
specific and stated and numbered separately.
Proposed Findings of Fact, Conclusions and Order should be included, and
copies thereof shall be served upon all parties. Oral argument before a majority of the
Commission will be permitted to all parties adversely affected by the
Administrative Law Judge’s recommendation who request such argument. Such request must accompany the filed
exceptions or reply (if any), and an original and 15 copies of each document
should be filed with the Commission.
The
Commission will make the final determination of the matter after the expiration
of the period for filing exceptions as set forth above, or after oral argument,
if one is held.
Further notice is hereby given that the Commission may, at its own discretion, accept or reject the Administrative Law Judge’s recommendations and that the recommendations have no legal effect unless expressly adopted by the Commission as its final order.
MEMORANDUM
While the Findings and Conclusions above detail the Administrative Law Judge’s analysis in this matter, one point deserves some additional exposition.
A key part of MCEA’s opposition to granting a Certificate of Need in favor of the LSr Project, pivots on the meaning of the greenhouse gas control provisions of Minnesota Statutes Chapter 216H. In argument, and its later filings, MCEA asserts that granting the Certificate of Need is at odds with legislative direction to reduce statewide greenhouse gas emissions 15 percent below 2005 levels by 2015, and 80 percent below 2005 levels by 2050.[347] This argument is unavailing.
While the Minnesota Legislature has established the schedule of reductions as “goals,” the methods by which our state will reach these lower emission levels has yet to be determined. What Minn. Stat. § 216H.02 does require, is that certain designated members of the Governor’s Cabinet develop and submit a “climate change action plan” for the Legislature’s review – presumably, so that the Legislature can direct the emission reduction process through additional legislation.[348] A “preliminary version” of the climate change action plan was submitted on February 1, 2008.[349]
Likewise important, none of the features of the preliminary plan suggests that the Certificate of Need requirements set forth in Minn. Stat. §§ 216B.243, subd. (3), have been abandoned, repealed or superseded in any way. Indeed, the preliminary plan recommends pursuing the hoped-for reductions in greenhouse gas emissions through government encouragement of “clean” and renewable energy technologies.[350]
For our purposes, in this case, it suffices to say that government encouragement of renewable energy technologies does not amount to a prohibition of, or restriction upon, the development of oil pipeline facilities. For this reason, until Chapter 216B is modified or repealed by the Legislature, its mutli-factor analysis continues to be the order of the day.
E. L. L.
[1] Ex. 200, § 7853.0240 at 1.
[2] Ex. 200, § 7853.0240 at 2.
[3] Ex. 200, § 7853.0240 at 5; see also, Exhibit D, Chart 6 to Ex. 200.
[4]
See,
e.g., Ex. 200, § 7853.0240 at 7; accord,
Ex. 1 at § 4415.0170 at 1.
[5] See, Summary of Written Comments, infra.
[6]
[7]
[8]
[9]
[10] Marshall County Public Hearing Transcript, at 32-35.
[11]
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21]
See,
Exhibit A to
[22]
[23] See, id., at 36-37.
[24]
[25]
[26]
[27]
[28]
[29]
[30]
[31]
[32]
[33]
[34]
[35]
[36]
[37]
[38] See, id., at 44-70.
[39]
[40]
[41] See, Fourth Prehearing Order, OAH Docket No. 8-2500-19094-2, at 2 (February 11, 2008).
[42] Compare generally, Executive Order 13337, 69 Fed. Reg. 25299 (May 5, 2004) (Issuance of Permits With Respect to Certain Energy-Related Facilities and Land Transportation Crossings on the International Boundaries of the United States) ("if the Secretary of State finds that issuance of a permit to the applicant would serve the national interest, the Secretary shall prepare a permit, in such form and with such terms and conditions as the national interest may in the Secretary’s judgment require").
[43] See, MCEA Written Comments, at 5 (December 14, 2007).
[44]
[45] Ex. 200, § 7853.0230 at 1.
[46]
[47] Ex. 200, § 7853.0530 at 1.
[48] Ex. 200, § 7853.0230 at 1-2.
[49] Ex. 202 at 2, 7; Ex. 3 at 2, 7.
[50] Ex. 3.
[51] Ex. 3 at 2, 7.
[52] Ex. 3 at 3.
[53]
[54] Ex. 202.
[55] Ex. 202 at 6.
[56] Ex. 202 at 3, 7.
[57] Ex. 202 at 7.
