10-2500-14695-2
G-252/CN-01-1826
STATE OF MINNESOTA
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE PUBLIC UTILITIES COMMISSION
|
|
|
|
In the Matter of the Application of the City of Hutchinson (Hutchinson Utilities Commission) for a Certificate of Need to Construct a Large Natural Gas Pipeline |
FINDINGS OF FACT, CONCLUSIONS, AND RECOMMENDATION |
This matter was heard by Administrative Law Judge Ken Nickolai on July 22 and 23, 2002, in the Small Hearing Room of the Minnesota Public Utilities Commission, 350 Metro Square Building, 121 Seventh Place East, Saint Paul, Minnesota. Public hearings were held on May 15, 2002, in Hutchinson, Minnesota, and on May 16, 2002, in Sleepy Eye, Minnesota.
Bruce E. Hanson, Oppenheimer, Wolff & Donnelly LLP, appeared on behalf of the applicant City of Hutchinson (Hutchinson Utilities Commission). Eric F. Swanson, Winthrop & Weinstine, P.A. and James R. Talcott, Senior Counsel, appeared on behalf of Northern Natural Gas Company. Cathy Ostrazeski and Brenda A. Bjorklund appeared on behalf of Reliant Energy Minnegasco (participating at the second pre-hearing conference and by written submission); Rebecca Comstock, Dorsey & Whitney LLP, appeared on behalf of Sibley-Renville Future Agricultural Interests Recognized, Inc. (Representation later withdrawn). Julia E. Anderson, Assistant Attorney General, and Linda S. Jensen, Assistant Attorney General, appeared on behalf of the Department of Commerce. Robert Harding appeared on behalf of the staff of the Public Utilities Commission.
NOTICE IS HEREBY GIVEN that pursuant to Minn. Stat. § 14.61, and the Rules of Practice of the Public Utilities Commission and the Office of Administrative Hearings, exceptions, if any, by any party adversely affected must be filed within fifteen (15) days of the mailing date hereof with the Executive Secretary, Minnesota Public Utilities Commission, 121 Seventh Place East, Suite 350, Saint Paul, MN 55101-2154. Exceptions must be specific, stated separately, and numbered. Proposed Findings of Fact, Conclusions and Order should be included, and copies shall be served upon all parties.. Oral argument before a majority of the Commission will be permitted to all parties adversely affected by the Administrative Law Judge’s recommendation. Such request must accompany the filed exceptions, and an original and fifteen (15) copies of each document should be filed with the Commission.
The Minnesota Public Utilities Commission will make the final determination of the matter after the expiration of the period for filing exceptions as set forth above, or after oral argument, if such is requested and held.
The Commission may, at its own discretion, accept or reject the Administrative Law Judge’s recommendation and the recommendation has no legal effect unless expressly adopted by the Commission as its final order.
STATEMENT OF ISSUE
Should the Minnesota Public Utilities Commission issue a Certificate of Need to the City of Hutchinson (Hutchinson Utilities Commission) for its proposed natural gas pipeline?
Based upon all of the proceedings herein, the Administrative Law Judge makes the following:
FINDINGS OF FACT[1]
Procedural History
Demand for Natural Gas
Alternatives to the Pipeline Proposal
42. The proposed natural gas pipeline will result in an additional supply of natural gas for heating, and to produce electricity, and to be used in production processes. It will permit Heartland Corn Products the opportunity to increase its production of ethanol.[78] Other benefits include increased investment of $26 million in the economy, an increase in employment and a short term increase in the sales and income tax base.[79]
43. The City of Hutchinson intends to comply with the relevant policies, rules, and regulations of the various state agencies, federal agencies and local governments that have jurisdiction over the proposed project.[80]
Based upon the foregoing Findings, the Administrative Law Judge makes the following:
CONCLUSIONS
1. Any of the Findings that more properly should be designated as Conclusions are adopted as such. Similarly, any of the Conclusions that more properly should be designated as Findings are adopted as such.
2. The Administrative Law Judge and the Public Utilities Commission duly have jurisdiction over this matter pursuant to Minn. Stat. § 14.50 et. seq., § 216B.243, and § 216B.2421.
