OAH Docket No. 8-2500-17840-2
MPUC Docket No. E-002/CN-04-1176 (Certificate of Need)
MPUC Docket No. E-002/TL-06-1677 (Route)
STATE OF MINNESOTA
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
In the Matter of the Petition of Northern States Power Company d/b/a Xcel Energy and Dairyland Power Cooperative for a Certificate of Need for a 115 kV and 161 kV Transmission Line from Taylors Falls to Chisago County Substation and In the Matter of the Petition of Northern States Power Company d/b/a Xcel Energy and Dairyland Power Cooperative for a Route Permit for a 115 kV and 161 kV Transmission Line from Taylor Falls to Chisago County Substation |
SummarY of testimony AT THE PUBLIC HEARINGS, findings of fact, conclusions and recommendations |
A prehearing conference was held on May 9, 2007, at 1:00 p.m. in the Commission’s large hearing room before Administrative Law Judge Eric L. Lipman. The following persons noted their appearance:
James P. Johnson, Assistant General Counsel, Xcel Energy Services Inc., 414 Nicollet Mall, Suite 2900, Minneapolis, MN 55401, and Michael Krikava, and Catherine A. Biestek, Briggs and Morgan, P.A., 2200 I.D.S. Center, 80 South 8th Street, Minneapolis, MN 55402, appeared on behalf of Northern States Power Company d/b/a Xcel Energy (Xcel Energy).
Jeffrey L. Landsman, Wheeler, Van Sickle & Anderson, S.C., 25 West Main Street, Suite 801 Madison, WI 53703 on behalf of Dairyland Power Cooperative (Dairyland).
Valerie M. Means, Assistant Attorney General, 445 Minnesota Street, Suite 1400, St. Paul, Minnesota 55101, appeared on behalf of the Department of Commerce (“Department”) for the Certificate of Need Proceeding.
Karen Finstad Hammel, Assistant Attorney General, 445 Minnesota Street, Suite 1400, St. Paul, Minnesota 55101, appeared on behalf of the Department for the Routing Proceeding.
Carol Overland, Overland Law Firm, Post Office Box 176, Red Wing, Minnesota 55066 by telephone on behalf of the City of Lindstrom, Minnesota (Lindstrom).
William Neuman, Concerned River Valley Citizens, 18837 Osceola Road, Shafer, Minnesota 55074 by telephone on behalf of Concerned River Valley Citizens (CRVC).
Robert Cupit and Bret Eknes, Minnesota Public Utilities Commission, Suite 350, 121 East Seventh Place, St. Paul, MN 55101-2147, on behalf of the Public Utilities Commission (the Commission or MPUC).[1]
Proceedings in the evidentiary and public hearings
for the consolidated Certificate of Need and Route Permit dockets came before Eric
L. Lipman, Administrative Law Judge on September 4, 5, 6, 7 and 10, 2007. Evidentiary hearings on the Certificate of
Need Docket were held on September 4, 5, and 10, 2007. Evidentiary hearings on the Route Permit
Docket were held on September 6 and 7, 2007.
Joint public hearings for both the Certificate of Need Docket and the
Route Permit Docket were held at the Chisago Lakes Area Library at 11754 302nd
Street, Chisago City, Minnesota 55012, on the evenings of September 4 and 5,
2007.
STATEMENT OF ISSUES
1.
Have Xcel Energy and Dairyland (collectively,
“Applicants”) met the criteria set forth in Minnesota Statutes §§ 216B.243
and 216B.2426 and Minnesota Rules Chapter 7489 for a Certificate of Need for a
115 kV/161 kV transmission line from the Chisago County Substation in
Minnesota to the Apple River Substation near Amery, Wisconsin?
2.
Does the Applicants’ proposed route from Taylor
Falls to Chisago County Substation balance the needs of the state’s “power supply and electric transmission
infrastructure,” with adjacent land uses, as set forth in Minn. Stat. § 216E.03,
subd. 7 and Minnesota Rules Chapter 7489?
Background on the
Joint Applications:
Xcel Energy and Dairyland have jointly
applied for a Certificate of Need authorizing certain upgrades to the
electrical transmission system serving east central Minnesota and northwestern
Wisconsin. The Applicants propose to
replace an existing 69 kV transmission line with a new 115 kV
electric transmission line between Xcel Energy’s Chisago County Substation (near
North Branch) and Taylors Falls, Minnesota.
Additionally, the Applicants propose to replace an existing 69 kV
transmission line with a 161 kV electric transmission line between Taylors
Falls, Minnesota and Dairyland’s Border Substation in St. Croix Falls,
Wisconsin.[2]
As detailed in its application materials, the Applicants maintain that the proposed 115 kV/161 kV transmission line is needed so as to provide additional transmission capacity, and to reliably serve both the existing and the future demands for electricity in east central Minnesota and northwestern Wisconsin.[3]
Additionally,
while acknowledging that the impacts of its proposed routing fall particularly
upon those who live and work along the existing corridor, the applicants
maintain that the benefits to the electricity system, and the wider region as a
whole, makes the proposed upgrades to the existing route the best among the
possible alternatives.
The Commission will issue Orders on the Application for Certification of Need and the Routing Permit submitted by the Applicants after examination of this Report, the hearing transcripts, all written filings submitted by the public, and all filings and arguments submitted by the Applicants, the Minnesota Department of Commerce and other persons and entities interested in this matter.
Based on the evidence in the hearing record, the Administrative Law Judge makes the following:
SUMMARY
OF TESTIMONY AT THE PUBLIC HEARINGS
Pursuant to Minn. R. 7848.2000, Subpart 11, the
Administrative Law Judge conducted public hearings on the evenings of September 4 and 5, 2007. The public hearings were held to elicit
public comment regarding the need for, and routing of, a 115 kV/161 kV
transmission line from the Chisago County Substation in Minnesota to the Apple River
Substation near Amery, Wisconsin.
Over the course of the two public hearings, 49 members of the public were in attendance and signed the hearing roster.[4] Nineteen of those who registered on the hearing roster offered testimony during the hearings. Twelve written comments were submitted before the close of the post-hearing comment period on September 14, 2007.
At the outset of the public hearings the Administrative Law Judge made introductory remarks, followed by short presentations from Robert Cupit of the Commission’s staff, Dr. Steve Rakow of the Energy Division of the Department, and David Birkholz, a Program Manager with the Energy Permitting Unit of the Department of Commerce, and a presentation from the Applicants. Following these presentations, members of the public asked questions of the presenters and shared their reactions to the material presented.
A summary of the testimony rendered at these evening hearings follows below:
Remarks by Mr. Gerald Adams: Mr. Adams, a homeowner on the proposed route along First Avenue in Lindstrom, expressed concerns over routing a large transmission line along the downtown corridor. With a wider, and more heavily trafficked Highway 8 planned for the area, Mr. Adams argued that upgrading the transmission line along the existing corridor presented special risks of hazard and injury. He suggested that the line was better placed elsewhere. Further, on aesthetic grounds, he urged that the larger towers associated with an 115kV line be placed outside of the downtown area.[5]
Remarks by Mayor Keith Carlson: Mr. Carlson, a long-time resident of Lindstrom, and its current Mayor, expressed preference for either the “Under the Lakes” routing option (Lindstrom’s Proposed “Option E”) or an option that placed the transmission line underground along Highway 8. Mayor Carlson expressed the view that the type of transmission line towers proposed for placement along Highway 8 was appropriate for placement in rural locales, but not in an increasingly urbanized center, such as downtown Lindstrom. Additionally, Mayor Carlson argued that the City’s history of collaboration and cooperation with the hosting of this transmission line should not be “made worse” as the City works to become a shopping and tourism destination.[6]
Remarks by Ms. Joan Carlson: Ms. Carlson expressed the view that the threat of power outages and blackouts, as detailed in the Applicants’ presentation, was overstated – and completely at odds with her experience over many years in the area. She posited that the proposed routing was an attempt to overreach upon lower-income residents who are not as politically powerful as others in the state.[7]
Remarks by Mr. Chris DuBose: Mr. DuBose outlined the plans and steps that the City of Lindstrom has completed in recent years so as to develop the downtown corridor along Highway 8 as a tourist destination. Further, he detailed the special challenges that Lindstrom’s location presents when the City attempts to attract other, non-tourism-related business and industries to the Chisago Lakes Area. He urged that the upgraded line either be routed underground along Highway 8, or in the alternative, routed north away from the downtown corridor.[8]
Remarks by Councilman Curt Flug: Mr. Flug, a member of the Lindstrom City Council, expressed the view that the revenues that would be generated from existing power demand would be sufficient to underwrite an underground alternative for placement of the transmission line in downtown Lindstrom. He detailed the efforts that he and other members of the Council are making to revitalize “a struggling city.” Councilman Flug concluded that if underground alternatives were viable in wealthier communities, they should be viable in more modest communities, like Lindstrom, as well.[9]
Remarks by Mr. Richard Herold: Mr. Herold expressed the view that Xcel Energy had considerable land holdings in rural areas north of the City of Lindstrom and that it would be more appropriate for the Applicants to route the upgraded line along these parcels.[10]
Remarks by Ms. Shellene Johnson: Ms. Johnson, a former member of the Lindstrom City Council and a member of the Concerned River Valley Citizens, asserted that it was in the best interests of Minnesota residents to have the line buried along Highway 8 in Lindstrom. She pointed to the special arrangements that the Applicants have proposed for routing along the St. Croix River Bluff as setting out the proper and appropriate practice for other scenic areas – such as those in and around Lindstrom.[11] Additionally, following a colloquy with members of the Applicants’ panel, Ms. Johnson questioned whether the project was designed or intended to meet local needs. Instead, she argued that the proposal asks Minnesota residents and ratepayers to shoulder infrastructure costs, health risks and aesthetic burdens so as to efficiently service the demands of Wisconsin customers from the Chisago substation.[12]
Remarks by State Representative Jeremy Kalin: Representative Kalin made a few key points during his remarks. First, he posited that analysis of local needs that were developed by Mr. Duebner – who is an employee of the Midwestern Independent System Operator – should be approached with some skepticism. As Representative Kalin noted, whereas the current 69 kV line is not a part of the MISO system, an upgraded 115 / 161 kV transmission line would join the MISO grid as “a significant asset.” Secondly, Representative Kalin observed that each of the previous load forecasts that he has reviewed “have the same curve;” with each suggesting that “urgent action is needed.” He concludes that “the forecasting in general … ends up being kind of the self-fulfilling prophecy … [to] allay this need that is supposedly out there.” Finally, characterizing the proposed overhead routing of the transmission line along Highway 8 as “the least imaginative” option, he urged pursuit of an underground alternative. In Representative Kalis’ view, an underground alternative would reduce the visual impacts and preserve tourism as Lindstrom’s second largest industry.[13]
Remarks by Mr. Vincent Marier: Mr. Marier, a business owner along Highway 8, expressed concern as to the impact that the proposed routing will have upon the aesthetics and “small town feel” of the downtown business district. Additionally, pointing to concerns for his employees, Mr. Marier had several inquiries of the Applicants’ panel and Department staff about the effects of long-term exposure to Electro-Magnetic Fields.[14]
Remarks by Mr. Jerry Miller: Mr. Miller, President of the Lindstrom Economic Development Authority, detailed the City of Lindstrom’s efforts to capitalize upon its Swedish heritage and to develop the downtown corridor as a tourist destination. Among the challenges Lindstrom has faced in recent years was in encouraging the passengers in vehicles traveling along Highway 8 to stop and to patronize local businesses. From his perspective, placement of the transmission towers and transformers along Highway 8 is at odds with the local Economic Development Authority’s development plans for the corridor.[15]
Remarks by Ms. Carmelita Nelson: Ms. Nelson expressed concern that the proposed routing of the transmission line along Highway 8 would undermine the attractiveness and the viability of Lindstrom’s athletic fields, Farmer’s Market and the proposed “Swedish Immigrant Trail” – all of which would lie beneath the Applicants’ proposed line path. Ms. Nelson also offered the view that if the benefit to be obtained was more reliable power services, Minnesotans were more than prepared to suffer power outages of a day or two; and presumably she preferred this result to the proposed route.[16]
Remarks by former State Representative Peter Nelson: Representative Nelson, a former City Official and long-time resident, outlined the special challenges that Lindstrom has faced over the years in developing its commercial base. Representative Nelson argued that the combination of Lindstrom’s relative distance from Interstate Highway 35, and the recent rise in the price of gasoline, have intensified the City’s challenges in developing new businesses. Further, Representative Nelson argued that the placement of large transmission line support structures within along an urbanized business district was not appropriate. In his view, the added costs of an underground alternative along Highway 8 was justifiable and similar to other, earlier burdens spread across the base of ratepayers. Alternatively, Representative Nelson noted that notwithstanding the fact that a more rural placement of the transmission line might likely place it alongside property owned by his son, daughter-in-law and grandchildren he favored such an alternative over a route in downtown Lindstrom as a “much better choice” for “the greater good.”[17]
Remarks by Ms. Stacy Pearson: Ms. Pearson outlined the process by which the City of Lindstrom undertook its comprehensive planning efforts and how that this process persuaded City officials that pursuit of additional tourism-related dollars provided Lindstrom’s best prospects for remaining vibrant. Ms. Pearson described how the unique topography of Lindstrom – situated as it is on an isthmus, with a limited industrial zone, and roadways that are not conducive to trailer-truck traffic – have combined to depress efforts to attract manufacturers to the area. Accordingly, as part of a larger effort to focus upon development of a tourism-related economy, the City has undertaken a number of renovation projects; including refurbishing the City beaches and marina; upgrades to Highway 8; founding of a visitor’s center; joint ventures with the Swedish Institute, establishment of Swedish signage and upgrades to Lindstrom’s “Swedish Coffee Pot” water tower; among other items. Pointing to the series of tourism-related upgrades that have been completed, Ms. Pearson concludes “I would just humbly request that somebody sympathize with us and do something other than put these poles downtown.”[18]
Remarks by Councilman Jim Singer: Mr. Singer, a member of the Lindstrom City Council, outlined the plans that the Council has for revitalizing the downtown corridor and development of the “Swedish Immigrant Trail.” He regards the proposed placement of larger transmission towers and a higher capacity line along the points of the trail as directly at odds with the City’s plan to attract tourists, grow and develop. He favors routing of the transmission line north of the City of Lindstrom.[19]
Remarks by Mr. Gerold Swanson: Mr. Swanson made several inquiries about the configuration of transmission and distribution under the Applicants proposal.[20]
Remarks by Mr. Joe Tromberg: Mr. Tromberg, a member of the Chisago Lakes Restoration Association, detailed the efforts that the Association has been making to improve the tourism prospects for the City of Lindstrom. Analogizing from his work as a contractor in the Heating and Air Conditioning industry, Mr. Tromberg notes that when he would “wire a control system … I go through a lot of work to hide those wires because they look bad. You should do the extra to go around the city.” Regarding the downtown corridor as an important asset for the “entire community,” Mr. Tromberg favors those alignment options which route the transmission line through more rural areas.[21]
Remarks by Councilman Joseph R. Wishy: Mr. Wishy, a member of the Lindstrom City Council, echoed Mr. DuBose’s remarks regarding the City’s goal to establish a tree-lined tourist destination along downtown corridor. Mr. Wishy expressed the view that the willingness of the City’s forefathers to accommodate earlier, lower voltage transmission lines should not foreclose the current generation of City residents from realizing their development plans.[22]
Written Comments
Submitted by Participants of the Public Hearing
Twelve written comments were received by the Administrative Law Judge before the close of the post-hearing comment period. A summary of the written comments follows below:
Written Comments from Gay Lynn Adams: In her written remarks, Mrs. Adams made four key points: She questioned whether the energy needs described by the Applicants could be better attained through conservation measures; she detailed what she regarded as a poor history by Xcel Energy of customer service; she linked the existing transmission line with deflated property values along 1st Avenue in Lindstrom; and she expressed grave concern over the siting of “huge metal pilings” in the downtown area.
