OAH 8-2200-20122-2
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE MINNESOTA POLLUTION CONTROL AGENCY
|
In the Matter of the Administrative Penalty Order issued
to the City of |
FINDINGS OF FACT,CONCLUSIONS ANDRECOMMENDATION |
This matter came on for an evidentiary hearing before Administrative Law Judge Eric L. Lipman on May 18, May 19 and May 28, 2009. Following the receipt of Post-Hearing Memoranda from the parties, the hearing record closed on July 10, 2009.
Lawrence W. Pry, Assistant Attorney General, appeared on behalf of the
Minnesota Pollution Control Agency (MPCA or the agency). Roger A. Jensen, of the law firm of Jensen,
1. Did the Respondents violate the requirements of Minnesota Rules and the National Pollutant Discharge Elimination System/State Disposal System Permit governing construction activity, as set forth in the Notice and Order for Expedited Hearing issued January 8, 2009?
2. Did the MPCA have a reasonable basis to impose an administrative penalty of $5,600?
The Administrative Law Judge recommends that the Commissioner of the
Pollution Control Agency affirm-in-part the Administrative Penalty Order
against the City of
Based upon the evidence in the hearing record, the Administrative Law Judge makes the following:
1.
2.
Respondent
Arnt Construction Co., Inc. (“Arnt”) is a
3.
The Lake
Avenue Project involved the reconstruction of approximately 1.5 miles of
roadway and sidewalks between Highway 61 and
4.
Prior to the construction project,
5.
Similarly,
the storm sewer that was in place along
6.
In addition to refurbishing the existing
thoroughfare, the City improved a bike path that lay parallel to
7.
The
Lake Avenue Project was a difficult and politically controversial undertaking. During a series of public meetings around the
City of
8. Moreover, because of the scope and scale of the improvements to the roadway, the City assumed greater regulatory risk. By undertaking more substantial repairs and improvements that a simple overlay to the existing roadway, the City was obliged to seek coverage under the Minnesota Pollution Control Agency’s (MPCA) National Pollutant Discharge Elimination System State Disposal System general storm water permit (NPDES Permit).[8]
9.
Notwithstanding
the greater engineering, political and regulatory risks to the City of
undertaking a wide range of improvements to
10. Construction activities on the Lake Avenue Project began on or around June 7, 2007 and ended on or around October 31, 2007.[10]
11. The City was the owner of the improvements and Arnt was its general contractor. In order to ensure that Arnt fulfilled its contractual obligations, the City deployed inspectors from its engineering department to oversee the progress of the work during each work day, and senior officials of the City, including its Engineer and City Manager, toured the project at the end of their respective workdays during the construction period.[11]
12.
During their impromptu reviews of the
construction site, City Engineer Mark Burch and City
13. Alongside much of the Twin Cities metropolitan area, the Lake Avenue Project was battered by heavy rainfall during the summer and autumn of 2007. During September and October of 2007, for example, there were more than 20 days of rainfall; with some rain events including more than an inch of precipitation.[13]
14.
Storm water presents a difficult and important
challenge for the state’s environmental regulators. The principal concern follows from the fact
that pollutants adhere to sediment in turbid water. Sediment-laden storm water can act as a
“vehicle” which carries pollutants into protected waters of the state, and the
pollutants themselves can have dramatic impacts upon water quality and habitat. Thus, state regulators are eager to foreclose
the routes by which pollutants can enter important waters of the state –
including
15.
Combating the large and unusual amounts of storm
water on the project site was a genuine challenge for City officials and
Arnt. Because even an upgraded
16. To meet this challenge, the City and Arnt employed a pyramiding series of storm water and sediment management strategies. At the curb and gutters along Lake Avenue, Arnt laid a specially-manufactured vinyl fabric that permits storm water to filter into the storm sewer but retains dirt and sediment above-ground. The sewer systems then ran to an upgraded sump system which itself filtered the storm water and drew out debris. Water from the sump system then ran through pipes to a set of riprap boulders that were placed above a sediment collection basin. As the storm water ran over the riprap, its energy was dissipated and sediment filtered out on to the boulders.[16]
17.
Because of the volume of precipitation that fell
during the construction period was greater than expected, City officials
decided to temporarily transform a portion of
18. In the Storm Water Pollution Prevention Plan (“SWPPP”) submitted by the City with its NPDES Permit application, the City pledged that “[d]ewatering or basin draining activities of turbid or sediment laden water will be discharged to temporary sediment basins or treated with appropriate BMPs”[18]
19.