Based on the foregoing Findings of Fact and Conclusions, the Administrative Law Judge makes the following:
RECOMMENDATION
That the application of City of Hutchinson (Hutchinson Utilities Commission) for a certificate of need for a new large energy facility be granted.
Dated this 9th day of October, 2002
s/Kenneth A. Nickolai
KENNETH A. NICKOLAI
Chief Administrative Law Judge
MEMORANDUM
The purpose of this proceeding is to determine if there is evidence of need sufficient to warrant HUC constructing an 89 mile pipeline connecting with the Northern Border Pipeline near Trimont, MN and extending north to the City of Hutchinson. Minnesota Stat. § 216B.243 places this responsibility on the Commision.
The Commission rules, at part 7851.0120, say that “A certificate of need shall be granted to the applicant” if the Commission addresses four issues in the affirmative. To assist the Commission when considering the application of its rule to this case, this memorandum will examine each issue separately.
Future adequacy, reliability, or efficiency of energy supply
The first issue is whether the probable result of denial would adversely affect the future adequacy, reliability, or efficiency of energy supply to the applicant, to the applicant’s customers, or to the people of Minnesota and neighboring states…” This portion of the rule then lists five factors to be considered.[81]
The ALJ is persuaded that denying this certificate of need would have adverse affects on the future adequacy, reliability and efficiency of the energy supply to affected persons. The record established that there is an immediate need for additional capacity on peak days. Department witness Minder and Northern witness Loos agreed that the existing Northern pipeline is currently capacity constrained and there is a need for additional capacity.[82] HUC has the need to maintain natural gas service to its customers while generating electricity using its gas fired generating capacity. Other Northern customers on the Willmar branch line are also, at times, capacity constrained by the limits of the current Northern system. At a minimum, construction of the pipeline will free capacity for the remaining Northern customers on the Willmar branch line.
There is also sufficient evidence that HUC’s demand for natural gas in the future will continue to grow. The City and surrounding area are growing and there is an industrial and commercial base of natural gas customers.[83] The record contains extensive testimony about the appropriate method of forecasting demand but each of the forecasts concluded the demand would exceed 30,000 MMBtu by the year 2016, assuming HUC will be adding gas fired electrical generating capacity during that time. Northern witness Loos forecasted that maximum summer load to be 31,900[84], while disagreeing that HUC should build a pipeline large enough to meet that load.[85] Hutchinson witness Schedin forecast the daily total demand in 2016 to be 34,672 MMBtu.[86] Department of Commerce witness Shah concluded the upper end of the range of estimated demand for the year 2016 to be 30,968 dth/day[87]. While the parties have disagreed over the proper methodology and the precise estimates, the record establishes that demand for natural gas is increasing and that it is almost certain to exceed 30, 000 MMBtu by the year 2016. Since the current level of demand is, at times, capacity constrained on the existing Northern pipeline, additional pipeline capacity is necessary.
Other sub-factors to be considered under this heading are conservation efforts, promotional practices, the ability of current and planned facilities to meet the future demand and the effect on the proposed facility in making efficient use of resources. As set out in the findings and conclusions, past and present conservation efforts were considered when examining the growth of demand. Similarly, the Department of Commerce witness Minder examined the practices of Hutchinson and concluded that there had been no promotional efforts to increase demand. Existing facilities are now capacity constrained, so they cannot meet the expected growth in demand. Finally, the proposed facility will allow HUC to more efficiently use its natural gas for its turbine generator through increasing the gas pressure to the higher level recommended by the manufacturer.
A More Reasonable and Prudent Alternative
The second item in the rule is whether “a more reasonable and prudent alternative to the proposed facility has not been demonstrated by a preponderance of evidence on the record by parties or persons other than the applicant…” The rule then lists a number of factors to consider.[88]
Northern argues the law places the burden on HUC to demonstrate that there is no more reasonable and prudent alternative, and that HUC has failed to meet that burden. To support its position, Northern argues the Commission Order in MPUC Docket No. G-008/CNJ-95-514, September 12, 1996, Order Granting Certificate of Need, (Minnegasco) placed the burden squarely on the applicant. It further argues that to the extent that the language of Minn. Rules 7851.0120 (B) seeks to shift that burden, it violates state law.