Written Comments from Daniel D. Hoolihan: In his written remarks, Mr. Hoolihan, who is both an Electrical Engineer specializing in Electromagnetic Compatibility Engineering, and a resident of Lindstrom, Minnesota, submitted a series of technical questions about the features of the proposed route. At their core, Mr. Hoolihan’s inquiries questioned the wisdom of routing a high-voltage transmission line through the downtown corridor of Lindstrom.
Written Comments from Commissioner Gary F. Gerke: In his written remarks, Mr. Gerke, a member of the Lindstrom Planning Commission urged both approval of the Certificate of Need and routing of the transmission line north of the City of Lindstrom. He argued that the proposed routing in the downtown corridor “will negate much of what the [Lindstrom Economic Development Authority is] trying to accomplish.”
Written Comments from Carrie Lesnau: In her written remarks, Ms. Lesnau urged approval of an underground alignment option for the transmission line in the downtown corridor. Noting both that “[s]mall towns are about atmosphere and aesthetics, [and] part of our success is in how we look,” she argued that the incremental costs associated with placing the transmission line underground along the downtown corridor, was justifiable. As Ms. Lesnau reasoned, it would “insulate the City from the loss of benefit for our millions dollars in investment” in recent and planned improvements.
Written Comments from Superintendent Michael McLoughlin: In his written remarks, Superintendent McLoughlin of the Chisago Lakes School District, expressed concerns that the proposed transmission line alignment would traverse both Bryant Environmental Center in Taylors Falls and the Chisago Lakes Middle School. He argued that a policy of “prudent avoidance” would result in routing transmission lines away from “schools and area used by students.”
Written Comments from former State Representative Peter Nelson: In his written remarks Representative Nelson detailed his view that the best route for any transmission line would be further north than the proposed alignment through the City of Lindstrom. Additionally, pointing to aspects of an earlier routing application, which do not appear in the currently proposed plan, Representative Nelson argued that the proposed routing vindicates aesthetic interests unevenly and incompletely – addressing some aesthetic interests along the St. Croix River Valley but none in the City of Lindstrom.
Written Comments from Councilman Joseph R. Wishy: In his written remarks, Councilman Wishy detailed further how the routing of the transmission line through Lindstrom’s downtown corridor conflicts with the City’s tourism-related objectives.
A Petition, signed by 49 residents of Minnesota, stating their objections to the routing of the 115/161 kV transmission line through the City of Lindstrom, was received.
Written Comments from Saint Croix Scenic Coalition: In its written remarks, the Coalition detailed its concerns over the “direct negative visual impact from the proposed installation of the [High Voltage Transmission Line] where, after descending the River bluff face underground, it transitions to overhead and crosses Wild Mountain Road (County Highway 16), a part of the byway, in Taylors Falls.” The Coalition “vigorously oppose[s] overhead construction.” Instead, it urges a continuation of the underground routing “under the St. Croix Scenic Byway at County 16 before transition to overhead for the River crossing.” Submitted along with its comments were maps of the Byway and a copy of a study commissioned by the Coalition entitled “Attractiveness in the St. Croix Valley: An Analysis of Perceptual Judgment and Landscape Dimensions.”
Written Comments from the Department of Natural Resources: In written comments, Matt Langan, an Environmental Planner with the DNR’s Division of Ecological Services, suggested a slight revision to Table 13 of the Environmental Assessment (so as to add Mattson Lake) and noted that the proposed routing “along the western bluff of the St. Croix River is consistent with DNR’s previous understanding of the project.” Further, Mr. Langan went on to observe that the “DNR supports the plans for reducing the number of lines crossing the river, as well as eliminating overhead lines coming down the bluff.” Concluded Mr. Langan, because “this is an existing corridor, DNR recommends mitigation measures described in the [Environmental Assessment] be accepted, and does not recommend any additional underground crossings.”
Written Comments from the Department of Commerce: In written remarks, Assistant Attorney General Karen Finstad Hammell wrote to make three key points on behalf of the Energy Permitting Staff. First, notwithstanding the claims of the City of Lindstrom and CRVC, the Department asserted that members of the public were provided a sufficient opportunity to contribute to, and comment upon, the scoping of the environmental review. Second, the Department offered its view as to the meaning and import of the Environmental Quality Board’s holdings regarding noise mitigation efforts in an important decision from 2001: In the Matter of the Exemption Application by Minnesota Power for a 345/230 kV High Voltage Transmission Line Known as the Arrowhead Project.[23] Third, pointing to the Commission’s request that the Department “conduct the environmental review process, including any specific requests to the ALJ concerning preparation of a report or making a recommendation to the Commission on the route,” the Department asserted that “under its delegated authority, [it] is not making an additional requests for any recommendation to the Commission in the route proceeding.”
Written Comments from Co-Applicant, Xcel Energy: In written remarks, counsel for Co-Applicant, Xcel Energy, Michael C. Krikava, wrote to make two clarifications regarding details in the Environmental Assessment and, as stipulated among the parties to the formal proceedings, to submit the Affidavit of Publication as a late-filed exhibit. With respect to the clarifications, Mr. Krikava detailed the amount of the incremental increase in the costs of construction for the “Around the Lakes Over Head Alternative” and the dimensions of the underground vaults and duct banks that are suggested for use in Segment 5 of the Applicants’ routing proposal.
FINDINGS OF FACT
The Parties
and Participants:
1. Northern States Power Company, a Minnesota corporation and wholly-owned subsidiary of Xcel Energy Inc., is a public utility. Among other business interests, Xcel Energy owns and operates high voltage transmission lines in Minnesota and delivers electricity to its customers in Minnesota and other states.
2.
Dairyland is a not-for-profit generation and
transmission cooperative that provides the wholesale electrical requirements
and other services for 25 electric distribution cooperatives and 19 municipal
utilities and has a service area that extends to four states, including
Minnesota and Wisconsin.[24]
3.
The City of Lindstrom intervened as a formal party
in the Certificate of Need proceeding and joined as a formal participant in the Route Permit proceeding. The existing 69 kV transmission line, as
well as the center line of the Applicants’ proposed route travel through the City
of Lindstrom.
4.
CRVC intervened as a formal party in the
Certificate of Need proceeding and joined as a formal participant in the Route Permit proceeding.
5.
The Department is authorized by statute to
participate in matters before the Commission involving utility rates and
adequacy of utility services and to intervene in Certificate of Need
proceedings.[25]
Procedural
Background:
6.
On July 30, 2004, Applicants filed a petition for
approval of a notice plan (Certificate of Need Notice Plan) with the Commission
pursuant to Minn. R. 7829.2550 for a transmission project in east central
Minnesota.
7.
On October 6, 2004, the Commission issued an Order
Approving Notice Plan with Modifications.
8.
On June 30, 2006, Applicants filed a modified
Certificate of Need Notice Plan.
9.
On September 9, 2006, the Commission issued an
Order Approving Revised Notices as Further Modified.
10.
On October 10, 2006, Applicants filed a Notice Plan
Compliance Filing required by the Commission’s September 2006 order.
11. On November 16, 2006, Applicants filed their Certificate of Need Application.[26]
12.
On
December 6, 2006, Applicants filed a notice of intent to file a Route Permit
Application using the alternative permitting process with the Commission
pursuant to Minn. R. 7829.5500, subp. 2 for a transmission project in east
central Minnesota.
13.
On January 5, 2007, Applicants filed a Route Permit
Application[27] for the
Chisago County transmission project under the Alternative Permitting Process,
MPUC Docket No. E-002/TL-06-1677.
14.
On January 24, 2007, Applicants filed a Notice of
Route Permit Application and Public Meeting.
15.
On February 12, 2007, the Commission issued an
Order Accepting the Certificate of Need Application as Substantially Complete
and directing that an Environmental Assessment be completed for both the Certificate
of Need and Route Permit proceedings.
16.
On February 12, 2006, Applicants filed a
Supplemental Filing to the Certificate of Need Application and Errata.[28]
17.
On February 12, 2007, the Commission issued a
Notice and Order for Hearing referring the Certificate of Need matter to the
Office of Administrative Hearings for contested case proceedings; authorizing
joint public hearings in the Certificate of Need docket and the Route Permit
docket; and combining the environmental review proceedings in both the Certificate
of Need and Route Permit dockets. In this Order, the Commission also authorized
the EFP Staff to establish an advisory task force and develop a proposed
structure and charge for the task force.
18.
On
February 22, 2007, the EFP Staff sent a letter to local government officials in
the proposed route area, soliciting individuals to serve as members of the
Advisory Task Force.
19.
On February 23, 2007, the First Prehearing
Conference was held before the Administrative Law Judge.
20.
On February 26, 2007, the Administrative Law Judge
issued a First Prehearing Order, establishing a schedule and setting procedures
for additional proceedings. The First Prehearing Order established an
intervention deadline of March 19, 2007.
21.
On February 27, 2007, the Department held a public
information meeting in Lindstrom, Minnesota to inform the public about the
proposed project and the regulatory proceedings; discuss environmental, social,
and economic issues of importance in the area potentially affected; and to
gather public input regarding the scope of the Environmental Assessment
required by Minnesota Rules 7849.5700 and the Commission’s February 12, 2007
order. At the meetings, public had an
opportunity to ask questions about the proposed project, to suggest
alternatives, and to outline specific impacts that should be addressed by the Department
in its Environmental Assessment. The
public was given until March 30, 2007, to submit written comments on the scope
of the Environmental Assessment. [29]
22.
Because
of the lack of affirmative responses regarding participation in the Advisory
Task Force, on March 12, 2007, the EFP Staff filed a letter to the Commission
notifying the Commission of the lack of participation and the EFP Staff’s
intent to work with those government officials and members of the public to
form an informal advisory group.
23.
The City
of Lindstrom asserts that the timeframe within which responsive replies were
due was too compressed to facilitate meaningful participation by stakeholders.[30]
24.
On March
13, 2007, the EFP Staff filed a letter to local government officials in the
proposed route area inviting them to participate in an informal advisory group
in lieu of the formal Advisory Task Force.
25.
On March 19, 2007, the City of Lindstrom and CRVC
both filed petitions for intervention.
26.
On March 30, 2007, the Working Group
submitted its report, A View From the Ground, Alternative Routes & Least
Environmental Cost Considerations for the Proposed Chisago Electric Transmission Line Project.[31]
27.