[58]
[59] Ex. 400.
[60] Ex. 401.
[61] Ex. 402.
[62] Ex. 404.
[63] Ex. 502.
[64] Ex. 405.
[65] Ex. 403
[66] First
Prehearing Order, OAH Docket No. 8-2500-19094-2 at 1 (August 23, 2007).
[67]
Additional public information meetings will
be held for the companion Alberta Clipper and Southern Lights Diluent Projects
– both of which are proposed to extend southeast of
[68] Exs. 203, 204, 205, 206.
[69] Exs. 207, 208.
[70] Ex. 5.
[71] Ex. 4.
[72] Ex. 501.
[73] Exhibits 7, 8, 9, 10.
[74] Ex. 6.
[75] Transmittal Letter, Ex. 6 at ii.
[76] See, Ex. 6.
[77]
See,
[78] See, Fourth Prehearing Order, OAH Docket No. 8-2500-19094-2, at 2.
[79] Compare generally, Minn. R. 1400.6200 (5) and 1405.0800 (C) (2007).
[80] Transcript of the January 22, 2007 Contested Case Hearing at 31-33, 69
[81] Ex. 200, § 7853.0230 at 3 n.1.
[82] Ex. 200, § 7853.0230 at 2.
[83] Ex. 200, § 7853.0230 at 2-3.
[84] Ex. 200, § 7853.0240 at 1.
[85] Ex. 200, §§ 7853.0240 at 1; 7853.0510 at 7.
[86] Ex. 200, § 7853.0510 at 7.
[87] Contested Case Hearing Transcript, at 15 (January 28, 2007).
[88]
[89] Ex. 1, § 4415.0170 at 1.
[90] Ex. 200, § 7853.0240 at 1; Ex. 203 at 9.
[91] Ex. 1, § 4415.0170 at 1.
[92]
[93] Ex. 200, § 7853.0240 at 1; Ex. 203 at 9.
[94] See, MPUC Dockets PL9/CN-07-465, PPL-07-361.
[95] Ex. 200, § 7853.0240 at 7.
[96] Ex. 200, § 7853.0230 at 3-5.
[97] Ex. 200. § 7853.0530 at 2.
[98] Ex. 200, § 7853.0540 at 3.
[99]
[100] Ex. 208 at 35, 37.
[101] Ex. 200, § 7853.0240 at 2.
[102] Ex. 208 at 19, 21 and 24.
[103] Ex. 208 at 20-21.
[104]
Ex. 208 at 15; compare also, Ex. 203 at 16.
[105] Ex. 208 at 15.
[106] Ex. 208 at 17, n. 13.
[107] Ex. 208 at 14, n. 5; Ex. 200, § 7853.0510 at 7.
[108] Ex. 208 at 14, n. 5; Ex. 200, § 7853.0510 at 7; Ex. 203 at 10.
[109] See, Note 100 supra.
[110] Ex 200, § 7853.0240 at 4-6.
[111] Ex. 208 at 20-23.
[112]
Ex. 208 at 38; see also, Contested Case Hearing Transcript at 69, 86-88 and 98.
[113] Contested Case Hearing Transcript at 25.
[114] Ex. 200, § 7853.0530 at 1-2.
[115] Ex. 200, § 7853.0530 at 1-2; Contested Case Hearing Transcript at 24-25.
[116] Ex. 200, § 7853.0260 at 1.
[117] See, Letter of Director Edward Garvey and Commissioner Brad Moore (February 1, 2008) (http://www.state.mn.us/mn/externalDocs/Commerce/Letter_for_preliminary_climate_change_action_plan_020508104727_MPCA-MDC%202-1-08.pdf).
[118] See, Preliminary Climate Change Action Plan, at 1-2 (February 1, 2008) (http://www.state.mn.us/mn/externalDocs/Commerce/Preliminary_Climate_Change_Action_Plan_020508104330_MN-CCAP%20Final%202-1-08.pdf).
[119] Ex. 211 at 12-13.
[120] Ex. 211 at 13.
[121] Contested Case Hearing Transcript, at 46.
[122] Ex. 208 at 28-30.
[123] Ex. 208 at 30.
[124] Ex. 200, § 7853.0250 at 6.
[125] Ex. 200, § 7853.0540 at 2-4.
[126] Ex. 200, § 7853.0510 at 1.
[127] Ex. 200, § 7853.0260 at 1.