The ALJ is not persuaded by Northern’s arguments. The rule clearly places the burden “by a preponderance of the evidence” on parties other than the applicant to demonstrate there is a more reasonable and prudent alternative. The Commission Order in Minnesgasco is consistent with that conclusion.
The record contains an analysis of the relative costs of the two financial proposals made by Northern to HUC.[89] The February 22, 2002 offer was rejected by Hutchinson as being too costly and not extending beyond the time when additional generating capacity is expected to be added.[90] While a Northern witness testified that this offer would have environmental benefits, since no construction would be necessary, details of facility needs to meet anticipated demands in the timeframe beyond 2011 were not provided. The ALJ is thus persuaded that the February 22, 2002 offer is not a more reasonable and prudent alternative to the proposed pipeline because of its cost and failure to address the longer term needs identified by the forecast of demand for natural gas.
The April 24, 2002 offer is more cost effective in a 20 year time frame, if the cost of construction exceeds HUC’s estimate and is in excess of $31 million. [91] However, Northern’s proposal does meet the increased demand forecast beginning in 2011.[92] When examined over the 40-year expected physical life of the proposed pipeline, the April 24, 2002 offer is more expensive, even when the cost of the HUC pipeline is assumed to be as high as $39 million. [93] Because the proposal fails to address the likely need for increased capacity beginning in 2011, the ALJ is persuaded that this is not a more reasonable or prudent alternative.
Other sub-items to be examined under this portion of the rule include; the appropriateness of the size, type and time of the proposed facility, the effects on the natural and socioeconomic environments and the expected reliability compared to reasonable alternatives. The forecast of demand indicates a substantial growth in natural gas demand through 2016. While the size of the proposed pipeline may be larger than needed to serve the needs of the City of Hutchinson, there is evidence that HUC is seeking to have other entities use the capacity. In addition, there is no evidence that a small pipeline would cost substantially less. A smaller pipeline would not provide the potential benefits to the adjacent communities of additional service or potential competition to Northern. There will be adverse environmental consequences from the project during the construction. The evidence is that HUC is seeking to mitigate those affects with appropriate government bodies. Northern states that at least the February offer would not have such environmental consequences. The ALJ is persuaded that additional pipeline construction will be needed at some point[94] and that the environmental affects of this project, when properly mitigated, will be no greater than any other future construction alternative.
Consequences to society of granting the certificate of need.
The third rule factor to be considered by the Commission is “the consequences to society of granting the certificate are more favorable than the consequences of denying the certificate…” The rule then lists four sub-factors to examine.[95] The ALJ is persuaded that the consequences of granting the certificate are more favorable than a denial. The proposed project will increase the supply of natural gas in an area of the state that has a constrained supply. That will allow a more reliable supply of energy to that portion of the state encouraging economic development and permit more electric generation, reducing the need for Hutchinson to purchase electricity from others at peak times. Other benefits include increased investment of $26 million in the economy, an increase in employment and a short term increase in the sales and income tax base.[96] While construction will have short term adverse environmental impacts, long term environmental benefits arise from the more efficient use of HUC’s generating capacity.
Compliance with other government regulations
The rules also require the Commission to consider a fourth factor that “it has not been demonstrated on the record that the design, construction, or operation of the proposed facility will fail to comply with those relevant policies, rules and regulations of other state and federal agencies and local governments.”
There is ample evidence in the record to support the conclusion that HUC intends to comply with applicable policies, rules and regulations of the federal, state, and local government. Department of Commerce witness Gross reviewed the list of permits to be obtained and concluded there is no evidence that the proposed facility would fail to comply with applicable requirements.[97]
For these reasons, the ALJ respectfully recommends the Commission conclude that the requirements of the rule are satisfied and that the Certificate of Need be granted.
K.A.N.
[1] References to the record are provided for the convenience of the Commission and their Staff. Reference to one place in the record to support a finding does not mean that is the only support for that finding in the record.