On April
6, 2007, the EFP Staff filed its response to the City of Lindstrom’s Motion to
Extend the Advisory Task Force, requesting that the issue be certified to the
Commission.
28.
On April 9, 2007, the Administrative Law Judge
issued Interim Orders on Intervention, granting the City of Lindstrom’s
petition for intervention and taking CRVC’s petition for intervention under
advisement pending review of supplemental filings.
29.
On April
9, 2007, the City of Lindstrom filed with the Commission a Petition for a
Contested Case in the Route Permit docket.
30.
On April
11, 2007, the Chisago Task Force issued its recommendations.
31.
On April 18, 2007, CRVC filed a response to the
Interim Orders on Intervention.
32.
On April 24, 2007, the Administrative Law Judge
issued a Second Order on Intervention, granting CRVC’s petition for
intervention.
33.
On May 1, 2007, the Administrative Law Judge issued
a Scheduling Order, scheduling a second prehearing conference on May 9, 2007,
to discuss changes to the schedule set in the First Prehearing Order.
34.
On May
1, 2007, the Commission issued an Order Denying Motion to Extend Time Frame of
Advisory Task Force and Requiring Collaboration.
35.
On May 9, 2007, a Second Prehearing Conference was
held before the Administrative Law Judge.
On May 29, 2007, the Administrative Law Judge issued a Second Prehearing
Order, adopting a hearing schedule and procedures applicable to both the
Certificate of Need and the Route Permit proceedings.
36.
On July 13, 2007, Applicants submitted prefiled
testimony of David Duebner[32],
Michael P. Dunham[33],
Thomas G. Hillstrom[34],
and Charles A. Thompson.[35] The City of Lindstrom submitted prefiled
testimony of John Olinger.[36] The Department submitted prefiled testimony
of Dr. Stephen Rakow,[37]
David E. Birkholz,[38]
and Hwikwon Ham.[39]
37.
On August 17, 2007, Applicants submitted prefiled
rebuttal testimony of David Duebner,[40]
Michael P. Dunham,[41]
Thomas G. Hillstrom,[42]
and Charles A. Thompson.[43]
38.
On August 20, 2007, the City of Lindstrom submitted
prefiled rebuttal testimony of A. Bruce Poole.[44]
39.
On August 20, 2007, the Department filed its Environmental
Assessment.[45]
40.
On August 22, 2007, the Administrative Law Judge
issued a Third Prehearing Order, scheduling a prehearing conference on August
28, 2007.
41.
On August 23, 2007, Applicants moved to file
additional rebuttal testimony of David Duebner in response to the City of
Lindstrom testimony of Bruce Poole.
42.
On August 23, 2007, Notice of the Public Hearings
was published in the St. Paul Pioneer Press.
43.
On August 28, 2007, a Third Prehearing Conference
was held before the Administrative Law Judge, during which the Administrative
Law Judge granted Applicants’ motion to file additional rebuttal testimony of
David Duebner.
44.
On
August 28, 2007, the EFP Staff published Notice of the Availability of the
Environmental Assessment in the EQB Monitor.
45.
On August 29, 2007, Applicants submitted prefiled
additional rebuttal testimony of David Duebner with attachments.[46]
46.
Hearings to obtain public comment were conducted at
7 p.m. on September 4 and 5, 2007, at the Chisago Lakes Area Library at 11754
302nd Street, Chisago City, Minnesota 55012.
Members of the public attended both hearings and submitted comments on
the record.
47.
Evidentiary hearings in the Certificate of Need
proceeding were conducted on September 4 and 5, 2007, at the Chisago Lakes Area
Library at 11754 302nd Street, Chisago City, Minnesota 55012; and on September
10, 2007, at the Minnesota Department of Commerce at 85 Seventh Place East,
Suite 500, St. Paul, Minnesota 55101.
Witnesses for Xcel Energy, Dairyland, the City of Lindstrom, and the
Department testified at the evidentiary hearings.
48.
The public comment period and period to comment on
the Environmental Assessment remained open until September 14, 2007.
49. On September 14, 2007, the EFP Staff filed their Comments and Request for Findings of Fact.
50. On September 14, 2007, Xcel Energy filed its Comments to the Environmental Assessment.
The Applicants’ Proposal to Meet the Demand for Electricity:
51.
The Applicants’ Certificate of Need Application
seeks authorization to construct the proposed 115 kV/161 kV transmission
project.
52.
By the Joint Certificate of Need Application, Xcel
Energy and Dairyland seek certification for the replacement of an existing
69 kV electric transmission line with a new electric transmission line
consisting of 115 kV and 161 kV elements between the Chisago County
Substation near North Branch, Minnesota and the Apple River Substation near
Amery, Wisconsin. Specifically, the
proposal consists of a 115 kV transmission line from Xcel Energy’s Chisago
County Substation to a new Xcel Energy substation called Lawrence Creek, to be
located near Taylors Falls, Minnesota.
53.
The first five miles of the existing 69 kV
transmission line, extending south from the Chisago County Substation, was
built to 115 kV standards in 1995 and requires no physical change.
54.
The line voltage from the Lawrence Creek Substation
to the Border Substation in St. Croix Falls, Wisconsin would be
161 kV.
55.
Applicants propose to place the new line
underground through the land use district within the Lower St. Croix National
Scenic Riverway, with the exception of the river crossing located in the
vicinity of the St. Croix Falls dam. Under
the proposal, the electric transmission line will continue on from the Border
Substation to the Apple River Substation located near Amery, Wisconsin. In this segment, the transmission line will
replace an existing 69 kV transmission line with a 161/69 kV double
circuit line; upgrades which have been earlier approved by the Public Service
Commission of Wisconsin.[47]
56.
The new Lawrence Creek Substation would be located
on disturbed agricultural land near the City of Taylors Falls’ wastewater
treatment facility just outside the city’s boundary in Shafer Township. Transformers and switching equipment that
would be needed to accommodate 115 kV, 161 kV, 69 kV, and
distribution voltages would be installed at Lawrence Creek.[48]
57.
In 2006 dollars, the transmission line project as
proposed by the Applicants will cost approximately $64,200,000.[49]
58.
If the proposed project is approved, Xcel Energy
will own approximately 21 miles of the proposed transmission line located in
Minnesota, at an estimated cost of $47,472,000. Xcel Energy’s affiliate
Northern States Power Company, a Wisconsin corporation (“NSPW”), will own the
portion of the 161 kV facilities in St. Croix Falls from the
Minnesota/Wisconsin border at the St. Croix River Crossing to the Border
Substation. Dairyland will own
approximately 21 miles of the proposed transmission line from the Border
substation to the Apple River substation, at an estimated cost of $16,229,000.
59.
East Central Energy, the local electric
distribution cooperative serving the Shafer, Minnesota area, has agreed to
defray a small portion of the project costs ($500,000), but is not an Applicant
in these proceedings.[50]
60.
In addition to the proposed transmission line,
Applicants have identified the need for various equipment upgrades and a new
115/161 kV substation (denominated as the Lawrence Creek Substation) to be
located near the City of Taylors Falls. The
Applicants maintain that the development of a new substation is an integral
part of the larger program of improvements to increase transmission capacity
and reliability in the area.[51]
61.
As proposed by the Applicants, the new transmission
line would use existing corridor alignments, requiring approximately only 1.2
miles of new transmission line corridor near the new Lawrence Creek
Substation. The existing 69 kV
transmission line has a 50-foot wide right-of-way that lies 25 feet on each
side of the transmission line centerline.
The proposed 115 kV/161 kV transmission line would be built on
structures that range between 60 to 90 feet tall placed at intervals of
approximately 260 to 285 feet apart along the line route.[52]
62.
Applicants’ proposed project will also include
expansion work at the Lindstrom and Shafer Substations to accommodate the
switching gear, bus work and new transformers necessary to integrate a new
115 kV line into these distribution substations. Under the Applicants’ proposal, these
substations would be converted from 69 kV to 115 kV operations.[53]
63.
If the Applicants receive a Certificate of Need to
construct the transmission facilities, routing approvals must also be obtained
from the Commission and local authorities to construct any approved lines. Applicants are simultaneously applying for
the required Route Permit for the proposed transmission facilities using the
Alternative Permitting Process.
Applicants assert that that construction on an approved line could begin
during calendar year 2008. Applicants
estimate that the project could be operational by 2010.[54]
64. The Department agreed that the proposed 115 kV/161 kV transmission line is needed for system reliability support in east central Minnesota and northwestern Wisconsin. The Department recommended that the Commission grant the Certificate of Need for the proposed project.[55]
Development of the Proposal and Alternatives:
65.
The existing 69 kV transmission system serving
east central Minnesota and northwestern Wisconsin has three transmission
sources: the Chisago 115-69 kV (18.75 MVA) transformer; the Arden Hills
115-69 kV (70 MVA) transformer; and the two Apple River 161-69 kV (67
MVA) transformers.
66.
The system is operated with an Arden Hills-St.
Croix Falls 69 kV line, a St. Croix Falls-Apple River 69 kV line, and
a radial Chisago County-Lindstrom 69 kV line. Because the City of Lindstrom is served via a
radially operated 69 kV line from the Chisago County Substation, if there
is a fault on the Chisago County 115/69 kV transformer or on the Chisago –
Lindstrom 69 kV line, the customers served from the Lindstrom Substation
would be without power.[56]
67.
At the present time, only the Lindstrom
Substation is served from Chisago County Substation. A switch on the existing 69 kV
transmission system on the east side of the Lindstrom Substation is kept open
to prevent damage to the circuit. If too
much electrical current flows through the 69 kV transmission line, and the
switch was closed, transformers and conductors along the line could be damaged
– and power outages result. [57]
68.
The St. Croix Falls hydro-electric plant is
centrally located in the system and has a maximum output of 24 MW and an
average output of 12 MW. The
substations in east central Minnesota served from this system include:
Lindstrom, Shafer, Scandia, May, and Birch.
Northwestern Wisconsin substations served from this system are: St.
Croix Falls, Osceola, Farmington, Trap Rock, Border, Sand Lake, Balsam Lake,
Eureka, and Milltown. [58]
69.
Several previous studies have identified the need
for improvements to the transmission system in east central Minnesota and
northwestern Wisconsin in order so as to maintain service reliability in the area. Those studies include: the Hugo Area
Long-Range Electric Delivery Study conducted in December 1994; the NSP
Long-Range Delivery System Study, Central Twin Cities Area conducted in
February 2000; and the Chisago Electric Reliability Project, Hybrid
115/161 kV Analysis conducted in September 2001.[59]
70.
The Chisago County – Apple River study (attached as
Appendix B to Applicants’ Certificate of Need Application), was conducted to
determine what system improvements might be needed in light of the improvements
that have been made to the transmission system since 1996. This study was undertaken in 2004.[60]
71.
Seven different options to meet the need for electrical
reliability in the east central Minnesota and northwestern Wisconsin areas were
initially considered:[61]
72.
Option AW: Option
AW includes a Stone Lake 345-161 kV tap of the Arrowhead-Weston
345 kV line.
73.
Option CA: Option
CA includes Chisago-Lindstrom-Shafer-Lawrence Creek 115 kV line and
Lawrence Creek-St. Croix Falls-Apple River 161 kV line (“Chisago Electric
Reliability Project”), with both line sections hosting bundled phase
conductors.
74. Option CA1: Option CA1 includes a Chisago-Lawrence Creek 115 kV line, a new Lawrence Creek Substation, a Lawrence Creek-St. Croix Falls-Border 161 kV line, and a Border-Apple River 161/69 kV double circuit line.[62] Option CA1 also includes a single conductor per phase instead of bundled conductor for each phase.
75.
Option DF: Option DF includes reconfiguration of the 69 kV system in
east central Minnesota and northwestern Wisconsin, upgrading the Chisago County
Substation 115-69 kV transformer and adding reactive support. Option DF would separate the
transmission system in the northeastern Twin Cities from the transmission
system in northwestern Wisconsin. This
separation would be accomplished by operating a circuit breaker at the St.
Croix Falls Substation to interrupt the flow of electricity. This alternative option would require
construction of new lines and electrical components in both Minnesota and
Wisconsin. The required additions
include a higher capacity transformer at the Chisago County Substation and
capacitor installations at Lindstrom and Scandia. Further, a new three mile, 69 kV
transmission line circuit would be installed between St. Croix Falls and the
Border Substation. This transmission
line circuit would run through the City of St. Croix Falls and would not
replace any existing circuits. Other facets
of this alternative include upgrading the existing 69 kV line from Border
Tap to Apple River to a higher capacity 69 kV line and upgrading the
115 kV line from the King Substation to the Willow River Substation to a
higher capacity 115 kV line. The 115 kV
line from the Red Rock Substation to the River Falls Substation would be
upgraded by replacing the existing 115 kV conductors with higher capacity
795 kcmil 26/7 ACSS conductors.[63]
76.
Option GN: Option
GN is a distributed generation option which includes 20 MW of generation
at Lawrence Creek Substation, 50 MW generation at Apple River substation,
and 50 MW generation at Hurley Substation.
Further, the existing Wheaton generation (located at Eau Claire,
Wisconsin and owned by NSPW) would be run as required.
77.
