|
|
OAH 58-1902-17543-2 Agency No. BC2507822 |
STATE OF
OFFICE OF ADMINISTRATIVE HEARINGS
FOR THE COMMISSIONER OF LABOR AND INDUSTRY
|
In the Matter of Nest Builders LLC and Timber Land Company |
FINDINGS OF FACT, CONCLUSIONS AND RECOMMENDATION |
The
above-entitled
Michael
J. Tostengard,
1.
Did
2.
Did
3.
Has
4.
Did
Respondent Nest Builders violate Minn. Stat. § 326.91, subd. 1 (8) by failing
to pay a subcontractor for plumbing services?
5.
Did
Respondent Nest Builders violate Minn. Stat. § 45.027, subd. 1a by failing
to respond to the Department’s requests for information?
6.
Has
Respondent Nest Builders demonstrated financial irresponsibility, in violation
of Minn. Stat. § 326.91, subd. 1(6), by failing to satisfy judgments?
Based on the evidence in the hearing record, the Administrative Law Judge makes the following:
1.
Respondent Nest Builders and
2.
The Department requires licensees to take a test
before becoming licensed. Each business
entity has a qualifying person who takes the test, is responsible for
continuing education, and answers for the entity’s conduct of its affairs. When one individual is the qualifying person
for more than one licensed entity, the Department imputes any misconduct of one
licensed entity to the other. Larry
Allar is the qualifying person for both Nest Builders and
3.
Sometime in late 2005, Westonka Mechanical
Contractors (Westonka) filed a complaint against both Nest Builders and
4.
By
5.
On
6.
On
7.
At the April 11th meeting, Allar and
LeCuyer discussed judgments that Westonka had recently obtained against Nest
Builders and
8.
At the time when Westonka obtained the
judgments, Allar was working with Westonka to resolve the disputes. The Parties agreed to continue the original
court dates for the cases Westonka had filed, but Allar did not receive notice
of the new court dates. As a result, the
judgments were entered by default. Westonka
and Nest Builders have reached an agreement about the amount to be paid to
satisfy the judgments against Nest Builders and
9.
Sometime after the April 11th
meeting, LeCuyer discovered six more judgments against
Automated Lifestyles
Waterproofing, Inc.
Kings Marble
Tabery Tile, Inc.
Multiple creditors
10.
The last judgment listed above relates to
11.
Thomas D. Johnson, vice-president of Bridgewater
Bank in
12.
The sales manager of
13. Two of Nest Builders’ subcontractors submitted letters for the hearing. They attested to being paid timely and to the quality of Allar’s work. A homeowner for whom Nest Builders had constructed a 1.5 million dollar home also wrote of his satisfaction with the quality of Allar’s work.[16]
14.
At the present time, Nest Builders is engaged in
building a 1.8 million dollar town home project in
Based on these Findings of Fact, the Administrative Law Judge makes the following:
1. The Administrative Law Judge and the Commissioner of Labor and Industry are authorized to consider the charges against Respondent under Minn. Stat. §§ 45.027, 326.91, 14.50, and Executive Order 193.
2. Respondent received due, proper and timely notice of the charges against him and of the time and place of the hearing. This matter is, therefore, properly before the Commissioner and the Administrative Law Judge.
3. The Department has complied with all relevant procedural legal requirements.
4. As the party proposing that certain action be taken, the Department has the burden of proving facts at issue by a preponderance of the evidence.http://www.oah.state.mn.us/aljBase/602017359.rt.htm - _ftn29[18]
5.
The Department has shown, by a preponderance of
the evidence, that
6. The Department has shown, by a preponderance of the evidence, that Respondent Timber Land failed to respond timely to the Department’s request for information, in violation of Minn. Stat. § 45.027, subd. 1a.
7.
The Department has failed to show, by a
preponderance of the evidence, that
8. The Department has shown, by a preponderance of the evidence, that Respondent Nest Builders is financially irresponsible, in violation of Minn. Stat. § 326.91, subd. 1(6).
9. The Department has shown, by a preponderance of the evidence, that Respondent Nest Builders failed to respond timely to the Department’s request for information, in violation of Minn. Stat. § 45.027, subd. 1a.
10. The Department has failed to show, by a preponderance of the evidence, that Respondent Nest Builders violated Minn. Stat. § 326.91, subd. 1(8) by failing to pay a subcontractor for plumbing services.
11.