[2] Transcript Vol. 4, p. 18
[3] Transcript Vol. 5A, p. 14
[4] Ex. 1, p. 2
[5] Ex. 1, p. 3
[6] Transcript Vol. 4, p. 27 and p. 38
[7] Ex. 1, p. 3, Transcript Vol. 4, p. 26
[8] Ex. 15 at Sec. 7851.0250 (A)(1)
[9] Ex.1, p. 3
[10] Ex. 15, Section 7851.0230, p. 2
[11] Ex. 15, Section 7851.0230, p. 2
[12] See, Exhibit 50.
[13] Ex. 15, Section 7851.0290, p. 6, Ex.14, p. 6
[14] Ex. 45; Transcript Vol. 4, p. 104, p. 113, p. 114
[15] Ex. 72
[16] Ex. 15, Section 7851.0310, p.2
[17] Transcript Vol. 5A, p. 67
[18] Transcript Vol. 5B, p. 63
[19] Transcript Vol. 4, p. 84
[20] Transcript Vol. 4, p. 90
[21] Transcript Vol. 5B, p. 21.
[22] Transcript Vol. 4, p. 86
[23] Transcript Vol. 4, p. 55
[24] Ex. 15, Section 7851.0240, p. 1
[25] Ex. 15, Section 7851.0240, p. 1
[26] Transcript Vol. 4, pp. 85-86
[27] Transcript Vol 4, p. 88
[28] Transcript Vol. 4, pp. 205-6
[29] Transcript Vol. 4, pp. 205-206
[30] Transcript Vol. 4, page 206
[31] Ex. 15, Section 7851.0240, p. 2
[32] Transcript Vol. 4, p. 41
[33] Transcript Vol. 4, p. 55
[34] Exhibit 4
[35] This is at the higher end of witness Shah’s range. Transcript Vol. 5B, pp. 30-31
[36] Ex. 74, table 1. Northern witness Loos estimated demand at 32,300 DTH in 2016. Ex. 76, p. 14
[37] Ex. 15, Section 7851.0270, p. 21
[38] Exhibit 14, pp. 2-3, Ex. 3
[39] Transcript Vol. 4. p.54, 68-69
[40] Transcript Vol. 4, p. 87
[41] Ex. 15, Section 7851.0260, p. 4
[42] Transcript Vol. 5B, pp. 5-7.
[43] Transcript Vol. 5B, pp. 8-9, Ex. 15, Section 7851.0250, p. 3
[44] Transcript Vol. 4, p. 87
[45] Ex. 76, p. 6 and pp. 9-10
[46] The ALJ makes no findings or conclusions with respect to the status of the proposed pipeline as one subject to “Open Access”. The record contains the legal position of the Department and of Reliant Energy/Minnesgasco on this point, but the only testimony on the issue was in respect to whether municipal bond financing could be used if the pipeline is not restricted to muniipal users. At the close of the hearing, the Department and HUC requested that this issue be addressed to the Commission after a ruling on the Certificate of Need. Vol. 5B, pp. 75-77.
[47] Ex. No. 42
[48] Transcript Vol. 4, p. 92, July 22, 2002
[49] Transcript Vol. 4, page 93, July 22, 2002
[50] Ex. 40.
[51] Ex. 76, p. 10.
[52] Ex. 4
[53] Ex. 4, April 24, 2001, letter p. 2.
[54] Ex.69, Schedule WJF-1
[55] Ex. 69, Schedule WJF-2
[56] Ex. 15, Revised Section 7851.0290, pp. 4-11
[57] Ex. 14, p. 4
[58] Ex. 80, p. 6, Attachment 2
[59] Transcript Vol. 4, p. 66
[60] Transcript Vol. 4, p. 66
[61] Ex. 12.
[62] Ex. 14, p. 4
[63] Transcript Vol. 5B, pp. 60-61. Ex. 51.
[64] Ex. 51
[65] Transcript Vol. 5B, pp. 40, 42, 47, 55
[66] Ex. 15, section 7851.0270, p. 21
[67] Transcript Vol. 5A, pp. 79-81
[68] Ex. 80, pp 16-18. Ex. 15, Sec 7851.0340, p.2, p. 19
[69] Letter Glenn Novotny, June 4, 2002
[70] Transcript Vol. 4, pp. 104, 105
[71] Northern witness, Fowler, testified that Northern’s February 22, 2002 offer would have environmental benefits since it would not require any significant construction of new facilities. Ex. 69, p.8.