Option KP: Option
KP includes converting the King-Pine Lake-Hydro Lane-T Corners 115 kV line
to 161 kV operation, converting the Red Rock-Crystal Cave 115 kV line
to 161 kV operation and constructing a second Pine Lake-Apple River
161 kV line.
78.
Options RB and RBD: Option RB includes rebuilding the existing
Chisago-St. Croix Falls-Hugo 69 kV line and St. Croix Falls-Apple River
69 kV line, upgrading the Chisago 115-69 kV transformer, and installing
a new 115-69 kV transformer at the Hugo Substation. Option RBD consists of installing a new,
higher capacity 69 kV transmission line from the Chisago County Substation
to a new substation, called the Lawrence Creek Substation, near Taylors
Falls. The line from Lawrence Creek to
the St. Croix Falls Substation in Wisconsin, as well as the river crossing
line, would also be replaced with a higher capacity 69 kV line. The existing 115-69 kV transformer at
the Chisago County Substation would be replaced with a larger, 187 MVA unit and
other electrical components would be upgraded to higher capacity.[64]
79.
Option RC: Option
RC includes placement of either a new 161 kV or a 230 kV transmission line from
the Rock Creek Substation and crossing the Saint Croix River on, or near, the
Highway 70 Bridge.
80.
Options AW, KP, RC do not upgrade the 69 kV
system in east central Minnesota and northwestern Wisconsin and, therefore, do
not address the local area load serving needs.
Consequently, these options were not pursued in depth by the Applicants.[65]
81.
Similarly, because Option CA did not address, or
mitigate, the cross tripping of the existing Eau Claire-Arpin 345 kV line it
was not pursued in depth by the Applicants.[66]
82.
Because the initial analysis demonstrated that the
Arden Hills-Lawrence Creek 69 kV line upgrade could be deferred, Option RB
became option RBD.[67]
83.
Option GN, the distributed generation option, was
rejected from further consideration because of its high cost. The net cumulative present value to install
and operate the distributed generation option from 2005 to 2034 was $185,000,000. It was therefore determined to be
economically infeasible.[68]
84.
From this field of eight alternatives, the
Applicants focused upon the three alternatives that it regarded as the most “electrically
viable”: Options CA1, DF and RBD.[69]
85.
Option CA1: Option
CA1, the proposed project, provides long-term load serving capability to the
local area transmission system between Chisago, St. Croix Falls, Arden Hills,
and Apple River Substations. It has a 50
percent greater load serving capability than the 69 kV Rebuild Alternative
(Option RBD detailed below). With
115 kV lines in Minnesota and 161 kV in Wisconsin, the proposed
project also fits well into the design of the area transmission system and
provides for operating flexibility. Among the competing alternatives, the proposed
project is also the least cost plan.
Even when the costs of underground construction in the St. Croix
National Scenic Riverway are included, the cost of the proposed project totals
$64,200,000 in 2006 dollars.[70]
86.
Option DF: Option
DF provides adequate load serving to east central Minnesota loads only until
approximately 2012, when the line voltages would are projected to be inadequate. Further, this option aggravates the 115 kV
tie line loads between Minnesota and Wisconsin.
For this reason, Option DF necessarily implies a rebuilding of the Red
Rock-River Falls 115 kV line and the King-Willow River 115 kV
line. Assuming underground construction
in the St. Croix National Scenic Riverway, the cost of this reconfiguring
69 kV option totals $89,220,000 in 2006 dollars.[71]
87.
Option RBD:
Option RBD provides long-term load serving to the local area, but does
not compare favorably to the cost and performance of the Applicants’
proposal. The proposed project can serve
approximately 50 percent more local area load than Option RBD and, unlike
Option RBD, significantly improves tie line flows from Minnesota to Wisconsin. Lastly, assuming underground construction in
the St. Croix National Scenic Riverway, the cost of the rebuild 69 kV
option in 2006 dollars is $81,770,000.[72]
88.
Assessing costs and performance of the
alternatives, the Applicant’s transmission planning engineers concluded that
the proposed project was the best option to address the need for system
reliability in east central Minnesota and northwestern Wisconsin.[73]
The Applicants’ Proposal for Routing the Transmission Line:
89.
By their
Route Permit Application, Xcel Energy and Dairyland seek a permit for their
proposed project that will upgrade the existing 69 kV transmission line
from the Chisago County Substation to the St. Croix River in Taylors Falls,
Minnesota to 115 kV/161 kV.
The proposed project has six distinct segments in Minnesota, which are
described below:[74]
90.
Segment
1 – Chisago Substation to Karmel Avenue (No Construction):
Segment 1 is a 4.9 mile segment of an existing line between the Chisago
County Substation to a point approximately 900 feet west of the intersection of
Karmel Avenue and Stacy Trail - County State Aid Highway (“CSAH”) 19. The existing transmission line is currently
operated at 69 kV but is capable of operating at 115 kV and would not
require any alteration.[75] The double circuit 115/69 kV portion of
the route exits the Chisago County Substation to the west, turning south
immediately for approximately 1,600 feet, before turning east along a field
edge for approximately 2,000 feet. The
transmission line then turns south for 3.5 miles, crossing CSAH 14 until it
reaches Stacy Trail/CSAH 19. At this
point the double circuit line separates and the proposed route follows the existing
69 kV transmission line along CSAH 19 east for approximately 3,300 feet.
91.
Segment
2 – Karmel Avenue to Lindstrom Substation (Rebuild from 69 kV to
115 kV): Segment 2 begins approximately 900 feet west
of the intersection of Karmel Avenue and Stacy Trail/CSAH 19 and terminates at
the Lindstrom Substation. It is
approximately 2.2 miles in length. From
its starting point west of Karmel Avenue, the route follows Stacy Trail - CSAH
19 approximately 1.9 miles east to Lincoln Road. From Lincoln Road, the line turns south for
approximately 1,280 feet to the Lindstrom Substation. The line will enter the Lindstrom Substation from
the west. The existing structures along
this segment are not now capable of supporting the proposed 115 kV line
and will be replaced.
92.
Segment
3 – Lindstrom Substation to Shafer Substation Tap (Rebuild from 69 kV to
115 kV): As the 115 kV transmission line exits
the Lindstrom Substation to the south it will follow the existing 69 kV
transmission line Right of Way (ROW) through the cities of Lindstrom and Center
City for approximately 2.8 miles to the Shafer Substation. The existing structures in this segment are
not capable of supporting the proposed 115 kV line and will likewise be
replaced. The proposed transmission line
will continue along the alignment of the existing 69 kV line and follow
U.S. Highway 8 from a point east of Elm Street to Center City. In Center City, the proposed line will
deviate from U.S. Highway 8 and will continue northeast along the existing
transmission ROW, crossing the northeastern edge of South Center Lake to the
tap point in the Shafer Substation.
93.
Segment
4 – Shafer Substation Tap to a Newly Developed Lawrence Creek Substation
(Rebuild from 69 kV to 115 kV): East of the Shafer Substation
tap point, the proposed route follows County Road 82 - 310th Street for
approximately 6.1 miles, until it reaches the site for the new Lawrence Creek
Substation. The existing structures in
this segment are not capable of supporting the proposed 115 kV line and
will be replaced. The new substation is
proposed to be located in the southwest quarter of Section 26, Township 34N,
Range 19W. In order to enter the new
Lawrence Creek Substation, the transmission line will need to follow a new
alignment for approximately 0.22 miles north from County Road 82 - 310th
Street in the vicinity of the half section of Section 26. Approximately 0.49
miles of the existing transmission line would be removed as a result of this
rerouting. At the Lawrence Creek
Substation, the voltage of the transmission line will change from 115 kV
to 161 kV. The existing 69 kV
line from Arden Hills, Minnesota will be doubled-circuited with the 115 kV
line on the new 0.22 mile segment as it terminates at the Lawrence Creek
Substation. Additionally, approximately
0.25 miles of the existing Arden Hills single-circuit 69 kV line will be
rerouted so as to re-position the line for the double-circuit segment.[76]
94.
Segment
5 – Lawrence Creek Substation to CSAH 20 (Rebuild from 69 kV to
161 kV): Segment 5 is a 1.4-mile 161 kV segment
from the proposed Lawrence Creek Substation to the top of the west bluff of the
St. Croix River at Chestnut Street - CSAH 20.
This segment is along a new alignment for approximately 0.4 miles east
of the Lawrence Creek Substation, at which point the line turns northeast and
follows the existing 69 kV line corridor for approximately one mile. The existing structures in the rebuild
portion of this segment are not capable of supporting the proposed 161 kV
line and will be replaced.
95.
Segment
6 – CSAH 20 to St. Croix Falls Substation (Rebuild from 69 kV to
161 kV): Segment 6 follows the existing 69 kV
line for approximately 0.7 miles from the top of the west bluff to the St Croix
River crossing. So as to mitigate the visual
impacts to the St. Croix River Valley, the 161 kV transmission line is
proposed to be constructed underground from the top of the bluff to the base of
the bluff at Trunk Highway 95. From Trunk
Highway 95 east to the river crossing, the proposed line will be constructed
above the ground. As part of the
proposed upgrades, Xcel Energy will remove the existing overhead transmission
line and the existing distribution lines from the west bluff. At the river crossing, the Project will
result in a net reduction of 10 wires crossing the river (the removal of 15
existing wires crossing the river and installation of three conductors and two
shield wires).
96.
Wisconsin
Segment: Crossing the St. Croix River, the proposed
transmission line continues to the St. Croix Substation in Wisconsin. In the St. Croix Substation, the line would be
routed underground. The line would
travel east along Louisiana Avenue, and then south on Blanding Woods Road, into
an industrial park. The underground
161 kV transmission line would then turn east and continue underground
beneath Pine Street and East Pine Street to the Dairyland Border
Substation. Near the Dairyland Border
Substation, the 161 kV transmission line would transition to an overhead transmission
line that would be double-circuited with an existing Dairyland 69 kV
transmission line. The line would then follow
an existing alignment southward to the Sand Lake Substation and generally
eastward to the Apple River Substation.
The Public Service Commission of Wisconsin (“PSCW”) has already approved
the route for this portion of the proposed line that will be located in
Wisconsin.
CONCLUSIONS
1.
The Public Utilities Commission and Administrative
Law Judge have jurisdiction to consider the Application for a Certificate of
Need.
2.
The Commission issued an Order Accepting
Certificate of Need Application as Substantially Complete on February 12,
2007.
3.
Minn. Stat. § 216B.243 provides that a
Certificate of Need is required for a “large energy facility” as that term is
defined in Minn. Stat. § 216B.2421.
A large energy facility includes “any high voltage transmission line
with a capacity of 100 kilovolts or more with more than ten miles of its length
in Minnesota or that crosses a state line.”
Minn. Stat. § 216B.2421, subd. 2
(3).
4.
The proposed 115 kV/161 kV transmission
line constitutes a large energy facility and requires a Certificate of Need
from the Commission before construction may begin.
I. Analysis of the Need for the Facilities
5.
Minn. Stat. § 216B.243, subd. 3 and subd. 3a set
forth the statutory requirements for large energy facilities. The provisions relevant to a Certificate of
Need for a high voltage transmission line are:
a. Subd. 3. Showing required for construction. No proposed large energy facility shall be certified for construction unless the applicant can show that demand for electricity cannot be met more cost effectively through energy conservation and load-management measures and unless the applicant has otherwise justified its need. In assessing need, the commission shall evaluate:
(1) the accuracy of the long-range energy demand forecasts on which the necessity for the facility is based;
(2) the effect of existing or possible energy conservation programs under sections 216C.05 to 216C.30 and this section or other federal or state legislation on long-term energy demand;
(3) the relationship of the proposed facility to overall state energy needs, as described in the most recent state energy policy and conservation report prepared under section 216C.18, or, in the case of a high-voltage transmission line, the relationship of the proposed line to regional energy needs, as presented in the transmission plan submitted under section 216B.2425;
(4) promotional activities that may have given rise to the demand for this facility;
(5) benefits of this facility, including its uses to protect or enhance environmental quality, and to increase reliability of energy supply in Minnesota and the region;
(6) possible alternatives for satisfying the energy demand or transmission needs including but not limited to potential for increased efficiency and upgrading of existing energy generation and transmission facilities, load-management programs, and distributed generation;
(7) the policies, rules, and regulations of other state and federal agencies and local governments;[77]
* * *
(9) with respect to a high-voltage transmission line, the benefits of enhanced regional reliability, access, or deliverability to the extent these factors improve the robustness of the transmission system or lower costs for electric consumers in Minnesota;
(10) whether the applicant or applicants are in compliance with applicable provisions of sections 216B.1691 and 216B.2425, subdivision 7, and have filed or will file by a date certain an application for certificate of need under this section or for certification as a priority electric transmission project under section 216B.2425 for any transmission facilities or upgrades identified under section 216B.2425, subdivision 7;
(11) whether the applicant has made the demonstrations required under subdivision 3a;[78]
b. Subd. 3a. Use of renewable resource. The commission may not issue a certificate of need under this section for a large energy facility that generates electric power by means of a nonrenewable energy source, or that transmits electric power generated by means of a nonrenewable energy source, unless the applicant for the certificate has demonstrated to the commission’s satisfaction that it has explored the possibility of generating power by means of renewable energy sources and has demonstrated that the alternative selected is less expensive (including environmental costs) than power generated by a renewable energy source. For purposes of this subdivision, “renewable energy source” includes hydro, wind, solar, and geothermal energy and the use of trees or other vegetation as fuel.