The temporary collection basin was “de-watered”
by pumping the basin water on to a field with a very slight grade. At the bottom of this slight grade, in the
lake bed, Arnt positioned a silt fence and a silt curtain so as to prevent any
deposits of sediment into the waters of
20.
The use
of vinyl fabric coverings under the storm sewer grates on
21.
The MPCA and
22. Acting on behalf of the MPCA under this agreement, staff of the Ramsey Conservation District (“RCD”) conducted nine inspections at the Lake Avenue Project between June 2007 and April 2008. These inspections were undertaken to assess Arnt’s and the City’s compliance with the terms of the NPDES Permit.[22]
23. During the inspections that occurred in the autumn of 2007, MPCA and RCD staff identified several violations of the Permit at the Lake Avenue Project.[23]
September 19, 2007 Inspection:
24. Receiving the referral of a citizen complaint from the Rice Creek Watershed District, Thomas Petersen of the Ramsey Conservation District undertook an inspection of the Lake Avenue Project site on September 19, 2009. Before making his way to the site, Peterson asked Brian Gove, MPCA Compliance Coordinator for State Compliance Inspectors, to join him during the inspection. Gove agreed.[24]
25.
As detailed in a later investigation report,
Petersen noted that exposed and potentially erodible soils had not been
adequately protected, excessive sediment had been accumulating in
26.
Additionally, Mr. Petersen noted in his
inspection report that no sediment was seen entering
September 21, 2007 Inspection:
27. After a significant rainfall on September 20, Petersen returned to the Lake Avenue Project site on September 21, 2007 for a follow-up inspection.[27]
28.
During his inspection tour, Mr. Petersen noted
deficiencies that were present during the earlier inspection tour on September
19; specifically, stockpiles of topsoil in
29.
It
cannot be determined from the evidence in the record that the stockpiles of
topsoil in Lake Avenue, accumulations of sediment in the street and poorly
functioning inlets, observed by Mr. Petersen on September 21, were the same
stockpiles, accumulations of sediment and poorly functioning inlets observed on
September 19, 2007.[29]
October 2, 2007 Inspection:
30. Petersen returned to the Lake Avenue Project site for a follow-up inspection on October 2, 2007.[30]
31.
During his inspection tour, Mr. Petersen noted
deficiencies that were present during the earlier inspection tour on September
19; specifically, accumulations of sediment in the street and poorly
functioning inlets. Further, Petersen
noted exposed soils within a short distance of
32. Michael Goodnature, Conservation Specialist with the Ramsey Conservation District accompanied Petersen on the October 2, 2007 inspection tour. During the tour, Goodnature took a series of digital photographs. The photographs were received into the evidentiary hearing record as Exhibits X through MM.[32]
33.
Mr. Goodnature retrieved a sample of water from
Post-Inspection Events:
34.
The grading of
35. The installation of sod along the curb sides of the Lake Avenue Project began on October 8 and was completed on October 26, 2007.[35]
36. On April 24, 2008, the MPCA issued an Alleged Violations Letter to Respondents.[36]
37. On May 16, 2008, the Agency issued an Administrative Penalty Order. In the Order, the MPCA asserted that the Respondents failed to comply with following requirements of the NPDES Permit:
(a) Part IV, Section B 2, relating to erosion controls for exposed soils;
(b) Part IV, Section B 4, relating to energy dissipation by pipe outlets;
(c) Part IV, Section C 1, relating to minimum sediment control practices;
(d) Part IV, Section C 4, relating to protections for storm drain inlets;
(e) Part IV, Section E 4, maintenance of sediment control measures; and,
(f) Part IV, Section E 4 f, removal of accumulated sediment.