[128]
[129]
Id;
Ex. 205 at 4.
[130]
[131]
Id;
Ex. 205 at 4.
[132] Ex. 200, § 7853.0540 at 9, n. 1.
[133] Ex. 200, § 7853.0250 at 2-3.
[134] Ex. 200, § 7853.0540 at 1 and 5-6.
[135] Ex. 200, § 7853.0540 at 10.
[136] Ex. 200, § 7853.0540 at 10; see also, Ex. 200, § 7853.0540 at 13.
[137] Ex. 208 at 8-9; compare, Ex. 200, § 7853.0540 at 10 and 13
[138]
[139]
Id;
Ex. 205 at 4.
[140] Ex. 200, § 7853.0540 at 11.
[141] Ex. 200, § 7853.0540 at 7.
[142] Ex. 200, § 7853.0540 at 11.
[143]
[144]
[145]
Id;
Ex. 205 at 4.
[146] Ex. 208 at 9-10; Ex. 200, § 7853.0540 at 2, 7 and 12.
[147] Ex. 200, § 7853.0540 at 2-4.
[148]
[149] Ex. 200, § 7853.0540 at 3.
[150]
[151]
[152] Ex. 200, § 7853.0540 at 13, 15; compare also, Ex. 200, § 7853.0230 at 3.
[153] Ex. 200, § 7853.0540 at 15.
[154] Ex. 208 at 9-12.
[155] Ex. 200, § 7853.0540 at 9; Ex. 207 at 8.
[156]
[157]
[158]
[159]
[160] Ex. 200, § 7853.0230 at 3.
[161] Ex. 1, Tab C at 3-3.
[162]
[163]
[164] Ex. 209 at 5.
[165] Ex. 207 at 17.
[166] Ex. 200, § 7853.0620 at 1; Ex. 200, § 7853.0630 at 6-7; Ex. 1, Appendix B at 23.
[167] Ex. 200, § 7853.0620 at 1; Ex. 1, Appendix B at 22.
[168] Ex. 200, § 7853.0230 at 7-8.
[169] Ex. 200, § 7853.0620 at 4.
[170]
[171] Ex. 200, § 7853.0620 at 3.
[172]
Ex. 200, § 7853.0630 at 6; Ex. 1,
Appendix C at 23; compare also, Ex.
1, Appendix F (Petroleum-Contaminated Soil Management Plan).
[173] Ex. 200, § 7853.0630 at 7.
[174]
Testimony of Bob Patton,
[175] Ex. 209 at 3.
[176]
[177]
Testimony
of Bob Patton,
[178]
Testimony
of Mike Harris,
[179] Ex. 1, Appendix E; see also, Testimony of Bob Patton, Marshall County Public Hearing Transcript, at 30-31.
[180] Ex. 1, Appendix E, see also, Minn. Stat. § 216E.10 (3)(b) (2006).
[181] Testimony of Bob Patton, Marshall County Public Hearing Transcript, at 30-31.
[182] Ex. 200, § 7853.0250 at 3.
[183] See, 49 C.F.R. Part 195 (2007); Ex. 200, § 7853.0270 at 2.
[184] See, e.g., 49 C.F.R. §§ 192.303 – 192.325 (2007); 49 C.F.R. § 195.112 (2007).
[185] Ex. 200, § 7853.0270 at 1.
[186]
[187]
[188]
Ex. 200, § 7853.0270 at 1-6; Testimony of Mark Sitek,
[189] Ex. 200, § 7853.0270 at 1; compare, e.g., 49 C.F.R. § 192.935 (2007); 49 C.F.R. § 192.937 (2007).
[190] Ex. 200, § 7853.0270 at 4.
[191]
See,
Testimony of Denise Hamsher,
[192] Ex. 200, § 7853.0270 at 3.
[193] Ex. 200, § 7853.0270 at 2-3.
[194]
[195]
Testimony
of Mark Sitek,
[196]
Testimony
of Denise Hamsher,
[197] Ex. 200, § 7853.0250 at 2-3; Ex. 207 at 21-22; Ex. 210 at 8-9.
[198] Ex. 200, § 7853.0540 at 4 and 9.
[199] Ex. 207 at 20.
[200] Ex. 207 at 15.
[201] Ex. 208 at 7.
[202] Ex. 200, § 7853.0250 at 6; Ex. 207 at 20.
[203] Ex. 207 at 20-21; Ex. 200, § 7853.0240 at 3.