6. Further, Minn. Stat. § 216B.2426 provides that “the Commission shall ensure that opportunities for the installation of distributed generation, as that term is defined in section 216B.169, subdivision 1, paragraph (c), are considered in any proceeding under section 216B.2422, 216B.2425, or 216B.243.” Minn. Stat. § 216B.169 defines distributed generation as: “(c) ‘High-efficiency, low-emissions, distributed generation’ means a distributed generation facility of no more than ten MW of interconnected capacity that is certified by the commissioner under subdivision 3 as a high-efficiency, low-emissions facility.”
7. Minn. R. 7849.0120 provides that a Certificate of Need for a high voltage transmission line shall be granted if it is determined that:
A. the probable result of denial would be an adverse effect upon the future adequacy, reliability, or efficiency of energy supply to the applicant, to the applicant’s customers, or to the people of Minnesota and neighboring states, considering:
(1) the accuracy of the applicant’s forecast of demand for the type of energy that would be supplied by the proposed facility;
(2) the effects of the applicant’s existing or expected conservation programs and state and federal conservation programs;
(3) the effects of promotional practices of the applicant that may have given rise to the increase in the energy demand, particularly promotional practices which have occurred since 1974;
(4) the ability of current facilities and planned facilities not requiring certificates of need to meet the future demand;
(5) the effect of the proposed facility, or a suitable modification thereof, in making efficient use of resources;
B. a more reasonable and prudent alternative to the proposed facility has not been demonstrated by a preponderance of the evidence on the record, considering:
(1) the appropriateness of the size, the type, and the timing of the proposed facility compared to those of reasonable alternatives;
(2) the cost of the proposed facility and the cost of energy to be supplied by the proposed facility compared to the costs of reasonable alternatives and the cost of energy that would be supplied by reasonable alternatives;
(3) the effects of the proposed facility upon the natural and socioeconomic environments compared to the effects of reasonable alternatives;
(4) the expected reliability of the proposed facility compared to the expected reliability of reasonable alternatives;
C. by a preponderance of the evidence on the record, the proposed facility, or a suitable modification of the facility, will provide benefits to society in a manner compatible with protecting the natural and socioeconomic environments, including human health, considering:
(1) the relationship of the proposed facility, or a suitable modification thereof, to overall state energy needs;
(2) the effects of the proposed facility, or a suitable modification thereof, upon the natural and socioeconomic environments compared to the effects of not building the facility;
(3) the effects of the proposed facility, or a suitable modification thereof, in inducing future development;
(4) the socially beneficial uses of the output of the proposed facility, or a suitable modification thereof, including its uses to protect or enhance environmental quality; and
D. the record does not demonstrate that the design, construction, or operation of the proposed facility, or a suitable modification of the facility, will fail to comply with relevant policies, rules, and regulations of other state and federal agencies and local governments.
8. In addition, Minn. R. 7849.0230 requires that the Department prepare an Environmental Report evaluating the proposal and any alternatives. Because the Applicants are simultaneously seeking a Route Permit under the Alternative Permitting Process governed by Minn. R. 7849.5500 to 7849.5720, the Commission, in its February 12, 2007 order, combined the environmental review in both the Certificate of Need and Route Permit Dockets. The Commission directed that the environmental assessment completed in the Alternative Permitting Process address the Certificate of Need analysis of alternatives.
9. Applicants bear the burden of proving the need for the proposed facilities and demonstrating that the criteria set for in statute and rule have been satisfied.
10. The best supported system plan option is the Applicants’ proposed 115 kV and 161 kV transmission line from the Chisago County Substation to Taylors Falls. As detailed below, this plan is appropriate and sound when measured against the alternative approaches set forth in Minn. Stat. § 216B.243, subd. 3 and subd. 3a. Additionally, the Applicants’ proposal satisfies the functional criteria set forth in Minn. R. 7849.0120.
11. None of the alternatives that were considered yield commensurate benefits to consumers, ratepayers and the public at large.[79]
Minn. R. 7849.0120, Criteria A (1) -
Forecast Accuracy:
12.
The service area for the proposed 115 kV/161 kV
line (from the Chisago County Substation to Taylors Falls) has experienced
substantial population growth and growth in the amounts of electricity used.[80]
13.
The population of Chisago County is projected to
increase by 24 percent from 2005 to 2020; Washington County’s population is
projected to increase by 43 percent by 2020; and the population of Polk County
in Wisconsin is projected to increase by 18 percent by 2020.[81]
14.
Likewise, demand and energy use is increasing in
east central Minnesota and northwestern Wisconsin. For example, in 2000 there were 2,100 hours
when demand in the 69 kV study region exceeded 50 MW; and in 2002,
there were 2,980 hours of demand above 50 MW. The peak electric power demand is expected to
grow at a rate of 2.3 percent to 3.1 percent annually – and could reach
118 MW by 2015.[82]
15.
The Department concluded that the peak demand
forecasts provided in the Applicants’ Certificate of Need Application are
reasonable and that a need exists for increased transmission capacity in the
area to ensure reliable local electricity service.[83]
16.
When evaluating the performance of the electric
transmission system, electrical engineers utilize computer simulations of the
interconnected system to evaluate performance under a range of scenarios and to
evaluate the performance of alternative solutions. In simulations, critical pieces of equipment
and critical circuits are assumed to be removed from service in various power
demand circumstances to evaluate the ability of the remaining system to perform
under such a contingency. As part of the
analysis, three different conditions of demand were modeled. First, the peak electrical demand at
distribution substations was modeled.
Second electrical demand at the time of winter peak was modeled. Third, simulations of off-peak periods during
summer months when power transfers tend to be high were modeled. Each of these three system conditions were
simulated at forecasted levels of demand in the study area for 2002, 2006,
2011, and 2015.[84]
17.
The Applicants forecast that electricity demand
will continue to grow and thus the risk or exposure to power failure increases
with time. For example, Table 4.3 of
Applicants’ Certificate of Need Application illustrates peak electrical demand
at area substations through the year 2015.[85] The forecasts reveal that the demand for
electricity already exceeds the capacity of the system in the event that the
69 kV transmission system experiences an equipment failure. Because system demand already exceeds
capacity many time throughout the year, changes in forecasts of growth merely extend
the length of exposure to the risk of power system failure. In the event of foreseeable outages, the
current system will not be adequate to maintain service during periods of
moderate to high demand.[86] Service to customers would be interrupted
until either the failure is repaired, or until loads on the system are reduced
to the point electric service can be restored.[87]
18. Applicants have provided reasonable forecasts for east central Minnesota and northwestern Wisconsin and sufficient evidence to demonstrate the need for the proposed 115 kV and 161 kV transmission line.
Minn. R. 7849.0120, Criteria A (2) – The Palliative
Effects of Conservation:
19.
Demand side management (“DSM”) is capable of
reducing the need for system improvements needed to serve increased load by
reducing demand. No program of
conservation improvements, that could reduce the demand in the local Chisago
County and northwestern Wisconsin, has been identified, such that the proposed upgrades
would not be needed.
20.
The Department concurs with the Applicants’
assessment that while DSM can reduce the rate of growth, it is unlikely that it
would be able to reduce actual existing load levels.[88]
21. Accordingly, even if conservation measures could address the energy needs, so as to keep the current demand from rising – a matter that is far from certain upon this record – the existing 69 kV transmission system is not well suited to meet needs in the event of a serious contingency. Conservation efforts are not likely to sufficiently depress demand so as to improve the contingent load serving capability of the existing 69 kV transmission system and permit reliable service to the substations in the area.[89]
Minn. R. 7849.0120, Criteria A (3) – The
Effects of Promotional Practices:
22.
The Applicants’ general claims that both population
and electricity demand in the service area are on the rise were not
contradicted. There was no evidence in
the record linking this rise in demand for electricity to promotional or
marketing practices of the Applicants.
Minn. R. 7849.0120, Criteria A (4) – The Feasibility
of Smaller Facilities:
23.
There was no evidence that existing or planned
facilities that do not require a Certificate of Need could meet the reliability
needs identified in the Certificate of Need Application.
Minn. R. 7849.0120, Criteria A (5) – Efficiencies
of the Proposed Facilities:
24.
The proposed project includes a series of efficient
new uses of existing resources. First,
the upgrades of 69 kV lines to 115 kV facilitates the completion of a
115 kV transmission loop to Arden Hills, and contributes to overall system
reliability. Second, terminating at
115 kV at the Chisago County Substation would take advantage of the
existing Chisago County Substation 345-115 kV transformer capacity, thus
eliminating the need for additional transformers at the Chisago County
Substation.[90] Third, building the transmission line from
the Chisago County Substation to the new Lawrence Creek Substation at
115 kV, and upgrading to 161 kV to the new Lawrence Creek Substation
would enable the Lindstrom and Shafer Substations to be converted more
economically and re-utilize existing distribution transformers. Additionally, transforming from 115 kV to
161 kV at the proposed Lawrence Creek Substation would provide for
efficient integration of the upgraded facilities with the Dairyland 161 kV
system in northwestern Wisconsin.
25.
The criteria established in Minn. R. 7849.0120 (A)
support granting the Certificate of Need.
Minn. R. 7849.0120, Criteria B (1) – The
Size, Type and Timing of Alternatives:
26.
Applicants included a detailed engineering analysis
in the Certificate of Need Application that examined three alternative system
improvements to meet the reliability issues facing east central Minnesota and
northwestern Wisconsin.[91]
27.
After considering capital costs, system electrical
losses, technical performance and a number of other factors, Applicants
selected the 115 kV/161 kV line proposed in the Certificate of Need
Application.
28.
In evaluating available options, Applicants
evaluated a direct current (“DC”) transmission line. A DC circuit is generally a feasible
alternative for transporting power long distances without intermediate
connections. Because the objective of
the proposed project is to improve the transmission system load serving
reliability in east central Minnesota and northwestern Wisconsin, and not to
directly transport large amounts of energy over long distances,[92]
Applicants established that a DC circuit was not a viable alternative.
29.
Applicants appropriately evaluated undergrounding
as an alternative.[93] Specifically, Applicants considered
undergrounding in the St. Croix National Scenic Riverway. Applicants propose undergrounding the
161 kV transmission line in St. Croix National Scenic Riverway, except for
the river crossing, in order to acquire necessary permits from the Minnesota
Department of Natural Resources (“DNR”), the U.S. National Park Service
(“NPS”), and the U.S. Army Corps of Engineers (“ACOE”).[94]
30.
Applicants also addressed the possibility of
generation alternatives.[95] While it is technically possible that
generation capabilities could be located within those areas, both in terms of meeting
energy needs in the event of an outage, and the costs of such solutions, local
generation is a poor alternative to the proposed upgrades. Three or four 25 to 40 MW generators
would need to be placed near source points within the study area in order to
ensure the power supply at the same level of reliability as the proposed
transmission project. Two or three
generating units would need to operate to provide protection from the
possibility of a transmission failure, and a spare unit would need to be in
place so as to accommodate planned or forced outages of one of the generating
units. These generators would be
dedicated to meeting only local energy needs, because the existing 69 kV
transmission system is not capable of transmitting sufficient power elsewhere
along the grid. A typical 25 MW gas
fired combustion turbine costs about $30 to $35 million. A 40 MW unit costs approximately $40 to
$45 million Accordingly, the cost of generation would be substantially higher
than the cost of the proposed transmission upgrade project, and the resulting
delivery system would be less reliable than if the proposed transmission
upgrade is constructed. Applicants
correctly concluded that the addition of generation to the system is not a
sensible alternative to the proposed project.[96]
31.
Applicants also concluded that the use of renewable
generation resources also would not be an adequate alternative to the proposed
transmission project. Renewable
generation sources, such as wind generation, would be an intermittent resource
only and, therefore, would not serve the identified need in the east central
Minnesota and northwestern Wisconsin areas.[97]
32.
Likewise, the scale of a local wind generation
alternative would be massive – with the Department projecting that a comparable
solution would require the deployment of between 180 and 300 wind turbines. [98]
33.
The Department shares the Applicants’ assessment
that generation is not an appropriate alternative for the proposed project.[99] Applicants have provided sufficient
justification for eliminating additional generation (including renewable
generation) as a viable alternative.
34.
The proposed transmission line provides the most
reasonable and efficient means of meeting electricity service reliability
issues in east central Minnesota and northwestern Wisconsin.[100]
35.
Based upon the reliability concerns in east central
Minnesota and northwestern Wisconsin, Applicants have demonstrated that the size,
type and timing of the proposed transmission facilities is more appropriate
than other alternatives.
Minn. R. 7849.0120, Criteria B (2) –
Comparing the Cost of Alternatives:
36.
The Department reviewed Applicants’ screening
analysis of the final three alternatives and concluded it was reasonable.[101]
37.
After conducting its own analysis, the Department
concluded that Applicants’ proposal was the least cost proposal.[102]
38.