The Administrative Penalty Order noted that because the Lake Avenue Project was complete and fully stabilized, the MPCA did not require further corrective action from the City or Arnt.[37]
38. As part of the Joint Powers Agreement Enforcement Referral Forum, agency officials enhanced the base penalty in this case by fifteen percent – for a total of $338 – on the grounds that the City and Arnt failed to comply with corrective actions as directed by agency inspectors.[38]
39. The Administrative Penalty Order imposed a nonforgivable penalty of $5,660.[39]
40. On June 12, 2008, Arnt mailed a letter to the MPCA requesting administrative review of the Order.[40]
41. So as to facilitate settlement discussions between the parties, on June 27, 2008, Arnt waived its right to an evidentiary hearing within thirty days of its written request for review.[41]
42. On August 21, 2008, the City mailed a letter to the MPCA requesting administrative review of the Order.[42]
43. In advance of the third day of the evidentiary hearing, MPCA and Arnt Construction, Inc. arrived at a settlement of the agency’s claim against that firm.[43]
Based upon these Findings of Fact, and for the reasons detailed in the Memorandum below, the Administrative Law Judge makes the following:
1. The Administrative Law Judge and the Minnesota Pollution Control Agency have jurisdiction to consider the violations against Respondents pursuant to Minn. Stat. §§ 14.50 and 116.072, subd. 6.
2. Respondents received proper and timely notice of the violations and of the time and place of the hearing. This matter is, therefore, properly before the MPCA and the Administrative Law Judge.
3. The MPCA has complied with all relevant procedural legal requirements.
4.
Pursuant to
5. The requirements of Appendix A in the MPCA General Permit Authorization to Discharge Storm Water Associated with Construction Activity under the National Pollutant Discharge Elimination System/State Disposal System Permit (NPDES/SDS) Program are incorporated by reference into the rules of the MPCA, pursuant to Minn. R. 7090.0060.
6. The MPCA has shown by a preponderance of the evidence that Respondents violated NPDES Permit Part IV. B. 2, by failing to stabilize slopes that were within 200 lineal feet of White Bear Lake within 14 days of the construction of the temporary sediment basin.
7. The MPCA did not demonstrate by preponderance of the evidence that Respondents violated NPDES Permit Part IV. B. 4.
8. The MPCA has shown by a preponderance of the evidence that Respondents violated NPDES Permit Part IV. C. 1, by failing to minimize sediment from entering the gutter systems and storm sewer inlets.
9. The MPCA did not demonstrate by preponderance of the evidence that Respondents violated NPDES Permit Part IV. C. 4
10. The MPCA did not demonstrate by preponderance of the evidence that Respondents violated the inspection requirements of NPDES Permit Part IV. E. 4
11. The MPCA has shown by a preponderance of the evidence that Respondents violated NPDES Permit Part IV. E. 4. F, by failing to remove off-site accumulations of sediment in a manner sufficient to minimize off-site impacts.
12.
Upon this evidentiary record, the Administrative
Law Judge cannot conclude that any sediment from the Lake Avenue Project was
discharged into
13. Because the agency did not establish that the City and Arnt failed to comply with corrective actions as directed by agency inspectors, enhancement of the base penalty by fifteen percent is inappropriate. The Commissioner should reduce the penalty amount by $338.
14. The MPCA has shown by a preponderance of the evidence that, based on the factors set forth in Minn. Stat. § 116.072, subd. 2, application of a nonforgivable penalty is reasonable.
15. Any of the Findings of Fact more properly designated Conclusions are hereby adopted as such.
Based upon these Findings of Fact and Conclusions, and for the reasons explained in the Memorandum that follows below, the Administrative Law Judge makes the following:
The Commissioner of the Minnesota Pollution Control Agency should:
1. AFFIRM-IN-PART the Administrative Penalty Order against the City of White Bear Lake and Arnt Construction, Co., Inc.;
2. Reduce the $5,600 administrative penalty by $338.
Dated: August 10, 2009.
/s/ Eric L. Lipman
_________________________
ERIC
L. LIPMAN
Administrative
Law Judge
This report is a recommendation, not
a final decision. The Commissioner of
the Pollution Control Agency will make the final decision after a review of the
record. The Commissioner may adopt,
reject or modify these Findings of Fact, Conclusions, and Recommendations. Under
If the Commissioner fails to issue a final decision
within 90 days of the close of the record, this report will constitute the
final agency decision under
Under Minn. Stat. § 14.62, subd. 1, the agency is
required to serve its final decision upon each party and the Administrative Law
Judge by first class mail or as otherwise provided by law.