[204] See Ex. 200, § 7853.0640 at 1-8.
[205] Ex. 207 at 38.
[206] See, e.g., MCEA Post-Hearing Reply Comments at 10 (February 8, 2008).
[207]
See,
Testimony of Paul Meneghini,
[208] Ex. 5.
[209] Ex. 4.
[210] Ex. 8, at 8.
[211] Ex. 6, at 2.
[212] See, e.g., Written Comments of G. Berbee and A. Peterson.
[213] See, Ex. 6, at 2-3.
[214] Ex. 8, at 8.
[215]
[216] Ex. 200, § 7853.0230 at 7-9; see also, Testimony of Paul Meneghini, Kittson County Public Hearing Transcript, at 58-59; Testimony of Cortland Kleven, Kittson County Public Hearing Transcript, at 37-38 and 57-58.
[217] Ex. 2.
[218] Ex. 2.
[219]
Ex. 2.
[220] See, Ex. 1, Tab C, Figures 1.2-1 and 1.3-1.
[221] Ex. 5; Ex. 1, Tab C at 1-3; Ex. 1, Tab C, Appendix A.
[222] Ex. 5.
[223] Ex. 8, at 10.
[224] Ex. 4, Tab 1.
[225] Ex. 9, at 9.
[226]
[227] Ex. 4, Tab 2.
[228] Ex. 9, at 10-11.
[229]
[230] Ex. 4, Tab 3.
[231] Ex. 10, at 9.
[232]
[233] Ex. 4, Tab 4.
[234] Ex. 10, at 9.
[235]
[236]
[237] Ex. 4, Tab 5.
[238] Ex. 8, at 11.
[239]
[240] Ex. 4, Tab 6.
[241] Ex. 8, at 11.
[242]
[243] Ex. 4, Tab 7.
[244] Ex. 8, at 12.
[245]
[246] Ex. 4, Tab 8.
[247] Ex. 9, at 11.
[248]
[249] Ex. 4, Tab 9.
[250] Ex. 9, at 11.
[251] See, In the Matter of the Application of
Enbridge Energy for a Route Permit - Southern Lights Pipeline, Docket No.
PL-9/PPL-07-360, Order Accepting Items and Extending Deadlines (Nov. 30, 2007) (https://www.edockets.state.mn.us/EFiling/ShowFile.do?DocNumber=4854127).
[252] Ex. 1, Tab C, at 3-3.
[253] Ex. 1, Tab C, Table 4.3.5-1.
[254] Ex. 1, Tab C, Section 4.3.5.
[255]
[256] Ex. 1, Tab C, Table 4.3.6-1.
[257] Ex. 1, Tab D, Appendix D.
[258] Ex. 1, Tab C, Table 4.3.6-2.
[259] Ex. 1, Section 4415.0140, at 2.
[260] Ex. 1, Tab C, Table 4.2-1.
[261] Ex. 1, Tab C, Section 8.3.3.
[262] Id; Testimony of Michael Harris, Pennington County Public Hearing Transcript, at 39-40; compare also, Testimony of Paul Meneghini, Pennington County Public Hearing Transcript, at 40-41.
[263]
Testimony
of Michael Harris,
[264] See, Ex. 12; Marshall County Public Hearing Transcript, at 25-26.
[265]
[266] Ex. 1, Section 4415.0145; Ex. 1, Tab C, Sections 2, 5, 6, 7, 8, 9 and 11.
[267] Ex. 1, Tab C, Section 11.1.
[268] Ex.1, Tab C, Section 11.1.2.
[269] Ex. 1, Tab D, Appendix B at 10-13.
[270] Ex. 1, Section 4415.0145, at 4; Ex. 1, Tab D, Appendix B, Section 7.7, at 28.
[271]
Testimony
of Michael Harris, Pennington County Public Hearing Transcript, at 40; see also, id. 43-51.
[272] Ex. 1, Section 4415.0145, at 5.
[273] Ex. 1, Section 4415.0145, at 5; Ex. 1, Tab C, Section 9; Ex. 1, Tab D, Appendix C.
[274]
[275] Ex. 1, Section 4415.0145, at 7; Ex. 1, Tab C, Section 10.1.
[276] Ex. 1, Section 4415.0145, at 7.
[277]
[278] Ex. 1, Tab C, Sections 3.2.4, 4.2 and 4.3.