Applicants have demonstrated that the cost of the
proposed facilities and the energy to be supplied by the proposed facilities
are more reasonable and prudent than that of the alternatives.
Minn. R. 7849.0120, Criteria B (3) –
Comparing the Impacts of Alternatives:
39.
The primary public benefit of the proposed project
is its elimination of the current capacity limitations, and overall reliability
limits, in the existing 69 kV transmission system in east central
Minnesota and northwestern Wisconsin.[103]
40.
The proposed project and the alternatives have
similar environmental impacts. Land uses
across the proposed and alternative project areas include a mixture of
agriculture, residential, commercial and recreational uses. Communities in the project area include
Lindstrom, Center City, Shafer, and Taylors Falls in Minnesota and St. Croix
Falls in Wisconsin.[104]
41.
Because the proposed project and the 69 kV
Rebuild Alternative involves the replacement of an existing transmission line
with a new conductor on taller structures, Applicants asserted that there would
be no significant incremental adverse impacts that would prevent the project or
this alternative from being executed. These
options would use the centerline of the existing 69 kV transmission line
with minimal additional widened right-of-way corridor.[105]
42.
The 69 kV Reconfiguration Alternative requires
a higher-capacity upgrade of the existing 115 kV transmission lines from
King Substation to the Willow River Substation and from the Red Rock Substation
to the River Falls Substation. The land
use in this alternative project area is non-residential urban or built-up
land. Communities in the project area
include Oak Park Heights, Stillwater, and Bayport.[106]
43.
Applicants found no significant land use or
environmental issues that would prevent its proposal from being
implemented. Nor did Xcel Energy find
any environmental issues that would impose an extraordinary cost to mitigate.[107]
Minn. R. 7849.0120, Criteria B (4) –
Comparing the Reliability of Alternatives:
44.
Based upon Xcel Energy’s engineering analysis, all
of the options studied appear to meet applicable North American Electric Reliability
Corporation (“NERC”) system reliability standards.
45.
Among the competing alternatives the proposed
project offers the best overall electrical results because it addresses
existing and projected load serving needs; it will perform well under “system
intact” conditions; it will perform well under a variety of contingent loading
scenarios and voltages; and offers the prospect of the least system losses.[108]
Minn. R. 7849.0120, Criteria C (1) – The
Effect Upon Energy and Capacity Needs:
46.
The proposed project will improve service
reliability to east central Minnesota and northwestern Wisconsin. The proposed facilities are upgrades to local
load serving capabilities and will have a small impact upon the state’s overall
energy and capacity needs.
Minn. R. 7849.0120, Criteria C (2) – Natural and Socioeconomic Environments:
47.
Without the proposed upgrades, or other
alternative, electricity customers in east central Minnesota and northwestern
Wisconsin will be at ever increasing risk of system failures, low voltages and
unplanned blackouts. These risks
increase over time.[109]
Minn. R. 7849.0120, Criteria C (3) – Inducements
to Future Development:
48.
There is no evidence in the record that the
proposed project will induce future development in the area beyond the development
and population growth that is already anticipated.[110] Indeed, to the extent that the record speaks
to this point at all, the record suggests that localities in the service area
face genuine challenges in spurring hoped-for residential and commercial development.[111]
Minn. R. 7849.0120, Criteria C (4) –
Socially Beneficial Outputs:
49.
The proposed project offers improved system
longevity, efficiency, capacity and reliability to the residents and businesses
in east central Minnesota and northwestern Wisconsin.
50.
By utilizing the existing 69 kV centerline and
placing the line underground in the St. Croix River Valley, the proposed
project minimizes potential environmental, land use, and aesthetic effects.[112]
51.
The criteria set forth in Minnesota Rule
7849.0120(c) support granting Certificates of Need for the proposed 115 kV
and 161 kV transmission line.
Minn. R. 7849.0120, Criteria D – Federal,
State and Local Requirements:
52.
Applicants have committed to comply with all
relevant policies, rules, and regulations of state and federal agencies and
local governments relating to the construction and operation of the proposed
transmission line, including but not limited to the National Electric Safety
Code (“NESC”) and NERC standards. There
was no evidence in the record to the effect that the Applicants could not, or
would not, comply with these parallel requirements.[113]
53.
The criterion set forth in Minnesota Rule
7849.0120(D) has been satisfied.
The
Requirements of Minnesota Rule 7849.0230:
54.
The Department timely completed the Environmental
Assessment required by the Commission’s February 12, 2007 Order.
55.
Asserting that the “proposed line would be located in
essentially the same place as the existing line,” and that “[o]perating the
transmission line at the higher voltage level of 115 kV would also not
result in a significant environmental impact, the Department concluded that the
proposed project “would have no significant unavoidable adverse impacts ….”[114]
The
Requirements of Minnesota Statutes § 216B.243:
56.
The proposed project also satisfies the applicable
criteria established in Minn. Stat. § 216B.243, Subd. 3:
(a)
The proposed project will ensure safe and reliable
service to the Applicants’ customers during peak periods.[115]
(b)
The need for the proposed project cannot be avoided
through the use of energy conservation programs.[116]
(c)
The proposed project will have a positive impact on
serving the needs of electricity customers in the region.[117]
(d)
The needs addressed by the proposed project were
not prompted by the promotional and marketing activities of the Applicants.[118]
(e)
The proposed project will increase reliability of
the energy supply in east central Minnesota and northwestern Wisconsin.[119]
(f)
The needs addressed by the proposed project could
not be effectively met, and these system upgrades avoided, through
load-management programs or new distributed generation.[120]
(g)
The proposed project will comply with the policies,
rules and regulations of federal, state and local governments.[121]
(h)
In comparison to other transmission or generation
options, the proposed project enhances “regional reliability, access …
[and] deliverability” of electric power, “improve[s] the robustness of the
transmission system” and does so for “lower costs for electric consumers in
Minnesota.”[122]
57.
Applicants have met the requirements of Minn. Stat.
§ 216B.243, subd. 3 (10).
58.
The Commission has determined that both Applicants
are meeting the good faith effort requirement of the renewable energy
objectives statute; and the Department shares the view Applicants have
satisfied this statutory requirement.[123]
59.
Applicants explored the possibility of generating
power by means of renewable energy sources and demonstrated that the proposed
project is less costly than power generated by wind turbines. The requirements of Minn. Stat.
§ 216B.243, subd. 3a have been satisfied.[124]
60.
The Applicants have complied with all applicable
substantive and procedural requirements for a Certificate of Need.
61.
The record in this proceeding demonstrates that the
Applicants have satisfied the criteria set forth in Minn. Stat. § 216B.243
and Minn. Rule 7849.0120.
62.
No party or person has demonstrated by a
preponderance of the evidence that there is a more reasonable and prudent
alternative to the proposed 115 kV/161 kV transmission line.
63.
The Department has prepared an appropriate
Environmental Assessment that reasonably addresses all of the subjects
identified in the Scoping Decision.
64.
No conditions on the Certificates of Need are
necessary.
II. Analysis of the Proposed Routing
65. Minnesota Statute § 216E.03, subd. 2 provides that “[n]o person may construct a high-voltage transmission line without a route permit from the commission [and that a] high-voltage transmission line may be constructed only along a route approved by the commission.”
66. An applicant may seek a Route Permit using the alternative permitting process if the proposed project is a high-voltage line between 100 and 200 kV.[125]
67. The Commission authorized the use of the alternative permitting process for the Applicants’ proposed 115 kV and 161 kV transmission line.
68. Because the Applicants are applying for the Route Permit through the alternative permitting process, the Applicants are not obliged to propose alternative sites or routes those that are included in their application.[126]
69. However, during the scoping process for the Environmental Assessment, “any person may suggest an alternative site or route” to be evaluated by the Electricity Facility Permitting Staff of the Department.[127]
70. The EFP Staff timely completed the Environmental Assessment required by Minnesota Rule 7849.5700 and the Commission’s February 12, 2007 Order.
Statutory
Criteria for Assessing the Route Permit Application:
71. Minn. Stat. § 216E.03, subd. 7, provides that the Commission’s route permit determinations “must be guided by the state’s goals to conserve resources, minimize environmental impacts, minimize human settlement and other land use conflicts, and ensure the state’s electric energy security through efficient, cost-effective power supply and electric transmission infrastructure.” The statute further provides that to “facilitate the study, research, evaluation, and designation of sites and routes, the commission shall be guided by, but not limited to, the following considerations”:
(1) Evaluation of research and investigations relating to the effects on land, water and air resources of large electric power generating plants and high-voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment;
(2) Environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state;
* * *
(5) Analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired;
(6) Evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted;
(7) Evaluation of alternatives to the applicant’s proposed site or route proposed pursuant to subdivisions 1 and 2;[128]
(8) Evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way;
(9) Evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations;
(10) Evaluation of the future needs for additional high-voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications;
(11) Evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved; and,
(12) When appropriate, consideration of problems raised by other state and federal agencies and local entities.[129]
Regulatory Criteria for Assessing the Route
Permit Application:
72. Minnesota Rule 7849.5910 provides that when determining whether to issue a route permit for a high voltage transmission line, the Commission shall consider the following relevant factors:
A. Effects on human settlement, including, but not limited to, displacement, noise, aesthetics, cultural values, recreation, and public services;
B. Effects on public health and safety;
C. Effects on land-based economies, including, but not limited to, agriculture, forestry, tourism, and mining;
D. Effects on archaeological and historic resources;
E. Effects on the natural environment, including effects on air and water quality resources and flora and fauna;
F. Effects on rare and unique natural resources;
G. Application of design options that maximize energy efficiencies, mitigate adverse environmental effects, and could accommodate expansion of transmission or generating capacity;
H. Use or paralleling of existing rights-of-way, survey lines, natural division lines, and agricultural field boundaries;
* * *
J. Use of existing transportation, pipeline, and electrical transmission systems or rights-of-way;
K. Electrical system reliability;
L. Costs of constructing, operating, and maintaining the facility which are dependent on design and route;
M. Adverse human and natural environmental effects which cannot be avoided; and
N. Irreversible and irretrievable commitments of resources.[130]
73. Neither Minnesota Rule 7849.5930 (governing prohibited routes of high voltage transmission lines through wilderness and parks and natural areas), nor 7849.5940 (governing prohibited sites for large electric power generating plants) are applicable to the proposed project route.
Minn. R. 7849.5910, Criteria A – Effects Upon Human Settlements:
74. In order to obtain the necessary permitting for the proposed project from the Minnesota Department of Natural Resources (“DNR”), the U.S. National Park Service (“NPS”), and the U.S. Army Corps of Engineers (“ACOE”), the Applicants proposed to place the transmission line underground in the vicinity of the St. Croix National Scenic Riverway, crossing the river overhead at the same point as the existing 69 kV transmission line. The proposed project will result in a net reduction of 10 wires crossing the St. Croix River (the removal of 15 existing wires crossing the river and the installation of three conductors and two shield wires).[131]
75. While all three of the alternatives studied by the Applicants meet the systems anticipated requirements through at least 2015, the proposed project’s higher voltage provides 50 percent greater load serving capability and it is the upgrade option that with the fewest additional elements.
76. Applicants do not anticipate that any existing homes or businesses will be displaced by the proposed route.
77. While there were reports in the public hearing record of irritating noise levels from the current 69 kV transmission line, the greater weight of the evidence is that noise impacts of the proposed project will be minimal.[132]
78. The primary impacts of the proposed project will be aesthetic. The supporting structures for the line, towering 60 to 90 feet above the ground, at intervals of approximately 260 to 285 feet apart along the line route, will impact the view sheds along the line route.[133]
79. To the extent that the proposed project will negatively impact the view shed above the Swedish Immigrant Trail, the routing will have an impact upon cultural values within the proposed project area.[134]
80. There is not evidence in the record to suggest that the proposed project will impact the delivery of public services; except that, in a generalized fashion, improvements in the overall reliability of the electricity transmission system, will, as it does other enterprises, contribute to the timely delivery of public services.[135]
81. Any impacts to traffic will be minimized through coordination with MnDOT and county and city transportation departments.
Minn. R. 7849.5910,
Criteria B – Effects Upon Public Health and Safety:
82. No effects on public health or safety are anticipated if the proposed project is implemented.
83. The proposed project would be constructed to comply with NESC and Xcel Energy guidelines and standards.
84. The underground portion of the proposed transmission line will be marked appropriately and inaccessible to the public.
85. The maximum electric field associated with the proposed project is 0.70 kV/meter underneath the conductors measured at one meter above the ground, which is significantly less than the EQB’s maximum standard of 8 kV/meter. The maximum magnetic field for the upgraded line would be 56 milligaus at the edge of the right-of-way (25 feet from the centerline).
86. The Minnesota Department of Health has concluded that the cumulative evidence from scientific studies on the effects of exposure to EMF does not yet show that EMFs cause negative health effects.[136]
87. As noted above, asserting that the “proposed line would be located in essentially the same place as the existing line,” and that “[o]perating the transmission line at the higher voltage level of 115 kV would also not result in a significant environmental impact,” the Department concluded that the proposed project “would have no significant unavoidable adverse impacts ….”[137]
Minn. R. 7849.5910,
Criteria C – Effects Upon Land-Based Economies:
88. Expansion of existing rights-of-way for the proposed route will be minimal along the rebuild portion of the route; new rights-of-way or easements will generally be confined to the area for the Lawrence Creek Substation and new transmission lines near that substation.