MEMORANDUM
The MPCA has the authority to require NPDES/SDS permits prior to commencement
of construction activity, so as to assure that the activity is conducted in
accordance with the permit and applicable rules, and to assess a penalty for
violations of the permit and rules. The
administrative law judge must affirm the penalty unless the MPCA fails to prove
that the violations occurred and that the amount of the penalty is reasonable.[45] The amount of the penalty shall be set
aside only if it represents a clear abuse of the agency’s discretion.[46]
Claim Regarding a Violation of NPDES Permit
Part IV, Section B 2:
The MPCA
asserts that the City and Arnt failed to stabilize the side slopes of the temporary sediment basin in
By way of reply, the City offers three
defenses to liability under this portion of the Administrative Penalty Order: (1) the NPDES Permit merely requires that
stockpiles of soil around the sedimentation pond be ringed with silt fences;[49]
(2) the start-date for the period within which the slopes of the basin must be
stabilized runs from the date on which the first inspection occurred;[50]
and (3) the period within which the slopes of the basin needed to be stabilized
never began to run because the temporary sediment basin was always “actively
worked.”[51] None of these arguments are availing.
The NPDES Permit obliged the City and Arnt
to stabilize the slopes that were within 200 lineal feet of the basin. The best and most natural reading of the Permit
obliges the stabilization work to be complete no later than 14 days after the
temporary sediment basin was first constructed.
Adopting the City’s reading of the Permit would, conceivably, authorize the
postponing of stabilization work for as long as workmen were performing
construction-related duties near the basin; a reading that is at odds with the
purpose of the erosion-prevention requirements.[52]
Because the slopes that were within 200
lineal feet of
Claim Regarding a Violation of NPDES Permit
Part IV, Section B 4:
The MPCA asserts that the City and Arnt failed to install adequate energy
dissipation measures at the storm water pipe outlet to the temporary sediment
basin. In the view of the MPCA, the set
of rip rap boulders beneath the outlet pipe were too few in number and spaced
too widely apart to meet the applicable anti-erosion standard.[54]
By way of reply, the City
asserts that it did deploy sufficient riprap, silt fences and engineering
features in the temporary sedimentation basin to meet the applicable standard.[55] The Administrative Law Judge agrees.
The applicable standards in the
NPDES Permit are:
Pipe outlets must be provided with temporary or permanent energy
dissipation within 24 hours of connection to a surface water.
….
Dewatering or basin draining … related to construction activity that may
have turbid or sediment laden discharge water must be discharged to a temporary
or permanent sedimentation basin on the project site whenever possible…. The Permitee(s) must ensure that discharge
points are adequately protected from erosion and scour.[56]
Not only did Messrs. Burch and Arnt testify
credibly that the anti-erosion measures in place adequately dissipated the
energy of the storm water entering the temporary sedimentation basin, the
record does not include evidence of significant erosion or scour at the
discharge point to the basin.
For these reasons, the
Commissioner should dismiss this portion of the Administrative Penalty Order.
Claim Regarding a Violation of NPDES Permit
Part IV, Section C 1:
The MPCA asserts that the City and Arnt failed to install adequate sediment
control measures on the curb along
By way of reply, the City asserts that any silt laden storm water washing over the exposed boulevards would be restrained by one or more of series of countermeasures – including, an indentation at the top of the curve line; silt fabric over the inlets to storm sewers; an underground sump infiltration system; riprap at the Matoska Park inlet to the temporary sedimentation basin; and a series of silt fences and curtains at the outlet point in White Bear Lake.[58] The Administrative Law Judge disagrees.
The applicable standard in the
NPDES Permit is: “Sediment control practices must minimize sediment from
entering surface waters, including curb and gutter systems and storm sewer
inlets.”[59]
While mindful that there was an atypical and unusually large amount of rainfall during the construction of the Lake Avenue Project, the indentation on the curb line was not designed for the purpose of restraining sediment-laden storm water and was not effective in minimizing sediment from entering the gutter systems and storm sewer inlets.[60] Similarly, downstream countermeasures were not (and could not be) effective in meeting the City’s obligation to minimize the entry of sediment into the gutter and storm sewer systems.
For these reasons, the Commissioner should sustain this portion of the Administrative Penalty Order.
Claim Regarding a Violation of NPDES Permit
Part IV, Section C4:
The MPCA asserts that the City and Arnt failed to adequately protect all storm
drain inlets along the Project
corridor by installing functional
and appropriate inlet protections. The
MPCA argues that when it became clear that the use of vinyl fabric was not
effectively draining storm water from
By way of reply, the City asserts that the application of silt fabric over the storm drain inlet is a widely used and accepted sediment control practice, which meets the requirement of the Permit.[62] The Administrative Law Judge agrees.