[72] Letter from U.S. Energy Services, June 5, 2002
[73] Ex. 80, p. 13, Letter from U.S. Energy Services, June 5, 2002.
[74] Letter, U.S. Energy Services, Inc., dated June 5, 2002. However, the extent to which non-municipal customers will be able to use transmission capacity on the proposed line is unclear on the record because of the to be resolved dispute over whether the proposed line will be subject to Open Access requirements.
[75] State Senator Steve Dill letter dated May 24, 2002
[76] Letter, Minnesota Municipal Utilities Association, June 6, 2002; Letter, City of Brownton, May 15, 2002.
[77] Ex. 40
[78] Letter, Heartland Corn Products, April 29, 2002
[79] Ex. 80, p. 13.
[80] Exhibit 80, page 19
[81] The factors are: (1) the accuracy of the applicant's forecast of demand for the type of energy that would be supplied by the proposed facility; (2) the effects of the applicant's existing or expected conservation programs and state and federal conservation programs; (3) the effects of the applicant's promotional practices that may have given rise to the increase in the energy demand, particularly promotional practices that have occurred since 1974; (4) the ability of current facilities and planned facilities not requiring certificates of need to meet the future demand; and (5) the effect of the proposed facility, or a suitable modification of it, in making efficient use of resources.
[82] Transcript Vol. 5B, pp. 11-12 (Minder); Transcript Vol. 5A, p. 63 (Loos)
[83] State demographer Gillaspy testified that growth in the City of Hutchinson has been most noticeable in manufacturing, construction, and the professional services sector. Ex. 73, p. 3.
[84] Northern witness Fowler testified that the total capacity needed would be 25,000 DTH/day, however, that projection was only through the year 2011. Ex. 69, p. 8; Ex. 76, p. 14
[85] Transcript Vol. 5A, pp. 78-79
[86] Ex. 75, table 1
[87] Transcript Vol. 5B, p. 30
[88] The factors are: (1) the appropriateness of the size, the type, and the timing of the proposed facility compared to those of reasonable alternatives; (2) the cost of the proposed facility compared to the costs of reasonable alternatives and the cost of energy that would be supplied by reasonable alternatives; (3) the effects of the proposed facility upon the natural and socioeconomic environments compared to the effects of reasonable alternatives; and (4) the expected reliability of the proposed facility compared to the expected reliability of reasonable alternatives.
[89] Northern witnesses discussed other possible alternatives such as foregoing off-system electric sales to reduce the need for natural gas fired electric generation, construction of a remote electric generating plant in Trimont, MN and a transmission line to Hutchinson, acquiring dual fuel electric generating capacity or a peak shaving plant. See, Ex. 76, pp. 17-18. While these alternatives were placed on the record, no evidence detailing their possible implementation or comparable costs and benefits was made. There is then not sufficient evidence in the record to give them serious consideration.
[90] Ex. 15, Section 7851.0290, pp. 3-12, Section 7851.0270, p.32
[91] Transcript Vol. 5B, pp. 60-61, Ex. 51
[92] Ex. 69, p.8. and WJF-2 attached
[93] Ex. 51, Transcript, Vol. 5B, p 41
[94] Looking at the April offer, Northern agrees there will be a capacity deficiency under that proposal by the year 2011 and that new facilities will be added at that time. Transcript, Vol. 5A, pp.73-74.
[95] The factors are: (1) the relationship of the proposed facility, or suitable modification of it, to overall state energy needs; (2) the effects of the proposed facility, or a suitable modification of it, upon the natural and socioeconomic environments compared to the effects of not building the facility; (3) the effects of the proposed facility, or a suitable modification of it, in inducing future development; and (4) the socially beneficial uses of the output of the proposed facility, or a suitable modification of it, including its uses to protect or enhance environmental quality.
[96] Ex. 80, p. 13
[97] Ex. 80, p. 19