89. There is no evidence in the record of anticipated impacts upon current mining or forestry in the proposed project area.
90. The impacts on agricultural lands will be minimal, consisting of possible short-term crop damage in the course of constructing the line in the right-of-way, and long-term agricultural land conversion due to pole placement and substation construction in the Lawrence Creek Substation area. Approximately 4.1 acres of land will be converted from agricultural use by construction of the Lawrence Creek Substation.
91. To the extent that the proposed project negatively impacts the view sheds above the Swedish Immigrant Trail, and discourages the taking (and marketing) of commemorative photographs of Lindstrom’s “Swedish Coffee Pot” water tower,[138] the proposed alignment has a negative impact upon Lindstrom’s tourism-related goals and objectives.
Minn. R. 7849.5910, Criteria D – Effects
Upon Historic Resources:
92. As noted above, to the extent that the proposed project will negatively impact the view shed above the route of the Swedish Immigrant Trail, the routing will have an impact upon historical resources within the proposed project area.[139]
93. It is not anticipated that the proposed route will have any impacts on previously identified archaeological resources.
Minn. R. 7849.5910,
Criteria E – Effects Upon the Natural Environment:
94. The proposed project’s impact to the natural environment, including effects on air and water quality resources and flora and fauna will be minimal and short-term. Any impacts will occur during the construction of the line (e.g., temporary impacts on air quality due to construction-related emissions and on wetlands).
Minn. R. 7849.5910,
Criteria F – Effects Upon Unique Natural Resources:
95. The proposed project is not anticipated to have any impact on rare and unique resources because 97 percent of the line is a rebuild along the existing corridor of the 69 kV transmission line, and the new portion of the route in the Lawrence Creek Substation area is within previously disturbed agricultural land.
96. Xcel Energy has committed to working with the DNR to determine appropriate mitigation actions when necessary.
Minn. R. 7849.5910,
Criteria G – The Benefits of Specific Design Options:
97. The proposed project substantially mitigates environmental effects. By utilizing the existing rights-of-way, the Applicants have sought to reduce and avoid impacts to human settlement, land-based economies and natural resources.
98. Yet, as detailed further below, because the “Around the Lakes Over Head Alternative” avoids the special and definite tourism-related impacts associated with routing the line along the City of Lindstrom’s downtown corridor, it best balances the various needs of regional customers.
Minn. R. 7849.5910,
Criteria H – Uses of Existing Topographic Features:
99. Ninety-seven (97) percent of the proposed transmission line uses the same rights-of-way as the existing 69 kV transmission line that it will replace. Poles will be placed on section lines and field breaks where possible.
Minn. R. 7849.5910,
Criteria J – Uses of Existing Transmission Systems:
100. Ninety-seven (97) percent of the proposed transmission line uses the same rights-of-way as the existing 69 kV transmission line that it will replace.
Minn. R. 7849.5910,
Criteria K – Effects Upon Electrical System Reliability:
101. As provided in the Applicants’ Certificate of Need Application, the proposed project is critical to maintaining the reliability of the current 69 kV transmission system serving east central Minnesota and northwestern Wisconsin.
Minn. R. 7849.5910,
Criteria L – The Costs of Implementing the Design:
102. The proposed 115/161 kV transmission line and substation upgrades are estimated at a total construction cost of $64,200,000 (assuming underground construction through the St. Croix National Scenic Riverway).[140]
103. The average annual maintenance costs are about $500 per mile of transmission line.[141]
104. The proposed route uses existing transmission line corridors to the maximum extent possible, which will minimize land acquisition costs.[142]
105. As detailed in the Memorandum below, notwithstanding the $1.4 million added incremental costs associated with the “Around the Lakes Over Head Alternative,” this alternative path is one that the Commission should closely consider. By avoiding the special and definite tourism-related impacts associated with routing the line along the City of Lindstrom’s downtown corridor, the “Around the Lakes Over Head Alternative” best balances the various needs of regional customers.[143]
Minn. R. 7849.5910,
Criteria M – Avoiding Adverse Effects:
106. The unavoidable impacts to human and natural environment from the proposed project are minimal. Construction-related activities would cause short-term impacts, mainly in the form of disturbed soils, potential dust emissions, and temporary traffic disruption associated with construction equipment and material delivery.
Minn. R. 7849.5910,
Criteria N – Irretrievable Commitments of Resources:
107. There are very few commitments of resources associated with the proposed project that are irreversible and irretrievable but include those resources primarily related to construction.
108. Construction resources that will be used include concrete, steel and hydrocarbon fuel.
109. If the 115 /161 kV transmission line were removed in the future, the land could be restored to its prior condition and put to a different use.
Analysis
of Statutory Factors Under Minnesota Statute § 216E.03, subdivision 7:
(1) Evaluation of research and investigations relating to the effects on land, water and air resources of high-voltage transmission lines and the effects of water and air discharges and electric and magnetic fields resulting from such facilities on public health and welfare, vegetation, animals, materials and aesthetic values, including baseline studies, predictive modeling, and evaluation of new or improved methods for minimizing adverse impacts of water and air discharges and other matters pertaining to the effects of power plants on the water and air environment.
110. See, Conclusions 74 - 106.
(2) Environmental evaluation of sites and routes proposed for future development and expansion and their relationship to the land, water, air and human resources of the state.
111. See, Conclusions 74 to 106.
(5) Analysis of the direct and indirect economic impact of proposed sites and routes including, but not limited to, productive agricultural land lost or impaired.
112. See, Conclusions 74 to 81 and 88 to 93.
(6) Evaluation of adverse direct and indirect environmental effects that cannot be avoided should the proposed site and route be accepted.
113. See, Conclusions 94 to 96 and 106.
(8) Evaluation of potential routes that would use or parallel existing railroad and highway rights-of-way.
114. See, Conclusions 68 to 70.
(9) Evaluation of governmental survey lines and other natural division lines of agricultural land so as to minimize interference with agricultural operations.
115. See, Conclusions 74 to 81, 88 to 101 and 106.
(10) Evaluation of the future needs for additional high-voltage transmission lines in the same general area as any proposed route, and the advisability of ordering the construction of structures capable of expansion in transmission capacity through multiple circuiting or design modifications.
116. See, Conclusions 9 to 46.
(11) Evaluation of irreversible and irretrievable commitments of resources should the proposed site or route be approved.
117. See, Conclusions 107 to 109.
(12) When appropriate, consideration of problems raised by other state and federal agencies and local entities.
118. Applicants considered the requests and requirements of the DNR, the NPS and the ACOE when it proposed undergrounding the proposed transmission project in the St. Croix National Scenic Riverway.[144]
119. There is no evidence in the record that the proposed route will violate the rules of any other state agency or government department.
120.
Any of the foregoing Findings of Fact that are more
properly designated as Conclusions are adopted as such and incorporated by
reference.
Based upon on the foregoing Conclusions, the
Administrative Law Judge makes the following:
RECOMMENDATIONS
1. The Administrative Law Judge recommends that the application for a Certificate of Need a 115 kV/161 kV transmission line from the Chisago County Substation near North Branch, Minnesota to the Apple River Substation near Amery, Wisconsin, be GRANTED.
2. The Administrative Law Judge recommends that the Routing Permit be GRANTED, AS MODIFIED by the “Around the Lakes Over Head” option.
Dated this 19th day of November,
2007.
s/Eric L. Lipman_________________
ERIC L. LIPMAN
Administrative Law Judge
MEMORANDUM
While the Conclusions set forth above detail the Administrative Law
Judge’s analysis of the factual record, three arguments that were featured in
the post-hearing submissions deserve a more detailed discussion.
The Department’s Request that the ALJ Not
Submit a Recommendation with Respect to the Line Routing:
As noted above, pointing to the Commission’s request that the Department “conduct the environmental review process, including any specific requests to the ALJ concerning preparation of a report or making a recommendation to the Commission on the route,” the Department asserted that “under its delegated authority, [it] is not making an additional requests for any recommendation to the Commission in the route proceeding.”[145]
While acknowledging the special (and indeed, indispensable) relationship between the Department’s Energy Facility Permitting staff, and the Commission, in the view of Administrative Law Judge the Department over-reads the various delegation orders in this matter. First, the various referral Orders issued by the Commission on February 12 and May 1, 2007 do not speak directly to omitting recommendations. The relevant orders are much broader charters to the Department and the Office of Administrative Hearings; principally, to undertake the work that is needed to establish a complete record for later review.
Second, while agreeing with the Department that the Commission’s Orders provide that the EFP staff may request the Office of Administrative Hearings to undertake particular assignments related to the combined dockets, the best reading of the directives is that the Commission was extending a helping hand (or more precisely, the hands of its agents, the OAH) should the Department require any assistance. It is not the best reading of those Orders to say that the power to request additional services from OAH implies a delegation of the Commission’s authority to have Administrative Law Judges refrain from other activities.[146] Indeed, it seems that if the Commission wanted the OAH only to undertake those tasks that were later assigned by the Department, the various referral Orders would have made the point plain.
Third, the rationale – from the perspective of the Commission – of having the Administrative Law Judge develop Findings of Fact and Conclusions, but not to undertake the last, short step of rendering a Recommendation, is not at all clear. Indeed, truncating the work at the very last moment does not seem to be a natural or economical dividing line for the work load that has been delegated. The Department’s reading of the Commission’s Orders, therefore, is not one that follows directly or easily from the surrounding circumstances.
Fourth, particularly in circumstances like this case, where the Department’s methods in developing the Environmental Assessment has come under vigorous attack,[147] the public’s clear expectation is that the Office of Administrative Hearings was hired, in part, to render an independent assessment of the contents of the hearing record. While the Department’s EFP staff is undoubtedly the Commission’s principal team of advisors on routing matters,[148] it is not clear from the referral Orders (or surrounding statutes and regulations) that it is to be the only advisor. To the contrary, the proceedings in the combined dockets stand for the proposition that detailed advice and recommendations will come to the Commission from all quarters.
Finally, because the Administrative Law Judge’s views are merely recommendations, which the Commission is free to ignore in whole or in part, the risk of harm that might follow from uttering those last few words seems slight. If the Administrative Law Judge has misread the Commission’s Orders and instructions, ignoring the proffered recommendations is a ready and very easy cure.
The Claimed Failure of the Department to
Hire an Electrical Engineer:
In its papers, the City of Lindstrom argues that the analysis undertaken
by the Department’s Energy Facility Permitting staff should be wholly
discounted by the Commission because the Department did not route either the
underlying application or elements of the Environmental Assessment to an
electrical engineer for review.[149]
Blasting the Department’s proffered analysis in the CON proceeding as a
“farce” and an “abdication of duty,” the City argues that the Department staff
is not qualified to advise the Commission as to the need for the proposed
facilities.[150]
Notwithstanding its very sharp tone, the City’s argument runs far ahead of the accompanying law. The City points to no statute or regulation requiring the referral of the Department’s draft materials to an electrical engineer and the Administrative Law Judge is aware of no such requirement. At best, the City’s critique blends both scientific and political objections to the Department’s analysis; but the criticism is not rooted in the law.
The Around the Lakes Alternative and the
Case of People
for Environmental Enlightenment and Responsibility Inc., v. Minnesota Environmental Quality Council:
In its Post-Hearing briefs, the Applicants rely heavily upon the decision of the Minnesota Supreme Court in People for Environmental Enlightenment and Responsibility Inc. (“PEER”), v. Minnesota Environmental Quality Council, 266 N.W.2d 858 (Minn. 1978) for the proposition that upgrades along existing transmission lines are strongly favored over the proliferation of new HVTL routes.[151] While the Applicants’ summary of the decision in PEER is accurate, it is, in the judgment of the Administrative Law Judge, incomplete. When read in its entirety, the factual circumstances and the Court’s analysis in PEER leads to a contrary conclusion and details why the Commission should closely review the “Around the Lakes Over Head” routing option.
In PEER, the Court focused upon properly balancing the interests of the 35 homeowners who lived adjacent to transmission line alternative “Route 7,” against the public’s broader environmental interests in Long Lake and a 130-acre parcel of virgin, old-growth oak woods that lay underneath the path of transmission line alternative “Route 3.” In PEER, the Minnesota Environmental Quality Council staff favored a “Route 7” routing alternative, whereas the applicant-utilities and the homeowners both favored routing the transmission line along “Route 3.”[152]
This case is factually different than PEER, in ways that are significant to the later analysis. First, a choice between the Applicants’ favored route along the existing transmission line corridor, and the “Around the Lakes Over Head” option, does not implicate the same type of unique and “noncompensable”[153] environmental assets as was the case in PEER. Indeed, to the extent that the record speaks of unique regional assets deserving special guardianship, those assets exist along the proposed route in downtown Lindstrom and not along the more rural path around Chisago Lake.[154]
Secondly, the Minnesota Supreme Court remanded the proceedings in PEER so that the agency could complete the type of inquiries that are furnished by this record – namely, whether the homes proposed for condemnation “are, because of their unique characteristics, not replaceable.”[155] In the view of the Administrative Law Judge, this record goes very far in establishing such uniqueness. The particular topography of Lindstrom – situated as it is on an isthmus, with a limited industrial zone, and with roadways that are not conducive to trailer-truck traffic – combine to very dramatically reduce Lindstrom’s development options if it is not to be a retail and tourism center. Likewise, the serial and coordinated efforts that the City has undertaken to develop a tourism-related economy make clear that its claims are not pretextual; geared only to avoid the receipt of the transmission line that is needed by the wider region.[156] Indeed, in a powerful reply to suggestions of N.I.M.B.Y. – “Not in My Back Yard” – both the current and the former Mayor of Lindstrom each urged that the upgraded line be routed closer to their own families so as to avoid the projected impacts upon the downtown corridor.[157] By itself, this fact makes the PEER case distinguishable and augers for the Commission’s close review of the “Around the Lakes Over Head” alternative.