[279] Ex. 1, Tab C, Section 3.2.4; Ex. 1, Tab C, Section 4; Ex. 1, Tab D, Appendix E; see also, Testimony of Paul Meneghini, Marshall County Public Hearing Transcript,, at 43-44; Testimony of Jerrid Anderson, Red Lake County Public Hearing Transcript, at 43-44
[280] Ex. 1, Tab C, Section 4.3.6, pp. 4-6.
[281]
[282]
[283]
[284] Ex. 1, Section 4415.0115, subp. 4, D.(3), at 2; see also, Ex. 200, Section 7853.0230.
[285] Ex. 1, Tab D, Appendix B, Section 2.1, p. 3.
[286]
[287] Ex. 1, Tab C, Section 2.3.1, p. 2-3.
[288]
[289]
[290] Ex. 1, Tab C, Section 5.1.
[291]
[292]
See,
[293] See, Ex. 200, Section 7853.0230 at 7-9; Ex. 207 at 23-24.
[294] Ex. 1, Tab C, Appendices B, C, E, F and G.
[295] Ex. 1, Tab C, Appendix B at 26-29 and 31; Ex. 1, Tab C, Appendix E at 59.
[296]
[297]
[298] Ex. 5; Ex. 6 at 1.
[299] Compare, Exhibits 5 and 115.
[300]
[301] Ex. 1, Section 4415.0165, at 1-2.
[302] Compare generally, Ex. 207 at 23-24.
[303]
[304] Ex. 208 at 19 - 24.
[305] Ex. 208 at 18.
[306]
See,
[307]
See,
[308] Ex. 200, § 7853.0250 at 6.
[309] Ex. 200, § 7853.0510 at 1.
[310] Ex. 1 at § 4415.0170 at 1.
[311] Ex. 200, § 7853.0240 at 1; Ex. 203 at 9.
[312] Ex. 208 at 38.
[313] Ex. 200, § 7853.0540 at 1-15.
[314] Ex. 200, § 7853.0540 at 5-6, 10; Ex. 208 at 8-9.
[315] Ex. 208 at 8-9.
[316] Ex. 200, § 7853.0540 at 2.
[317] Ex. 200, § 7853.0540 at 2-4; Ex. 208 at 12.
[318] Ex. 207 at 20-21; Ex. 200, § 7853.0240 at 3.
[319] Ex. 200, § 7853.0240 at 6-7; Ex. 207 at 20-21; Ex. 208 at 34-37; see also Testimony of Adam J. Heinen, Contested Case Hearing Transcript at 58, 95 and 101-105.
[320] Ex. 1 at § 4415.0170 at 1.
[321] See, e.g., Ex. 207 at 20-23.
[322] Ex. 207 at 8.
[323]
Compare,
[324]
[325] The Environmental Quality Board formerly governed the pipeline routing process through Minnesota Rules Chapter 4415. Chapter 4415 was subsequently renumbered without substantive changes to Chapter 7852.
[326] Guide to Minnesota Environmental Review Rules, at 20 (http://www.eqb.state.mn.us/documents/rulguid3.pdf).
[327]
[328]
[329]
[330]
[331]
[332]
[333]
[334]
[335]
[336]
[337] Compare also, Ex. 1, Section 7852.3000; Ex. 200, Section 7853.0230; Ex. 207 at 23-24.
[338] Ex. 9, at 6-7; see also, Ex. 8 at 8.
[339]
[340] See generally, Ex. 207 at 23-24.
[341] Ex. 1, Tab D, Appendix B.
[342] Ex. 1, Tab D, Appendix C.
[343] Ex. 1, Tab D, Appendix E.
[344] Ex. 1, Tab D, Appendix F.
[345] Ex. 1, Tab D, Appendix G.
[346] Ex. 200, Section 7853.0610 at 7.
[347]
See,
[348]
See,
[349] See, Letter of Director Edward Garvey and Commissioner Brad Moore (February 1, 2008) (http://www.state.mn.us/mn/externalDocs/Commerce/Letter_for_preliminary_climate_change_action_plan_020508104727_MPCA-MDC%202-1-08.pdf).
[350] See, Preliminary Climate Change Action Plan, at 1-2 (February 1, 2008) (http://www.state.mn.us/mn/externalDocs/Commerce/Preliminary_Climate_Change_Action_Plan_020508104330_MN-CCAP%20Final%202-1-08.pdf).