The Department has shown, by a preponderance of
the evidence, that discipline
12. Minn. Stat. § 326.91 empowers the Commissioner to take disciplinary action against the Respondents as a result of the Respondents’ violations of Minn. Stat. §§ 45.027, subd. 1a and 326.91, subd. 1(6).
13.
Based upon these Conclusions, and for the reasons explained in the accompanying Memorandum, the Administrative Law Judge makes the following:
Based
upon these Conclusions, the Administrative Law Judge recommends that: that
Dated: June 4, 2007
s/Linda
F. Close
|
LINDA
F. CLOSE Administrative
Law Judge |
Reported: Taped,
1 tape(s)
No
transcript prepared
This
St.
Financial
Irresponsibility
Minn. Stat. § 326.91, subd. 1(6)
permits the Department to take disciplinary action against a licensee who
demonstrates financial irresponsibility.
The Department has met its burden of showing financial irresponsibility
on the part of both
Nest Builders likewise failed to pay a subcontractor—Westonka—who then obtained a judgment against Nest Builders. Although Allar believed Westonka’s claims were excessive, he did not attempt to work out terms of payment until after Westonka had filed a complaint with the Department and followed up with legal action. As of the date of the hearing, the judgment had not been satisfied.
Allowing the license of the most
serious violator—
Failing
to Use Payment Proceeds to Pay Subcontractors
In its Second Amended Statement of Charges, the Department asserted that the Respondents, by failing to pay Westonka, violated Minn. Stat. § 326.91, subd. 1(8). That subparagraph sets forth, as a basis for disciplinary action, a licensee’s failure to use payment proceeds on a job to pay subcontractors. The ALJ has ruled against the Department on this issue because there was no evidence that either Timber Land or Nest Builders received payment for the jobs on which Westonka worked and for which it was not paid. Proof of payment is an element of the violation. Since no evidence of payment was offered, the Department’s claims based on subparagraph eight fail.
Failure
to Respond to the Department
The
Public Interest
The Commissioner is responsible to insure the public’s protection from unscrupulous, incompetent residential contractors. Certainly the Commissioner sees cases where contractors have bilked homeowners of thousands of dollars for work performed shoddily or not at all. The importance of protecting the public from such dishonest or inept residential construction contractors cannot be ignored.
However, the present case does not fit
the typical pattern of dishonesty or incompetence. The major problem relates to
It was apparent at hearing that Allar,
the qualifying person for
It was equally apparent at hearing
that Allar is highly competent as a builder.
His clients, his vendors, and even one of his long-time subcontractors have
attested to the high quality of his work.[23] Allar was recently asked to work on state
building code standards regarding energy conservation.[24] He continually tries to learn better
construction techniques.[25]
In
determining what discipline to impose, the Commissioner should weigh against the existence of the Timber Land judgments
and Allar’s delay in responding to the Westonka complaint,[26]
the positive evidence for Nest Builders.
In addition, the
L.
F. C.
[1] Testimony of Larry Allar.
[2] Testimony of Gregg LeCuyer.
[3] Test. of G. LeCuyer.
[4] Test. of G. LeCuyer; Ex. 1-2.
[5] Test. of G. LeCuyer; Ex. 3-4.
[6] Test. of G. LeCuyer.
[7] Test. of L. Allar.
[8] Test. of G. LeCuyer; Test. of L. Allar.
[9] Test. of G. LeCuyer.
[10] Test. of G. LeCuyer; Ex. 7.
[11] Test. of L. Allar.
[12] Test. of G. LeCuyer; Ex. 7.
[13] Test. of L. Allar; Ex. 8.
[14] Ex. 8.
[15] Ex. 8.
[16] Ex. 8; Test. of L. Allar.
[17] Test. of L. Allar.
[18] Although
[19] While the Department’s requests for responses were pending, Allar was dealing directly with Westonka to resolve their payment disputes. It appeared that Allar believed he could resolve the Department’s concerns in this manner. This, of course, is not true, and does not excuse the failure to respond directly to the Department. However, it may explain, in part, the reason for Allar’s delay in responding to the Department.
[20] Ex. 8.
[21] Ex. 8; Test. of L. Allar.
[22] Test. of L. Allar.
[23] Ex. 8.
[24] Test. of L. Allar.
[25] Ex. 8; Test. of L. Allar.
[26] While the Department’s requests for responses were pending, Allar was dealing directly with Westonka to resolve their payment disputes. It appeared that Allar believed he could resolve the Department’s concerns in this manner. This, of course, is not true, and does not excuse the failure to respond directly to the Department. However, it may explain, in part, the reason for Allar’s delay in responding to the Department.