E.L.L.
[1] Compare, Minn. Stat. § 216B.243,
subd. 4 (2006) (designation by the Commission of an employee to facilitate
public participation in the hearing process).
[2] Exhibit 1 at 1.1.
[3] See generally, Exs. 2
at Chapters 1, 4, and 8; Ex. 5 at 5-6.
[4] See, Public Hearing Sign-In Sheets
(September 4 and 5, 2007).
[5] See, September 5, 2007 Evening Hearing,
Tr. at 54-57.
[6] See, September 4, 2007 Evening Hearing,
Tr. at 40-54; see also, September 5,
2007 Evening Hearing, Tr. at 90-100.
[7] See, September 4, 2007 Evening Hearing,
Tr. at 59-60.
[8] See, September 4, 2007 Evening Hearing,
Tr. at 33-37.
[9] See, September 4, 2007 Evening Hearing,
Tr. at 61-63.
[10] See, September 4, 2007 Evening Hearing, Tr.
at 27-28.
[11] See, September 4, 2007 Evening Hearing,
Tr. at 78-86.
[12] See, September 5, 2007 Evening Hearing,
Tr. at 68-90.
[13] See, September 4, 2007 Evening Hearing,
Tr. at 64-75.
[14] See, September 5, 2007 Evening Hearing,
Tr. at 26-42.
[15] See, September 5, 2007 Evening Hearing,
Tr. at 42-45.
[16] See, September 4, 2007 Evening Hearing,
Tr. at 54-58.
[17] See, September 5, 2007 Evening Hearing,
Tr. at 57-66; 106-115; accord, Written
Comments of P. Nelson, summarized infra.
[18] See, September 5, 2007 Evening Hearing,
Tr. at 45-51; 100-105.
[19] See, September 4, 2007 Evening Hearing,
Tr. at 86-88.
[20] See, September 4, 2007 Evening Hearing,
Tr. at 29-33.
[21] See, September 4, 2007 Evening Hearing,
Tr. at 75-78.
[22] See, September 4, 2007 Evening Hearing,
Tr. at 39-40.
[23] In the Matter
of the Exemption Application by Minnesota Power for a 345/230 kV High Voltage
Transmission Line Known as the Arrowhead Project, OAH Docket No. 10-2901-12620-2 (2001) (MEQB Docket
No. MP-HVTL-EA-1-99) (http://www.oah.state.mn.us/aljBase/290112620.rt.htm).
[24] Ex. 26
at 2.
[25] See, Minn. Stat. §§
216B.243 (7), 216C.09 (b) and 216C.10 (a) (9) (2006).
[26] Ex. 1.
[27] Ex. 3.
[28] Ex. 2.
[29] Ex. 518 at 6.
[30] See, Lindstrom’s
Initial Post-Hearing Brief, at 12-14.
[31] See, Ex. 518 (Environmental Assessment),
Appendix C.
[32] Exs. 5-6.
[33] Exs. 10-15.
[34] Ex. 18-19.
[35] Ex. 26.
[36] Exs. 201-205.
[37] Exs. 519-528.
[38] Ex. 517.
[39] Exs. 501-508.
[40] Exs. 7.
[41] Exs. 16-17.
[42] Exs. 20-22.
[43] Exs. 27.
[44] Exs. 206A, 206B, 207-213.
[45] Ex. 518.
[46] Exs. 8 and 9.
[47] Ex. 1 at Chapters 1 and 2.
[48] Ex. 1 at 2.6.
[49] Exs. 1 at 4.24; Ex. 2, Table 3.1
[50] Exs. 2 and 10 at 4. Great
River Energy (“GRE”) is the generation and transmission cooperative that
provides power supplies to East Central Energy.
[51] Ex. 1 at 2.6.
[52] Ex. 1 at 2.5 – 2.13.
[53] Ex. 1 at 2.6.
[54] Ex. 1 at 2.12.
[55] Exs. 501 at 6:18-20, 8:29-30, 10:29-32 and 13:12-14; Ex. 511 at
45:18.
[56] Exs. 1 at 4.3-4.5 and 5 at 8-9.
[57] Ex. 1 at 4.3 and Appendix B.
[58] Ex. 1,
Appendix B at 2.
[59] Exs.1,
Appendix B at 7; 214, 216 and 217.
[60] Exs. 1, Appendix B and 5 at 3.
[61] Exs. 1, Appendix B at 3-4 and 5 at 3-4.
[62] Id.
[63] Exs. 1, Appendix B at 4 and 5 at 4-5.
[64] Exs. 1, Appendix B at 4 and 5 at 4.
[65] Ex. 1, Appendix B at 4 and 21.
[66] Id.
[67] Id, at 5.
[68] Id.
[69] Id, at 4.
[70] Exs. 1 at 4.24-25 and Appendix B at 4; 2 at 3.11.
[71] Exs. 1 at 4.17, 4.24 and Appendix B; 2 at 3.11.
[72] See, Exs. 1 at 4.24; 2
at 3.11.
[73] Ex. 1 at 4.24-25.
[74] Ex. 3 at 13 – 18.
[75] Ex. 3 at 13.
[76] The exact alignment of the 115 kV line and 69 kV line will be determined after the location of the Lawrence Creek Substation has been finalized. See, Ex. 3 at 40.
[77] Subdivision 3(8) is inapplicable to the transmission facilities
proposed here as they are intended to provide transmission not generation. Compare,
Minn. Stat. § 216B.243 (3) (8) (2006) (“any feasible combination of energy
conservation improvements, required under section 216B.241, that can (i)
replace part or all of the energy to be provided by the proposed facility, and
(ii) compete with it economically”).
[78] Subdivision 3(12) is inapplicable because it relates solely to
generating plants: “if the applicant is proposing a nonrenewable generating
plant, the applicant’s assessment of the risk of environmental costs and
regulation on that proposed facility over the expected useful life of the
plant, including a proposed means of allocating costs associated with that
risk.”
[79] Compare, Minn. R. 7849.0110 (2007)
(“the Commission shall consider only those alternatives proposed before the
close of the public hearing and for which there exists substantial evidence on
the public record as to the criteria set forth in Part 7849.0120”).
[80] Ex. 1 at 1.6 - 1.11.
[81] Ex. 2 at S1.
[82] Ex. 1 at 4.10. Xcel Energy
provided additional information regarding forecast of demand and electric
energy consumption in the study area. See Ex. 1 at Appendix A.
[83] Exs. 501 at 13; 519 at 45:16 - 18.
[84] Ex. 1 at 4.13 - 4.14.
[85] Ex. 1 at 4.11.
[86] Exs. 1 at 4.11 - 4.13; 5 at 5-6.
[87] See generally, Ex. 1 at
4.3 – 4.5.
[88] See, Ex. 519 at
12:17-22.
[89] Exs. 5 at 11-12; 519 at 11 – 13.
[90] Ex. 1 at 4.19.
[91] Ex. 1 at 4.21 - 4.25 and Appendix B.
[92] Ex. 1 at 4.21.
[93] Compare, Minn. R.
7849.0260 (B) (7) (2007).
[94] Exs. 1 at 8.4; 18 at 11-12.
[95] Compare, Minn. R.
7849.0260 (B) (1) (2007).
[96] Exs. 1 at 4.19-4.21; 5 at 12.
[97] Ex. 5 at 13:1-5.
[98] Ex. 518 at 25.
[99] Ex. 519 at 37:5-9.
[100] See, Ex. 1 at 4.24 - 4.25.
[101] Ex. 519 at 17:10-12.
[102] Ex. 519 at 24:8 to 25:1-3.
[103] Ex. 1 at 8.3 - 8.4.
[104] Ex. 1 at 7.1.
[105] Ex. 1 at 7.1-7.8.
[106] Ex. 1 at 7.10.
[107] Ex. 18 at 4.
[108] See, Exs. 1, Appendix B
and 5 at 5 – 6.
[109] Ex. 5 at 13.
[110] Compare, 2001 Laws of
Minnesota, Ch. 212, Art. 7, Section 31.
[111] Compare generally, September 5, 2007
Evening Hearing, Tr. at 43-50 and 61-62.
[112] Ex. 1 at 4.24-4.25.
[113] Ex. 18 at 6-7.
[114] Ex. 518 at 78.
[115] Compare, Minn. Stat.
§ 216B.243, subd. 3 (1) (2006).
[116] Compare, Minn. Stat.
§ 216B.243, subd. 3 (2) (2006) with Ex. 501 at 6:13-14.
[117] Compare, Minn. Stat.
§ 216B.243, subd. 3 (3) (2006).
[118] Compare, Minn. Stat.
§ 216B.243, subd. 3 (4) (2006).
[119] Compare, Minn. Stat.
§ 216B.243, subd. 3 (5) (2006).
[120] Compare, Minn. Stat.
§ 216B.243, subd. 3 (6) (2006).
[121] Compare, Minn. Stat.
§ 216B.243, subd. 3 (7) (2006).
[122] Compare, Minn. Stat.
§ 216B.243, subd. 3 (9) (2006).
[123] Ex. 519 at 42:8-14.
[124] Ex. 5 at 13:1-5; compare also, Ex. 519 at 10 - 11.
[125] See, Minn.
Stat. § 216E.04 (2) (3) (2006).
[126] Compare,
Minn. R. 7849.5530 (2007).
[127] Compare,
Minn. R. 7849.5700 (2) (B) (2007).
[128] This factor is not applicable to a project subject to the
alternative permitting process. See,
Minn. R. 7849.5520 (3) (2007) (providing that under the alternative permitting
process, the applicant need not propose any alternative sites or routes to the
preferred site or route).
[129] Subdivision
7(b)(3)-(4) are likewise inapplicable as the proposed transmission facilities
are intended to provide transmission but not generation. See,
Minn. Stat. § 216E.03 (7) (b) (3) and (4) (2006).
[130] Minn. R. 7849.5910 (I) (2007) is inapplicable to the transmission
facilities proposed here as they are intended to provide transmission but not
generation.
[131] See, Ex. 3 at 15.
[132] Compare, September 5,
2007 Evening Hearing, Tr. at 28 and 55 with Ex. 518 at 38 - 40.
[133] Compare generally, Ex. 3
at 13 - 35.
[134] See, Ex. 201 at 6;
Testimony of Todd Clarkowski, Vol. 4, at 80 - 82.
[135] Ex. 518 at 35.
[136] See, Ex. 3 at 43 - 44.
[137] Ex. 518 at 78.
[138] Compare generally, September 5, 2007
Evening Hearing, Tr. at 92 - 93.
[139] See generally, September 5, 2007 Evening
Hearing, Tr. at 91 - 94.
[140] Exs. 2 at 3.11; 10 at 4:23-25.
[141] Ex. 10 at 6:9-10.
[142] Ex. 10 at 12:21-25.
[143] See generally, Ex. 20,
Figure 1, at 13; Testimony of Thomas Hillstrom, Tr. Vol. 2A, at 69.
[144] Exs. 1 at 7.4 - 7.5; 18 at
11 - 12; accord, Written Comments of
M. Langan.
[145] See, Written Comments of the Department
of Commerce, at 7.
[146] Compare, Minn. R. 7849.5710 (2) (2007)
("The hearing examiner shall not prepare a report or make any
recommendation to the commission unless the commission requests the hearing
examiner to do so").
[147] See, e.g., Initial Post-Hearing Brief of
the City of Lindstrom, at 12 - 17 and 23 - 26.
[148] Compare generally, Minn. Stat. § 216E.03
(11) (2006).
[149] See, Initial Post-Hearing Brief of the
City of Lindstrom, at 3, 17 and 21.
[150] Id., at 13 and 17.
[151] See, e.g., Applicants’ Joint Initial
Post-Hearing Brief at 31 and 39.
[152] See, PEER, 266 N.W.2d at 862.
[153] Id. at 874.
[154] See, Conclusions 91, 92 and 105.
[155] See, PEER, 266 N.W.2d at 874.
[156] See, e.g., Ex. 201 at 6; Testimony of Todd
Clarkowski, Vol. 4, at 80 – 82; September 5, 2007 Evening Hearing, Tr. at 45-51
and 100-105.
[157] See, September 4, 2007 Evening Hearing,
Tr. at 40-41; September 5, 2007
Evening Hearing, Tr. at 114-15.