The applicable standard in the
NPDES Permit is: “All storm drain inlets must be protected by appropriate [Best
Management Practices (BMPs)] during construction until all sources with
potential for discharging to the inlet have been stabilized.”[63]
The
fabric coverings used by the City and Arnt did protect from the storm drain
inlets from receiving sediment during the construction process and were in use
until nearby discharge sources had been stabilized.
For these reasons, the
Commissioner should dismiss this portion of the Administrative Penalty Order.
Claim Regarding a Violation of NPDES Permit Part IV, Section E 4:
The MPCA asserts that the City and Arnt failed to adequately inspect the sediment
control measures in the storm sewer inlets along
By way of reply, the City asserts that under the terms of the NPDES Permit it had 24 hours within which to discover and remediate any improperly functioning sediment control device. Moreover, MPCA did not establish that any of devices that were not operating on September 19, September 21 or October 2 were likewise inoperative 24 hours later.[65] The Administrative Law Judge agrees.
The applicable standards in the
NPDES Permit are:
The Permittee(s) (either the owner or operator, whoever is identified in
the SWPPP) must routinely inspect the construction site once every seven (7)
days during active construction and within 24 hours after a rainfall event
greater than 0.5 inches in 24 hours.
….
All erosion prevention and
sediment control [Best
Management Practices] must be
inspected to ensure integrity and effectiveness. All nonfunctional [Best Management Practices] must be
repaired, replaced, or supplemented with functional [Best Management Practices]….”[66]
While the Administrative Law Judge is sympathetic to the inspectors’ claims that their work schedules might not permit them to return to a construction site for a follow-on inspection within 24 hours, it does not follow that because a group of storm water inlets were unprotected on September 19 and also September 21, there was a violation of the NPDES standard.[67] Without more – namely that the same inlets were in disrepair between the two inspection dates – the agency cannot establish that any particular inlet was unnoticed and in disrepair for more than 24 hours.
For this reason, the Commissioner should dismiss this portion of the Administrative Penalty Order.
Claim Regarding a Violation of NPDES Permit
Part IV, Section E.4.F:
The MPCA asserts that the City and Arnt failed to remove accumulated sediment from the curb and gutter so as to prevent this debris from entering the storm
sewers or causing blockages that posed safety hazards on
By way of reply, the City asserts that it undertook a regimen of daily street sweeping alternately deploying subcontracted and city-owned sweepers to accomplish this work. Because street sweeping was accomplished within 24 hours of significant rain events, argues the City, it met the requirement of Section E (4) (f) of the Permit. The Administrative Law Judge disagrees.
The applicable standard in the
NPDES Permit is:
All
erosion prevention and sediment control BMPs must be inspected to ensure
integrity and effectiveness. All nonfunctional BMPs must be repaired,
replaced, or supplemented with functional BMPs. The Permittee(s) must investigate and comply with the following inspection
and maintenance requirements:
….
If sediment escapes the construction site,
off-site accumulations of sediment must be removed in a manner and at a
frequency sufficient to minimize off-site impacts (e.g., fugitive sediment in
streets could be washed into storm sewers by the next rain and/or pose a safety
hazard to users of public streets).[69]
Under the terms of the Permit, the City was obliged to take such
measures as would minimize the off-site impacts, particularly those which might
pose a safety hazard to users of the public streets. Under the strain of the unusually high
amounts of rainfall, the City did not meet this very demanding standard. More countermeasures were possible, and
required, so as to reduce the levels of standing water in
For this reason,
the Commissioner should sustain this portion of the Administrative Penalty
Order
E. L. L.
[1] Notice and Order for Hearing, at 2.
[2] Notice and Order for Hearing, at 2; Exhibits A, C and K.
[3] Exs. B and 10; Testimony of Thomas Petersen.
[4] Testimony of Mark Burch.
[5]
[6] Testimony of Mark Sather.
[7]
[8] Exs. B, C, D and G.
[9] Test. of M. Sather.
[10] Ex. K.
[11] Test. of M. Burch; Test. of M. Sather.
[12]
[13] Exs. 11 and 12.
[14] Testimony of Brian Gove; Test. of M. Burch.
[15] Testimony of Nicholas Arnt.
[16] Test. of N. Arnt; Test. of M. Burch; Exs 5A – 5C; Exs. 6A – 6E.
[17] Exs. 3, HH, II, JJ and KK; Test. of
[18] Ex. G.
[19] Exs. JJ and BBB.
[20] Ex. W-7, W-9 and LLL; Test. of M. Burch.
[21] Ex. Q; Test. of T. Petersen.
[22] Ex. Q.
[23] Exs. H, I and J.
[24] Test. of T. Petersen.
[25] Ex. H.
[26] Ex. H at 3.
[27] Exs. I; Test. of T. Petersen.
[28]
[29] Test. of T. Petersen; Ex. I (“My follow-up inspection on 9/21/07 found that the stock piles seen on 9/19/07 were removed”); see also¸ Test. of B. Gove.
[30] Ex. J.
[31]
[32] Testimony of Michael Goodnature.
[33] Test. of M. Goodnature; Ex. W-16.
[34] Test. M. Burch; Exs. 7C – 7G; 9A – 9S.
[35] Exs. K and 14-D; Test. M. Burch; Test. G. Lehner.
[36] Ex. L.
[37] Ex. A.
[38] Ex. Q at 7.
[39] Ex. Q at 9.
[40] Ex. R.
[41] Ex. S.
[42] Ex. U.
In its letter, the City asserted that its request for review was timely
because the MPCA had not properly served the Administrative Penalty Order. The City asserted that mailing the
Administrative Penalty Order to the City’s Public Works Director, rather than
to the Mayor or the City Clerk, was not proper service. The City stated that it
had submitted its request for review within thirty days of its attorney
receiving actual notice of the Order.
[43] Evidentiary Hearing Digital Recording (May 28, 2009).
[44] See also, Minn. Stat. § 115.03, subd. 1.
[45] Minn. Stat. § 116.072, subds. 2 and 6 (b) and (c).
[46] In re
Henry Youth Hockey Ass’n, 511 N.W.2d 452, 456 (Minn. App. 1994); see also, In the Matter of the Administrative Penalty Order Issued to
Paul-William Environmental, Inc., 1995 WESTLAW 311742 at *4 (
[47] Compare, MPCA’s Memorandum of Law at 2 with Ex. E, Part IV, ¶ (B) (2).
[48] See, Exs. 8A and 8F - 8L.
[49] Compare, City’s Memorandum of Law at 3 and Exs. 8L and TT with Ex. E, Part IV, ¶ (C) (5).
[50] Compare, City’s Memorandum of Law at 4 with Ex. E, Part IV, ¶ (B) (2).
[51] Compare, City’s Memorandum of Law at 5 with Ex. E, Part IV, ¶ (B) (2).
[52] Compare, Ex. E, Part IV, ¶ (C) (2) (“The timing of the installation of sediment control practices may be adjusted to accommodate short-term activities such as clearing, or grubbing or passage of vehicles. Any short-term activity must be completed as quickly as possible and the sediment control practices must be installed after the activity is completed. However, sediment control practices must be installed immediately after the activity is completed. However, sediment control practices must be installed before the next precipitation event even if the activity is not complete”).
[53] See, Exs. W-6, BB, FF, II and JJ.
[54] MPCA’s Memorandum of Law at 2-3.
[55] City’s Memorandum of Law at 5.
[56] Ex. E, Part IV, ¶¶ (B) (4) and (D)(1).
[57] MPCA’s Memorandum of Law at 3.
[58] City’s Memorandum of Law at 6 – 8.
[59] Ex. E, Part IV, ¶ (C)(1).
[60] Exs. 4B – 4E, 4I, X – CC, KK and MMM; Test. of T. Petersen; Test or B. Gove; Testimony of Nicholas Arnt.
[61] MPCA’s Memorandum of Law at 3-5; compare, Exs. 13, K through CC, YY, FF,
XX, LLL and MMM; Test. of B. Gove.
[62] City’s Memorandum of Law at 8-9.
[63] Ex. E, Part IV, ¶ (C) (4).
[64] MPCA’s Memorandum of Law at 3-4; see also, Exs. Z, AA, YY, FEF, LLL, MMM; Test. of T. Petersen; Test. of B. Gove.
[65] City’s Memorandum of Law at 9-10.
[66] Ex. E, Part IV, ¶ (E) (1) and (4).
[67] Compare, Test. of T. Petersen; Test. of B. Gove with Test. of M. Burch; Test. of M. Sather; Test. of N. Arnt; Testimony of Gary Lehner.
[68] MPCA’s Memorandum of Law at 4-5.
[69] Ex. E, Part IV, ¶ (E) (4) (f).